 PUBLIC WORKS DEPARTMENTWATER RESOURCES DEPARTMENTProceeding of the Engineer-in-Chief, WRD and Chief Engineer (General)PWD, Chepauk, Chennai – 600 005.Present:Er S.Jeyaraman,B.E., F.I.E, F.I.V., Engineer-in-Chief, WRD and Chief Engineer (General) PWD,* * * * * * * *Proceedings No. HDO / Sr.DO/31257/ 2010-2 Dated 06.04.2010Sub:Steel – Revised rate for steel for adoption in estimates with effect from 01.04.2010 – Approved – Communicated.

Page 2: Public Works Department Water Resources Department Proceeding of the Engineer

 Ref: This office proceeding No. HDO / 31257/ 2009-2 Dated21.05.2009****** The cost of steel fixed and communicated already in this officeproceedings cited is hereby revised and fixed as below for adoption in theestimateswith effect from 01.04.2010.Steel Rods of all sizes Rs. 36000/- per M.T (Rupees thirty six thousand only) 2. The above rate is inclusive of all taxes, freight charges at Stockyard/ dealer’s godown. Necessary lead charges (i.e. excluding loading andunloading charges) as applicable as per conveyance table may be allowedfrom the stockyard / dealer’s godown to the site of work, if duly certified byan officer not below the rank of Assistant Executive Engineer.3. However, in the case, if the source is specified as

“Stockyard”, thesame shall be decided and approved by the Superintending Engineersconcerned.4. The receipt of this proceeding shall be acknowledged.Engineer-in-Chief, WRD

Page 3: Public Works Department Water Resources Department Proceeding of the Engineer

andChief Engineer (General), PWD. To1. All the Chief Engineers of WRD, PWD.2. 

Page 4: Public Works Department Water Resources Department Proceeding of the Engineer

 The Chief Engineer (Buildings) PWD, Chennai.5.3.  The Chief Engineer, WRD, PWD, D R & C S, Chennai.54.  The Chief Engineer (General) Highways

Page 5: Public Works Department Water Resources Department Proceeding of the Engineer

Department, Chennai.5.

 

 5. 

Page 6: Public Works Department Water Resources Department Proceeding of the Engineer

All the Superintending Engineers of WRD Circles for necessary action.Copy to the Special Secretary to Government, Finance Department, Chennai.9Copy to the Deputy Secretary

Page 7: Public Works Department Water Resources Department Proceeding of the Engineer

to Government, Finance Department, Chennai.9Copy to the Principal Secretary to Government, Public Works Department,Chennai.9.Copy to the Special Secretary

Page 8: Public Works Department Water Resources Department Proceeding of the Engineer

to Government, Public Works Department,Chennai.9.Copy to the Commissioner, Corporation of Chennai, Chennai.3.Copy to the Engineering Director, TWAD

Page 9: Public Works Department Water Resources Department Proceeding of the Engineer

Board, Chennai.5.Copy to the Chief Engineer (Civil Design), TNEB, Anna Salai, Chennai.2.Copy to the Chief Engineer (Civil Design), Tamil Nadu Slum Clearance

Page 10: Public Works Department Water Resources Department Proceeding of the Engineer

Board,Kamarajar salai, Chennai.5.Copy to the Director of Technical Education, Guindy, Chennai.25.Copy to the Chief Engineer, Tamil Nadu State Police Housing

Page 11: Public Works Department Water Resources Department Proceeding of the Engineer

Corporation,Chennai.10.Copy to the Joint Chief Engineer (General), PWD, Chennai.5.Copy to the Joint Chief Engineer (Irrigation), WRD, Chennai.5.Copy to

Page 12: Public Works Department Water Resources Department Proceeding of the Engineer

the Joint Chief Engineer (Buildings), PWD, Chennai.5Copy to the Superintending Engineer, PWD, Planning and Designs Circle,Chennai.5.Copy to the Head Draughting Officer,

Page 13: Public Works Department Water Resources Department Proceeding of the Engineer

Office of the Engineer-in-Chief, WRDand Chief Engineer (General) PWD, Chennai.5.Copy to the Head Draughting Officer I & II, O/o the Chief Engineer (Buildings),PWD,

Page 14: Public Works Department Water Resources Department Proceeding of the Engineer

Chennai.5.Copy to the Special Grade DO, Sr DOs, DO and JDOs in HDO section, Officeof the Engineer-in-Chief WRD and Chief Engineer (General) PWD, Chennai.5.Copy to

Page 15: Public Works Department Water Resources Department Proceeding of the Engineer

Stock file.Spare copies – 5 Nos. 

 INDEXSl.No.Description Page

Page 16: Public Works Department Water Resources Department Proceeding of the Engineer

1 General Note 01-072 General Note – Table 08-103 Rates of Labour 11-154 Rates of Materials 16-235 Rates of Works

Page 17: Public Works Department Water Resources Department Proceeding of the Engineer

24-356 Head Load 367 Conveyance Table in Plains 378 Conveyance Table in Hills 389 Rates of Other

Page 18: Public Works Department Water Resources Department Proceeding of the Engineer

Construction Materials 39-6110 Rates of Electrical Items of Works 62-84 

 GENERAL NOTE1. 

Page 19: Public Works Department Water Resources Department Proceeding of the Engineer

For special nature of works, for which rates are not covered in theSchedule of Rates, such as road works, water supply, drainage, etc.,separate schedule of rates issued by the respective officers /

Page 20: Public Works Department Water Resources Department Proceeding of the Engineer

department / board are to be followed.2. Extra percentage other than those for the specified areas noted below,shall not be allowed.1. 

Page 21: Public Works Department Water Resources Department Proceeding of the Engineer

For the Entire State(i) An extra 10%on Labour, Rates of work where human labour alone isinvolved and for Head load shall be allowed for the works in respect of 

Page 22: Public Works Department Water Resources Department Proceeding of the Engineer

Municipal Corporationsviz. (I) Chennai City and 32 Km belt aroundChennai City limit (II) Coimbatore Corporation limit (III) Trichy Corporationlimit, (IV) Madurai Corporation limit, (V) Salem

Page 23: Public Works Department Water Resources Department Proceeding of the Engineer

Corporation limit, (VI)Tirunelveli Corporation limit, (VII) Tiruppur Corporation limit, (VIII) ErodeCorporation limit, (IX) Thoothukudi Corporation limit and (X)

Page 24: Public Works Department Water Resources Department Proceeding of the Engineer

VelloreCorporation limit. (ii) An extra 5% forLabour, Rates of work where human labour alone isinvolved and for Head load shall be

Page 25: Public Works Department Water Resources Department Proceeding of the Engineer

allowed for the works in theMunicipallimits. This extra percentage shall be applicable only for the municipalareas where different extra percentages allowed already.(iii) 

Page 26: Public Works Department Water Resources Department Proceeding of the Engineer

An extra 10% forRates of labour and Rates of work where human labouralone is involved shall be allowed forsewer works under unhygieniccondition.(iv) 

Page 27: Public Works Department Water Resources Department Proceeding of the Engineer

An extra 20%over the rates of labour, Rates of work where humanlabour alone is involved and conveyance charges shall be allowed for worksin the campus of central jails.