8/10/2019 Pumping Station Programme
1/11
-
8/10/2019 Pumping Station Programme
2/11
Sheet 2 of 11
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
MS42 CCTV System 18 14MAR09 02APR09
MS34 Mimic Panel 18 14MAR09 02APR09
MS33 Control Desk 18 14MAR09 02APR09
MS36 Lighting fixtures 18 14MAR09 02APR09
MS18 Ceiling materials 18 21MAR09 09APR09
MS19 Paints 18 21MAR09 09APR09
MS17 Wall & Floor Tiles 18 21MAR09 09APR09
MS40 Lifting Equipment 18 22MAR09 11APR09
MS12 DI Cover/Surface box 18 04APR09 23APR09
MS31 HVAC Systems 18 08APR09 28APR09
MS28 MSB/MCC/Control Panels 18 22APR09 12MAY09
MS21 Doors/Windows/Louvers 18 04MAY09 24MAY09
MS24 Marker post 18 12MAY09 01JUN09
MS22 Plumbing and Sanitary fittings 18 23MAY09 11JUN09
MS43 Reservoir Instrumentation 18 21JUN09 11JUL09
MS23 Metal works 18 04JUL09 23JUL09MS27 Transformers 18 30JUL09 19AUG09
MS39 Fire detection & Fighting systems 18 30JUL09 19AUG09
MS41 Boundary and Street Lighting 18 25AUG09 14SEP09
MS30 Cables 18 09SEP09 29SEP09
MS32 Cable tray & Accessories 18 09SEP09 29SEP09
MATERIAL APPROVALS
MA01 Pipes & Fittings 1 02DEC08 02DEC08
MA08 Wrapping Materials 1 07DEC08 07DEC08MA10 Polyethylene Sleeving 1 14DEC08 14DEC08
MA11 Trench Marker tape 1 14DEC08 14DEC08
MA02 Butterfly Valves 1 16DEC08 16DEC08
MA03 Gate Valves 1 16DEC08 16DEC08
MA04 Flap Valves 1 16DEC08 16DEC08
MA05 Air Valves 1 16DEC08 16DEC08
MA15 Tanking materials 1 21DEC08 21DEC08
MA14 Reinforcement 1 21DEC08 21DEC08
MA13 Concrete 18 25DEC08 14JAN09MA25 Pumps 18 01FEB09 21FEB09
MA20 Boundary Wall sections 18 15FEB09 07MAR09
MA09 Couplings,Flange Adaptors,Dismantling Joints 1 16FEB09 16FEB09
MA29 VSD Units 18 10MAR09 30MAR09
MA26 Flow meters & Flow control Valves 18 11MAR09 31MAR09
MA38 Pressure guages/Pressure switches/Transmitters 18 11MAR09 31MAR09
MA07 Non - Return Valve 18 22MAR09 11APR09
MA37 PLC/Marshalling Cabinets 18 22MAR09 11APR09
MA35 Announciator Panel 18 22MAR09 11APR09
MA34 Mimic Panel 18 22MAR09 11APR09
MA33 Control Desk 18 22MAR09 11APR09
MA06 Altitude Valves 18 22MAR09 11APR09
MA36 Lighting fixtures 18 22MAR09 11APR09
2008 2009 2010S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Sheet 2 of 11
-
8/10/2019 Pumping Station Programme
3/11
Sheet 3 of 11
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
MA19 Paints 18 29MAR09 18APR09
MA40 Lifting Equipment 18 30MAR09 19APR09
MA42 CCTV System 18 04APR09 23APR09
MA16 Block & accessories 18 05APR09 25APR09
MA31 HVAC Systems 18 16APR09 06MAY09
MA18 Ceiling materials 18 19APR09 09MAY09
MA17 Wall & Floor Tiles 18 19APR09 09MAY09
MA28 MSB/MCC/Control Panels 18 30APR09 20MAY09
MA12 DI Cover/Surface box 18 03MAY09 23MAY09
MA21 Doors/Windows/Louvers 18 12MAY09 01JUN09
MA24 Marker post 18 20MAY09 09JUN09
MA22 Plumbing and Sanitary fittings 18 31MAY09 20JUN09
MA23 Metal works 18 12JUL09 01AUG09
MA43 Reservoir Instrumentation 18 12JUL09 01AUG09
MA27 Transformers 18 08AUG09 27AUG09
MA39 Fire detection & Fighting systems 18 08AUG09 27AUG09MA41 Boundary & Street Lighting 18 15SEP09 05OCT09
MA30 Cables 18 17SEP09 07OCT09
MA32 Cable tray & Accessories 18 17SEP09 07OCT09
DESIGN PREPARATION
DP01 Topographic Survey -RPS Site 10 20NOV08 01DEC08
DP02 Topographic Survey - Pipeline Route 24 02DEC08 29DEC08
DP03 Boreholes & Geotechnical - RPS Site 6 02DEC08 08DEC08
DP06 General Layouts,Levels&Preliminary design - RPS 15 04DEC08 21DEC08DP07 Detailed design - Reservoirs 45 10DEC08 31JAN09
DP15 Hydraulic Analysis 15 31DEC08 17JAN09
DP12 Detailed design - PS Mechanical arrangement 20 31DEC08 22JAN09
DP10 Detailed design - RPS site works 60 31DEC08 10MAR09
DP04 Trailpits & Geotechnical - Pipeline route 24 04JAN09 31JAN09
DP08 Detailed design - Pipeline Plan & Profile 45 10JAN09 02MAR09
DP09 Detailed design - Chambers - Mechanical 45 18JAN09 10MAR09
DP13 Detailed design - PS Civil,Electrical & Instru., 24 03FEB09 02MAR09
DP14 Detailed design - PS Structural 12 12MAR09 25MAR09DP11 Detailed design - Chambers Structural 24 21MAR09 16APR09
DP16 Surge Analysis 20 22MAR09 13APR09
DESIGN SUBMITTALS
DS01 Topographic Survey -RPS Site 1 02DEC08 02DEC08
DS03 Boreholes & Geotechnical - RPS Site 1 09DEC08 09DEC08
DS06 General Layouts,Levels&Preliminary design - RPS 6 16DEC08 22DEC08
DS07 Detailed design - Reservoirs 30 29DEC08 01FEB09
DS02 Topographic Survey - Pipeline Route 1 30DEC08 30DEC08DS15 Hydraulic Analysis 7 11JAN09 18JAN09
DS12 Detailed design - PS Mechanical arrangement 6 19JAN09 25JAN09
DS04 Trailpits & Geotechnical - Pipeline route 1 01FEB09 01FEB09
2008 2009 2010S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Sheet 3 of 11
-
8/10/2019 Pumping Station Programme
4/11Sheet 4 of 11
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
DS10 Detailed design - RPS site works 24 12FEB09 11MAR09
DS08 Detailed design - Pipeline Plan & Profile 24 14FEB09 12MAR09
DS13 Detailed design - PS Civil,Electrical & Instru., 12 18FEB09 03MAR09
DS09 Detailed design - Chambers - Mechanical 12 26FEB09 11MAR09
DS14 Detailed design - PS Structural 7 19MAR09 26MAR09
DS11 Detailed design - Chambers Structural 12 05APR09 18APR09
DS16 Surge Analysis 7 15APR09 22APR09
DESIGN APPROVALS
DA01 Topographic Survey -RPS Site 1 03DEC08 03DEC08
DA03 Boreholes & Geotechnical - RPS Site 1 18DEC08 18DEC08
DA06 General Layouts,Levels&Preliminary design - RPS 6 24DEC08 30DEC08
DA02 Topographic Survey - Pipeline Route 1 08JAN09 08JAN09
DA07 Detailed design - Reservoirs 30 12JAN09 15FEB09
DA15 Hydraulic Analysis 7 19JAN09 26JAN09
DA12 Detailed design - PS Mechanical arrangement 6 27JAN09 02FEB09
DA04 Trailpits & Geotechnical - Pipeline route 1 18FEB09 18FEB09
DA10 Detailed design - RPS site works 24 21FEB09 19MAR09
DA08 Detailed design - Pipeline Plan & Profile 24 22FEB09 21MAR09
DA13 Detailed design - PS Civil,Electrical & Instru., 12 26FEB09 11MAR09
DA09 Detailed design - Chambers - Mechanical 12 07MAR09 19MAR09
DA14 Detailed design - PS Structural 7 28MAR09 04APR09
DA11 Detailed design - Chambers Structural 12 13APR09 26APR09
DA16 Surge Analysis 7 23APR09 30APR09
PROCUREMENTPLACING ORDER
PO01 Pipes & Fittings - Order - 1 6 03DEC08 09DEC08
PO13 Wrapping Materials - Order 1 6 25DEC08 31DEC08
PO03 Butterfly Valves - Order - 1 6 25DEC08 31DEC08
PO05 Gate Valves - Order - 1 6 25DEC08 31DEC08
PO07 Flap Valves - Order - 1 6 25DEC08 31DEC08
PO09 Air Valves - Order - 1 6 25DEC08 31DEC08
PO17 Polyethylene Sleeving 6 14JAN09 20JAN09
PO21 Tanking materials 6 15JAN09 21JAN09
PO20 Reinforcement 6 26JAN09 01FEB09
PO31 Pumps 6 22FEB09 28FEB09
PO26 Boundary Wall sections 6 08MAR09 14MAR09
PO15 Couplings,Flange Adaptors,Dismantling Joints - 1 6 14MAR09 19MAR09
PO02 Pipes & Fittings - Order - 2 6 21MAR09 26MAR09
PO48 CCTV System 6 25APR09 30APR09
PO06 Gate Valves - Order - 2 6 25APR09 30APR09
PO08 Flap Valves - Order - 2 6 25APR09 30APR09
PO16 Couplings,Flange Adaptors,Dismantling Joints - 2 6 26APR09 02MAY09
PO14 Wrapping Materials - Order 2 6 26APR09 02MAY09
PO18 Trench Marker tape 6 04MAY09 10MAY09
2008 2009 2010S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Sheet 4 of 11
-
8/10/2019 Pumping Station Programme
5/11Sheet 5 of 11
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
PO35 VSD Units 6 05MAY09 11MAY09
PO32 Flow meters & Flow control Valves 6 06MAY09 12MAY09
PO11 Altitude Valves 6 17MAY09 23MAY09
PO46 Lifting Equipment 6 25MAY09 31MAY09
PO42 Lighting fixtures 6 03JUN09 09JUN09
PO44 Pressure guages/Pressure switches/Transmitters 6 10JUN09 16JUN09
PO37 HVAC Systems 6 11JUN09 17JUN09
PO39 Control Desk 6 21JUN09 27JUN09
PO34 MSB/MCC/Control Panels 6 25JUN09 01JUL09
PO40 Mimic Panel 6 25JUN09 01JUL09
PO41 Announciator Panel 6 29JUN09 05JUL09
PO43 PLC/Marshalling Cabinets 6 02JUL09 08JUL09
PO04 Butterfly Valves - Order - 2 6 04JUL09 09JUL09
PO12 Non-return Valves 6 08JUL09 14JUL09
PO24 Ceiling materials 6 19JUL09 25JUL09
PO23 Wall & Floor Tiles 6 19JUL09 25JUL09PO19 DI Cover/Surface box 6 02AUG09 08AUG09
PO49 Reservoir Instrumentation 6 02AUG09 08AUG09
PO33 Transformers 6 29AUG09 03SEP09
PO25 Paints 6 06SEP09 12SEP09
PO22 Block & accessories 6 13SEP09 19SEP09
PO10 Air Valves - Order - 2 6 19SEP09 24SEP09
PO45 Fire detection & Fighting systems 6 03OCT09 08OCT09
PO47 Boundary & Street Lighting 6 06OCT09 12OCT09
PO38 Cable tray & Accessories 6 08OCT09 14OCT09
PO29 Metal works 6 11OCT09 17OCT09
PO36 Cables 6 12NOV09 18NOV09
PO27 Doors/Windows/Louvers 6 29DEC09 04JAN10
PO30 Marker post 6 06JAN10 12JAN10
PO28 Plumbing and Sanitary fittings 6 17JAN10 23JAN10
MATERIAL DELIVERY
D26 Reinforcement 150 09MAR09 30AUG09
D27 Tanking materials 6 02APR09 08APR09D18 Wrapping Materials - Shipment 1 6 16APR09 22APR09
D23 Polyethylene Sleeving 6 06MAY09 12MAY09
D01 Pipes&Fittings - Shipment 1 6 11MAY09 17MAY09
D02 Pipes & Fittings - Shipment 2 6 10JUN09 16JUN09
D03 Pipes & Fittings - Shipment 3 6 11JUL09 16JUL09
D08 Butterfly Valves - Shipment 1 6 30JUL09 05AUG09
D10 Gate Valves - Shipment 1 6 30JUL09 05AUG09
D12 Flap Valves - Shipment 1 6 30JUL09 05AUG09
D14 Air Valves - Shipment 1 6 30JUL09 05AUG09
D53 Pipes&Fittings-Shipment4 6 09AUG09 15AUG09
D32 Boundary Wall sections 270 19AUG09 29JUN10
D24 Trench Marker tape 6 24AUG09 30AUG09
D19 Wrapping Materials - Shipment 2 6 10SEP09 16SEP09
2008 2009 2010S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Sheet 5 of 11
-
8/10/2019 Pumping Station Programme
6/11Sheet 6 of 11
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
D04 Pipes & Fittings - Shipment5 6 12SEP09 17SEP09
D21 Couplings,Flange Adaptors,Dismantling Joints - 1 6 12SEP09 17SEP09
D54 Pipes&Fittings-Shipment6 6 11OCT09 17OCT09
D28 Block & accessories 30 25OCT09 28NOV09
D05 Pipes & Fittings - Shipment 7 6 10NOV09 16NOV09
D55 Pipes&Fittings-Shipment8 6 09DEC09 15DEC09
D11 Gate Valves - Shipment 2 6 02JAN10 07JAN10
D13 Flap Valves - Shipment 2 6 02JAN10 07JAN10
D22 Couplings,Flange Adaptors,Dismantling Joints - 2 6 03JAN10 09JAN10
D06 Pipes & Fittings - Shipment9 6 09JAN10 14JAN10
D52 Lifting Equipment 6 20JAN10 26JAN10
D16 Altitude Valves 6 24JAN10 30JAN10
D44 Cable tray & Accessories 6 28JAN10 03FEB10
D31 Paints 6 31JAN10 06FEB10
D37 Pumps 6 02FEB10 08FEB10
D20 Wrapping Materials - Shipment 3 6 04FEB10 10FEB10D43 HVAC Systems 6 18FEB10 24FEB10
D07 Pipes&Fittings - Shipment 10 6 09MAR10 15MAR10
D51 Fire detection & Fighting systems 6 16MAR10 22MAR10
D17 Non-return Valves 6 17MAR10 23MAR10
D48 Lighting fixtures 6 17MAR10 23MAR10
D30 Ceiling materials 6 28MAR10 03APR10
D29 Wall & Floor Tiles 6 28MAR10 03APR10
D40 MSB/MCC/Control Panels 6 08APR10 14APR10
D42 Cables 6 08APR10 14APR10
D25 DI Cover/Surface box 6 11APR10 17APR10
D41 VSD Units 6 15APR10 21APR10
D09 Butterfly Valves - Shipment 2 6 17APR10 22APR10
D39 Transformers 6 20APR10 26APR10
D33 Doors/Windows/Louvers 6 20APR10 26APR10
D15 Air Valves - Shipment 2 6 24APR10 29APR10
D38 Flow meters and Flow control valves 6 01MAY10 06MAY10
D35 Metal works 6 16MAY10 22MAY10
D45 Control Desk 6 26MAY10 01JUN10
D50 Pressure guages/Pressure switches/Transmitters 6 02JUN10 08JUN10
D46 Mimic Panel 6 06JUN10 12JUN10
D34 Plumbing and Sanitary fittings 6 13JUN10 19JUN10
D47 Announciator Panel 6 15JUN10 21JUN10
D56 Boundary & Street Lighting 6 15JUN10 21JUN10
D49 PLC/Marshalling Cabinets 6 24JUN10 30JUN10
D36 Marker post 6 07JUL10 13JUL10
D58 Reservoir Instrumentation 6 13JUL10 19JUL10
D57 CCTV System 6 11AUG10 17AUG10
2008 2009 2010S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Sheet 6 of 11
-
8/10/2019 Pumping Station Programme
7/11Sheet 7 of 11
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
CONSTRUCTION
RESERVOIR - 1
RE101 Setting out 3 03JAN09 05JAN09
RE102 Excavation 42 06JAN09 23FEB09
RE103 Preparation of Excavated surfaces 12 24FEB09 09MAR09RE104 Blinding 60 10MAR09 18MAY09
RE105 Wall footing & Floor Slab 102 18MAR09 14JUL09
RE106 Wall 102 18APR09 13AUG09
RE107 Columns 102 18APR09 13AUG09
RE108 Roof Slab 204 18MAY09 10JAN10
RE109 Prestressing Wall & Shotcreting 102 11JAN10 09MAY10
RE111 Roof Coating 42 10MAY10 27JUN10
RE113 Hydro testing 32 28JUN10 03AUG10
RE114 Back filling 30 04AUG10 07SEP10
RE115 External Wall Coating 30 08SEP10 12OCT10
RE116 Interlock,gravel around reservoir , stairs. 30 16SEP10 20OCT10
RESERVOIR - 2
RE201 Setting out 3 06JAN09 08JAN09
RE202 Excavation 60 24FEB09 04MAY09
RE203 Preparation of Excavated surfaces 12 05MAY09 18MAY09
RE204 Blinding 60 19MAY09 27JUL09
RE205 Wall footing & Floor Slab 102 15JUL09 10NOV09RE206 Wall 102 12AUG09 08DEC09
RE207 Columns 102 12AUG09 08DEC09
RE208 Roof Slab 204 09SEP09 04MAY10
RE209 Prestressing Wall & Shotcreting 102 05MAY10 31AUG10
RE213 Hydro testing 32 01SEP10 07OCT10
RE211 Roof Coating 36 01SEP10 12OCT10
RE214 Back filling 24 09OCT10 04NOV10
RE215 External Wall Coating 24 06NOV10 02DEC10
RE216 Interlock,gravel around reservoir, stairs 26 11NOV10 11DEC10
PUMP HOUSE
PUMP HOUSE STRUCTURAL & CIVILPHC01 Setting Out 6 12MAR09 18MAR09
PHC02 Excavation 30 19MAR09 22APR09
PHC03 Blinding - Underground Pump Room 6 23APR09 29APR09
PHC04 Tanking & Screed - Underground Pump room 6 30APR09 06MAY09
PHC05 Base Slab - Underground Pump room 30 07MAY09 10JUN09
PHC06 Walls- Underground Pump room 30 11JUN09 15JUL09
PHC07 Backfilling - Underground Pump room 6 16JUL09 22JUL09
PHC08 Blinding - Cable gallery 4 23JUL09 27JUL09
PHC09 Tanking & Screed - Cable Gallery 4 28JUL09 01AUG09
PHC10 Base slab - Cable gallery 12 02AUG09 15AUG09
2008 2009 2010S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Sheet 7 of 11
-
8/10/2019 Pumping Station Programme
8/11
Sheet 8 of 11
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
PHC11 Walls - Cable Gallery 18 16AUG09 05SEP09
PHC12 Backfilling - Cable Gallery 4 06SEP09 09SEP09
PHC13 Column Footings& Ground Beams 12 10SEP09 23SEP09
PHC15 Ground Slab 12 24SEP09 07OCT09
PHC17 Columns 6 08OCT09 14OCT09
PHC18 Low Level Roof Slab & Upstands 30 15OCT09 18NOV09
PHC19 High Level Roof Slab & Upstands 30 19NOV09 23DEC09PHC20 Blockworks 30 24DEC09 27JAN10
PHC21 Internal Plaster 22 11JAN10 04FEB10
PHC22 External Plaster 40 06FEB10 23MAR10
PHC24 Internal Painting - First coat 22 07FEB10 03MAR10
PHC23 Roof Waterproofing 30 15FEB10 21MAR10
PHC25 External Painting - First coat 30 24MAR10 27APR10
PHC26 Ceiling 45 05APR10 26MAY10
PHC27 Floor & Wall Tiles 45 28APR10 19JUN10
PHC28 Doors/Windows/Louvres 18 20JUN10 10JUL10PHC29 Sanitary fixtures 12 20JUN10 03JUL10
PHC30 Chequer Plates/Grating/Floorings/Handrails 24 14OCT10 10NOV10
PHC31 Painting final coat 24 11NOV10 08DEC10
PUMP HOUSE - MECH/ELECT/INSTRUMENTATIONPHE01 Lifting Equipment 36 07FEB10 20MAR10
PHE06 Cable tray & accessories 150 15FEB10 08AUG10
PHE02 Pumps 166 21MAR10 29SEP10
PHE05 HVAC System 60 22MAR10 30MAY10
PHE14 Fire Detection & Fighting systems 150 23MAR10 13SEP10PHE03 Pipes,Fitting & Valves 175 24MAR10 13OCT10
PHE15 Transformers & HV Cabling works 130 28APR10 26SEP10
PHE07 MSB/MCC/Control Panels/Cabling 130 06MAY10 04OCT10
PHE08 VSD Units 75 02JUN10 28AUG10
PHE12 Lighting Fixtures 75 10JUN10 05SEP10
PHE09 Measuring and Control Instrumentation 60 01JUL10 08SEP10
PHE04 Pressure guages,Transmitter & switches 24 11AUG10 07SEP10
GUARD HOUSE
G01 Setting out 6 27JUL09 02AUG09
G02 Excavation 6 03AUG09 09AUG09
G03 Column Footings 18 10AUG09 30AUG09
G04 Groun Beams 18 31AUG09 20SEP09
G05 Ground Slab 18 21SEP09 11OCT09
G06 Columns 18 12OCT09 01NOV09
G07 Roof slab & Upstands 30 02NOV09 06DEC09
G08 Blockworks 24 09JAN10 04FEB10
G09 Internal Plaster 24 06FEB10 04MAR10
G11 Roof Waterproofing 30 15FEB10 21MAR10
G10 External Plaster 24 22MAR10 18APR10
G15 Painting first coat 18 19APR10 09MAY10
2008 2009 2010S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Sheet 8 of 11
-
8/10/2019 Pumping Station Programme
9/11
Sheet 9 of 11
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
G12 Floor/Wall/Ceiling Finishes 30 10MAY10 13JUN10
G16 Electrical/Fire detection & fighting system 90 14JUN10 26SEP10
G13 Doors/Windows/Louvers 18 19JUL10 08AUG10
G14 Sanitary fixtures 24 09AUG10 05SEP10
G17 Painting final coat 24 27SEP10 24OCT10
SWITCHGEAR BUILDING
SW01 Setting out 6 08AUG09 13AUG09
SW02 Excavation 6 15AUG09 20AUG09
SW03 Column Footing 12 22AUG09 03SEP09
SW04 Ground beams 12 05SEP09 17SEP09
SW05 Ground Slab 12 19SEP09 01OCT09
SW06 Columns 12 03OCT09 15OCT09
SW07 Roof slab & Upstands 30 17OCT09 19NOV09
SW08 Blockworks 24 23DEC09 19JAN10
SW09 Internal Plaster 24 20JAN10 16FEB10
SW10 External Plaster 24 17FEB10 16MAR10
SW11 Roof Waterproofing 24 17MAR10 13APR10
SW12 Floor/Wall/Ceiling Finishes 30 14APR10 18MAY10
SW13 Door/Windows/Louvres 12 19MAY10 01JUN10
SW14 Painting - first coat 12 02JUN10 15JUN10
SW15 Electrical works 65 16JUN10 30AUG10
SW16 Painting final coats 12 31AUG10 13SEP10
TANKER FILLING STATION
L01 Setting out 7 30MAY09 06JUN09
L02 Excavation 10 07JUN09 17JUN09
L03 Pump Room Civil works 180 18JUN09 13JAN10
L04 Mechanical & Electrical works 180 14JAN10 11AUG10
LAGOON
LG01 Setting out 7 12MAY09 19MAY09
LG02 Excavation including forming slopes 45 20MAY09 11JUL09
LG03 Boreholes 26 12JUL09 10AUG09
LG05 Concrete to Lagoon side 150 11AUG09 01FEB10
LG04 Drain Pipelines & Manholes 150 20OCT09 12APR10
LG06 Metal work & Finishes 90 23MAY10 04SEP10
BOUNDARY WALL
B01 Setting out 60 30MAY09 06AUG09
B02 Excavation 105 12JUL09 10NOV09
B03 Blinding 105 20JUL09 18NOV09
B04 Column Footing 260 27AUG09 26JUN10
B05 Columns 260 14SEP09 13JUL10
B06 Lower Wall Panels 260 01OCT09 31JUL10
2008 2009 2010S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Sheet 9 of 11
2008 2009 2010
-
8/10/2019 Pumping Station Programme
10/11
Sheet 10 of 11
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
B07 Upper Wall Panels 260 03NOV09 01SEP10
B08 Finishes & Gates 60 02SEP10 10NOV10
RESERVOIR INLET & OUTLET , TFS INLET PIPELINES
R01 Setting Out 40 12MAY09 27JUN09
R02 Excavation 110 27AUG09 02JAN10
R03 Pipe wrapping 110 19SEP09 24JAN10
R04 Bedding 110 19SEP09 24JAN10
R05 Pipe Laying 110 27SEP09 01FEB10
R09 Chambers - Base & Walls 180 01OCT09 28APR10
R06 Surround and partial Backfilling 110 05OCT09 09FEB10
R07 Initial Testing 60 20DEC09 27FEB10
R10 Chambers - Fitting & Valves 120 23JAN10 10JUN10
R08 Final Backfiiling 90 24JAN10 08MAY10
R11 Chambers - Metalworks,covers & Finishes 120 12JUN10 28OCT10
PIPELINE: RISING MAIN 2
12100M-DN900,325M-DN600 & 70M-DN300R201 Survey & Setting out Pipeline Route 300 22FEB09 06FEB10
R202 Trench Excavation 400 02MAR09 10JUN10
R211 Pipe wrapping 340 18MAY09 17JUN10
R203 Bedding 340 19MAY09 19JUN10
R204 Pipe Laying 340 27MAY09 27JUN10
R205 Pipe surround & Partial back filling 340 04JUN09 05JUL10
R207 Chambers - Base & Wall 340 15JUN09 15JUL10
R214 Road crossing works 320 01JUL09 08JUL10
R206 Initial Hydrotest 320 13AUG09 21AUG10
R209 Final Backfilling 340 31AUG09 30SEP10
R212 Chambers - Fittings & Valves 270 22SEP09 02AUG10
R210 Reinstatement 270 16DEC09 26OCT10
R213 Chambers- Covers & Finishes 90 03AUG10 15NOV10
PIPELINE: RISING MAIN - 1
8100M-DN900 & 60M-DN600RI201 Survey & Setting out Pipeline Route 275 30MAR09 13FEB10
RI202 Trench Excavation 330 05MAY09 24MAY10
RI203 Pipe wrapping 330 17JUN09 06JUL10
RI204 Bedding 330 17JUN09 06JUL10
RI205 Pipe Laying 330 25JUN09 14JUL10
RI206 Pipe surround & Partial back filling 330 12JUL09 31JUL10
RI207 Initial Hydrotest 330 05AUG09 24AUG10
RI208 Chambers - Base & Wall 300 06AUG09 21JUL10
RI211 Final Backfilling 330 31AUG09 19SEP10
RI213 Road crossing works 270 09SEP09 20JUL10
RI209 Chambers - Fittings & Valves 240 19NOV09 25AUG10
RI212 Reinstatement 240 20JAN10 26OCT10
RI210 Chambers-Covers & Finishes 60 26AUG10 03NOV10
2008 2009 2010S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Sheet 10 of 11
2008 2009 2010
-
8/10/2019 Pumping Station Programme
11/11
Sheet 11 of 11
Activity
ID
Activity
Description
Orig
Dur
Early
Start
Early
Finish
MISC.ELECTRICAL & INSTRUMENTATION WORKS
RI214 External Cabling 75 26MAY10 21AUG10
RI215 Boundary & Street lighting works 45 24JUL10 13SEP10
RI216 CCTV System 30 02SEP10 06OCT10
RI217 Reservoir Instrumentation works 12 09OCT10 21OCT10
ROAD WORKS & LANDSCAPING
LA01 Excavation for Road & Kerbs 60 17MAR10 25MAY10
LA02 Road Kerbs 90 04APR10 17JUL10
LA06 Landscaping works 150 25MAY10 15NOV10
LA03 Sub-Base 75 01JUN10 26AUG10
LA04 Asphalt works - Primecoat & Base course 45 10AUG10 30SEP10
LA05 Asphalt works-Tack coat & Wearing course 45 02OCT10 22NOV10
TESTING & COMMISSIONING
T01 Final Cleaning,Flushing,Sterlization & Testing 26 30AUG10 24SEP10
T06 Final Pipeline Connections to Existing Line. 25 27SEP10 25OCT10
T02 Pre-commissioning works - Elect,Mech & Instru 30 05OCT10 03NOV10
T03 Commissioning works- - Elect,Mech & Instru 31 04NOV10 09DEC10
T04 Handing over of the project. 1 12DEC10 12DEC10
T05 End of Project 0 12DEC10
2008 2009 2010S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Sheet 11 of 11