project management

30
PROJECT MANAGEMENT (Pass 1) GA Tech CS 3300 AY 2002 Spring 2002

Upload: samuel90

Post on 23-Jun-2015

297 views

Category:

Business


0 download

TRANSCRIPT

Page 1: Project Management

PROJECT MANAGEMENT

(Pass 1)GA Tech CS 3300 AY 2002

Spring 2002

Page 2: Project Management

Development process- when to do what phase- document

Management structure- hierarchical, peer,...

Risk identification & retirement

Plan project

Integrate & test system

Analyze requirements

Design

Maintain

Test unitsImplement

Software Engineering Roadmap:

Corporate practices

Development phases

Schedule

Cost estimate

SPMP

Adapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission.

Page 3: Project Management

Learning Goals

• Understand the term “project management”

• Organize teams

• Specify project management plans

• Define and retire risks

• Estimate costs very early in the life cycle

• Create high level projects schedules

• Write a Software Project Management Plan

Adapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission.

Page 4: Project Management

The Variables of Project

Management

Can somewhat vary the following factors.

1. The total cost of the project, e.g., increase expenditures

2. The capabilities of the product, e.g., subtract from a list of features

3. The quality of the product, e.g., increase the mean time between failure

4. The date on which the job is completed. e.g., reduce the schedule by 20%

e.g., postpone project's completion date one monthAdapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission.

Page 5: Project Management

Bullseye Figure for Project Variables

cost

capability duration

defectdensity

Target :$70K

Target : 30 wks

Target : 4 defects/Kloc

Target:100%

Adapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission.

Page 6: Project Management

Bullseye Figure for Project Variables

cost

capability duration

defectdensity

Target :$70K

Actual: 100%

Target : 30 wksTarget :

4 defects/Kloc

thisproject

Actual:1 defect/Kloc

Actual:20 wks

Actual:$90K

Target:100%

Adapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission.

Page 7: Project Management

RoadMap for Project Management

1. Understand project content, scope, & time frame

2. Identify development process (methods, tools, languages, documentation and support) -- section 4 of chapter 1

3. Determine organizational structure (organizational elements involved) -- see section 3

4. Identify managerial process (responsibilities of the participants) -- see section 3 of case study 1 at end of chapter

6. Develop staffing plan -- see section 3.5 of case study 1

5. Develop schedule (times at which the work portions are to be performed) -- see section 6

7. Begin risk management -- see section 4

8. Identify documents to be produced -- see SQAP 4.2

9. Begin process itself -- described in chapters 3-10

Adapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission.

Page 8: Project Management

1.* Distribute start time, end time, and agenda with approximate times– list important items first

2.* Ensure “strawman” items prepared3. Start on time4. Have someone record action items‡

5. Have someone track time & prompt members6. Get agreement on the agenda and timing7. Watch timing throughout, and end on time

– allow exceptions for important discussion– stop excessive discussion; take off line

8. Keep discussion on the subject 9.** E-mail action items & decision summary.

Plan and Execute Meetings

* in advance of meeting ‡ actions members must perform ** after meeting Adapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission.

Page 9: Project Management

Specify Agendas

1. Get agreement on agenda & time allocation

2. Get volunteers to … :… record decisions taken and action items

… watch time and prompt members (see figure tbd)

3. Report progress on project schedule -- 10 mins

4. Discuss strawman artifact(s) -- x mins

5. Discuss risk retirement -- 10 mins

<MORE ITEMS>metrics and process improvement?

n. Review action items -- 5 mins

Adapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission.

Page 10: Project Management

Optimal Size for Interaction (Approximate)

Number of people with whom developer must frequently interact

Developer communicates regularly with eleven people. Communication time outweighs benefits of interaction

Developer communicates regularly with no one. No communication time lost, but developer is too isolated and has no help.

Key: = engineer

Approximateoptimal range

3 7

Effectiveness per developer

Adapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission.

Page 11: Project Management

Hierarchical Project Management Organizations

Larger Projects:Smaller Projects:

No separate Marketing?No separate QA organization?

Subdivide QA into testing, …?Subdivide Engineering into

system engineering, …?Adapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission.

Page 12: Project Management

Gaming Industries ConsolidatedPresident

VP EngineeringVP Marketing. . .

IV&V

EncounterGame 123. . . SQA

Game Lab. . .

SoftwareEngineering

Labs

Adapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission.

Page 13: Project Management

Horizontal Project Management Organizations

Gil WarnerTeam leader

Ian CorlissTeam member

Nel TremontTeam member

Fran SmithTeam member

Team facilitator?

Adapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission.

Page 14: Project Management

Organize a Team

1. Select team leader: responsibilities: – ensure all project aspects active– fill all gaps

3. Designate leader roles & document responsibilities team leader: proposes and maintains… SPMP configuration management leader: ... SCMP quality assurance leader: ... SQAP, STP requirements management leader: ... SRS design leader: ... SDD implementation leader: ... code base

2. Leaders’ responsibilities:– propose a strawman artifact (e.g. SRS, design)– seek team enhancement & acceptance– ensure designated artifact maintained & observed– maintain corresponding metrics if applicable

4. Designate a backup for each leader as perAdapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission.

Page 15: Project Management

Peer Organizations for Larger Projects

Team of leaders

Adapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission.

Page 16: Project Management

  Project

Airline reserv. project

Bank accountg.

project

Molecular analysis project

Fluid mechanics

project

Func-tional Unit

Project manage-ment dpt

Al PruittFull time

Quinn Parker

Half time

Ruth PellaFull time

Fred Parsons

Full time

Marketing dpt

Oscar MartFull time

Pete Merrill

Full time

Sue MoreHalf time

Elton MarstonFull time

Engineer-ing dpt

Hal Egberts

......

Ben Ehrlich

......

Mary Ericson

.....

Len Engels.....

Table 2.1 Matrixed organization

Page 17: Project Management

Name

Team Leader

CM Leader.

QALeader

Requ. Mngmnt Leader

Design Leader

Implemen- tation

Leader

Ed Braun X         X

Al Pruitt   X        

Fern Tryfill     X      

Hal Furnass       X    

Karen Peters

        X  

Liaison with VP Eng.     MarketingSoft. Eng.

Lab 

Table 2.11 Encounter Staffing

Plan

Adapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission.

Page 18: Project Management

Program Monitoring & Control

Adapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission.

Page 19: Project Management

The Four Risk Activities

(1) Identification

Mindset: try to continually identify risks

(2) Retirement planning

(3) Prioritization

(4) Retirement or mitigation

Adapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission.

Page 20: Project Management

Risk Sources Ordered by Importance (Keil, Cule, Lyytinen, Schmidt)

1. Lack of top management commitment

2. Failure to gain user commitment

3. Misunderstanding of requirements

4. Inadequate user involvement

5. Failure to manage end-user expectations

6. Changing scope and/or objectives

7. ….

Page 21: Project Management

Projectfinish

The Risk Management Mindset

Projectstart

Identification Retirement

2. “Java skills not high enough.”

1. “May not be possible to superimpose images adequately.”

1. Retirement by conquest: Demonstrate image super- imposition

Risk 1

Risk 2

Risk 1

Projectfinish

Risk 2

2. Retirement by avoidance: Use C++

Projectstart

Graphics reproduced with permission from Corel.Adapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission.

Page 22: Project Management

 

Likelihood1-10

 1 = least

likely

Impact1-10

 1 = least impact

Retire-ment cost

1-101 = lowest retirement

cost

Priority computation

Resulting priority

 Lowest number handled

first

The highest priority

risk

10(most likely)

10 (most

impact)

1 (lowest

retirement cost)

(11-10)*(11-10)

*1 1

The lowest

priority risk

1 (least likely)

1 (least

impact)

10(highest

retirement cost)

(11-1)*(11-1)

*10 1000

Table 2.2 A way to compute risk priorities

Adapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission.

Page 23: Project Management

Risk title(details given

above)

Like-lihood1-10

 1=least likely

Im-pact1-10

 1=least impact

Retire-ment cost 1-101=lowest

retirement cost

Pri-ority

 lowest

number handled

first

Retirement / mitigation plan

Respon-sible

engineer

Target com-

pletion date

            

   

1 Super-imposing images

3 10 1 8Experiment with Java images.

P. R. 2/1/99

 2

Deficient Java skills

9 6 8 80

H.T., K.M., V.I. and L.D. to attend training course beginning 1/5/99 at Ultra Training Corp, obtain Java level 2 certification by 3/1/99 and level 3 certification by 4/15/99

H. L. 4/15/99

3

Alan Gray may be pulled off this project

3 7 9 288Susan Ferris to

inspect all of Alan's work

S.F.Contin-

ual

.

.

... ... ... ... ... ... ... ...

Table 2.3  Sample Risk Analysis for Encounter Case Study

Adapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission.

Page 24: Project Management

*:in advance of first meeting M: at meeting **: between meetings

Identify and Retire Risks

1.* Each team member spends 10 mins. exploring his or her greatest fears for the project’s success

2.* Each member specifies these risks in concrete language, weights them, writes retirement plans, (see format above) & e-mails to the team leader

3.* Team leader integrates and prioritizes results 4.M Group spends 10 mins. seeking additional risks 5.M Team spends 10 mins. finalizing the risk table

– Designates responsible risk retirement engineers

6.** Responsible engineers do risk retirement work7.M Team reviews risks for 10 mins. at weekly meetings

– responsible engineers report progress– team discusses newly perceived risks and adds them

Page 25: Project Management

FactorWeight (1-10)

Benefit of Language 11 to 10=best

Benefit of Language 21 to 10=best

Internet-friendly 3 8 2

Familiarity to development team 8 3 9

Compilation speed 5 2 8

Runtime speed on processor p

1 7 3

Score 3*8 + 8*3 + 5*2 + 1*7

= 65

3*2 + 8*9 + 5*8 + 1*3

= 121

Table 2.4 Example of method for deciding language choice

Adapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission.

Page 26: Project Management

Create an Initial Schedule

1. Indicate the milestones your must observe– usually includes delivery date

2. Back these up to introduce the milestones you need– e.g., begin system testing well before delivery

3. Designate a time at which all requirements frozen

The remaining steps depend on the process used. We will assume an iterative process.

4. Show first iteration: establishes minimal capability– usually: keep it very modest, even trivial, in capability– benefit: exercises the development process itself

5. Show task of identifying & retiring risks– starting from project inception

6. Show unassigned time (e.g., week) near middle?

7. Complete the schedule Adapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission.

Page 27: Project Management

High Level Task Chart with Fixed Delivery Date:Order of Completion

Month 1

1 2 3 4

Month 2

1 2 3 4

Month 3

1 2 3 4

Month 4

1 2 3 4

Month 5

1 2 3 4

Milestones (1*) Delivery

Begin system testing

Iteration 1

Iteration 2(6)

(4)

(3) Freeze requirements

Risk identification & retirement

(5)

* Indicated the order in which the parts of this table were built

SCMP complete

SQAP complete

SPMP rel. 1 complete

(2)

Prep. for maintenance

Adapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission.

Page 28: Project Management

Month 1

1 2 3 4

Month 2

1 2 3 4

Month 3

1 2 3 4

Month 4

1 2 3 4

Month 5

1 2 3 4

MilestonesDelivery

Complete testing

Iteration 1

Iteration 2

Freeze requirements

Risk I&R

SCMPSQAP

SPMP rel. 1

E. Braude 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

J. Pruitt 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

F. Tryfill 1 1 1 1 1 1 1 1 1 1 1 1 1

H. Furnass 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 K. Peters 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

Tasks

Work BreakdownStructure

Excluding Secretarial

TOTAL 5.5 5.5 5.5 5.5 5.5 5.5 5.5 5.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 4.5 3.5 3.5

F. Smith (tech support) .5 .5 .5 .5 .5 .5 .5 .5 .5 .5 .5 .5 .5 .5 .5 .5 .5 .5 .5 .5

Adapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission.

Page 29: Project Management

Level Labor Allocation for Fixed Labor Total

Month 1

1 2 3 4

Month 2

1 2 3 4

Month 3

1 2 3 4

Month 4

1 2 3 4

Month 5

1 2 3 4

MilestonesRelease to production

Complete testing

Iteration 1

Iteration 2

Freeze requirements

Risk ID & retire

2 2 2 3 2 2 3

2 2 2 1 1 1

4 4 4 3 3 4

4 4 4 4 4 3 3 4 4 4 4 3 3 4 4 4 4 4

4 4 4 4 4

4 4

4

Given team size:

To be assigned4

Halvacation

Karenvacation

Adapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission.

Page 30: Project Management

Summary

• Project management: “silver bullet”?

• “People” aspects co-equal technical

• Specify SPMP

• Define and retire risks

• Estimate costs with several methods– expect to revisit and refine

– use ranges at this stage

• Schedule project with appropriate detail

• Maintain a balance among cost, schedule, quality and functionality

Adapted from Software Engineering: An Object-Oriented Perspective by Eric J. Braude (Wiley 2001), with permission. Graphics reproduced with permission from Corel.