project feasibility analysis in engg. economics

Upload: thapa-pramod

Post on 09-Apr-2018

230 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/8/2019 Project Feasibility Analysis in Engg. Economics

    1/21

    ENGINEERING ECONOMICS

    FINAL COURSE PRESENTATION

    PRESENTED BY:

    Pramod Thapa 064bme625Susheel Regmi 064bme646

    Umanga Bhattarai 064bme647Utsav S. Rajbhandari 064bme648

  • 8/8/2019 Project Feasibility Analysis in Engg. Economics

    2/21

    p r e p a r e d b y : -

    & D Solar Solut ions PROJECT FEASIBILITY ANALYSIS

    UPSS NGINEERI NG SOUTIONS NGINEE RING SOUTIONS

  • 8/8/2019 Project Feasibility Analysis in Engg. Economics

    3/21

    Problem statement

    R&D solar solutions that manufactures solar heating equipment, namely improved solar water heater. The initial investment is Rs.70 lakhs. The production target is 250

    units per year till the service life of 10 years. During these years, it would invest in

    R&D. At the end of year 6, additional Rs.5lakhs,in bulk is, invested for R&D. After

    its current service life, the continuation would be based in the progress by the R&D.The land is on rent while other fixed assets are the capital investment. With the

    assumption of escalation rate of 5%, the depreciation for building and machinery to

    be 15% and 25% respectively. The annual insurance cost is 2.5% . The revenue per

    unit production for the first year is Rs50,000 and it will increase by 5% each year

    thereafter. The MARR of the company is assumed to be 15%

  • 8/8/2019 Project Feasibility Analysis in Engg. Economics

    4/21

    OBJECTIVES

    To make the engineering economic analysis using Project Evaluation Technique

    To Develop a Discounted Cash Flow (DCF) model for the project and find out whether

    the project is feasible or not.

    To check out whether the project can be carried out further along with R&D.

    To find out the IRR for the project.

    To find the payback period of the project

    The non-commercial objective of this project is to replace diesel and kerosene burning

    water boilers in various industries and household purposes in Nepal with high

    efficiency solar water heaters to reduce imported fossil fuel use and related GHG

    emissions

  • 8/8/2019 Project Feasibility Analysis in Engg. Economics

    5/21

    METHODOLOGY

  • 8/8/2019 Project Feasibility Analysis in Engg. Economics

    6/21

    Methodology (continued)

    Analysis Tools used:Discounted Payback PeriodNet Present Value

    Annual Equivalent ValueInternal Rate Of Return

  • 8/8/2019 Project Feasibility Analysis in Engg. Economics

    7/21

    Discounted Payback period

    Payback period is the time needed to recover theinitial investment by the net cash flows produced by the investment.

    But it doesnt show the profit.

  • 8/8/2019 Project Feasibility Analysis in Engg. Economics

    8/21

    NPV

    Present worth (PW) is an equivalent cash flow at present, generally att =0, to all the cash flows associated with a project.

    NPV =A i (P/F, i, n) NPV =A i (P/F, i, n)

    If NPV > 0, accept the investmentIf NPV = 0, remain indifferentIf NPV< 0, reject the investment.

  • 8/8/2019 Project Feasibility Analysis in Engg. Economics

    9/21

    AEV

    It is measurement of investment on equal paymentannual basis.

    AE(i)=PW(i)(A/P,I,N)

    If AE>0, accept the projectIf AE =0, remain indifferentIf AE

  • 8/8/2019 Project Feasibility Analysis in Engg. Economics

    10/21

    IRR

    Internal rate of return (IRR) of a project is the interestrate, i, which makes PW(i) = 0.

    Methods of project Evaluation by IRR If IRR>MARR, accept the projectIf IRR = MARR, remain indifferentIf IRR < MARR, reject the project

  • 8/8/2019 Project Feasibility Analysis in Engg. Economics

    11/21

  • 8/8/2019 Project Feasibility Analysis in Engg. Economics

    12/21

    Capital Costs

  • 8/8/2019 Project Feasibility Analysis in Engg. Economics

    13/21

    Annual Expenditures

  • 8/8/2019 Project Feasibility Analysis in Engg. Economics

    14/21

    Revenue

  • 8/8/2019 Project Feasibility Analysis in Engg. Economics

    15/21

    Project Cash Flow

  • 8/8/2019 Project Feasibility Analysis in Engg. Economics

    16/21

    Project evaluation techniques

    We have used following method for project evaluation:

    Payback period:Between 5 th and 6 th year

    Net Present Value (NPV):PW(15%)=Rs. 5143000

    Annual equivalent value: AE(15%)=Rs. 1025000

    Internal rate of return:IRR=28%

  • 8/8/2019 Project Feasibility Analysis in Engg. Economics

    17/21

    Payback Period

    Discounted payback periodyear Cash flow % cash cumulative

    0 -7000 0 -7000

    1 1445 -1050 -6605

    2 1758 -991 -5838

    3 2040 -876 -4673

    4 2302 -701 -3072

    5 2549 -461 -984

    6 2285 -148 1153

    7 3016 173 4342

    8 3348 651 8341

    9 3664 1251 13256

    10 3862 1988 19107

    Payback period is between 5 th and 6 th year Very attractive for a company

    which is planning furtherexpansion in future.

  • 8/8/2019 Project Feasibility Analysis in Engg. Economics

    18/21

    NPV and AEV

    NPV: Assume, MARR=15%=iFor our project,

    NPV(15%)= A i (P/F, i, n) =Rs. 5143000

    As, NPV is +ve, so we accept project

    AEV: AE(15%)=Rs. 1025000

    Attractive Annual income

  • 8/8/2019 Project Feasibility Analysis in Engg. Economics

    19/21

    IRR NPV Profile

    year Cash Flow Discount rate NPV 0 -7000 0%19,268

    1 1445 5%12,471

    2 1758 10%7,896

    3 2040 15%4,723

    4 2302 20%2,459

    5 2549 25%803

    6 2285 30%(437)

    7 3016 35%(1,386)

    8 3348 40%(2,127)

    9 3664 45%(2,715)

    10 3862 50%(3,190)

    IRR = 28% Very attractive for investors

  • 8/8/2019 Project Feasibility Analysis in Engg. Economics

    20/21

    CONCLUSION

    v The project is feasible and is profitable.

    v Investment on R&D is also feasible.

    v The project can be even carried out further after the

    projected life based on the progress report from R&D.

    v The payback period is very good.

    v The IRR is attractive enough to attract any investor, if

    required.

  • 8/8/2019 Project Feasibility Analysis in Engg. Economics

    21/21

    THANK YOU ! ! !