Chapter 8
Scheduling
© 2012 John Wiley & Sons Inc.
![Page 2: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/2.jpg)
8-8-22
Useful Abbreviations
CPM - Critical Path MethodPERT - Program Evaluation and Review
Technique
![Page 3: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/3.jpg)
8-8-33
Background
Schedule is the conversion of a project action plan into an operating timetable
Basis for monitoring a project One of the major project management tools Work changes daily, so a detailed plan is
essential Not all project activities need to be scheduled at
the same level of detail
![Page 4: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/4.jpg)
8-8-44
Background Continued
Most of the scheduling is at the WBS level, not the work package level
Only the most critical work packages may be shown on the schedule
Most of the scheduling is based on network drawings
![Page 5: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/5.jpg)
8-8-55
Network Scheduling Advantage
Consistent frameworkShows interdependencesShows when resources are neededEnsures proper communicationDetermines expected completion date Identifies critical activities
![Page 6: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/6.jpg)
8-8-66
Network Scheduling Advantage Continued
Shows which of the activities can be delayed
Determines start datesShows which task must be coordinatedShows which task can be run parallelRelieves some conflictAllows probabilistic estimates
![Page 7: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/7.jpg)
8-8-77
Network Scheduling Techniques: PERT (ADM) and CPM (PDM)
PERT was developed for the Polaris missile/submarine project in 1958
CPM developed by DuPont during the same time
Initially, CPM and PERT were two different approaches– CPM used deterministic time estimates and allowed
project crunching– PERT used probabilistic time estimates
Microsoft Project (and others) have blended CPM and PERT into one approach
![Page 8: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/8.jpg)
8-8-88
Terminology
Activity - A specific task or set of tasks that are required by the project, use up resources, and take time to complete
Event - The result of completing one or more activities
Network - The combination of all activities and events that define a project– Drawn left-to-right– Connections represent predecessors
![Page 9: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/9.jpg)
8-8-99
Terminology Continued
Path - A series of connected activitiesCritical - An activity, event, or path
which, if delayed, will delay the completion of the project
Critical Path - The path through the project where, if any activity is delayed, the project is delayed– There is always a critical path– There can be more than one critical path
![Page 10: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/10.jpg)
8-8-1010
Terminology Continued
Sequential Activities - One activity must be completed before the next one can begin
Parallel Activities - The activities can take place at the same time
Immediate Predecessor - That activity that must be completed just before a particular activity can begin
![Page 11: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/11.jpg)
8-8-1111
Terminology Continued
Activity on Arrow - Arrows represent activities while nodes stand for events
Activity on Node - Nodes stand for events and arrows show precedence
![Page 12: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/12.jpg)
8-8-1212
AON and AOA Format
Figure 8-3
Figure 8-2
![Page 13: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/13.jpg)
8-8-1313
Constructing the Network
Begin with START activityAdd activities without precedences as
nodes– There will always be one– May be more
Add activities that have those activities as precedences
Continue
![Page 14: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/14.jpg)
8-8-1414
Gantt (Bar) Charts
Developed by Henry L. GanttShows planned and actual progressEasy-to-read method to know the current
status
![Page 15: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/15.jpg)
8-8-1515
Advantages and Disadvantage
Advantages– Easily understood– Provide a picture of the current state of a
projectDisadvantage
– Difficult to follow complex projects
![Page 16: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/16.jpg)
8-8-1616
Microsoft Project Gantt Chart
Figure 8-11
![Page 17: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/17.jpg)
8-8-1717
Microsoft Project AON Network
Figure 8-12
![Page 18: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/18.jpg)
8-8-1818
Solving the Network
Table 8-1
![Page 19: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/19.jpg)
8-8-1919
The AON Network from the previous table
Figure 8-13
![Page 20: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/20.jpg)
8-8-2020
Calculating Activity Times
2
22
6
64
ab
bmaTE
![Page 21: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/21.jpg)
8-8-2121
The Results
Table 8-2
![Page 22: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/22.jpg)
8-8-2222
Critical Path and Time
Figure 8-15
![Page 23: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/23.jpg)
8-8-2323
Critical Path and Time Continued
Figure 8-16
![Page 24: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/24.jpg)
8-8-2424
Slack
Figure 8-16
![Page 25: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/25.jpg)
8-8-2525
Slack Values
Table 8-3
![Page 26: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/26.jpg)
8-8-2626
Precedence Diagramming
Finish to startStart to startFinish to finishStart to finish
![Page 27: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/27.jpg)
8-8-2727
Precedence Diagramming Conventions
Figure 8-17
![Page 28: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/28.jpg)
8-8-2828
Microsoft Projects
Table 8-4
![Page 29: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/29.jpg)
8-8-2929
Gantt Chart
Figure 8-18
![Page 30: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/30.jpg)
8-8-3030
AON Network
Figure 8-19
![Page 31: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/31.jpg)
8-8-3131
Microsoft Project Calendar
Figure 8-23
![Page 32: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/32.jpg)
8-8-3232
Uncertainty of Project Completion Time
Assume activities are statistically independent
Variance of a set of activities is the sum of the individual variances
Interested in variances along the critical path
![Page 33: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/33.jpg)
8-8-3333
Example
45.52645.1745.543
22.1745.57
334350)(
2
ZD
DZ
![Page 34: Project Management Chapter-08](https://reader033.vdocuments.net/reader033/viewer/2022051100/577c852d1a28abe054bc04e7/html5/thumbnails/34.jpg)
8-8-3434
Toward Realistic Time Estimates
Calculations are based on 1% chance of beating estimates
Calculations can also be based on 5% or 10% Changing the percentage requires changing the
formulae for variance When using 5%, the divisor changes to 3.29 When using 10%, the divisor changes to 2.56