project management basic concepts

96
Opermgt 345 Shannon January, 2001 1 Project Management Basic Concepts

Upload: nellis

Post on 09-Jan-2016

38 views

Category:

Documents


2 download

DESCRIPTION

Project Management Basic Concepts. What is a Project?. A Project is a series of activities and tasks that: Have a specific tasks and activities to be completed with certain objectives. Have a defined start and end dates Have funding limits (if applicable) Consume Resources. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Project Management Basic Concepts

Opermgt 345 Shannon January, 20011

Project ManagementBasic Concepts

Page 2: Project Management Basic Concepts

Opermgt 345 Shannon January, 20012

What is a Project?

A Project is a series of activities and tasks that:

1. Have a specific tasks and activities to be completed with certain objectives.

2. Have a defined start and end dates

3. Have funding limits (if applicable)

4. Consume Resources

Page 3: Project Management Basic Concepts

Opermgt 345 Shannon January, 20013

Typical Project Structure

ProjectDefinition

ProjectDefinition

ProjectPlanning

ProjectPlanning

ProjectImplementation

ProjectImplementation

ProjectMonitoring

ProjectMonitoring

ProjectAdjustment

ProjectAdjustment

ProjectEvaluation

ProjectEvaluation

Page 4: Project Management Basic Concepts

Opermgt 345 Shannon January, 20014

Project Life CycleR

esou

rces

and

Eff

ort

Phase 1

•Goals•Scope•Baseline•Requirements•Feasibility•Desirability

ConceptualDesign

Phase 2

AdvancedDevelopment

•Plan•Budget•Schedule•Management Commitment

Phase 3

DetailedDesign

•Define Responsibility•Team•Organization Structure•Detailed Plan•Kickoff

Phase 4

ProjectImplementation

•Manage•Measure•Control•Update and Modify Plan•Problem Solve

ProjectTermination

Phase 5

•Closeout•Document•Suggest Improvements•Reassign•Dissolve Project Team

Page 5: Project Management Basic Concepts

Opermgt 345 Shannon January, 20015

Successful Projects

A successful project is one which achieves the following objectives:– Completed On Time– Completed Within Cost– Meets Performance Criteria– Minimum Disruption of the Main Work of the

Organization– Effective Utilization of Resources

Page 6: Project Management Basic Concepts

Opermgt 345 Shannon January, 20016

The Triple Play ofProject Management

Constraints

Time Cost

Performance

Page 7: Project Management Basic Concepts

Opermgt 345 Shannon January, 20017

Triple Constraint Trade-offs

Budget

ScheduleEarly Late TIME

$

Performance Specifications

Better

Worse

Page 8: Project Management Basic Concepts

Opermgt 345 Shannon January, 20018

Major causes of failure

Selection of a unsound projectSelecting the wrong person as a project

managerLack of support from upper managementMisused management techniquesProject termination not planned

Page 9: Project Management Basic Concepts

Opermgt 345 Shannon January, 20019

Project Definition

Build Canoe Rental Building onCoeur d A’lene Lake

Page 10: Project Management Basic Concepts

Opermgt 345 Shannon January, 200110

Form Project Team

•Select Project Leader

•Identify Key People

•Gain Management Commitment

•Define Project Team Operating Rules

Page 11: Project Management Basic Concepts

Opermgt 345 Shannon January, 200111

Project Manager

Page 12: Project Management Basic Concepts

Opermgt 345 Shannon January, 200112

Project Manager Skills• Scheduling and time mgt. skills

• Technical skills ( scope of project )

• Leadership skills ( goals, performance measures)

• Resource mgt., human relationship skills.

• Communication skills

• Negotiation skills

• Marketing, Contracting, customer relationship skills

• Budgeting and cost skills.

Page 13: Project Management Basic Concepts

Opermgt 345 Shannon January, 200113

Major Interactions of project stakeholders

Project Manager

Government agencies

ConsultantsTop Management

Financial Managers Client

Project Team Other Organization Subcontractors

Page 14: Project Management Basic Concepts

Opermgt 345 Shannon January, 200114

Project Manager Responsibilities

1. Responsibility to the parent Org.

2. Responsibility to the project and client

3. Responsibility to the member of the project team

Page 15: Project Management Basic Concepts

Opermgt 345 Shannon January, 200115

Selecting Project ManagerList of some of the most popular attributes:

• A strong technical background

• A hard-nosed manager

• A matured individual

• Someone who is currently avaiable

• Someone on good terms with senior executive

• A person who can keep the project team happy

• One who has worked in several departments

• A person who can walk on ( or part ) the waters.

Page 16: Project Management Basic Concepts

Opermgt 345 Shannon January, 200116

Selecting the PM

• Credibility– Technical credibility ( technical knowledge )– Administrative credibility ( managing resources( money, people,

material) keeping the project on scheule.

• Sensitivity– It is related to the ability of the manager to discover the problems

at early stages and solve the team’s problems if we have some conflects

• Leadership and management style– Leadership is defined as the ability of affecting others in away

that gurantees the project profitability to the org. and sociey.

• Ability to work under stress

Page 17: Project Management Basic Concepts

Opermgt 345 Shannon January, 200117

Project Planning

• There are several reasons why we must use considerable care when planning projects

• The primary purpose of planning is to establish a set of directions in sufficient detail to tell the project team exactly :– What must be done?– When it must be done?– What resources to use ?

Page 18: Project Management Basic Concepts

Opermgt 345 Shannon January, 200118

Project plan Elements:

• Overview : – A short summary of the objectives and scope of

the project– Directed to top mgt. and contains a statement of

goals of the project– A description of the managerial structure that

will be used for the project.– A list of major milestones in the project schdule.

Page 19: Project Management Basic Concepts

Opermgt 345 Shannon January, 200119

Project plan Elements:

• Objectives:– More detailed statement of general goals noted

on the overview section.– The statement should include profit and

competitive aims as well as technical goals.

• General approach:– Describes both the managerial ( style of mgt. )

and the technical approaches ( required equipments, technology ) to the work.

Page 20: Project Management Basic Concepts

Opermgt 345 Shannon January, 200120

Project plan Elements:

• Contractual aspects: ( list for )– All reporting requirements– Customer-supplied resources.– Advisory commitees– Project review– Cancellation procedures.– Specific management agreements– subcontracts

Page 21: Project Management Basic Concepts

Opermgt 345 Shannon January, 200121

Project plan Elements:

• Schedules:– Various schedules.– Lists all milestones events.– All tasks, and their durations…..

• Resources:– The budget– Both capital and expense requirements are

detailed by task. ( Project budget )– Cost monitoring and control procedures.

Page 22: Project Management Basic Concepts

Opermgt 345 Shannon January, 200122

Project plan Elements:

• Personnel :– Expected personnel requirements– Special skills needed– Types of training needed– Possible recruiting problems.– Legal and political restrictions.

Page 23: Project Management Basic Concepts

Opermgt 345 Shannon January, 200123

Project plan Elements:

• Evaluation Methods:– Every project should be evaluated against

standards and by methods established at the project inception.

– This section include :• A brief description of the procedure to be followed

in monitoring , collecting, storing, and evaluating the history of the project.

Page 24: Project Management Basic Concepts

Opermgt 345 Shannon January, 200124

Project plan Elements:

• Potential problems:– External and internal potential problems.

Page 25: Project Management Basic Concepts

Opermgt 345 Shannon January, 200125

Work-Breakdown- Structure (WBS)

• It is a result family tree , subdivision of the major tasks( hw, services , etc ) and the data required to produce the final product , it acts as a vehicle for breaking down the work into smaller elements.

Page 26: Project Management Basic Concepts

Opermgt 345 Shannon January, 200126

Work-Breakdown- Structure (WBS)

• We have 2 types of WBS:– Managerial level

– Technical level

Work Breakdown Structure.htm

Page 27: Project Management Basic Concepts

Opermgt 345 Shannon January, 200127

Earned Value Analysis• It is a continuous comparison between the

plan of the project data and the actual data.

Budgeted and Committed Cost:

Variance = Budgeted cost – committed cost

Variance (+ve ) = Unconsumed Cost

Variance ( -ve ) = Over spend activities

Page 28: Project Management Basic Concepts

Opermgt 345 Shannon January, 200128

Cost and Schedule Variances

Page 29: Project Management Basic Concepts

Opermgt 345 Shannon January, 200129

Cost and Schedule Variances

Page 30: Project Management Basic Concepts

Opermgt 345 Shannon January, 200130

BCWSBudgeted Cost of Work Schedule

A B C D E F G H I J

X1 X2 X3 X4 X5 X6 X7 X8 X9 X10

NOW

BCWS = X1 + X2 + X3 + X4 + X5 $

This is the sum of all the costs up to the specific activity that is stated in budget plan.

Page 31: Project Management Basic Concepts

Opermgt 345 Shannon January, 200131

BCWPBudgeted Cost of Work Performed

BCWP = X1 + X2 + X3 + 0.8 X4 + 0.5 X5 $

This is the sum of all the costs up to the specific activity in relation with its completion percentage.

A B C D E

100%

X1

100%

X2

100%

X3

80%

X4

50%

X5

Page 32: Project Management Basic Concepts

Opermgt 345 Shannon January, 200132

ACWPActual Cost of Work Performed

ACWP = Actual cost of work done.

This is the total costs of the work done on reality provided by project manager on the financial monitor.

Page 33: Project Management Basic Concepts

Opermgt 345 Shannon January, 200133

Page 34: Project Management Basic Concepts

Opermgt 345 Shannon January, 200134

• If BCWP > BCWS ( over spend )

• If BCWP < BCWS ( time is late -ve )

• If BCWP > BCWS

( +ve time is more than sufficient )

Page 35: Project Management Basic Concepts

Opermgt 345 Shannon January, 200135

Page 36: Project Management Basic Concepts

Opermgt 345 Shannon January, 200136

Forecasting• It is the process of prediction of the future

events.

• Benefits of forecasting:1. To estimate the cost of remaining parts

of a project ( forecasted value ).

2. To identify the source and places of certain problems in the budget plan.

3. It is a tool for corrective actions.

Page 37: Project Management Basic Concepts

Opermgt 345 Shannon January, 200137

ForecastingMathematical Expressions

• The Cost Performance Index ( CPI ):

CPI = BCWP / ACWP

• It gives a good indication whether the project is performing financially well or not.

• CPI > 1 : Good performance.

• CPI < 1 : Bad performance ( shortages

• Overspend ).

Page 38: Project Management Basic Concepts

Opermgt 345 Shannon January, 200138

ForecastingMathematical Expressions

• The Schedule Performance Index ( SPI ):

SPI = BCWP / BCWS

• It is a good indicator for the project timing.

• SPI > 1 : Good performance.

• SPI < 1 : Bad performance (Poor ).

Page 39: Project Management Basic Concepts

Opermgt 345 Shannon January, 200139

ForecastingMathematical Expressions

• Budgeting Cost to Completion ( BCC ):

• The Amount of money needed to completion.

• BCC = BAC – BCWP

• It is defined as the amount of money required to complete a project where it is partially completed ( remaining money ).

Page 40: Project Management Basic Concepts

Opermgt 345 Shannon January, 200140

ForecastingMathematical Expressions

• Estimated Cost to Completion ( ECC ):

• Its more realistic value than budgeted.

• ECC = BCC / CPI

• It depends on CPI which is a by product of the actual cost of work performed.

• Forecasted Cost to Completion ( FCC ):

• FCC = ACWP + ECC

Page 41: Project Management Basic Concepts

Opermgt 345 Shannon January, 200141

Page 42: Project Management Basic Concepts

Opermgt 345 Shannon January, 200142

Example

• The R&D department of a company has been developing a new product line, the project manager is concerned whether the following provided data is exhibiting a good project performance, calculate the following and comment on the project status to convince the project manager.

1. CPI,BCC, ECC, SPI, FCC.

Page 43: Project Management Basic Concepts

Opermgt 345 Shannon January, 200143

Work Package

Budgeted Cost Completion Time month

Actual Cost

% Complete

B49 20000 1 23500 100%

B50 20000 2 20500 100%

B51 37000 3 23000 70%

B52 27000 4 27000 100%

B53 12000 5 4500 60%

B54 28000 6 18500 75%

B55 40000 7 ---- ----

184000

Page 44: Project Management Basic Concepts

Opermgt 345 Shannon January, 200144

Solution• BCWS = 20000 + 20000 + 37000 + 27000 + 12000 + 28000 =

144000 $• ACWP = 23500+20500+23000+27000+4500+18500 =

117000 $• BCWP = 20000 + 20000 + ( 37000 x 0.7 ) + 27000 +

( 12000 x 0.6 ) + ( 28000 x 0.75 ) =

119900 $

CPI = BCWP / ACWP = 119900 / 117000 = 1.02 good performance.

Page 45: Project Management Basic Concepts

Opermgt 345 Shannon January, 200145

• BAC = Budget at Completion = 184000• BCC = BAC – BCWP = 184000 – 119900 =

64100$• ECC = BCC / CPI = 64100/1.02 = 62843.14

$• SPI = BCWP / BCWS = 119900 / 144000 =

0.832 < 1 Poor performance according to time.

• FCC = ACWP + ECC = 117000 + 62843.14

= 179843.14 $

Page 46: Project Management Basic Concepts

Opermgt 345 Shannon January, 200146

Comments• We do not have any financial problem i.e the

budgeted cost (money resources) is larger than the forecasted values, we conclude that the money is available , it is more than sufficient as the indicators were positive, the only problem we have is the time.

Page 47: Project Management Basic Concepts

Opermgt 345 Shannon January, 200147

Comparing ProjectsProject SPI CPI

A 0.78 (2) 0.68 (2)

B 0.96 (1) 0.98 (1)

C 0.46 (3) 0.51 (4)

D 0.46 (4) 0.64 (3)

Page 48: Project Management Basic Concepts

Opermgt 345 Shannon January, 200148

Problem : Compare between the following projects according to the time and cost consumed:

WP budget actual %comp

A 435 395 100%

B 320 409 90%

C 125 -

d 570 -

WP budget actual %comp

A 820 800 100%

B 750 920 90%

C 1000 730 65%

D

E

700

850

--

---

--

---

Project A Project B

Page 49: Project Management Basic Concepts

Opermgt 345 Shannon January, 200149

Scheduling

• Scheduling : is the process of converting a project action plan into an operating time table.

• Why scheduling ? To answer the following questions:– If each activity goes according to plan , then when will the

project be completed?– Which tasks are most critical to ensure the timely completion

of the project?– Which tasks can be delayed , if necessary , without delaying

project completion and by how much?– More specifically , at what times should each activity begin

and end?– At any given time during the project, how much money

should have been spent?– Is it worthwhile to incur extra costs to accelerate some of the

activities? If so, then which ones?

Page 50: Project Management Basic Concepts

Opermgt 345 Shannon January, 200150

Network Techniques

• PERT• CPM• PERT/CPM is based on a diagram that

represents the entire project as a network of arrows and nodes.

• Two most popular approaches are :– AOA : activity on arrow ( PERT )– AON : activity on node ( CPM )

Page 51: Project Management Basic Concepts

Opermgt 345 Shannon January, 200151

Project Representation

• A network is a form of project representation schemes that use arrows and nodes to represent activities and their relationships.

» A

» 3 days

1 5

Page 52: Project Management Basic Concepts

Opermgt 345 Shannon January, 200152

Rules for constructing a network

1. Arrow represents the activity

2. Circles represents time event ( start, finish)

3. Any activity can be represented by one arrow only

4. All activities having no predecessor should start at the same “start node” of the network.

5. All activities having no successors should finish in one “finish node” in the network.

6. Two nodes can only represent one activity

Page 53: Project Management Basic Concepts

Opermgt 345 Shannon January, 200153

Notes for constructing a network

Page 54: Project Management Basic Concepts

Opermgt 345 Shannon January, 200154

Forward Path Calculation

• Early Start ( ES )

• Early Finish ( EF )

• The earliest possible start time of an activity leaving a node equals the maximum of the early finish time of all activities entering that node

• EF = ES + duration

Page 55: Project Management Basic Concepts

Opermgt 345 Shannon January, 200155

Backward Path Calculation

• Late Finish ( LF )

• Late Start ( LS )

• The latest possible finish time of an activity entering a node equals the minimum of the late start time of all activities leaving that node

• LS = LF - duration

Page 56: Project Management Basic Concepts

Opermgt 345 Shannon January, 200156

4 questions must be answered to begin modeling process:

• What are the major project activities?

• What are the sequencing requirements or constraints for these activities?

• Which activities can be conducted simultaneously?

• What are the estimated time requirements for each activity?

Page 57: Project Management Basic Concepts

Opermgt 345 Shannon January, 200157

Estimating the duration of project activities

• The length of each activity should be approximately in the range 0.5% to 2% of the length of the project.( 1 year -> between a day and week)

• If the number of activities is very large ( above 250 ) then the project should be divided into subprojects.

Page 58: Project Management Basic Concepts

Opermgt 345 Shannon January, 200158

Two approaches are used for estimating the length of an activity

• Deterministic approach– Past data – If not exist :

• Modular approach • Benchmark job technique approach• Parametric technique ( cause-effect analysis , reg. analysis )

• Stochastic approach– Expected time estimation for an activity depends on:– a: Optimistic time : which will be required if execution goes

extremely well– m:most likely time, which will be required if execution is

normal– b: pessimistic time , which will be required if everything goes

badly.– Et(A) = ( a + 4 m + b ) / 6

Page 59: Project Management Basic Concepts

Opermgt 345 Shannon January, 200159

Difference Between PERT and CPM

• PERT used the arrow to represent an activity and CPM used the node.

• PERT used three estimates ( Opti, Pess. and Most likely ) of an activity’s required time, whereas CPM used just a single, best-time estimate.

Page 60: Project Management Basic Concepts

Opermgt 345 Shannon January, 200160

The Top Level Project Tasks

Brainstormthe

Major Tasks

Brainstormthe

Major Tasks

EstablishWork Flow

EstablishWork Flow

AB

C

D E F

G

Page 61: Project Management Basic Concepts

Opermgt 345 Shannon January, 200161

Define Top Level TasksCanoe Example

Site Preparation

Build Dock

Build Building

Finish and Ready for Business

Page 62: Project Management Basic Concepts

Opermgt 345 Shannon January, 200162

Sequence Top Level Tasks

Site Preparation

Build Dock

Build Building

Finish

Page 63: Project Management Basic Concepts

Opermgt 345 Shannon January, 200163

Sub-Tasks

A

B

C

D E F

G

Detailed Tasks

Detailed Tasks

Develop Work Sequence

Page 64: Project Management Basic Concepts

Opermgt 345 Shannon January, 200164

Brainstorm Sub-Tasks

Site Preparation Build Dock Build Building Finish

Dock Site

Building Site

Install Pilings

Build Dock

Foundation

Frame

Roof

Power

Siding

Paint

Order Canoes

Landscape

AssembleCanoes

Open forBusiness

Page 65: Project Management Basic Concepts

Opermgt 345 Shannon January, 200165

Work Breakdown Structure

Top Level Task

2nd LevelTask

2nd LevelTask

2nd LevelTask

2nd LevelTask

3rd LevelTask

3rd LevelTask

3rd LevelTask

3rd LevelTask

3rd LevelTask

3rd LevelTask

3rd LevelTask

3rd LevelTask

3rd LevelTask

Lower Level Tasks

Page 66: Project Management Basic Concepts

Opermgt 345 Shannon January, 200166

Sequence Sub-TasksTask Description Immediate Predecessor

A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canoes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M

Page 67: Project Management Basic Concepts

Opermgt 345 Shannon January, 200167

Build Network Diagram(PERT Chart)

(Activities on Arrows)

1

A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M

Task Predecessor

Page 68: Project Management Basic Concepts

Opermgt 345 Shannon January, 200168

Build Network Diagram(PERT Chart)

1 3A

Prep Dock Site

A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M

Task Predecessor

Page 69: Project Management Basic Concepts

Opermgt 345 Shannon January, 200169

Build Network Diagram(PERT Chart)

1 3A

Prep Dock Site

2

Order

Canoes

J

A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M

Task Predecessor

Page 70: Project Management Basic Concepts

Opermgt 345 Shannon January, 200170

Build Network Diagram(PERT Chart)

1 3A

Prep Dock Site

2

Order

Canoes

4

J

B

Prepare

Hut S

ite

6

D

HutFoundation

A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M

Task Predecessor

Page 71: Project Management Basic Concepts

Opermgt 345 Shannon January, 200171

Build Network Diagram(PERT Chart)

1 3A

Prep Dock Site

2

Order

Canoes

4

J

B

Prepare

Hut S

ite

6

D

HutFoundation

5C

Install Pilings9

E

Build Dock

A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M

Task Predecessor

Page 72: Project Management Basic Concepts

Opermgt 345 Shannon January, 200172

Build Network Diagram(PERT Chart)

1 3A

Prep Dock Site

2

Order

Canoes

4

J

B

Prepare

Hut S

ite

6

D

HutFoundation

5C

Install Pilings9

E

Build Dock

G

Power To H

ut A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M

Task Predecessor

Page 73: Project Management Basic Concepts

Opermgt 345 Shannon January, 200173

Build Network Diagram(PERT Chart)

1 3A

Prep Dock Site

2

Order

Canoes

4

J

B

Prepare

Hut S

ite

6

D

HutFoundation

5C

Install Pilings9

E

Build Dock

G

Power To H

ut

LAssemble Canoes

A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M

Task Predecessor

Page 74: Project Management Basic Concepts

Opermgt 345 Shannon January, 200174

Build Network Diagram(PERT Chart)

1 3A

Prep Dock Site

2

Order

Canoes

4

J

B

Prepare

Hut S

ite

6

D

HutFoundation

5C

Install Pilings9

E

Build Dock

G

Power To H

ut

LAssemble Canoes

7F

Frame Hut

Roof

I

A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M

Task Predecessor

Page 75: Project Management Basic Concepts

Opermgt 345 Shannon January, 200175

Build Network Diagram(PERT Chart)

1 3A

Prep Dock Site

2

Order

Canoes

4

J

B

Prepare

Hut S

ite

6

D

HutFoundation

5C

Install Pilings

7F

Frame Hut8

H

Side Hut

9E

Build Dock

G

Power To H

ut

I Roof

K Paint Hut

LAssemble Canoes

A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M

Task Predecessor

Page 76: Project Management Basic Concepts

Opermgt 345 Shannon January, 200176

Build Network Diagram(PERT Chart)

1 3A

Prep Dock Site

2

Order

Canoes

4

J

B

Prepare

Hut S

ite

6

D

HutFoundation

5C

Install Pilings

7F

Frame Hut8

H

Side Hut

9E

Build Dock

G

Power To H

ut

I Roof

K Paint Hut

LAssemble Canoes

10M

FinishLandscape

11N

Open forBusiness

A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M

Task Predecessor

Page 77: Project Management Basic Concepts

Opermgt 345 Shannon January, 200177

Build Network Diagram(PERT Chart) Canoe ExampleAdd Times

1 3A (3)

Prep Dock Site

2

Order

Canoes

4

J (2)

B (4)

Prepare

Hut S

ite

6

D (3)

HutFoundation

5C (6)

Install Pilings

7F (3)

Frame Hut8

H (2)

Side Hut

9E (4)

Build Dock

G (2)

Power To H

ut

I (2) Roof

K (4)Paint Hut

L (10)Assemble Canoes

10M (4)

FinishLandscape

11N (2)

Open forBusiness

A Prepare Dock Site 3 d B Prepare Hut Site 4 d C Install Dock Pilings 6 d D Foundation for Hut 3 d E Build Dock 4 d F Frame Hut 3 d G Power to Hut 2 d H Side the Hut 2 d I Roof the Hut 3 d J Order Canoes 2 d K Paint Hut 4 d L Assemble Canoes 10 d M Finish Landscaping 4 d NOpen for Business 2 d

Task Description Time

Page 78: Project Management Basic Concepts

Opermgt 345 Shannon January, 200178

Build Network Diagram(PERT Chart)

1 3A

Prep Dock Site

2

Order

Canoes

4

J

B

Prepare

Hut S

ite

6

D

HutFoundation

5C

Install Pilings

7F

Frame Hut8

H

Side Hut

9E

Build Dock

G

Power To H

ut

I Roof

K Paint Hut

LAssemble Canoes

10M

FinishLandscape

11N

Open forBusiness

A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M

Task Predecessor

Page 79: Project Management Basic Concepts

Opermgt 345 Shannon January, 200179

Build Network Diagram(PERT Chart) Canoe ExampleAdd Times

1 3A (3)

Prep Dock Site

2

Order

Canoes

4

J (2)

B (4)

Prepare

Hut S

ite

6

D (3)

HutFoundation

5C (6)

Install Pilings

7F (3)

Frame Hut8

H (2)

Side Hut

9E (4)

Build Dock

G (2)

Power To H

ut

I (2) Roof

K (4)Paint Hut

L (10)Assemble Canoes

10M (4)

FinishLandscape

11N (2)

Open forBusiness

A Prepare Dock Site 3 d B Prepare Hut Site 4 d C Install Dock Pilings 6 d D Foundation for Hut 3 d E Build Dock 4 d F Frame Hut 3 d G Power to Hut 2 d H Side the Hut 2 d I Roof the Hut 3 d J Order Canoes 2 d K Paint Hut 4 d L Assemble Canoes 10 d M Finish Landscaping 4 d NOpen for Business 2 d

Task Description Time

Page 80: Project Management Basic Concepts

Opermgt 345 Shannon January, 200180

Determining Project Length

Option 1: Sum all the task durations: A Prepare Dock Site - 3 d B Prepare Hut Site - 4 d C Install Dock Pilings A 6 d D Foundation for Hut B 3 d E Build Dock C 4 d F Frame Hut D 3 d G Power to Hut D 2 d H Side the Hut F 2 d I Roof the Hut F 3 d J Order Canoes and Receive Canoes - 2 d K Paint Hut H 4 d L Assemble Canoes J 10 d M Finish Landscaping L,I,K,E,G 4 d N Open for Business M 2 d

Sum = 52 daysAnything wrong with this approach?

Page 81: Project Management Basic Concepts

Opermgt 345 Shannon January, 200181

Determining Project Length

Option 2: Determine duration of each network path

Page 82: Project Management Basic Concepts

Opermgt 345 Shannon January, 200182

Network DiagramProject Paths

1 3A (3)

Prep Dock Site

2

Order

Canoes

4

J (2)

B (4)

Prepare

Hut S

ite

6

D (3)

HutFoundation

5C (6)

Install Pilings

7F (3)

Frame Hut8

H (2)

Side Hut

9E (4)

Build Dock

G (2)

Power To H

ut

I (2) Roof

K (4)Paint Hut

L (10)Assemble Canoes

10M (4)

FinishLandscape

11N (2)

Open forBusiness

Paths:

A-C-E-M-N = 19 days

Page 83: Project Management Basic Concepts

Opermgt 345 Shannon January, 200183

1 3A (3)

Prep Dock Site

2

Order

Canoes

4

J (2)

B (4)

Prepare

Hut S

ite

6

D (3)

HutFoundation

5C (6)

Install Pilings

7F (3)

Frame Hut8

H (2)

Side Hut

9E (4)

Build Dock

G (2)

Power To H

ut

I (2) Roof

K (4)Paint Hut

L (10)Assemble Canoes

10M (4)

FinishLandscape

11N (2)

Open forBusiness

Paths:

A-C-E-M-N = 19 daysB-D-F-H-K-M-N = 22 days

Network DiagramProject Paths

Page 84: Project Management Basic Concepts

Opermgt 345 Shannon January, 200184

1 3A (3)

Prep Dock Site

2

Order

Canoes

4

J (2)

B (4)

Prepare

Hut S

ite

6

D (3)

HutFoundation

5C (6)

Install Pilings

7F (3)

Frame Hut8

H (2)

Side Hut

9E (4)

Build Dock

G (2)

Power To H

ut

I (2) Roof

K (4)Paint Hut

L (10)Assemble Canoes

10M (4)

FinishLandscape

11N (2)

Open forBusiness

Paths:

A-C-E-M-N = 19 daysB-D-F-H-K-M-N = 22 daysB-D-F-I-M-N = 18 days

Network DiagramProject Paths

Page 85: Project Management Basic Concepts

Opermgt 345 Shannon January, 200185

1 3A (3)

Prep Dock Site

2

Order

Canoes

4

J (2)

B (4)

Prepare

Hut S

ite

6

D (3)

HutFoundation

5C (6)

Install Pilings

7F (3)

Frame Hut8

H (2)

Side Hut

9E (4)

Build Dock

G (2)

Power To H

ut

I (2) Roof

K (4)Paint Hut

L (10)Assemble Canoes

10M (4)

FinishLandscape

11N (2)

Open forBusiness

Paths:

A-C-E-M-N = 19 daysB-D-F-H-K-M-N = 22 daysB-D-F-J-M-N = 18 daysB-D-G-M-N = 15 days

Network DiagramProject Paths

Page 86: Project Management Basic Concepts

Opermgt 345 Shannon January, 200186

1 3A (3)

Prep Dock Site

2

Order

Canoes

4

J (2)

B (4)

Prepare

Hut S

ite

6

D (3)

HutFoundation

5C (6)

Install Pilings

7F (3)

Frame Hut8

H (2)

Side Hut

9E (4)

Build Dock

G (2)

Power To H

ut

J (2) Roof

K (4)Paint Hut

L (10)Assemble Canoes

10M (4)

FinishLandscape

11N (2)

Open forBusiness

Paths:

A-C-E-M-N = 19 daysB-D-F-H-K-M-N = 22 daysB-D-F-J-M-N = 18 daysB-D-G-M-N = 15 daysJ-L-M-N = 18 days

Network DiagramProject Paths

Page 87: Project Management Basic Concepts

Opermgt 345 Shannon January, 200187

Critical Path

The Critical Path is the Longest PathThrough the Network.

Page 88: Project Management Basic Concepts

Opermgt 345 Shannon January, 200188

1 3A (3)

Prep Dock Site

2

Order

Canoes

4

J (2)

B (4)

Prepare

Hut S

ite

6

D (3)

HutFoundation

5C (6)

Install Pilings

7F (3)

Frame Hut8

H (2)

Side Hut

9E (4)

Build Dock

G (2)

Power To H

ut

I (2) Roof

K (4)Paint Hut

L (10)Assemble Canoes

10M (4)

FinishLandscape

11N (2)

Open forBusiness

Network Diagram Canoe ExampleCritical Path

Paths:

A-C-E-M-N = 19 daysB-D-F-H-K-M-N = 22 daysB-D-F-J-M-N = 18 daysB-D-G-M-N = 15 daysJ-L-M-N = 18 days

Page 89: Project Management Basic Concepts

Opermgt 345 Shannon January, 200189

Completed Task Timetable

Task Description Immediate Predecessor Time ES LS EF LF

A Prepare Dock Site - 3 d 0 3 3 6 B Prepare Hut Site - 4 d 0 0 4 4 C Install Dock Pilings A 6 d 3 6 9 12 D Foundation for Hut B 3 d 4 4 7 7 E Build Dock C 4 d 9 12 13 16 F Frame Hut D 3 d 7 7 10 10 G Power to Hut D 2 d 7 14 9 16 H Side the Hut F 2 d 10 10 12 12 I Roof the Hut F 3 d 10 13 13 16 J Order Canoes and Receive Canoes - 2 d 0 4 2 6 K Paint Hut H 4 d 12 12 16 16 L Assemble Canoes J 10 d 2 6 12 16 M Finish Landscaping L,I,K,E,G 4 d 16 16 20 20 N Open for Business M 2 d 20 20 22 22

Page 90: Project Management Basic Concepts

Opermgt 345 Shannon January, 200190

Slack Time

Total Slack = The length of time an activity can bedelayed without affecting the projectcompletion time.

Total Slack = Late Start - Early Start

Total Slack = Late Finish - Early FinishFor Critical Activities

Free Slack = The time a task can be delayed without delaying another task.

Page 91: Project Management Basic Concepts

Opermgt 345 Shannon January, 200191

Slack Time

Task Description Immediate Predecessor Time ES LS EF LF Slack

A Prepare Dock Site - 3 d 0 3 3 6 3 B Prepare Hut Site - 4 d 0 0 4 4 0 C Install Dock Pilings A 6 d 3 6 9 12 3 D Foundation for Hut B 3 d 4 4 7 7 0 E Build Dock C 4 d 9 12 13 16 3 F Frame Hut D 3 d 7 7 10 10 0 G Power to Hut D 2 d 7 14 9 16 7 H Side the Hut F 2 d 10 10 12 12 0 I Roof the Hut F 3 d 10 13 13 16 3 J Order Canoes and Receive Canoes - 2 d 0 4 2 6 4 K Paint Hut H 4 d 12 12 16 16 0 L Assemble Canoes J 10 d 2 6 12 16 4 M Finish Landscaping L,I,K,E,G 4 d 16 16 20 20 0 N Open for Business M 2 d 20 20 22 22 0

Page 92: Project Management Basic Concepts

Opermgt 345 Shannon January, 200192

Critical Path Tasks

Critical Path = All tasks with slack = zero

Page 93: Project Management Basic Concepts

Opermgt 345 Shannon January, 200193

Critical Path Tasks

Task Description Immediate Predecessor Time ES LS EF LF Slack

A Prepare Dock Site - 3 d 0 3 3 6 3 B Prepare Hut Site - 4 d 0 0 4 4 0 *** C Install Dock Pilings A 6 d 3 6 9 12 3 D Foundation for Hut B 3 d 4 4 7 7 0 *** E Build Dock C 4 d 9 12 13 16 3 F Frame Hut D 3 d 7 7 10 10 0 *** G Power to Hut D 2 d 7 14 9 16 7 H Side the Hut F 2 d 10 10 12 12 0 *** I Roof the Hut F 3 d 10 13 13 16 3 J Order Canoes and Receive Canoes - 2 d 0 4 2 6 4 K Paint Hut H 4 d 12 12 16 16 0 *** L Assemble Canoes J 10 d 2 6 12 16 4 M Finish Landscaping L,I,K,E,G 4 d 16 16 20 20 0 *** N Open for Business M 2 d 20 20 22 22 0 ***

Critical Path = B - D - F - H - K - M - N

Page 94: Project Management Basic Concepts

Opermgt 345 Shannon January, 200194

CPM ( A-O-N) : ExampleCPM network for computer Design Project:

Activity Designation Pred. Dura

Design A - 21

Build prototype B A 4

Evaluate equipment C A 7

Test Prototype D B 2

Write equipment report E C,D 5

Write methods report F C,D 8

Write final report G E,F 2

Page 95: Project Management Basic Concepts

Opermgt 345 Shannon January, 200195

A21

C7

B4

F8

D2

E5

G2

Page 96: Project Management Basic Concepts

Opermgt 345 Shannon January, 200196

Determine the Critical path

• Forward pass:– ES : the earliest possible time the activity can

begin.– EF : the early start time the time needed to

complete the activity. ( EF = ES + Dur ) Backwards pass