project first prototype (1)
TRANSCRIPT
PartName
Part descrip
tionMaterial
Manufacturing
Process
Quantity
Unit Cost
Total Cost
Structures
This part deal with product because structures have an effect on strength in any part of product.
-Wood-Nail
-Drilling-Cutting-Hammering
2 40 80
Chair
This part made from wood and hold by nail . In this part
-Wood-Nail
-Drilling-Cutting-Hammering
1 300 300
PartName
Part descrip
tion
Material
Manufacturing
Process
Quantity
Unit Cost
Total Cost
Table
This part made from wood and hold by nail. In this part you can put a book , Laptop or Tablet and can do work in document type.
-Wood
-Nail
-Drilling-Cutting-Hammering-Dubbing-Painting
1 200 200
Inside of
Total Cost
80+300+200+500 = 1080 Baht
Record the number of hours spent in each
manufacturing process.
-Cutting= 3 hrs.
-Drilling= 2hr.
-Hammering= 1.30 hrs.
-Dubbing= 1.30hrs.
-Painting =2hrs.
Total = 10 hrs.
Provide difficulties and problems encountered during the prototype development.
- It’s hard to move because product didn’t have rollers.
- Material have a high cost.
- Use time to make too much.
Provide the solutions for your second prototype.
- Find rollers and shaft . And assembly it with product (First prototype)
- Find a material that people didn’t use it.
- Manage a time and prepare manufacturing processes that my product use.