project execution planning for building information … execution planning for building information...
TRANSCRIPT
Project Execution Planning forBuilding Information Modeling (BIM)Project Execution Planning forBuilding Information Modeling (BIM)Building Information Modeling (BIM) Building Information Modeling (BIM)
PACE Spring Seminar ‐ April 22nd, 2009PACE Spring Seminar ‐ April 22nd, 2009
Craig DublerNevena ZikicChitwan Saluja
Craig DublerNevena ZikicChitwan SalujaChitwan SalujaColleen KasprzakShane GoodmanJohn Messner, Ph.D
Chitwan SalujaColleen KasprzakShane GoodmanJohn Messner, Ph.D
Problem StatementProblem Statement
Many owners and project teamMany owners and project team members are struggling with how to ff ti l i l t BIM th h teffectively implement BIM throughout the lifecycle of a building project.
Project GoalProject Goal
Develop a method that focused on the decisions required to increase the Building Information Modelingrequired to increase the Building Information Modeling process efficiency throughout the stages of a building project:project:
PlanningDesignConstructionOperations
Project DeliverablesProject Deliverables
BIM Execution Planning GuideIncludes guidelines for BIM implementation at various project phasesIncludes guidelines for BIM implementation at various project phases.Posted and distributed through the buildingSMART Alliance.
BIM Implementation ResourcesBIM Implementation ResourcesSpreadsheets, Word Templates, and Process Map TemplatesAssist Team Member to make decisions necessary for BIM Use
implementationimplementation
Execution Planning ProcessExecution Planning Process
•Decision Support System to proceed from projectBIM UseBIM Use proceed from project characteristic to recommended BIM uses
BIM Use IdentificationBIM Use
Identification
•Develop a process specifically tailored to the project which includes tasks supported by BIM Process BIM Process BIM along with information exchanges between processes
PlanningPlanning
•Development of a detailed plan and procedure for each use and the information flow between the uses
BIM Execution Plan
D l t
BIM Execution Plan
D l t
Project X
BIM ExecutionDevelopmentDevelopment Execution
Plan
BIM Use IdentificationBIM Use Identification
BIM UseBIM UseBIM Use Identification
BIM Use Identification
BIM Process BIM Process PlanningPlanning
BIM Execution Plan
BIM Execution PlanPlan
DevelopmentPlan
Development
BIM Use – Engineering AnalysisBIM Use – Engineering Analysis
Lighting and Energy AnalysisLighting and Energy Analysis
BIM Use – 3D Design CoordinationBIM Use – 3D Design Coordination
3D MEP Coordination – Dickinson School of Law & Hershey Cancer Institute
BIM Use – Record ModelingBIM Use – Record Modeling
Record Modeling – Dickinson School of LawRecord Modeling Dickinson School of Law
Coordination Model Courtesy Gilbane Building Co.
BIM Process PlanningBIM Process Planning
BIM UseBIM UseBIM Use IdentificationBIM Use
Identification
BIM Process BIM Process PlanningPlanning
BIM Execution Plan
BIM Execution PlanPlan
DevelopmentPlan
Development
Planning the BIM Execution ProcessPlanning the BIM Execution Process
• BIM Use Map
Level 1•A high level process map that outlines the various BIM uses in the different phases and information exchange that bind them.
Level 2
• Template Process Map•Template process maps will be mapped out for various BIM uses for reference by the project teams. These will contain…….
Level 3
• Project Specific Process Map•The template process maps created in level 2 can then be taken to develop project specific process map, tailored to the process at handLevel 3 at hand.
Planning the BIM Execution ProcessPlanning the BIM Execution Process
• BIM Use Map
Level 1•A high level process map that outlines the various BIM uses in the different phases and information exchange that bind them.
Level 2
• Template Process Map•Template process maps will be mapped out for various BIM uses for reference by the project teams. These will contain…….
Level 3
• Project Specific Process Map•The template process maps created in level 2 can then be taken to develop project specific process map, tailored to the process at handLevel 3 at hand.
Template Process Map – Design CoordinationTemplate Process Map – Design CoordinationCoordinationCoordination
Planning the BIM Execution ProcessPlanning the BIM Execution Process
• BIM Use Map
Level 1•A high level process map that outlines the various BIM uses in the different phases and information exchange that bind them.
Level 2
• Template Process Map•Template process maps will be mapped out for various BIM uses for reference by the project teams. These will contain…….
Level 3
• Project Specific Process Map•The template process maps created in level 2 can then be taken to develop project specific process map, tailored to the process at handLevel 3 at hand.
Project Specific Process Map – Design Coordination (Millennium Science Project)Project Specific Process Map – Design Coordination (Millennium Science Project)( j )( j )
BIM Execution Plan DevelopmentBIM Execution Plan Development
Project Reference InformationBIM UseBIM Use
Project Goals /BIM Objectives
BIM Process Design
BIM Use IdentificationBIM Use
Identification
g
Delivery Strategy / Contract
BIM S D fi iti
Project X
BIM Execution BIM Process BIM Process
BIM Scope Definitions
Organizational Roles and Responsibilities
PlanPlanningPlanning
Communication Procedures
Technology Infrastructure NeedsBIM Execution Plan
BIM Execution Plan
Model Quality Control Procedures
Plan Development
Plan Development
Milestone Schedule
• May 15, 2009 – Draft Guide Complete
• May 2009 thru March 2010 Guide Implementation• May 2009 thru March 2010 – Guide Implementation
• March 2010 – Final Guide Complete
Acknowledgments
• Project Sponsors:– The Charles Pankow Foundation– The Construction Industry Institute (CII)– The Partnership for Achieving Construction Excellence e a t e s p o c e g Co st uct o ce e ce(PACE)
– Penn State Office of Physical Plant (OPP)
• Advisory Board Members – Balfour Beatty, Barton Malow
• Interview Participants Clark Gilbane• Interview Participants – Clark, GilbaneBIM Execution Website: bimex.wikispaces.com