CelaneseMethanol Plant Clear Lake, Texas$160,000,000 Contract Value
Worley Parsons
15 Month Duration
1,860,300 Workhours
148,000 LF of Piping –Spools
11,126 Pipe Welds -187,383 Weld Dia. Inches
1,022 Hydrostatic Test Packages
• Greenfield Project
• Turner Increased craft manpower from 300 to 900 over a 7-week period
• 110 pipe welders on the project
• Turner fabricated all piping with pipe sizes ranging up to 72” diameter
• Turner provided commissioning and start-up assistance
Zero Lost Time Accidents