project on developing and implementing an impact-based ... · impacts in many places and limited...
TRANSCRIPT
Project on
Developing and Implementing
an Impact-based
Severe Weather Warning System
Project Management Team:
Eugene Poolman, Elizabeth Webster, Ezekiel Sebego, Kevin Rae (SAWS)
Dechlan Pillay, Mark van Staden (NDMC)
Current Warning: Heavy rain of more than 50mm in 24 hours is expected
What is it about?
So??
What does it
mean to me?
History: Public Warning Hazards: (up to 2012)
FCAST-PRE-20130226.001.1 3
HAZARD DEFINITION1 Extremely heat Maximum temperature forecast 40C and above
2 Very cold Maximum temperatures 10C and below and/or Minimum -10C below
3 High discomfort Discomfort Index (D.I.), meeting or exceeding 38C (or 100 F)
4 Heat wave 3 consecutive days with maximum temperature to be more or equal to 5C higher than
the average maximum of the hottest month for the particular station in the FPG region/s
5 Gale force winds
and stronger
Average wind speed of more than 34knots (62 km/h) or gusts in excess of 44knots for
land based regions
6 Fire Danger
Rating
If the fire danger rating is high or extreme according to the NFDRS work instruction
7 Heavy rain 50 mm or more within 24 hours
8 Flash Flood Flash flood as defined by SAFFG work instruction
Warning : Within three hours from time of forecast
Watch : 3 to 6 hours from time of forecast
Advisory: Beyond 6 hours from the time of forecast
9 Snow Sufficient snow to cause significant traffic danger and/or disruptions in mountain passes,
major roads and/or highways and/or populated areas
10 Severe
thunderstorms
Severe Thunderstorm in line with the USA NSSL definition with one or any combination of
the following:
- Hail of greater than 19mm diameter or large amounts of small hail
- Tornadoes (any),
- Wind gusts 50kts or more, in association with a thunderstorm
History: Marine Warnings: (up to 2012)
FCAST-PRE-20130226.001.1 4
HAZARD DEFINITION1 Heavy swell Heavy swell greater than 4m with a period of at least 10s.
2 Very rough seas Total sea between 4m – 6m
3 High seas Total sea in excess of 6m - 9m
4 Very high seas Total sea in excess of 9 to 14m
5 Phenomenal seas Total sea in excess 14m
6 Abnormal waves Total sea greater than 5m with long period south westerly swell dominating.
Tz > 10s (as per NWP model and platform observation) (Zero crossing period)
Tp > 15s (as measured at nearest waverider buoy) (Peak energy period)
7 Gale force winds Average wind speed of Gale Force of 34 – 40 knots
8 Strong gale Average wind speed of Strong Gale Force of 41 – 47 knots
9 Storm strength
winds
Average wind speed of Storm strength of 48 – 55 knots
10 Violent storm
strength winds
Average wind speed of Violent Storm strength of 56 – 63 knots
11 Hurricane strength
winds
Average wind speed of Hurricane strength of 64 knots and more
12 Tropical storm A Tropical storm as named and defined by RSMC La Reunion with wind speeds in
excess of 47knots
13 Tropical cyclone A Tropical cyclone as named and defined by RSMC La Reunion
14 Reduced visibility When the visibility is expected to be less than 5 nm (10 km) (1nm = 1.852km)
Severe Weather Warning Levels (from 2013):
Reduced number of hazards to 7
No Alert
Special
Weather
Advisory
Weather WatchWeather
Warning
Be Aware! Be Prepared! Take Action!
No
hazardous
weather
expected
Early warning
of potential
hazardous
weather
Weather
conditions are
likely to become
hazardous
Hazard is already
occurring or is
imminent
2 to 6 days 1 to 3 days Next 24 hours
Intense large
weather
systems
Extreme heat
Heat Waves
Strong winds
High
discomfort
Heavy rain
Disruptive snow
Gales
High waves
Severe T/S
Flooding
Veldfire
conditions
Heavy rain
Disruptive snow
Gales
High waves
Severe T/S
Flooding
Veldfire conditions
International Developments?
WMO: Disconnect between warning of hydromet events, and the understanding of
their impacts
IMPACT-BASED WARNINGS• UK implemented in 2011• WMO Guidelines (latest version 2015)• Europe, USA, Australia in various versions • Pilot projects by WMO in Myanmar,
Mauritius, Mozambique, Malaysia, etc.
Subsequent SA Disaster Management
Survey and meetings (in 2013)
• Challenge from Disaster Managers:
Clear requirement of matter-of-fact information, i.e
non-scientific and to the point – minimize need for
complex interpretation
The need for improving communication to users to
enable their effective decision making
“Just tell me what is going to happen, when, where
and how serious it is”
Moving from:What the weather will be:
(Meteorological thresholds)
- 35 knot winds
- High seas
What the weather will do:
(Impact Warnings)
- small boats at risk of capsizing
To:
What is Impact-Based forecasting?
Impact-based Severe Weather Warning System
Scenario 1:
23 Feb 2010
- Road breached
- Several sheep drowned
Scenario 2:
8 June 2011
- Hundreds displaced
- Communities threatened
- Severe damaged
Impact-based Severe Weather Warning System
Why Impact-based forecasting in
South Africa?
• Huge variation in vulnerability of communities
across country (from densely populated cities,
vast rural communities, extensive agricultural
areas, varied infrastructure distribution)
• Severe weather conditions leading to serious
impacts in many places and limited impacts
elsewhere
Forecast needs to evolve from what weather will be, to
what weather will do…
Requires a paradigm shift:
• From warnings based on weather thresholds
(50mm in 24hrs)
• To warnings based on variations in vulnerability -
impact levels (minimal, minor, significant, severe)
Scenario 1:
23 Feb 2010
Scenario 2:
8 June 2011
- Road breached
- Several sheep drowned
- Hundreds displaced
- Communities threatened
- Severe damaged
Current Warning: Heavy rain of more than 50mm in 24 hours is expected
We need to change from this to….
Warning:
1. Orange warning for rain with a
medium likelihood of significant impacts
2. Yellow warning for rain with a high
likelihood of minor impacts
1
2
An impact-based Early Warning System
1
2
4 Year Project: Developing an
Impact-Based Severe Weather Warning Service
• Aim: Based on WMO recommendations, to develop, test and implement an Impact-based forecasting and warning service in South Africa, through close collaboration between forecasters and disaster managers
• Associated projects and sponsors:
SAWS and NDMC (Developing Impact-based SWWS)UK Newton Fund WP 4 (High Impact Weather)USAID/NOAA (Advancing IDSS in SA)
Project Timelines
OVERVIEW GANTT CHART: IMPACT-BASED SWWS (June 2017)2015/16 2016/17 2017/18 2018/19
Activities Apr-Sep Oct-Mar Apr-Sep Oct-Mar Apr-Sep Oct-Mar Apr-Sep Oct-Mar
1 Project development
OUTCOME 1: Subjective decision making process
2 Develop Guidelines
3 Prototype test Phase (NFC and NDMC)
4 Summer Pilot Phase (GT) GT KZN,FS, etc
5 Winter Pilot Phase (WC, EC, KZN, including marine)WC, EC
WC,EC,KZN, marine
6 Community level stakeholder workshops (2:City and Rural)Jhb, EC
7 Public information and awareness campaigns
8 Operational implementation (preparation)
OUTCOME 2: Objective decision support system
10 Develop scientific DSS vs 1
11 Develop scientific DSS vs 2
General
12 Wrap up workshop
13 Project conclusion
Decision Making Process Development
• Prototype developed and tested (2016):
– Forecasting process developed and tested in case studies
• Summer Pilot Phase (2016/2017): summer weather (Gauteng Province)
– Focus on heavy rain and severe thunderstorms
– 1-2 Dec 2016: Stakeholder workshop with NDMC, PDCM, MDMC’s in Gauteng
– Forecaster training for NFC forecasters
– 3 Event periods identified for potential adverse weather
– Demonstration warnings issued to disaster management (not yet to public)
Feedback from DMCs very positive and constructive (warnings are understandable)
Risk Matrix
DMS Development continued
• Winter Pilot Phase (2017): Winter rainfall regions (Western and Eastern Cape)
– Same format as summer pilot = focus on rain, wind, snow
– Stakeholder workshop (with WC-PDMC, WC & 2 EC MDMCs) held 3-4 May 2017
– Forecaster Training in CT (5-10 May) and PE (15-18 June)
– Pilot period from June to 30 Sept, through event periods
• Summer Pilot Phase continue (2017/18): In Gauteng, expanded to all summer provinces (KZN, FS, NW, NC, LM, MP)
– Stakeholder workshops and forecaster training latter part of 2017 or early 2018
• Public information and awareness campaign (2018):
– Pilot in 2 distinct communities (informal area in city, and deep rural)
• Development of GIS-based Decision Support System using vulnerability information and NWP products
• Operational implementation upon successful pilot phases
Marine Pilot Phase 2018
• Specific Aim:
– To test impact-based warnings and the co-ordination between relevant stakeholders and SAWS during severe weather, tuning for operationalization
– Focuses on the near-shore (<15nm) and beach area
• Stakeholder Workshop 6-7 March 2018 George:
– Relevant marine representatives
– Disaster managers from District MDMCs, PDMCs, NDMC, SAWS
– Introduce the pilot test phase focussing on disasters related to waves, wind and visibility
– Introduce the concept of Impact-based SWWS
– Develop marine impact table
– Agree on coordination mechanisms during the pilot test phase
• Event test periods
– Test Impact-based warnings to be issued and coordination during these periods with marine stakeholders and NOT yet to the public
– Current operational EWS system is still in place and old style warnings still to be used in parallel
So, how does it work?
• Impact tables helps with high-level distinguishing between less severe and more severe impact levels
• Impact level depends on vulnerability in local area to impacts • Content determined by marine stakeholders input
Minimal Minor Significant Severe
Day to day activities
not affected but
some small scale
impacts occur
Some local
incidents, minor
disruptions,
'business as
usual' for
emergency
responders
Disruption to day to
day routines and
activities, mostly
localised.
Short-term strain
on emergency
responder
organisations
Widespread,
Prolonged
disruption to day to
day routines and
activities
Prolonged strain
on emergency
responders
organisations.
Generic description of different impact levels
So, how does it work?
• Forecasters identify a region where rainfall could result in adverse impacts
• Based on the Impact tables, the most appropriate impact level is identified for an area
• The expected likelihood of these impacts to occur is determined
• Then the appropriate warning risk level is established
?? July 2018.…..
So, how does it work?
• Forecasters identify a region where rainfall could result in adverse impacts
• Based on the Impact tables, the most appropriate impact level is identified for an area
• The expected likelihood of these impacts to occur is determined
• Then the appropriate warning risk level is established
• The same is done for areas with higher vulnerability
?? July 2018.…..
So, how does it work?
• Coordination with disaster management is important for orange and redwarnings
• Important to note the difference in impact and likelihood of the yellow and orange warnings
• These warnings require a different response from disaster management depending on its impactand likelihood levels
?? July 2018.…..
Example of Impact-based warning
Like
liho
od
High 2 6 10
Medium 1 5 9
Low 4 8
Very Low 3 7
Minimal Minor Significant Severe
Impact
• Impact-based warning system can work in South Africa
• Both forecasters and disaster managers have adapted quickly
to new paradigm of impact levels vs weather thresholds
• Strong support at all stakeholder workshops and in events
• Clear reduction in unnecessary warnings (esp. higher levels)
From 41 (old system) to 28 (new system) for same pilot phase periods
Some warnings issued in previous system (thresholds exceeded) did
not need one now due to local resilience (e.g. gales along the coast)
Coordination between forecasters and disaster managers improve
decision making on
warnings to be issued
• During 2 Pilot phases:
20 warnings issued for
Minor impacts, none for
Severe impacts so far
28
High 7 0 0
Medium 13 6 0
Low 2 0
Very Low 0 0
Minimal Minor Significant Severe
Number of Warnings issued
LIK
ELIH
OO
D
Total nr of Warnings:
IMPACT
Lessons learnt so far
Lessons learnt so far (2)
• Importance of involving both forecasters and disaster
managers in pilot event tests = dual ownership of warnings
• Effective communication & coordination between forecaster
and disaster manager prior and during a severe weather
event is crucial
Developed at the initial workshops and tuned in pilot test phases
Disaster manager must agree on significant or severe impact levels
Feedback during event – using dedicated WhatsApp group?
• Secondary hazards (e.g. the Knysna fires) can lead to
increased impact levels
• DM reaction to warnings – GT PDMC listed decision making
level and appropriate DM reaction to each of the 10 warnings
• Need for preparation of effective, actionable, communication
to general public in layman’s terminology
RISK
LEVEL
DECISION MAKER/RECIPIENT REQUIRED ACTIONS
1 DMO is the recipient and the
Decision maker
Ensure that relevant DM stakeholders are aware of the event.
2 Ensure that relevant DM stakeholders are aware of the event.
Advise stakeholders on necessary preparedness actions.
3 DMO is the recipient and the
Supervisor/ line manager is the
decision maker
Ensure awareness of event to relevant DM stakeholders.
Advise stakeholders on necessary preparedness cations
Check Agree on /revise /relevant response protocols/SOP
4 Ensure awareness of event to relevant DM stakeholders.
Advise stakeholders on necessary preparedness actions.
Check Agree on /revise /relevant response protocols/SOP
Ensure response resources are on standby
5 DMO is the recipient and the
Supervisor/line manager supports
decision making and Director is the
decision maker
Ensure awareness of event to relevant DM stakeholders.
Advise stakeholders on necessary preparedness actions.
Check Agree on /revise /relevant response protocols/SOP
Ensure response resources are on standby.
Dispatch /allocate resources /personnel in hotspot areas
6. DMO is the recipient and the
Supervisor/line manager and
Director supports decision making
process and the HOC is the
decision maker
Ensure awareness of event to all DM stakeholders.
Advise stakeholders on necessary preparedness actions.
Check Agree on /revise /relevant response protocols/SOP
Ensure response resources are on standby.
Dispatch /allocate resources /personnel in hotspot areas
Relocate communities in hot spot areas
Gauteng Disaster Management Response
Protocol
RISK
LEVEL
DECISION MAKER/RECIPIENT REQUIRED ACTIONS
7. DMO is the recipient and the
Supervisor/line manager supports
decision making and Director is the
decision maker and the HOC is
aware of decisions taken at all times.
HOC is on standby to take over
decision making if the likelihood
increases.
Ensure awareness of event to all DM stakeholders.
Advise stakeholders on necessary preparedness actions.
Check Agree on /revise /relevant response protocols/SOP
Ensure response resources are on standby.
Continuously communicate with SAWS so as to immediately Dispatch
/allocate resources /personnel in all hotspot and other vulnerable areas if the
likelihood increases
Continuously communicate with SAWS so as to immediately Relocate
communities in hot spot areas if likelihood increases
8 DMO is the recipient and the
Supervisor/line manager and Director
supports decision making process
and the HOC is the decision maker.
The MM/City manager is made
aware of the decision
Ensure awareness of event to all DM stakeholders.
Advise stakeholders on urgent necessary preparedness actions.
Check Agree on /revise /relevant response protocols/SOP
Ensure response resources are on standby.
Dispatch resources /personnel in hotspot areas
Continuously communicate with SAWS so as to immediately add resources
/personnel in all hotspot and other vulnerable areas if the likelihood increases
Continuously communicate with SAWS so as to immediately Relocate
communities in hot spot areas if likelihood increases
9 DMO is the recipient and the
Supervisor/line manager and Director
supports decision making process
and the HOC is the decision maker
supported by the MM/City manager.
The mayor is made aware
Ensure awareness of event to all DM stakeholders.
Advise stakeholders on urgent necessary preparedness actions.
Check Agree on /revise /relevant response protocols/SOP
Ensure all response resources are on standby.
Dispatch resources /personnel in hotspot areas
Continuously communicate with SAWS so as to immediately add resources
/personnel in all hotspot and other vulnerable areas if the likelihood increases
Relocate communities
10 DMO is the recipient and the
Supervisor/line manager, Director
supports decision making process
and the HOC takes operational
decisions and MM overall strategic
and financial decisions- Mayor
provides oversight and makes
political decisions.
Ensure awareness of event to all DM stakeholders.
Advise stakeholders on urgent necessary preparedness actions.
Check Agree on /revise /relevant response protocols/SOP
Dispatch resources /personnel in all areas
Continuously communicate with SAWS so as to immediately add resources
/personnel
Relocate communities
Conclusion
• Good progress in the project to implement an Impact-based SWWS in South Africa
Forecasting process developed and tested
Summer pilot phase: Gauteng done summer 2016/17
Winter pilot phase: Western and Eastern Cape in winter 2017
• Collaboration of various stakeholders SAWS, DMCs (national, provincial, local), other specialist partners (universities, relevant sector departments)
• It will change the EWS to into a user oriented risk-based EWS, adapted for South African conditions
We are “learning as we are doing”
Thank You
“One cannot be vulnerable if one is not threatened, and one cannot be
threatened if one is not exposed and vulnerable.
Hazard and vulnerability are mutually conditioning situations and neither can exist on its own” (Cardona 2004)