project management basic concepts
DESCRIPTION
Project Management Basic Concepts. What is a Project?. A Project is a series of activities and tasks that: Have a specific tasks and activities to be completed with certain objectives. Have a defined start and end dates Have funding limits (if applicable) Consume Resources. - PowerPoint PPT PresentationTRANSCRIPT
Opermgt 345 Shannon January, 20011
Project ManagementBasic Concepts
Opermgt 345 Shannon January, 20012
What is a Project?
A Project is a series of activities and tasks that:
1. Have a specific tasks and activities to be completed with certain objectives.
2. Have a defined start and end dates
3. Have funding limits (if applicable)
4. Consume Resources
Opermgt 345 Shannon January, 20013
Typical Project Structure
ProjectDefinition
ProjectDefinition
ProjectPlanning
ProjectPlanning
ProjectImplementation
ProjectImplementation
ProjectMonitoring
ProjectMonitoring
ProjectAdjustment
ProjectAdjustment
ProjectEvaluation
ProjectEvaluation
Opermgt 345 Shannon January, 20014
Project Life CycleR
esou
rces
and
Eff
ort
Phase 1
•Goals•Scope•Baseline•Requirements•Feasibility•Desirability
ConceptualDesign
Phase 2
AdvancedDevelopment
•Plan•Budget•Schedule•Management Commitment
Phase 3
DetailedDesign
•Define Responsibility•Team•Organization Structure•Detailed Plan•Kickoff
Phase 4
ProjectImplementation
•Manage•Measure•Control•Update and Modify Plan•Problem Solve
ProjectTermination
Phase 5
•Closeout•Document•Suggest Improvements•Reassign•Dissolve Project Team
Opermgt 345 Shannon January, 20015
Successful Projects
A successful project is one which achieves the following objectives:– Completed On Time– Completed Within Cost– Meets Performance Criteria– Minimum Disruption of the Main Work of the
Organization– Effective Utilization of Resources
Opermgt 345 Shannon January, 20016
The Triple Play ofProject Management
Constraints
Time Cost
Performance
Opermgt 345 Shannon January, 20017
Triple Constraint Trade-offs
Budget
ScheduleEarly Late TIME
$
Performance Specifications
Better
Worse
Opermgt 345 Shannon January, 20018
Major causes of failure
Selection of a unsound projectSelecting the wrong person as a project
managerLack of support from upper managementMisused management techniquesProject termination not planned
Opermgt 345 Shannon January, 20019
Project Definition
Build Canoe Rental Building onCoeur d A’lene Lake
Opermgt 345 Shannon January, 200110
Form Project Team
•Select Project Leader
•Identify Key People
•Gain Management Commitment
•Define Project Team Operating Rules
Opermgt 345 Shannon January, 200111
Project Manager
Opermgt 345 Shannon January, 200112
Project Manager Skills• Scheduling and time mgt. skills
• Technical skills ( scope of project )
• Leadership skills ( goals, performance measures)
• Resource mgt., human relationship skills.
• Communication skills
• Negotiation skills
• Marketing, Contracting, customer relationship skills
• Budgeting and cost skills.
Opermgt 345 Shannon January, 200113
Major Interactions of project stakeholders
Project Manager
Government agencies
ConsultantsTop Management
Financial Managers Client
Project Team Other Organization Subcontractors
Opermgt 345 Shannon January, 200114
Project Manager Responsibilities
1. Responsibility to the parent Org.
2. Responsibility to the project and client
3. Responsibility to the member of the project team
Opermgt 345 Shannon January, 200115
Selecting Project ManagerList of some of the most popular attributes:
• A strong technical background
• A hard-nosed manager
• A matured individual
• Someone who is currently avaiable
• Someone on good terms with senior executive
• A person who can keep the project team happy
• One who has worked in several departments
• A person who can walk on ( or part ) the waters.
Opermgt 345 Shannon January, 200116
Selecting the PM
• Credibility– Technical credibility ( technical knowledge )– Administrative credibility ( managing resources( money, people,
material) keeping the project on scheule.
• Sensitivity– It is related to the ability of the manager to discover the problems
at early stages and solve the team’s problems if we have some conflects
• Leadership and management style– Leadership is defined as the ability of affecting others in away
that gurantees the project profitability to the org. and sociey.
• Ability to work under stress
Opermgt 345 Shannon January, 200117
Project Planning
• There are several reasons why we must use considerable care when planning projects
• The primary purpose of planning is to establish a set of directions in sufficient detail to tell the project team exactly :– What must be done?– When it must be done?– What resources to use ?
Opermgt 345 Shannon January, 200118
Project plan Elements:
• Overview : – A short summary of the objectives and scope of
the project– Directed to top mgt. and contains a statement of
goals of the project– A description of the managerial structure that
will be used for the project.– A list of major milestones in the project schdule.
Opermgt 345 Shannon January, 200119
Project plan Elements:
• Objectives:– More detailed statement of general goals noted
on the overview section.– The statement should include profit and
competitive aims as well as technical goals.
• General approach:– Describes both the managerial ( style of mgt. )
and the technical approaches ( required equipments, technology ) to the work.
Opermgt 345 Shannon January, 200120
Project plan Elements:
• Contractual aspects: ( list for )– All reporting requirements– Customer-supplied resources.– Advisory commitees– Project review– Cancellation procedures.– Specific management agreements– subcontracts
Opermgt 345 Shannon January, 200121
Project plan Elements:
• Schedules:– Various schedules.– Lists all milestones events.– All tasks, and their durations…..
• Resources:– The budget– Both capital and expense requirements are
detailed by task. ( Project budget )– Cost monitoring and control procedures.
Opermgt 345 Shannon January, 200122
Project plan Elements:
• Personnel :– Expected personnel requirements– Special skills needed– Types of training needed– Possible recruiting problems.– Legal and political restrictions.
Opermgt 345 Shannon January, 200123
Project plan Elements:
• Evaluation Methods:– Every project should be evaluated against
standards and by methods established at the project inception.
– This section include :• A brief description of the procedure to be followed
in monitoring , collecting, storing, and evaluating the history of the project.
Opermgt 345 Shannon January, 200124
Project plan Elements:
• Potential problems:– External and internal potential problems.
Opermgt 345 Shannon January, 200125
Work-Breakdown- Structure (WBS)
• It is a result family tree , subdivision of the major tasks( hw, services , etc ) and the data required to produce the final product , it acts as a vehicle for breaking down the work into smaller elements.
Opermgt 345 Shannon January, 200126
Work-Breakdown- Structure (WBS)
• We have 2 types of WBS:– Managerial level
– Technical level
Work Breakdown Structure.htm
Opermgt 345 Shannon January, 200127
Earned Value Analysis• It is a continuous comparison between the
plan of the project data and the actual data.
Budgeted and Committed Cost:
Variance = Budgeted cost – committed cost
Variance (+ve ) = Unconsumed Cost
Variance ( -ve ) = Over spend activities
Opermgt 345 Shannon January, 200128
Cost and Schedule Variances
Opermgt 345 Shannon January, 200129
Cost and Schedule Variances
Opermgt 345 Shannon January, 200130
BCWSBudgeted Cost of Work Schedule
A B C D E F G H I J
X1 X2 X3 X4 X5 X6 X7 X8 X9 X10
NOW
BCWS = X1 + X2 + X3 + X4 + X5 $
This is the sum of all the costs up to the specific activity that is stated in budget plan.
Opermgt 345 Shannon January, 200131
BCWPBudgeted Cost of Work Performed
BCWP = X1 + X2 + X3 + 0.8 X4 + 0.5 X5 $
This is the sum of all the costs up to the specific activity in relation with its completion percentage.
A B C D E
100%
X1
100%
X2
100%
X3
80%
X4
50%
X5
Opermgt 345 Shannon January, 200132
ACWPActual Cost of Work Performed
ACWP = Actual cost of work done.
This is the total costs of the work done on reality provided by project manager on the financial monitor.
Opermgt 345 Shannon January, 200133
Opermgt 345 Shannon January, 200134
• If BCWP > BCWS ( over spend )
• If BCWP < BCWS ( time is late -ve )
• If BCWP > BCWS
( +ve time is more than sufficient )
Opermgt 345 Shannon January, 200135
Opermgt 345 Shannon January, 200136
Forecasting• It is the process of prediction of the future
events.
• Benefits of forecasting:1. To estimate the cost of remaining parts
of a project ( forecasted value ).
2. To identify the source and places of certain problems in the budget plan.
3. It is a tool for corrective actions.
Opermgt 345 Shannon January, 200137
ForecastingMathematical Expressions
• The Cost Performance Index ( CPI ):
CPI = BCWP / ACWP
• It gives a good indication whether the project is performing financially well or not.
• CPI > 1 : Good performance.
• CPI < 1 : Bad performance ( shortages
• Overspend ).
Opermgt 345 Shannon January, 200138
ForecastingMathematical Expressions
• The Schedule Performance Index ( SPI ):
SPI = BCWP / BCWS
• It is a good indicator for the project timing.
• SPI > 1 : Good performance.
• SPI < 1 : Bad performance (Poor ).
Opermgt 345 Shannon January, 200139
ForecastingMathematical Expressions
• Budgeting Cost to Completion ( BCC ):
• The Amount of money needed to completion.
• BCC = BAC – BCWP
• It is defined as the amount of money required to complete a project where it is partially completed ( remaining money ).
Opermgt 345 Shannon January, 200140
ForecastingMathematical Expressions
• Estimated Cost to Completion ( ECC ):
• Its more realistic value than budgeted.
• ECC = BCC / CPI
• It depends on CPI which is a by product of the actual cost of work performed.
• Forecasted Cost to Completion ( FCC ):
• FCC = ACWP + ECC
Opermgt 345 Shannon January, 200141
Opermgt 345 Shannon January, 200142
Example
• The R&D department of a company has been developing a new product line, the project manager is concerned whether the following provided data is exhibiting a good project performance, calculate the following and comment on the project status to convince the project manager.
1. CPI,BCC, ECC, SPI, FCC.
Opermgt 345 Shannon January, 200143
Work Package
Budgeted Cost Completion Time month
Actual Cost
% Complete
B49 20000 1 23500 100%
B50 20000 2 20500 100%
B51 37000 3 23000 70%
B52 27000 4 27000 100%
B53 12000 5 4500 60%
B54 28000 6 18500 75%
B55 40000 7 ---- ----
184000
Opermgt 345 Shannon January, 200144
Solution• BCWS = 20000 + 20000 + 37000 + 27000 + 12000 + 28000 =
144000 $• ACWP = 23500+20500+23000+27000+4500+18500 =
117000 $• BCWP = 20000 + 20000 + ( 37000 x 0.7 ) + 27000 +
( 12000 x 0.6 ) + ( 28000 x 0.75 ) =
119900 $
CPI = BCWP / ACWP = 119900 / 117000 = 1.02 good performance.
Opermgt 345 Shannon January, 200145
• BAC = Budget at Completion = 184000• BCC = BAC – BCWP = 184000 – 119900 =
64100$• ECC = BCC / CPI = 64100/1.02 = 62843.14
$• SPI = BCWP / BCWS = 119900 / 144000 =
0.832 < 1 Poor performance according to time.
• FCC = ACWP + ECC = 117000 + 62843.14
= 179843.14 $
Opermgt 345 Shannon January, 200146
Comments• We do not have any financial problem i.e the
budgeted cost (money resources) is larger than the forecasted values, we conclude that the money is available , it is more than sufficient as the indicators were positive, the only problem we have is the time.
Opermgt 345 Shannon January, 200147
Comparing ProjectsProject SPI CPI
A 0.78 (2) 0.68 (2)
B 0.96 (1) 0.98 (1)
C 0.46 (3) 0.51 (4)
D 0.46 (4) 0.64 (3)
Opermgt 345 Shannon January, 200148
Problem : Compare between the following projects according to the time and cost consumed:
WP budget actual %comp
A 435 395 100%
B 320 409 90%
C 125 -
d 570 -
WP budget actual %comp
A 820 800 100%
B 750 920 90%
C 1000 730 65%
D
E
700
850
--
---
--
---
Project A Project B
Opermgt 345 Shannon January, 200149
Scheduling
• Scheduling : is the process of converting a project action plan into an operating time table.
• Why scheduling ? To answer the following questions:– If each activity goes according to plan , then when will the
project be completed?– Which tasks are most critical to ensure the timely completion
of the project?– Which tasks can be delayed , if necessary , without delaying
project completion and by how much?– More specifically , at what times should each activity begin
and end?– At any given time during the project, how much money
should have been spent?– Is it worthwhile to incur extra costs to accelerate some of the
activities? If so, then which ones?
Opermgt 345 Shannon January, 200150
Network Techniques
• PERT• CPM• PERT/CPM is based on a diagram that
represents the entire project as a network of arrows and nodes.
• Two most popular approaches are :– AOA : activity on arrow ( PERT )– AON : activity on node ( CPM )
Opermgt 345 Shannon January, 200151
Project Representation
• A network is a form of project representation schemes that use arrows and nodes to represent activities and their relationships.
» A
» 3 days
1 5
Opermgt 345 Shannon January, 200152
Rules for constructing a network
1. Arrow represents the activity
2. Circles represents time event ( start, finish)
3. Any activity can be represented by one arrow only
4. All activities having no predecessor should start at the same “start node” of the network.
5. All activities having no successors should finish in one “finish node” in the network.
6. Two nodes can only represent one activity
Opermgt 345 Shannon January, 200153
Notes for constructing a network
Opermgt 345 Shannon January, 200154
Forward Path Calculation
• Early Start ( ES )
• Early Finish ( EF )
• The earliest possible start time of an activity leaving a node equals the maximum of the early finish time of all activities entering that node
• EF = ES + duration
Opermgt 345 Shannon January, 200155
Backward Path Calculation
• Late Finish ( LF )
• Late Start ( LS )
• The latest possible finish time of an activity entering a node equals the minimum of the late start time of all activities leaving that node
• LS = LF - duration
Opermgt 345 Shannon January, 200156
4 questions must be answered to begin modeling process:
• What are the major project activities?
• What are the sequencing requirements or constraints for these activities?
• Which activities can be conducted simultaneously?
• What are the estimated time requirements for each activity?
Opermgt 345 Shannon January, 200157
Estimating the duration of project activities
• The length of each activity should be approximately in the range 0.5% to 2% of the length of the project.( 1 year -> between a day and week)
• If the number of activities is very large ( above 250 ) then the project should be divided into subprojects.
Opermgt 345 Shannon January, 200158
Two approaches are used for estimating the length of an activity
• Deterministic approach– Past data – If not exist :
• Modular approach • Benchmark job technique approach• Parametric technique ( cause-effect analysis , reg. analysis )
• Stochastic approach– Expected time estimation for an activity depends on:– a: Optimistic time : which will be required if execution goes
extremely well– m:most likely time, which will be required if execution is
normal– b: pessimistic time , which will be required if everything goes
badly.– Et(A) = ( a + 4 m + b ) / 6
Opermgt 345 Shannon January, 200159
Difference Between PERT and CPM
• PERT used the arrow to represent an activity and CPM used the node.
• PERT used three estimates ( Opti, Pess. and Most likely ) of an activity’s required time, whereas CPM used just a single, best-time estimate.
Opermgt 345 Shannon January, 200160
The Top Level Project Tasks
Brainstormthe
Major Tasks
Brainstormthe
Major Tasks
EstablishWork Flow
EstablishWork Flow
AB
C
D E F
G
Opermgt 345 Shannon January, 200161
Define Top Level TasksCanoe Example
Site Preparation
Build Dock
Build Building
Finish and Ready for Business
Opermgt 345 Shannon January, 200162
Sequence Top Level Tasks
Site Preparation
Build Dock
Build Building
Finish
Opermgt 345 Shannon January, 200163
Sub-Tasks
A
B
C
D E F
G
Detailed Tasks
Detailed Tasks
Develop Work Sequence
Opermgt 345 Shannon January, 200164
Brainstorm Sub-Tasks
Site Preparation Build Dock Build Building Finish
Dock Site
Building Site
Install Pilings
Build Dock
Foundation
Frame
Roof
Power
Siding
Paint
Order Canoes
Landscape
AssembleCanoes
Open forBusiness
Opermgt 345 Shannon January, 200165
Work Breakdown Structure
Top Level Task
2nd LevelTask
2nd LevelTask
2nd LevelTask
2nd LevelTask
3rd LevelTask
3rd LevelTask
3rd LevelTask
3rd LevelTask
3rd LevelTask
3rd LevelTask
3rd LevelTask
3rd LevelTask
3rd LevelTask
Lower Level Tasks
Opermgt 345 Shannon January, 200166
Sequence Sub-TasksTask Description Immediate Predecessor
A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canoes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M
Opermgt 345 Shannon January, 200167
Build Network Diagram(PERT Chart)
(Activities on Arrows)
1
A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M
Task Predecessor
Opermgt 345 Shannon January, 200168
Build Network Diagram(PERT Chart)
1 3A
Prep Dock Site
A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M
Task Predecessor
Opermgt 345 Shannon January, 200169
Build Network Diagram(PERT Chart)
1 3A
Prep Dock Site
2
Order
Canoes
J
A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M
Task Predecessor
Opermgt 345 Shannon January, 200170
Build Network Diagram(PERT Chart)
1 3A
Prep Dock Site
2
Order
Canoes
4
J
B
Prepare
Hut S
ite
6
D
HutFoundation
A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M
Task Predecessor
Opermgt 345 Shannon January, 200171
Build Network Diagram(PERT Chart)
1 3A
Prep Dock Site
2
Order
Canoes
4
J
B
Prepare
Hut S
ite
6
D
HutFoundation
5C
Install Pilings9
E
Build Dock
A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M
Task Predecessor
Opermgt 345 Shannon January, 200172
Build Network Diagram(PERT Chart)
1 3A
Prep Dock Site
2
Order
Canoes
4
J
B
Prepare
Hut S
ite
6
D
HutFoundation
5C
Install Pilings9
E
Build Dock
G
Power To H
ut A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M
Task Predecessor
Opermgt 345 Shannon January, 200173
Build Network Diagram(PERT Chart)
1 3A
Prep Dock Site
2
Order
Canoes
4
J
B
Prepare
Hut S
ite
6
D
HutFoundation
5C
Install Pilings9
E
Build Dock
G
Power To H
ut
LAssemble Canoes
A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M
Task Predecessor
Opermgt 345 Shannon January, 200174
Build Network Diagram(PERT Chart)
1 3A
Prep Dock Site
2
Order
Canoes
4
J
B
Prepare
Hut S
ite
6
D
HutFoundation
5C
Install Pilings9
E
Build Dock
G
Power To H
ut
LAssemble Canoes
7F
Frame Hut
Roof
I
A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M
Task Predecessor
Opermgt 345 Shannon January, 200175
Build Network Diagram(PERT Chart)
1 3A
Prep Dock Site
2
Order
Canoes
4
J
B
Prepare
Hut S
ite
6
D
HutFoundation
5C
Install Pilings
7F
Frame Hut8
H
Side Hut
9E
Build Dock
G
Power To H
ut
I Roof
K Paint Hut
LAssemble Canoes
A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M
Task Predecessor
Opermgt 345 Shannon January, 200176
Build Network Diagram(PERT Chart)
1 3A
Prep Dock Site
2
Order
Canoes
4
J
B
Prepare
Hut S
ite
6
D
HutFoundation
5C
Install Pilings
7F
Frame Hut8
H
Side Hut
9E
Build Dock
G
Power To H
ut
I Roof
K Paint Hut
LAssemble Canoes
10M
FinishLandscape
11N
Open forBusiness
A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M
Task Predecessor
Opermgt 345 Shannon January, 200177
Build Network Diagram(PERT Chart) Canoe ExampleAdd Times
1 3A (3)
Prep Dock Site
2
Order
Canoes
4
J (2)
B (4)
Prepare
Hut S
ite
6
D (3)
HutFoundation
5C (6)
Install Pilings
7F (3)
Frame Hut8
H (2)
Side Hut
9E (4)
Build Dock
G (2)
Power To H
ut
I (2) Roof
K (4)Paint Hut
L (10)Assemble Canoes
10M (4)
FinishLandscape
11N (2)
Open forBusiness
A Prepare Dock Site 3 d B Prepare Hut Site 4 d C Install Dock Pilings 6 d D Foundation for Hut 3 d E Build Dock 4 d F Frame Hut 3 d G Power to Hut 2 d H Side the Hut 2 d I Roof the Hut 3 d J Order Canoes 2 d K Paint Hut 4 d L Assemble Canoes 10 d M Finish Landscaping 4 d NOpen for Business 2 d
Task Description Time
Opermgt 345 Shannon January, 200178
Build Network Diagram(PERT Chart)
1 3A
Prep Dock Site
2
Order
Canoes
4
J
B
Prepare
Hut S
ite
6
D
HutFoundation
5C
Install Pilings
7F
Frame Hut8
H
Side Hut
9E
Build Dock
G
Power To H
ut
I Roof
K Paint Hut
LAssemble Canoes
10M
FinishLandscape
11N
Open forBusiness
A Prepare Dock Site - B Prepare Hut Site - C Install Dock Pilings A D Foundation for Hut B E Build Dock C F Frame Hut D G Power to Hut D H Side the Hut F I Roof the Hut F J Order Canoes and Receive Canes - K Paint Hut H L Assemble Canoes J M Finish Landscaping L,I,K,E,G N Open for Business M
Task Predecessor
Opermgt 345 Shannon January, 200179
Build Network Diagram(PERT Chart) Canoe ExampleAdd Times
1 3A (3)
Prep Dock Site
2
Order
Canoes
4
J (2)
B (4)
Prepare
Hut S
ite
6
D (3)
HutFoundation
5C (6)
Install Pilings
7F (3)
Frame Hut8
H (2)
Side Hut
9E (4)
Build Dock
G (2)
Power To H
ut
I (2) Roof
K (4)Paint Hut
L (10)Assemble Canoes
10M (4)
FinishLandscape
11N (2)
Open forBusiness
A Prepare Dock Site 3 d B Prepare Hut Site 4 d C Install Dock Pilings 6 d D Foundation for Hut 3 d E Build Dock 4 d F Frame Hut 3 d G Power to Hut 2 d H Side the Hut 2 d I Roof the Hut 3 d J Order Canoes 2 d K Paint Hut 4 d L Assemble Canoes 10 d M Finish Landscaping 4 d NOpen for Business 2 d
Task Description Time
Opermgt 345 Shannon January, 200180
Determining Project Length
Option 1: Sum all the task durations: A Prepare Dock Site - 3 d B Prepare Hut Site - 4 d C Install Dock Pilings A 6 d D Foundation for Hut B 3 d E Build Dock C 4 d F Frame Hut D 3 d G Power to Hut D 2 d H Side the Hut F 2 d I Roof the Hut F 3 d J Order Canoes and Receive Canoes - 2 d K Paint Hut H 4 d L Assemble Canoes J 10 d M Finish Landscaping L,I,K,E,G 4 d N Open for Business M 2 d
Sum = 52 daysAnything wrong with this approach?
Opermgt 345 Shannon January, 200181
Determining Project Length
Option 2: Determine duration of each network path
Opermgt 345 Shannon January, 200182
Network DiagramProject Paths
1 3A (3)
Prep Dock Site
2
Order
Canoes
4
J (2)
B (4)
Prepare
Hut S
ite
6
D (3)
HutFoundation
5C (6)
Install Pilings
7F (3)
Frame Hut8
H (2)
Side Hut
9E (4)
Build Dock
G (2)
Power To H
ut
I (2) Roof
K (4)Paint Hut
L (10)Assemble Canoes
10M (4)
FinishLandscape
11N (2)
Open forBusiness
Paths:
A-C-E-M-N = 19 days
Opermgt 345 Shannon January, 200183
1 3A (3)
Prep Dock Site
2
Order
Canoes
4
J (2)
B (4)
Prepare
Hut S
ite
6
D (3)
HutFoundation
5C (6)
Install Pilings
7F (3)
Frame Hut8
H (2)
Side Hut
9E (4)
Build Dock
G (2)
Power To H
ut
I (2) Roof
K (4)Paint Hut
L (10)Assemble Canoes
10M (4)
FinishLandscape
11N (2)
Open forBusiness
Paths:
A-C-E-M-N = 19 daysB-D-F-H-K-M-N = 22 days
Network DiagramProject Paths
Opermgt 345 Shannon January, 200184
1 3A (3)
Prep Dock Site
2
Order
Canoes
4
J (2)
B (4)
Prepare
Hut S
ite
6
D (3)
HutFoundation
5C (6)
Install Pilings
7F (3)
Frame Hut8
H (2)
Side Hut
9E (4)
Build Dock
G (2)
Power To H
ut
I (2) Roof
K (4)Paint Hut
L (10)Assemble Canoes
10M (4)
FinishLandscape
11N (2)
Open forBusiness
Paths:
A-C-E-M-N = 19 daysB-D-F-H-K-M-N = 22 daysB-D-F-I-M-N = 18 days
Network DiagramProject Paths
Opermgt 345 Shannon January, 200185
1 3A (3)
Prep Dock Site
2
Order
Canoes
4
J (2)
B (4)
Prepare
Hut S
ite
6
D (3)
HutFoundation
5C (6)
Install Pilings
7F (3)
Frame Hut8
H (2)
Side Hut
9E (4)
Build Dock
G (2)
Power To H
ut
I (2) Roof
K (4)Paint Hut
L (10)Assemble Canoes
10M (4)
FinishLandscape
11N (2)
Open forBusiness
Paths:
A-C-E-M-N = 19 daysB-D-F-H-K-M-N = 22 daysB-D-F-J-M-N = 18 daysB-D-G-M-N = 15 days
Network DiagramProject Paths
Opermgt 345 Shannon January, 200186
1 3A (3)
Prep Dock Site
2
Order
Canoes
4
J (2)
B (4)
Prepare
Hut S
ite
6
D (3)
HutFoundation
5C (6)
Install Pilings
7F (3)
Frame Hut8
H (2)
Side Hut
9E (4)
Build Dock
G (2)
Power To H
ut
J (2) Roof
K (4)Paint Hut
L (10)Assemble Canoes
10M (4)
FinishLandscape
11N (2)
Open forBusiness
Paths:
A-C-E-M-N = 19 daysB-D-F-H-K-M-N = 22 daysB-D-F-J-M-N = 18 daysB-D-G-M-N = 15 daysJ-L-M-N = 18 days
Network DiagramProject Paths
Opermgt 345 Shannon January, 200187
Critical Path
The Critical Path is the Longest PathThrough the Network.
Opermgt 345 Shannon January, 200188
1 3A (3)
Prep Dock Site
2
Order
Canoes
4
J (2)
B (4)
Prepare
Hut S
ite
6
D (3)
HutFoundation
5C (6)
Install Pilings
7F (3)
Frame Hut8
H (2)
Side Hut
9E (4)
Build Dock
G (2)
Power To H
ut
I (2) Roof
K (4)Paint Hut
L (10)Assemble Canoes
10M (4)
FinishLandscape
11N (2)
Open forBusiness
Network Diagram Canoe ExampleCritical Path
Paths:
A-C-E-M-N = 19 daysB-D-F-H-K-M-N = 22 daysB-D-F-J-M-N = 18 daysB-D-G-M-N = 15 daysJ-L-M-N = 18 days
Opermgt 345 Shannon January, 200189
Completed Task Timetable
Task Description Immediate Predecessor Time ES LS EF LF
A Prepare Dock Site - 3 d 0 3 3 6 B Prepare Hut Site - 4 d 0 0 4 4 C Install Dock Pilings A 6 d 3 6 9 12 D Foundation for Hut B 3 d 4 4 7 7 E Build Dock C 4 d 9 12 13 16 F Frame Hut D 3 d 7 7 10 10 G Power to Hut D 2 d 7 14 9 16 H Side the Hut F 2 d 10 10 12 12 I Roof the Hut F 3 d 10 13 13 16 J Order Canoes and Receive Canoes - 2 d 0 4 2 6 K Paint Hut H 4 d 12 12 16 16 L Assemble Canoes J 10 d 2 6 12 16 M Finish Landscaping L,I,K,E,G 4 d 16 16 20 20 N Open for Business M 2 d 20 20 22 22
Opermgt 345 Shannon January, 200190
Slack Time
Total Slack = The length of time an activity can bedelayed without affecting the projectcompletion time.
Total Slack = Late Start - Early Start
Total Slack = Late Finish - Early FinishFor Critical Activities
Free Slack = The time a task can be delayed without delaying another task.
Opermgt 345 Shannon January, 200191
Slack Time
Task Description Immediate Predecessor Time ES LS EF LF Slack
A Prepare Dock Site - 3 d 0 3 3 6 3 B Prepare Hut Site - 4 d 0 0 4 4 0 C Install Dock Pilings A 6 d 3 6 9 12 3 D Foundation for Hut B 3 d 4 4 7 7 0 E Build Dock C 4 d 9 12 13 16 3 F Frame Hut D 3 d 7 7 10 10 0 G Power to Hut D 2 d 7 14 9 16 7 H Side the Hut F 2 d 10 10 12 12 0 I Roof the Hut F 3 d 10 13 13 16 3 J Order Canoes and Receive Canoes - 2 d 0 4 2 6 4 K Paint Hut H 4 d 12 12 16 16 0 L Assemble Canoes J 10 d 2 6 12 16 4 M Finish Landscaping L,I,K,E,G 4 d 16 16 20 20 0 N Open for Business M 2 d 20 20 22 22 0
Opermgt 345 Shannon January, 200192
Critical Path Tasks
Critical Path = All tasks with slack = zero
Opermgt 345 Shannon January, 200193
Critical Path Tasks
Task Description Immediate Predecessor Time ES LS EF LF Slack
A Prepare Dock Site - 3 d 0 3 3 6 3 B Prepare Hut Site - 4 d 0 0 4 4 0 *** C Install Dock Pilings A 6 d 3 6 9 12 3 D Foundation for Hut B 3 d 4 4 7 7 0 *** E Build Dock C 4 d 9 12 13 16 3 F Frame Hut D 3 d 7 7 10 10 0 *** G Power to Hut D 2 d 7 14 9 16 7 H Side the Hut F 2 d 10 10 12 12 0 *** I Roof the Hut F 3 d 10 13 13 16 3 J Order Canoes and Receive Canoes - 2 d 0 4 2 6 4 K Paint Hut H 4 d 12 12 16 16 0 *** L Assemble Canoes J 10 d 2 6 12 16 4 M Finish Landscaping L,I,K,E,G 4 d 16 16 20 20 0 *** N Open for Business M 2 d 20 20 22 22 0 ***
Critical Path = B - D - F - H - K - M - N
Opermgt 345 Shannon January, 200194
CPM ( A-O-N) : ExampleCPM network for computer Design Project:
Activity Designation Pred. Dura
Design A - 21
Build prototype B A 4
Evaluate equipment C A 7
Test Prototype D B 2
Write equipment report E C,D 5
Write methods report F C,D 8
Write final report G E,F 2
Opermgt 345 Shannon January, 200195
A21
C7
B4
F8
D2
E5
G2
Opermgt 345 Shannon January, 200196
Determine the Critical path
• Forward pass:– ES : the earliest possible time the activity can
begin.– EF : the early start time the time needed to
complete the activity. ( EF = ES + Dur ) Backwards pass