Work Progress – Areas A, B, & C – 1st & 2nd Floors
Remaining Work to Complete:• Food Service Equipment Remaining Installation Items• Contractor Punchlist Items• Final Cleaning• Air Balancing & Commissioning of HVAC Systems
Work Progress – Area D
Remaining Work to Complete:• Auditorium Wood Panel Installation• Stage Flooring• Auditorium Carpet Installation• Gym Flooring – Sanding, Sealing & Painting• Final Cleaning• Contractor Punchlist Items• Air Balancing & Commissioning of HVAC Systems
• Sand, Seal & Paint Gym Wood Floor • Stage Floor Installation • Complete Wood Panel Installation – Auditorium• Carpet Installation - Auditorium• Asphalt Paving • Site Landscaping
Scheduled Work for Next Few Weeks