project management s

Upload: coolpeer91

Post on 14-Apr-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 Project Management S

    1/44

    Project Management

  • 7/30/2019 Project Management S

    2/44

    Project Management Process

    Project unique, one-time operational activity or effort

  • 7/30/2019 Project Management S

    3/44

    Project Management Process

  • 7/30/2019 Project Management S

    4/44

    Project Management Process

  • 7/30/2019 Project Management S

    5/44

    Project Elements

    Objective Scope

    Contract requirements

    Schedules

    Resources

    Personnel

    Control

    Risk and problem analysis

  • 7/30/2019 Project Management S

    6/44

    Project Team and Project Manager

    Project team made up of individuals from various areas and

    departments within a company

    Matrix organization

    a team structure with members from functionalareas, depending on skills required

    Project manager

    most important member of project team

  • 7/30/2019 Project Management S

    7/44

    Scope Statement

    Scope statement a document that provides an understanding,justification, and expected result of a project

    Statement of work

    written description of objectives of a project

  • 7/30/2019 Project Management S

    8/44

    Work Breakdown Structure

    Work breakdown structure (WBS) Breaks a project into components,

    subcomponents, activities, and tasks

  • 7/30/2019 Project Management S

    9/44

    Work Breakdown Structure for Computer OrderProcessing System Project

  • 7/30/2019 Project Management S

    10/44

    Responsibility Assignment Matrix

    Organizational Breakdown Structure (OBS) a chart that shows which organizational units are

    responsible for work items

    Responsibility Assignment Matrix (RAM)

    shows who is responsible for work in a project

  • 7/30/2019 Project Management S

    11/44

    Responsibility Assignment Matrix

  • 7/30/2019 Project Management S

    12/44

    Global and Diversity Issues in ProjectManagement

    Global project teams are formed from differentgenders, cultures, ethnicities, etc.

    Diversity among team members can add anextra dimension to project planning

    Cultural research and communication areimportant elements in the planning process

  • 7/30/2019 Project Management S

    13/44

    Project Scheduling

    Steps

    Define activities

    Sequence activities

    Estimate time

    Develop schedule

    Techniques

    Gantt chart

    CPM/PERT

    Software

    Microsoft Project

  • 7/30/2019 Project Management S

    14/44

    Gantt Chart

    Graph or bar chart

    Bars represent the time for each task

    Bars also indicate status of tasks

    Provides visual display of project schedule

  • 7/30/2019 Project Management S

    15/44

    Example -1

    construction of a house1. Design a house and get finance 3 months

    2. Lay foundation

    Order and receive material

    2 months

    1 month

    3. Build house

    Select paint and after that

    select carpet

    3 months

    1 month

    1 month

    4. Finish work 1 month

  • 7/30/2019 Project Management S

    16/44

    Example of Gantt Chart

    | | | | |

    Activity

    Design houseand obtainfinancing

    Lay foundation

    Order and

    receivematerials

    Build house

    Select paint

    Select carpet

    Finish work

    0 2 4 6 8 10Month

    Month1 3 5 7 9

  • 7/30/2019 Project Management S

    17/44

    Project Control

    Time management Cost management

    Performance management

    Earned Value Analysis standard procedure to

    numerically measure a projects progress

    forecast its completion date and cost

    measure schedule and budget variation

  • 7/30/2019 Project Management S

    18/44

    Project Control

    Quality management Communication

    Enterprise project management

  • 7/30/2019 Project Management S

    19/44

    CPM/PERT

    Critical Path Method (CPM) DuPont & Remington-Rand Deterministic task times

    Activity-on-node network construction

    Project Evaluation and Review Technique (PERT) US Navy and Booz, Allen & Hamilton

    Probabilistic task time estimates

    Activity-on-arrow network construction

  • 7/30/2019 Project Management S

    20/44

    Project Network

    Activity-on-node (AON) nodes represent activities arrows show precedence

    relationships

    Activity-on-arrow (AOA) arrows represent activities

    nodes are events forpoints in time

    Event completion or beginning

    of an activity in a project

    1 32

    Branch Node

  • 7/30/2019 Project Management S

    21/44

    AON Network for House BuildingProject

    1

    3

    2

    2

    4

    3

    3

    1

    5

    1

    6

    1

    7

    1Start

    Design houseand obtainfinancing

    Order &receivematerials

    Selectpaint

    Selectcarpet

    Layfoundation

    Buildhouse

    Finish work

    Activity Number

    Activity Time

  • 7/30/2019 Project Management S

    22/44

    AOA Project Network for a House

    3

    2 0

    1

    3

    1 1

    11 2 4 6 7

    3

    5

    Layfoundation

    Design houseand obtainfinancing

    Order andreceivematerials

    Dummy

    Finishwork

    Selectcarpet

    Selectpaint

    Buildhouse

  • 7/30/2019 Project Management S

    23/44

    Concurrent Activities

    Dummy two or more activities cannot share same start andend nodes

    2 3

    Lay foundation

    Order material

    (a) Incorrect precedencerelationship

    (b) Correct precedencerelationship

    3

    42

    DummyLayfoundation

    Order material

    1

    2 0

  • 7/30/2019 Project Management S

    24/44

    SUM-1 Draw (AOA) network diagram for thedata given below

    Activity Immediate predecessor activity

    A -

    B A

    C A

    D B

    E C

    F D

    G E

    H F ,G

  • 7/30/2019 Project Management S

    25/44

    SUM-2 Draw a network diagram andfind critical path

    Activity Immediatepredecessor activity

    Duration ofactivity

    A - 12B A 8C A 4D A 3E B 12F C 18

    G C 5H E ,F 4I D ,G 9J H ,I 6

  • 7/30/2019 Project Management S

    26/44

    AON network

    1

    3

    2

    2

    4

    3

    3

    1

    5

    1

    6

    1

    7

    1

    Start

  • 7/30/2019 Project Management S

    27/44

    Critical Path

    Critical path

    Longest path through anetwork

    Minimum projectcompletion time

    A: 1-2-4-73 + 2 + 3 + 1 = 9 months

    B: 1-2-5-6-73 + 2 + 1 + 1 + 1 = 8 months

    C: 1-3-4-73 + 1 + 3 + 1 = 8 months

    D: 1-3-5-6-73 + 1 + 1 + 1 + 1 = 7 months

    1

    3

    2

    2

    4

    3

    3

    1

    5

    1

    6

    1

    7

    1Start

  • 7/30/2019 Project Management S

    28/44

    Activity Start Times

    13

    22

    43

    31

    51

    61

    71

    Start

    Start at 3 months Start at 6 months

    Start at 5 months

    Finish at 9 months

    Finish

  • 7/30/2019 Project Management S

    29/44

    Activity Scheduling

    Earliest start time (ES) earliest time an activity can start ES = maximum EF of immediate predecessors

    Forward pass

    starts at beginning of CPM/PERT network to determineearliest activity times

    Earliest finish time (EF) earliest time an activity can finish

    earliest start time plus activity time EF= ES + t

  • 7/30/2019 Project Management S

    30/44

    Activity Scheduling

    Latest start time (LS) Latest time an activity can start without delaying criticalpath time

    LS= LF - t

    Latest finish time (LF) latest time an activity can be completed without delayingcritical path time

    LF = minimum LS of immediate predecessors

    Backward pass Determines latest activity times by starting at the end ofCPM/PERT network and working forward

  • 7/30/2019 Project Management S

    31/44

    Activity Slack

    * Critical Path

    09988*7

    178676

    167565

    08855*4

    145343

    05533*2

    03300*1

    Slack SEFLFESLSActivity

  • 7/30/2019 Project Management S

    32/44

    Probabilistic Time Estimates

    Beta distribution probability distribution traditionally used in CPM/PERT

    a = optimistic estimatem = most likely time estimateb= pessimistic time estimate

    where

    Mean (expected time): t=a + 4m + b

    6

    Variance: 2 =

    2b - a

    6

  • 7/30/2019 Project Management S

    33/44

    Activity Time Estimates

    1 6 8 10 8 0.442 3 6 9 6 1.003 1 3 5 3 0.44

    4 2 4 12 5 2.785 2 3 4 3 0.116 3 4 5 4 0.117 2 2 2 2 0.008 3 7 11 7 1.789 2 4 6 4 0.44

    10 1 4 7 4 1.0011 1 10 13 9 4.00

    TIME ESTIMATES (WKS) MEAN TIME VARIANCEACTIVITY a m b t 2

  • 7/30/2019 Project Management S

    34/44

    Activity Early, Late Times & Slack

    ACTIVITY t ES EF LS LF S

    1 8 0.44 0 8 1 9 12 6 1.00 0 6 0 6 03 3 0.44 0 3 2 5 24 5 2.78 8 13 16 21 85 3 0.11 6 9 6 9 06 4 0.11 3 7 5 9 27 2 0.00 3 5 14 16 118 7 1.78 9 16 9 16 09 4 0.44 9 13 12 16 3

    10 4 1.00 13 17 21 25 8

    11 9 4.00 16 25 16 25 0

  • 7/30/2019 Project Management S

    35/44

    Total Project Variance

    2 = 22 + 52 + 8

    2 + 112

    = 1.00 + 0.11 + 1.78 + 4.00

    = 6.89 weeks

  • 7/30/2019 Project Management S

    36/44

    Probabilistic Network Analysis

    Determine probability that project iscompleted within specified time

    where = tp = project mean time = project standard deviation

    x = proposed project time

    Z = number of standard deviations thatx is from the mean

    Z=x -

  • 7/30/2019 Project Management S

    37/44

    Normal Distribution of Project Time

    = tp Timex

    Z

    Probability

  • 7/30/2019 Project Management S

    38/44

    Southern Textile

    What is probability that project is completed within 30 weeks?

    2 = 6.89 weeks

    = 6.89

    = 2.62 weeks

    Z=

    =

    = 1.91

    x -

    30 - 252.62

    From Table A.1, (appendix A) aZscore of 1.91 corresponds to aprobability of 0.4719. Thus P(30) = 0.4719 + 0.5000 = 0.9719

    = 25 Time (weeks)x = 30

    P(x 30 weeks)

  • 7/30/2019 Project Management S

    39/44

    Southern Textile

    What is probability that project is completed within 22 weeks?

    2 = 6.89 weeks

    = 6.89

    = 2.62 weeks

    Z=

    =

    = -1.14

    x -

    22 - 252.62

    From Table A.1, (appendix A) aZscore of 1.14 corresponds to aprobability of 0.3729. Thus P(22) = 0.5000 - 0.3729 = 0.1271

    = 25 Time (weeks)x = 22

    P(x 22 weeks)= 0.1271

    0.3729

  • 7/30/2019 Project Management S

    40/44

    Project Crashing

    Crashing reducing project time by expending additionalresources

    Crash time

    an amount of time an activity is reduced Crash cost cost of reducing activity time

    Goal

    reduce project duration at minimum cost

    P j t N t k B ildi H

  • 7/30/2019 Project Management S

    41/44

    Project Network Building a House

    112

    2

    8

    412

    3

    4

    5

    4

    6

    4

    7

    4

  • 7/30/2019 Project Management S

    42/44

    Project Crashing

    TOTAL

    NORMAL CRASH ALLOWABLE CRASHTIME TIME NORMAL CRASH CRASH TIME COST PERACTIVITY (WEEKS) (WEEKS) COST COST (WEEKS) WEEK

    1 12 7 $3,000 $5,000 5 $400

    2 8 5 2,000 3,500 3 500

    3 4 3 4,000 7,000 1 3,000

    4 12 9 50,000 71,000 3 7,000

    5 4 1 500 1,100 3 200

    6 4 1 500 1,100 3 200

    7 4 3 15,000 22,000 1 7,000

    $75,000 $110,700

    $500 $7000

  • 7/30/2019 Project Management S

    43/44

    Project Duration:

    36 weeks1

    12

    2

    8

    3

    4 5

    4

    6

    4

    7

    4

    $400

    $500

    $3000

    $7000

    $200

    $200

    $700012

    4FROM

    1

    7

    2

    8

    3

    4 5

    4

    6

    4

    7

    4

    $400

    $500

    $3000

    $7000

    $200

    $200

    $700012

    4

    Project Duration:

    31 weeksAdditional Cost:

    $2000

    TO

    C

  • 7/30/2019 Project Management S

    44/44

    Time-Cost Relationship

    Crashing costs increase as project durationdecreases

    Indirect costs increase as project durationincreases

    Reduce project length as long as crashing costsare less than indirect costs