Page 1: Présentation PowerPoint - INDICO-FNAL (Indico) · Final Metrology for CRP Planarity 20/07/2016 WA-105 Technical Board 9 • Will be performed in the cryostat by Dirk’steam •

WA-105

WA105 Technical Board – 20th of July 2016

Anode Deck Structure

Design status & Interface review

B. Aimard, M. Cailles, G. Deleglise, D. Duchesneau,

N. Geffroy, Y.Karyotakis, T. Yildizkaya

Page 2: Présentation PowerPoint - INDICO-FNAL (Indico) · Final Metrology for CRP Planarity 20/07/2016 WA-105 Technical Board 9 • Will be performed in the cryostat by Dirk’steam •

Main interfaces

20/07/2016 WA-105 Technical Board 2

• CRP Design – External dimensions

• Instrumentation – Detection plane connectors

• Signal Feedthrough

• Field Cage

• Extraction Grid – Design, Tooling and Production

• Final Metrology for CRP Planarity

• Suspension Feedthrough

• CRP Transport & Cryostat insertion

• Clean Room Organisation

• Cold Bath Test

Page 3: Présentation PowerPoint - INDICO-FNAL (Indico) · Final Metrology for CRP Planarity 20/07/2016 WA-105 Technical Board 9 • Will be performed in the cryostat by Dirk’steam •

CRP Design – External dimensions

20/07/2016 WA-105 Technical Board 3

• Global CRP geometry shared with Adamo

• Global geometry and dimensions are fixed,

• Local solutions have to be confirmed by tests and manufacturers

New

Page 4: Présentation PowerPoint - INDICO-FNAL (Indico) · Final Metrology for CRP Planarity 20/07/2016 WA-105 Technical Board 9 • Will be performed in the cryostat by Dirk’steam •

Instrumentation – Detection plane connectors

20/07/2016 WA-105 Technical Board 4

• Detection Plane geometry and connection pattern are in discussion with Adamo, Cosimo, Shuoxing and Sebastien

• LEM/Anode geometry updated in the CRP 3D model with connectors

• Test Pulse Cards inserted in the 3D model, geometry to be confirmed

• General connections, Grid HV supply, signal cables paths…

• To insure CRP vertical position

• Levelmeters will be added on sides of the 6x6

• LEM capacitive measurement has to be developed and tested

• To insure CRP lateral position

• A capacitive measurement system developped at LAPP will be integrated in the extraction grid support

• A meeting will be organised in the summer to fix those points

1

3

2

4

1

3

2

4

LEM / ANODE 3D model updated

New

Page 5: Présentation PowerPoint - INDICO-FNAL (Indico) · Final Metrology for CRP Planarity 20/07/2016 WA-105 Technical Board 9 • Will be performed in the cryostat by Dirk’steam •

Signal Feedthrough

20/07/2016 WA-105 Technical Board 5

• Chimneys dimension (depth and diameter, connectors) and geometry have to be

confirmed

• Connection procedure has to be refined

Page 6: Présentation PowerPoint - INDICO-FNAL (Indico) · Final Metrology for CRP Planarity 20/07/2016 WA-105 Technical Board 9 • Will be performed in the cryostat by Dirk’steam •

Field Cage

20/07/2016 WA-105 Technical Board 6

• Discussion with Adamo, Sebastien, Cosimo, Shuoxing, Franco and LAPP electronic

team to insure :

• No geometrical interference between Field Cage and CRP in low position

• No sparking between Field Cage and CRP Extraction Grid (HV)

• A meeting will be organised soon concerning « electrical » topics

Page 7: Présentation PowerPoint - INDICO-FNAL (Indico) · Final Metrology for CRP Planarity 20/07/2016 WA-105 Technical Board 9 • Will be performed in the cryostat by Dirk’steam •

Extraction Grid – Design, Tooling and Production

20/07/2016 WA-105 Technical Board 7

• Mechanical calculation has been performed to optimize cable tension

• G10 frame has been simulated to estimate the impact of the tension

• Brazing process has been already validated

• Tooling is curently being designed

• The production will need a collaborative effort to be set up

• Production in the clean room at CERN, during CRP assembly

• No storage: brazed parts are directly installed on the CRP

Page 8: Présentation PowerPoint - INDICO-FNAL (Indico) · Final Metrology for CRP Planarity 20/07/2016 WA-105 Technical Board 9 • Will be performed in the cryostat by Dirk’steam •

Extraction Grid – Design, Tooling and Production

20/07/2016 WA-105 Technical Board 8

• One G10 comb prototype has been received yesterday :

• Length : 1m, thickness : 0,25mm, 320 guiding grooves

New

Page 9: Présentation PowerPoint - INDICO-FNAL (Indico) · Final Metrology for CRP Planarity 20/07/2016 WA-105 Technical Board 9 • Will be performed in the cryostat by Dirk’steam •

Final Metrology for CRP Planarity

20/07/2016 WA-105 Technical Board 9

• Will be performed in the cryostat by Dirk’s team

• Laser tracking will be used

• Target supports are integrated in the G10 frame on the CRP

Lase

r

Page 10: Présentation PowerPoint - INDICO-FNAL (Indico) · Final Metrology for CRP Planarity 20/07/2016 WA-105 Technical Board 9 • Will be performed in the cryostat by Dirk’steam •

Suspension Feedthrough

20/07/2016 WA-105 Technical Board 10

Fixed part

Movable part

Drive positioning system

• After many investigations, SPFT design is now converging on a safe solution to insure vertical and lateral

displacements

• Details and geometry will be presented in a future TB

Page 11: Présentation PowerPoint - INDICO-FNAL (Indico) · Final Metrology for CRP Planarity 20/07/2016 WA-105 Technical Board 9 • Will be performed in the cryostat by Dirk’steam •

CRP Transport & Cryostat insertion

20/07/2016 WA-105 Technical Board 11

• CRP handling structure has to be designed

• For the moment, no discussion about the transport box design has been started

• Procedure for transport and insertion in the cryostat has to be discussed with Adamo and CERN

• CRP handling in the cryostat should be defined with the responsible team (Who? CERN?)

Page 12: Présentation PowerPoint - INDICO-FNAL (Indico) · Final Metrology for CRP Planarity 20/07/2016 WA-105 Technical Board 9 • Will be performed in the cryostat by Dirk’steam •

Clean Room Organisation

20/07/2016 WA-105 Technical Board 12

• Should be discussed with the different actors when production and assembly processes are validated

Page 13: Présentation PowerPoint - INDICO-FNAL (Indico) · Final Metrology for CRP Planarity 20/07/2016 WA-105 Technical Board 9 • Will be performed in the cryostat by Dirk’steam •

Cold Bath Test

20/07/2016 WA-105 Technical Board 13

• To be organized in the cryostat

Page 14: Présentation PowerPoint - INDICO-FNAL (Indico) · Final Metrology for CRP Planarity 20/07/2016 WA-105 Technical Board 9 • Will be performed in the cryostat by Dirk’steam •

Conclusions

20/07/2016 WA-105 Technical Board 14

• CRP design work follows the expected schedule

• Intermediate design incorporating all parts is shared with Adamo and with the collaboration

• The final design should be completed by mid-December

• The CAD version is updated regurlarly to take into account the latest information available

from the various interfaces

It is very important to address globally the various interfaces presented here.

It is urgent to set up an active communication among the concerned actors.