© 2004 Initiatives consulting, LLC 1
PSW
The Power of Gantt
• 1 page tells a lot!
• Outlines the whole Road
• Highlights key activities & milestones
• Indicates ahead or behind schedule
• Identifies critical path activities
• Great template for shareholder & board updates
• Calculates burn rate – if costs are entered
• Resource needs and over-allocations
– if effort is entered
ID Task Name1 Finalize project plan with Reflexite
2 Understand Reflexite's business, mission…
3 Understand Reflexite's competencies
4 Technical understanding of components
5 General optical components
6 Major subsystems
7 UPDATE #1
8 Articulate overlap (competencies to components)
9 Market understanding
10 Overall market (industry size, trends, regulations…)
11 Identify key players
12 Determine focus, key words
13 Search for players
14 Summarize players (build table)
15 UPDATE #2
16 Identify & filter opportunities
17 Brainstorm & scan for opportunities (10-50)
18 Start building ranking filters
19 Filter, prioritize players & opportunities (5-10)
20 Summarize top opportunities
21 Discuss & embellish (5 ideas)
22 Write 1 pg. Plan for action
23 Write 1-2 pg summaries (5 ideas)
24 Project close
25 Organize scrapbook
26 Create & deliver closing presentation
5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 4November December January February March
© 2004 Initiatives consulting, LLC 2
PSW
Envision
“Could I sell one tomorrow?”
Step 1
Envision the technical, marketing, and business tasks
that get your idea from where it is right now to a product that is routinely sold.
?
© 2004 Initiatives consulting, LLC 3
PSW
Task Table: Technology
Task Who* Effort Duration
*Underline the “leader”
Find & set up facilities. Hire Tech1 GandalphFrodo
1 day/wk-
2 months
Repeat base-line experiments with higher sample size and technochlorphenobob
FrodoTech1
1 day/wk3 day/wk
3 months
Design & build beta work units BilboOutsourced Eng
1 day/wk-
2 months
Run final beta prototype validation (vendor acceptance, operational features only)
FrodoOutsourced EngTech1
1 day/wk-3 days/wk
1 months
Repeat validation on beta with technochlorophenobob
FrodoTech1
0.5 day/wk5 days/wk
1 months
Step 2
© 2004 Initiatives consulting, LLC 4
PSW
Project Plan: Technology
Qtr1 Qtr2 Qtr3
•Repeat base-line
•Set up facilities
•Final Beta validation
Laboratory & prototyping
•Complete technology plan
Ready to sell!
Administrative
•Test Beta unit
Validation
•Finalize Beta unit
Lab ready
Step 3
© 2004 Initiatives consulting, LLC 5
PSW
Top 7 Worst Red Flags shown by early task tables & Gantt charts
• Blank page– “You can’t plan technology!” “Too many unknowns at this point!”
• Too many pages– Summarize, Roll-up tasks. Make the milestones more significant
• Hard to follow. Not organized. The story doesn’t flow – Group by phases or task categories
• Progresses too quickly– Be realistic with the effort & duration required
• No setup. No lead-times– Provide time to get facilities and equipment
• All activities begin at once and overlap– Recognize links (dependencies) and resource constraints
• Inappropriate time scale– Quarters or years are best for the big picture