project risk mgt at linde engineering.ecrisponsor.org/presentations/lo18 1-3 - linde_ecri...

26
Project Risk Mgt at Linde Engineering. ECRI Sponsors Meeting London, June 2018 Andreas Soellner

Upload: others

Post on 06-Apr-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Project Risk Mgt at Linde Engineering.ecrisponsor.org/presentations/lo18 1-3 - Linde_ECRI Presentation 20180607.pdf · gas, ammonia and methanol from any hydrocarbon feedstock —

Project Risk Mgt at Linde Engineering.

ECRI Sponsors Meeting

London, June 2018

Andreas Soellner

Page 2: Project Risk Mgt at Linde Engineering.ecrisponsor.org/presentations/lo18 1-3 - Linde_ECRI Presentation 20180607.pdf · gas, ammonia and methanol from any hydrocarbon feedstock —

2

What is our business ?

Page 3: Project Risk Mgt at Linde Engineering.ecrisponsor.org/presentations/lo18 1-3 - Linde_ECRI Presentation 20180607.pdf · gas, ammonia and methanol from any hydrocarbon feedstock —

3

Financial highlights by division

Operating margin increased in both divisions

Page 4: Project Risk Mgt at Linde Engineering.ecrisponsor.org/presentations/lo18 1-3 - Linde_ECRI Presentation 20180607.pdf · gas, ammonia and methanol from any hydrocarbon feedstock —

4

Integrated Gases and Engineering model

Synergies built on strong engineering foundation

Page 5: Project Risk Mgt at Linde Engineering.ecrisponsor.org/presentations/lo18 1-3 - Linde_ECRI Presentation 20180607.pdf · gas, ammonia and methanol from any hydrocarbon feedstock —

5

Linde Engineering

Core competence is the treatment of gases

Liquefaction

Separation

Thermal Cracking

Standardised plants EPC plantsComponents Services

Air

Hydrocarbons

Natural gas

Tail gases

Exhaust fumes

Hydrogen

Oxygen

Rare gases

Olefins

Nitrogen

Carbon monoxide

Carbon dioxide

Synthesis gas

Page 6: Project Risk Mgt at Linde Engineering.ecrisponsor.org/presentations/lo18 1-3 - Linde_ECRI Presentation 20180607.pdf · gas, ammonia and methanol from any hydrocarbon feedstock —

6

Engineering Division

2017 order intake by plant type

Page 7: Project Risk Mgt at Linde Engineering.ecrisponsor.org/presentations/lo18 1-3 - Linde_ECRI Presentation 20180607.pdf · gas, ammonia and methanol from any hydrocarbon feedstock —

7

Linde Engineering

Operations and sales offices

Engineering operations

Representative & sales offices

Aldershot

Johannesburg

Moscow

Seoul

Kuala Lumpur

Pulogadung, Jakarta

DresdenPullach/SchalchenPfungen

Samara

Hésingue

VadodaraAbu DhabiAl-Chubar

Dalian

HangzhouHolly Springs

Blue Bell

Houston

Tulsa

Major operating entities

Entity Location Employees as

of 10/2017

Total LE 6,167

Comments

LEHQ Pullach/Germany

Schalchen/Germany

1,855

774

Engineering

Manufacturing

LEDD Dresden/Germany 426 Engineering

LENA USA 484 Engineering

LEH Hangzhou/China 227 Engineering

LED Dalian/China 419 Manufacturing

LEI India 987 Engineering

Kolkata

Tehran

St. Petersburg

Page 8: Project Risk Mgt at Linde Engineering.ecrisponsor.org/presentations/lo18 1-3 - Linde_ECRI Presentation 20180607.pdf · gas, ammonia and methanol from any hydrocarbon feedstock —

8

Air Separation Plants

Product portfolio

— Modular air separation plants,

standardised and pre-fabricated

— Customised air separation units,

individually designed to meet

customer-specific demands

Key features

— 3,000 plants built in 80 countries,

thereof 400 plants owned &

operated by Linde Gases

— Highly energy efficient plants

— High safety and quality standards

— Superior plant availability and

low life-cycle cost

Page 9: Project Risk Mgt at Linde Engineering.ecrisponsor.org/presentations/lo18 1-3 - Linde_ECRI Presentation 20180607.pdf · gas, ammonia and methanol from any hydrocarbon feedstock —

9

Hydrogen & Synthesis Gas Plants

Product portfolio

— Production of hydrogen, CO, CO2, synthesis

gas, ammonia and methanol from any

hydrocarbon feedstock

— Syngas processing plants (gas separation and

purification)

Key features

— 500 plants built worldwide, more than

100 plants operated by Linde Gases

— Entire process chain for small, medium and

large scale production and treatment of

synthesis gas and H2/CO

— Utilisation of all petrochemical feedstock,

from natural gas through heavy oil to coal

— Highly efficient process (e.g. ammonia)

Page 10: Project Risk Mgt at Linde Engineering.ecrisponsor.org/presentations/lo18 1-3 - Linde_ECRI Presentation 20180607.pdf · gas, ammonia and methanol from any hydrocarbon feedstock —

10

Petrochemical Plants

Product portfolio

— Steam cracking: cracking furnaces and olefins

separation/purification

— Refinery and steam cracking integration

— Acetylene, butadiene and aromatics (BTX) recovery

— Olefins: Oxidative Coupling of Methane (OCM)

— Polyolefins (polyethylene & polypropylene)

— Linear Alpha Olefins

— Complex revamp

— Technical services for operation petrochemicals plants

Key features

— Comprehensive portfolio for olefin production and

derivatives

— Linde olefins technology recognised as leading

— Excellent market position and key references

— New products/technology development

Page 11: Project Risk Mgt at Linde Engineering.ecrisponsor.org/presentations/lo18 1-3 - Linde_ECRI Presentation 20180607.pdf · gas, ammonia and methanol from any hydrocarbon feedstock —

11

Natural Gas Plants

Product portfolio

— Natural gas processing

— Liquefaction of natural gas

— Liquefied Natural Gas (LNG)

regasification terminals and

bunkering

— LNG satellite stations (Cryostar)

— On-board re-liquefaction of

natural gas (Cryostar)

Key features

— Leading in the area of

small- to midscale LNG plants

— Covering the full LNG value

chain

— Manufacturer of cryogenic

key equipment

Page 12: Project Risk Mgt at Linde Engineering.ecrisponsor.org/presentations/lo18 1-3 - Linde_ECRI Presentation 20180607.pdf · gas, ammonia and methanol from any hydrocarbon feedstock —

12

PROJECT RISK MANAGEMENT

responsibility by Project Manager

supported by Project Risk Manager

ENTERPRISE RISK MANAGEMENT

LE, within Finance

CORPORATE RISK MANAGEMENT

Linde Group, Corporate Centre

Enterprise Risk Management – Project Risk Management

HR

risks

IT

risks

technical

risk management(HAZOP, safety reviews,

SIL, … )

commercial

project

risk management

project 2project 1 project ...

project

risks

financial

risks

market

risks

technology

risks

proposal 1

Linde Gas Linde Engineering

Region 1

Region 2

Page 13: Project Risk Mgt at Linde Engineering.ecrisponsor.org/presentations/lo18 1-3 - Linde_ECRI Presentation 20180607.pdf · gas, ammonia and methanol from any hydrocarbon feedstock —

13

• management of the risk assessment process

• ensure the availability of suitable reporting tools

• provide risk management support for risk owners across LE

• facilitation/coordination/reporting of risk assessments

• monitor and ensure progress on follow-up actions identified in the project risk workshop

(within responsibility of Sales / Project Manager)

• oversight/review of risk assessments prepared by others (e.g. project managers)

• provide risk and performance metrics

• promote a risk aware culture and an appropriate risk balance within LE

Objectives of Commercial Project Risk Management

8

Page 14: Project Risk Mgt at Linde Engineering.ecrisponsor.org/presentations/lo18 1-3 - Linde_ECRI Presentation 20180607.pdf · gas, ammonia and methanol from any hydrocarbon feedstock —

14

Risk Management Method based on Project Criticality

< 10 Mio. € ≥ 10 Mio. € ≥ 40 Mio. € ≥ 100 Mio. € ≥ 500 Mio. €

0 1 2 3 4

estimate simplified risk

register

risk register

E, EP EPC

project size

project

criticality

method

Page 15: Project Risk Mgt at Linde Engineering.ecrisponsor.org/presentations/lo18 1-3 - Linde_ECRI Presentation 20180607.pdf · gas, ammonia and methanol from any hydrocarbon feedstock —

15

Risk Management Process

What’s new in our process ?

risk monitoring

• standard reports

• KPI‘srisk planning

• 5 RWS

• participants of RWS

• timing of RWS

risk analysis

• human factor

• voting system

risk identification

• standard risk register

• focus on mitigation action

• responsibility and due date

risk handling

• job sheets

• follow up of mitigation measures 2

1

3

4

5

Page 16: Project Risk Mgt at Linde Engineering.ecrisponsor.org/presentations/lo18 1-3 - Linde_ECRI Presentation 20180607.pdf · gas, ammonia and methanol from any hydrocarbon feedstock —

16

Risk Workshops per Risk Category

Engineering & Technology • standards & requirements

• technical design concept

• LDs & make-good

• design of existing plant (revamps only)

• layout concept

• HSE concept

• commissioning & start-up concept

• other technology & conceptual design

risks

• technology & conceptual design

opportunities

Contractual & Commercial • contract concept

• terms of contract

• other contractual & commercial risks

• change order concept

• commercial & contractual opportunities

Project Environment • cultural & heritage

• weather & climatic conditions

• economical & business environment

• political environment

• social environment

• geological risks

• other environmental risks

• project environment opportunities

Project Execution &

Management

• project execution concept

• organization

• internal performance

• external performance

• time schedule

• other project execution risks

• project execution opportunities

• (pre-) commissioning and test run

Procurement & Logistics • procurement

• inspection & expediting

• logistics

• procurement & logistics opportunities

Construction • construction concept

• performance of construction

subcontractor(s) or partner(s)

• brownfield risks

• site installation & temp. facilities

• other construction risks

• construction opportunities

Page 17: Project Risk Mgt at Linde Engineering.ecrisponsor.org/presentations/lo18 1-3 - Linde_ECRI Presentation 20180607.pdf · gas, ammonia and methanol from any hydrocarbon feedstock —

17

Participants of the Risk Workshop

Procurement Manager

Project Risk Manager

Engineering Manager

Contract Manager

Project Manager Execution Project Manager Sales

Project Discipline Manager

Estimator

Experts

Construction Manager

Project Control Manager

*extendended number of participants wih criticality 4

Page 18: Project Risk Mgt at Linde Engineering.ecrisponsor.org/presentations/lo18 1-3 - Linde_ECRI Presentation 20180607.pdf · gas, ammonia and methanol from any hydrocarbon feedstock —

18

The new Risk Register is at the core of

the LE Project Risk activities

Execution phase

Risk

Workshops

Contingency

calculation

Mitigation

measures

Proposal phase

Risk / Contingency

update

Probability

0 % - 5 % Very Unlikely

5 % - 15 % Unlikely

15 % - 25 % Possible

25 % - 50 % Likely

50 % - 80 % Probable

Impact

0 - 0,05 Mio € Negligible

0,05 - 0,5 Mio € Minor

0,5 - 5 Mio € Moderate

5 - 50 Mio € Serious

> 50 Mio € Major

Negligible Minor Moderate Serious Major

Very

Unlikely 1 15 150 1500 9000

Unlikely 5 50 500 5000 30000

Possible 10 100 1000 10000 60000

Likely 20 200 2000 20000 120000

Probable 30 300 3000 30000 200000

not relevant

low

medium

high

very high

extreme

Semi-quantitative expert assessment of

remaining risk after successful mitigation

Risk mapping matrix Risk level mEuro

0 – 0.02

0.02 – 0.2

0.2 – 1

1 – 5.5

5.5 – 40

> 40

risk ID risk title risk description

risk

applic

able

risk

"type"

date of

observation management measure DRI due date

measur

e

status

probabilit

y (post

MM)

impact

(post MM)

risk level

(post MM)

302002Heavy rainfall and thunder

storms with wind gusts

Lightning warnings and heavy rain might

lead to disruption during construction

work and therefore to productivity loss

and delays during construction.

yesrisk

factor27.04.17

- Cost has to be considered in

estimate

- Time has to be considered in

schedule

- Include contract bad weather

clause

- A.B./GCP

- B.C./CPP

- C.D./CPCA

- 19.05.2017

- 30.05.2017

- 30.09.2017

ongoing Possible Moderate medium

Page 19: Project Risk Mgt at Linde Engineering.ecrisponsor.org/presentations/lo18 1-3 - Linde_ECRI Presentation 20180607.pdf · gas, ammonia and methanol from any hydrocarbon feedstock —

19

Voting Tool:

• an anonymous voting system makes participants independent from others in decision making

• differences in risk view become easier visible (in case of high variances)

• input optional, no obligation to vote when no profound judgement possible

Risk Workshop approach

Decision Making

Page 20: Project Risk Mgt at Linde Engineering.ecrisponsor.org/presentations/lo18 1-3 - Linde_ECRI Presentation 20180607.pdf · gas, ammonia and methanol from any hydrocarbon feedstock —

20

Activities after Risk Workshops

Example for a job sheet (A.B._20180315_Risk_Register_Project):

risk ID risk title risk descriptionrisk

type

date of

observationmanagement measure DRI due date

measure

status

105110 High expectations in

terms of modularization

Discussions in execution phase may occur

with client concerning "max modularization“

requested by client; Risk is that add. eng.

Hours for these discussions may apply

aware-

nes20.04.2018

- describe extent of modularization in

technical proposal

- include cost for

discussions in cost estimation

- A.B./ XXX

- C.D./ XXY

31.10.2018

30.11.2018

on-

going

20200 Terms of Contract

202002Unacceptable max. liability

cap (see also performance

guarantees and delays)

First project with GASUNIE which may lead to

addtional cost (eng. hours) and time delays.

risk

factor20.04.2018

Introduce acceptable liability

conditions

- A.B./ XXX 31.12.2020 on-

going

100000 Engineering &Technology

105000 Layout Concept

200000 Contractual & Commercial

overview of the risk register to all related participants

job sheets for the DRI (direct responsible individual)

in the job sheet: management measure, due dates

feedback to supervisory board, project controlling and risk management

overdue management measures influence KPI figures of the project

Page 21: Project Risk Mgt at Linde Engineering.ecrisponsor.org/presentations/lo18 1-3 - Linde_ECRI Presentation 20180607.pdf · gas, ammonia and methanol from any hydrocarbon feedstock —

21

Risk Management within Linde

Risk Report

Risk Workshop Results

Ongoing Measures (with projected finalisation date in the past highlighted in orange)

risk title due date

Short bidding and bid evaluation times during proposal phase 12.11.2015

Insufficient commissioning & start-up concept: urea 20.11.2015

Earthquake factors may be reduced 01.03.2016

Claims due to increased quantities 31.03.2016

Risk ID

601003

107001

606147

602006

Ongoing Measures (with projected finalisation date in the past highlighted in orange)

Top 20 risks

risk title

risk level

(post MM)

Growth due to urea package medium

Liquidated damages due to penalized milestones medium

Insufficient product quality/rate: urea medium

Procurement opportunities: Availability of high quality subcontractor for Urea package in case of successful initial negotiation phase (L1)opp- medium

"First of its kind" items

1. Country/client Only construction of small plant in NZ up to now

2. Technology: Urea, ATR First time construction of urea package and ATR

3. Urea EPC sub Chengda First time execution with subcontractor Chengda

4. Construction non-urea First time construction with subcontractor Fletcher

Top 10 Opportunities

risk title

risk level

(post MM)

Procurement opportunities: Availability of high quality subcontractor for Urea package in case of successful initial negotiation phase (L1)opp- medium

Value engineering measures related to other technical design conceptsopp- medium

Earthquake factors may be reduced opp- medium

Top 10 Construction risks

risk title

risk level

(post MM)

medium

Short bidding and bid evaluation times during proposal phase medium

Modularisation concept medium

Top 10 Procurement risks

risk title

risk level

(post MM)

Procurement opportunities: Availability of high quality subcontractor for Urea package in case of successful initial negotiation phase (L1)opp- medium

Extended intermediate storage cost due to bottlenecks and waiting timeslow

Missing or insufficient transportation concept low

Top 10 Project Execution risks

risk title

risk level

(post MM)

Liquidated damages due to penalized milestones medium

Insufficient support of licensors medium

Interface problems with vendors, suppliers or subcontractors (document management/handling, ProCorr, etc.)medium

Top 10 Contract risks

risk title

risk level

(post MM)

Missing or insufficient DOR between parties medium

Risks regarding taxes/customs/duties/fees low

Extreme currency fluctuations awareness

Top 10 Technology risks

risk title

risk level

(post MM)

Growth due to urea package medium

Insufficient product quality/rate: urea medium

Value engineering measures related to other technical design concepts opp- medium

Top 10 Technology risks

risk title

risk level

(post MM)

Growth due to urea package medium

Insufficient product quality/rate: urea medium

Value engineering measures related to other technical design concepts opp- medium

finalised measures: 78

ongoing measures 25

Risk Measure Status

con

tra

ctu

al

wo

rksh

op

/e

xe

cuti

on

ph

ase

0 2 4 6 8 10

0% 10% 20% 30% 40% 50%

Technical

Contractual

Environmental

Project Execution

Procurement

Construction

# of risks

risk portion

risk

cate

gory

Risks by category risk portion

# of risks

Page 22: Project Risk Mgt at Linde Engineering.ecrisponsor.org/presentations/lo18 1-3 - Linde_ECRI Presentation 20180607.pdf · gas, ammonia and methanol from any hydrocarbon feedstock —

22

Risk Management,

KPI Dashboard Page 1 (Example)

The Overall KPI weighted by the risk

score, tells, how many open

measures are delayed, devided by

numbers of projects. (open, but

deadline is exceeded)

The project KPI shows how many

open measures are delayed,

weighted by the risk score.

(Still open, but deadline is exceeded)

The number above the bar tells

how many measures are still

open for each project.

(delayed and intime).

Weighting

not relevant 1

awareness 1

low 1

medium 6

high 30

very high 207

• Crit. 2 EPC, 3 and 4

Project 1 Project 2 Project 3 Project 4 Project 5 Project 6 Project 7 Project 8 Project x

Page 23: Project Risk Mgt at Linde Engineering.ecrisponsor.org/presentations/lo18 1-3 - Linde_ECRI Presentation 20180607.pdf · gas, ammonia and methanol from any hydrocarbon feedstock —

23

–example

Guideline for

Contingency Drawdown

–introduction of upper and lower contingency thresholds per cost category

–lower threshold: Σ minimum of contingency range [Mio. € ] of corresponding risk levels

–upper threshold: Σ maximum of contingency range [Mio. € ] of corresponding risk levels

risk level Mio. €

not relevant 0 – 0,02

Low 0,02 – 0,2

medium 0,2 – 1

high 1 – 5,5

very high 5,5 - 40

upper threshold

lower threshold

selected value (e.g. 75% contingency

(linear interpolation))

total contingency

7,9 Mio.€

5,9 Mio.€

1,44 Mio.€

Targets

1. Profit trend with few fluctuations

2. Avoidance of excessive constraints for project managers

3. More consistent evaluation by introducing guidelines

Page 24: Project Risk Mgt at Linde Engineering.ecrisponsor.org/presentations/lo18 1-3 - Linde_ECRI Presentation 20180607.pdf · gas, ammonia and methanol from any hydrocarbon feedstock —

24

Profit and Contingency Tracking

time

Page 25: Project Risk Mgt at Linde Engineering.ecrisponsor.org/presentations/lo18 1-3 - Linde_ECRI Presentation 20180607.pdf · gas, ammonia and methanol from any hydrocarbon feedstock —

25

Risk Analysis on Linde Engineering Level

– risk registers of different projects, combined in one database

• comparable standard

• frequency of risks

• updating the risk register

(eliminate uncommon risks,

adopt frequent risks)

• evaluation of

➢ top risks

on group level

for entity

for region

for product line

Page 26: Project Risk Mgt at Linde Engineering.ecrisponsor.org/presentations/lo18 1-3 - Linde_ECRI Presentation 20180607.pdf · gas, ammonia and methanol from any hydrocarbon feedstock —

Thank you

for your attention