project scheduling progress report

21
Project Scheduling Progress Report By: Ernawati Mustafa Kamal School of Housing, Building & Planning Universiti Sains Malaysia

Upload: kaia

Post on 26-Feb-2016

77 views

Category:

Documents


6 download

DESCRIPTION

Project Scheduling Progress Report. By: Ernawati Mustafa Kamal School of Housing, Building & Planning Universiti Sains Malaysia. What is project?. A project is a collection of tasks that must be completed within certain time frame, with specific cost & quality. What is Project. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Project Scheduling Progress Report

Project SchedulingProgress Report

By: Ernawati Mustafa Kamal School of Housing, Building & Planning

Universiti Sains Malaysia

Page 2: Project Scheduling Progress Report

We leadWhat is project?

• A project is a collection of tasks that must be completed within certain time frame, with specific cost & quality.

Page 3: Project Scheduling Progress Report

We leadWhat is Project

What do we want?

Input• Land • Money (capital)• Labour• Material• Machine

Process Output• Design• Product• Buildings• Infrastructure

What do we do to get it done? How do we do it?

Planning

Page 4: Project Scheduling Progress Report

We leadProject Scheduling Objectives

• Estimating time of project by determining the earliest start and finish of each activity.

Finding the minimum cost schedule needed to complete the project by a certain date.

Investigating the results of possible delays in activity’s completion time.

Progress control

Smoothing out resource allocation over the duration of the project.

Page 5: Project Scheduling Progress Report

We leadProject Scheduling

• Tasks are called “activities.” - Estimated completion time (and sometimes costs) are associated with each activity.

- Activity completion time is related to the amount of resources committed to it.

- The degree of activity details depends on the application and how specific is the data.

Page 6: Project Scheduling Progress Report

We leadIdentifying the Activities of a Project

• To determine optimal schedules we need to– Identify all the project’s activities.

– Determine the precedence relations among activities.

Page 7: Project Scheduling Progress Report

We leadIdentifying Activities

• Example:

- Company A is a contractor & they need to

construct a house.

Page 8: Project Scheduling Progress Report

We leadIdentifying Activities

• Major task they need to perform & complete:

- Sub-structure

- Superstructure

- Internal Finishes

- Services and finishing

- External Works

Page 9: Project Scheduling Progress Report

We leadIdentifying Activities

• Company A needs to develop a precedence relations chart.

• The chart gives a concise set of tasks and their immediate predecessors.

Page 10: Project Scheduling Progress Report

We leadIdentifying Activities

Activity DescriptionA Piling

Sub-Structure B Pile caps and ground beams

C FrameD Upper Floors E RoofF Stairs and Ramps

Superstructure G External Walls H Windows and External DoorsI Internal Walls and Partitions J Internal Doors

Internal Finishes K Wall finishesL Floor FinishesM Ceiling Finishes

Page 11: Project Scheduling Progress Report

We leadIdentifying Activities

Activity DescriptionN Sanitary installation

Services & Finishing O Water installationP Electrical installation

Q Road, Paths, Pavings & SurfacingExternal Works R Landscaping and Irrigation Systems

S FencingT External drainageU External services

From the activity description chart, we can determine immediate predecessors for each activity.

Page 12: Project Scheduling Progress Report

We leadScheduling Tools & Techniques

• Mathematical Analysis- calculating theoretical early and late start and finish dates for all projects activities without regard for any resource limitations.

- The resulting dates are not schedule, but it indicate the time period within which activity should be schedule.

Page 13: Project Scheduling Progress Report

We leadMathematical Analysis

• Critical Path Method (CPM)

• Graphical Evaluation and Review Techniques (GERT)

• Program Evaluation and Review Technique (PERT)

Page 14: Project Scheduling Progress Report

We leadScheduling Tools & Techniques

• Bar Charts- Milestone charts- Gantt charts

• Horizontal time scale is used, often divided into weeks.

• Various operations comprising the project are listed vertically down the left-hand side.

Page 15: Project Scheduling Progress Report

We leadBar Charts

• The timing and duration of each operation indicated by a horizontal bar spanning the relevant period of weeks and shown on the same line as the operation it refers to.

Page 16: Project Scheduling Progress Report

We leadExample of Bar Charts

Page 17: Project Scheduling Progress Report

We leadExample of Bar Charts

Page 18: Project Scheduling Progress Report

We leadExample of Bar Charts

Page 19: Project Scheduling Progress Report

We leadExample of Bar Charts

Page 20: Project Scheduling Progress Report

We leadProgress Report

• It is a document used for updating the progress of work.

• Can be in many forms i.e: report (short report, formal report), memo, letter, or presentation.

Page 21: Project Scheduling Progress Report

We lead

What is expected to be in progress report?

• Background of the project• Discussion of achievement during that period

of time (including the photos).• Discussion of the problems arise• Discussion on the work to be completed.• Current cost/budget• Assessment of whether you will meet the

objectives in the proposed schedule and budget