    2DPMU, Pura Neguma, Jaffna

    LA wise Allocation Jaffna District

    Loc a l Au thorityTo ta l G ran t

    / (Rs.M n)

    2011

    (30%)

    2012

    (45%)

    2013

    (25%)

    J affna MC 102.83 31.00 46.00 25.83

    Chavakacheri UC 94.39 28.00 42.00 24.00

    Point-Pedro UC 98.43 30.00 44.00 25.00

    Valvettithurai UC 98.02 29.00 44.00 25.00

    Chavakachcheri PS 121.29 36.00 55.00 30.00Delft PS 99.81 30.00 45.00 25.00

    Karainagar PS 93.78 28.00 42.00 23.00

    Kayts PS 95.03 29.00 43.00 24.00

    Nallur PS 96.30 29.00 43.00 24.00

    Point - Pedro PS 127.48 38.00 57.00 32.00

    Vada. South west PS 101.35 30.00 46.00 25.00

    Vali. East PS 110.46 33.00 50.00 28.00

    Vali. North PS 104.20 31.00 47.00 26.00

    Vali. South PS 101.35 30.00 46.00 25.00

    Vali. South west PS 108.18 32.00 49.00 27.00Vali. West PS 100.38 30.00 45.00 25.00

    Velanai PS 103.33 31.00 46.00 26.00

    Sub Total 1756.61 525.00 790.00 439.83

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    2/61

    DescriptionJaffna

    Total2011 2012 2013

    Allocation 527.000 791.000 439.000 1757.000

    No.of Works 64 34 58 156

    Pura Neguma Commitment 439.094 403.590 803.976 1646.660

    Pura Neguma Expenditure 398.575 259.336 107.989 765.900

    UnderPreparation 1 43 44

    Tender called 2 2 2

    Termination 1 1

    0-50% 1 3 5 12

    51-75% 1 1 3

    76-99% 3 2 3

    100% 61 25 5 91

    3DPMU, Pura Neguma, Jaffna

    4DPMU, Pura Neguma, Jaffna

    103.83 Mn

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    3/61

    DPMU, Pura Neguma, Jaffna 5

    Se.No

    Name of

    Implementing

    Local Authority

    and Description

    of Sub Project

    Implementation Period

    No.of

    km/

    Sqf. Etc.

    TEC

    (Million)

    Commitment(Million)

    Progress Up to 31.07.

    2013

    (Mn)

    Start

    Date

    EndCommu

    nity

    (People)

    Commu

    nity

    Expendi

    ture

    Council

    (LA)

    Council

    Expendi

    ture

    Pura

    Neguma

    (World

    Bank &

    Govt)

    Pura

    Neguma

    Expendi

    ture

    Phy %

    Total

    Expenditur

    eDate

    1

    Construction of

    tarrroad at

    Vasanthapuram1st& 2nd lane

    2.8.2011 02.11.2011 0.35 1.799 0.057 0.057 0.119 0.095 1.623 1.358 100% 1.51

    2

    Reconstruction of

    Drainage at

    Sippithalai lane

    2.8.2011 02.11.2011 0.625 1.768 0.054 0.054 0.117 0.093 1.596 1.279 100% 1.426

    3

    Reconst. Of

    Thirunagar main

    channel

    Retaining wall

    from Thiyoku

    Nursary school

    26.03.12 26.06.12 0.23 6.073 0.184 0.184 0.388 0.105 5.5 4.311 100% 4.600

    4

    Mettaling &

    Tarring Nallur

    Thurka lane &

    Surrounding

    26.03.12 26.06.12 1.47 8.121 0.249 0.249 0.537 0.527 7.335 6.465 100% 7.241

    5

    Const. of

    Anjuthankulam

    outlet channel,retaining wall and

    culvert

    26.03.12 26.06.12 0.36 5.441 0.164 0.164 0.367 0.02 4.909 3.381 100% 3.565

    DPMU, Pura Neguma, Jaffna 6

    Se.No

    Name ofImplementing

    Local Authorityand

    Description ofSub Project

    ImplementationPeriod

    No.ofkm/

    Sqf. Etc.

    TEC(Million

    )

    Commitment(Million)

    Progress Up to 31.07.2013(Mn)

    StartDate

    EndDate

    Community

    (People)

    Community

    Expenditure

    Council(LA)

    CouncilExpendi

    ture

    PuraNegum

    a(WorldBank &Govt)

    PuraNegum

    aExpendi

    ture

    Phy %Total

    Expenditure

    6

    Mettaling &Tarring Vidan'slane and By

    lanes andconstruction &reconst. ofchannel andretaining wall

    26.03.12 26.06.12 1.74 6.832 0.205 0.205 0.45 0.27 6.176 5.436 100% 5.911

    7

    Reconstruction of

    Cheddiyar

    thoddam ,

    MurugesarVeethy and

    Construction of

    Culvert1.743

    18.607 0.203 0.000 1.28 0.002 17.12 2.103 Termination 2.105

    Reconstruction of

    Cheddiyar

    thoddam Veethy

    and Culvert -A

    13.107 0.119 0.925 12.063Tender

    Called

    Reconstruction of

    MurugesarVeethy - B

    2.118 0.05 0.136 1.932Tender

    Called

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    4/61

    DPMU, Pura Neguma, Jaffna 7

    Se.No

    Name ofImplementing

    LocalAuthority andDescription of

    Sub Project

    ImplementationPeriod

    No.ofkm/

    Sqf. Etc.

    TEC(Millio

    n)

    Commitment(Million)

    Progress Up to 31.07.2013(Mn)

    StartDate

    EndDate

    Community

    (People)

    Community

    Expenditure

    Council(LA)

    CouncilExpend

    iture

    PuraNegum

    a(WorldBank &Govt)

    PuraNegum

    aExpend

    iture

    Phy %Total

    Expenditure

    9

    Reconstruction of

    Mavadi Vairavarkovil , Kamel

    with channel and

    Drainage 26.09.2012 25.12.2012 0.66

    7.732 0.244 0.389 0.012 7.099 5.036 95% 5.048

    10

    Reconstruction of

    Bharathy

    &bylanes ,stanley

    lane and

    perinpanayakam

    Road

    9.001 0.148 0.571 0.001 8.281 0.055Under

    Preparation0.056

    11

    Reconstruction of

    Odai,Sivappiraka

    sam & Bylanes

    ,Thalaiyali

    Veethy, College

    Lane 5.10.2012 4.02.2013 0.742

    22.317 0.34 1.44 0.007 20.531 8.911 40% 8.918

    12

    Reconstruction of

    Water tank 1St

    . &3ed. Cross road

    ,Sinnakkadai 4th

    Cross Street &

    Kondady Veethy

    with drainge 26.09.2012 25.12.2012 0.38

    4.956 0.178 0.248 0.012 4.53 1.808 65% 1.820

    DPMU, Pura Neguma, Jaffna 8

    Se.No

    Name of

    Implementing

    Local Authority

    and Description of

    Sub Project

    Implementation Period

    No.of

    km/

    Sqf. Etc.

    TEC

    (Million)

    Commitment(Million)

    Progress Up to 31.07.

    2013

    (Mn)

    Start

    Date

    End

    Date

    Communi

    ty

    (People)

    Communi

    ty

    Expendit

    ure

    Council

    (LA)

    Council

    Expendit

    ure

    Pura

    Neguma

    (World

    Bank &

    Govt)

    Pura

    Neguma

    Expendit

    ure

    Phy %Total

    Expenditure

    13

    Reconstruction of

    Drainage at

    Convent road &

    Mathiyas Veethy

    21.09.2012 20.12.2012 0.42 6.624 0.199 0.333 0.012 6.092 3.449 100% 3.461

    14

    Reconstruction of

    Suvamiar

    Uppukulam

    Veethy with cross

    street &

    Reclamation Road

    5.10.2012 4.02.2013 2.49 11.723 0.367 0.588 0.007 10.768 3.451 45% 3.458

    15

    Recosntruction of

    Hindu ladies lane,

    Aththysoodi

    Veethy, Convent

    lane and Gana

    Vairavar Front

    lane

    5.10.2012 4.02.2013 1.80 10.878 0.257 0.612 0.007 10.008 6.336 90% 6.343

    Total 137.081 3.018 0.913 8.500 1.527 125.563 53.379 55.819

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    5/61

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    6/61

    12

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    7/61

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    8/61

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    9/61

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    10/61

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    11/61

    22

    94.39 Mn

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    12/61

    23DPMU, Pura Neguma, Jaffna

    Se.No Project No

    Name ofImplementing LocalAuthority andDescription of SubProject

    Location(Village)

    ImplementationPeriod

    TEC(Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate

    No.ofkm/Sqf.Etc.

    Communit

    y

    Com.Expenditure

    Council

    (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy%Total

    Expenditure

    1NELSIP/NP/J /ChUC/W/03(

    ChUC-1)

    Reconst. Of KalvayalRamalingam OldSchoo l J oint Road

    Kalvayal 2.8.2011 2.12.2011 1.6 12.151 0.385 0.384 0.743 0.451 11.023 8.548 100 9.383

    2NELSIP/NP/J /ChUC/W/04(

    ChUC-2)

    Reconst. OfMeesalai WestKerniyadi Veethy

    Meesalai 2.8.2011 2.12.2011 1.5 10.848 0.334 0.334 0.623 0.365 9.891 7.824 100 8.523

    3NELSIP/NP/J /ChUC/W/03

    Const. ofPaththiniyar ThuravuRoad

    Chavakachcheri

    20.03.2012 20.06.2012 1.1 9.499 0.349 0.35 0.625 0.293 8.525 7.228 100 7.871

    4NELSIP/NP/ J /ChUC/W/04

    Reconstruction ofNunavilKalvayal1stLane & AdiyampittyRoad

    NunavilDocumentation Workfo r Tend er 1.2 10.79

    5NELSIP/NP/ J /ChUC/W/05

    Reconstruction ofMavadipillaiyarRoad

    MeesalaiEast

    Documentation Workfor Tender

    1.4 15.77

    24DPMU, Pura Neguma, Jaffna

    Se.No Project No

    Name ofImplementing Local

    Authority andDescription of Sub

    Project

    Location(Village)

    ImplementationPeriod

    TEC(Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate

    No.ofkm/Sqf.Etc.

    Communit

    y

    Com.Expenditure

    Council

    (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy%Total

    Expenditure

    6NELSIP/NP/J /ChUC/W/06

    Reconstruction ofThalaiyady Amman2nd Lane

    Meesalai West

    DocumentationWork for Tender

    1.25 7.59

    7NELSIP/NP/J /ChUC/W/07

    Reconstruction ofBangalowRoad

    Meesalai -south

    DocumentationWork for Tender

    1.37 13.89

    8NELSIP/NP/J /ChUC/W/08

    Reconstruction ofSappachchimavadiPillaiyarKovilRoad

    Chavakachcheri

    DocumentationWork for Tender

    0.69 8.34

    9

    NELSIP/NP/J /C

    hUC/W/09

    Reconstruction of

    VeerapaththirarRoad

    Nunavil

    -West PreparingEstimate

    10NELSIP/NP/J /ChUC/W/10

    Reconstruction ofMuthaliyaveli Road

    Madduvil

    PreparingEstimate

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    13/61

    25

    Se.No Project No

    Name ofImplementing Local

    Authority andDescription of Sub

    Project

    Location(Village)

    ImplementationPeriod

    TEC(Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate

    No.ofkm/Sqf.

    Etc.

    Communit

    y

    Com.Expenditure

    Council

    (LA)

    Council

    Expen

    diture

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy%Total

    Expenditure

    11NELSIP/NP/J /ChUC/W/11

    Reconstruction of 4,5EllaiVeethy IyanarRoad

    KalvayalPreparingEstimate

    12NELSIP/NP/J /ChUC/W/12

    Reconstruction ofKirampuvilWestRoad

    Kalvayal

    PreparingEstimate

    13NELSIP/NP/J /ChUC/W/13

    Reconstruction ofKaththappadi Road

    Nunavil-Centre

    PreparingEstimate

    Total 4.2 32.498 1.068 1.068 1.991 1.109 29.439 23.600 25.871

    Reconst. of Kalvayal Ramalingam old school joint Road1.6 Km (8.548Mn)

    26DPMU, Pura Neguma, Jaffna

    Reconst. of Meesalai West Kerniyadi Road1.5 Km (7.824Mn)

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    14/61

    27

    Reconst. of Paththiniyarthuravu Road1.1Km (7.228Mn)

    28DPMU, Pura Neguma, Jaffna

    98.43 Mn

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    15/61

    29

    Se.No Project No

    Name ofImplementing Local

    Authority andDescription of Sub

    Project

    Location(Village)

    ImplementationPeriod

    TEC(Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate

    No.ofkm/Sqf.Etc.

    Communit

    y

    Com.Expenditure

    Council

    (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy%Total

    Expenditure

    1NELSIP/NP/J /PPUC/W/01

    Const. of Retainingwall

    BeachRoad

    16.03.2012 15.06.20120.348

    8.617 0.258 0.258 0.434 0.093 7.925 6.066 100% 6.417

    2NELSIP/NP/J /ACLG/W/01(PPUC)

    ConstructionAthiyady DCChannel

    Athiyady 11.07.2012 11.11.2012 1.230 28.078 0.846 0.000 1.543 0.000 25.689 1.94150%

    terminated

    1.941

    3NELSIP/NP/J /ACLG/W/07(PPUC)

    Reconstruction ofAththiyady DCChannel -Continuous Work

    Athiyadi 13.08.2012 09.02.2013 26.827 0.884 0.000 1.342 0.000 24.601 16.244 100% 16.244

    4PN/NP/J /CLG/W/02(PPUC)

    Reconstruction ofPeruveddy Channel

    Peruveddy

    21.02.2013 18.12.2013 41.584 1.248 0.000 2.078 0.000 38.258 25.016 80% 25.016

    5NELSIP/NP/J /PPUC/W/02

    Construction o fChannel atPeruveddi Visvakula

    J oint Lane

    Pointpedo

    Preparing Estimate

    Total0.348 105.1 3.236 0.258 5.397 0.093 96.473 49.267 49.618

    30DPMU, Pura Neguma, Jaffna

    Const. of Retaining Wall 0.348Km (6.066 Mn)

    Reconst. of Aththiyady Drainage Channel 1.230Km (25.689 Mn)

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    16/61

    31DPMU, Pura Neguma, Jaffna

    32DPMU, Pura Neguma, Jaffna

    98.02 Mn

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    17/61

    33DPMU, Pura Neguma, Jaffna

    Se.No Project No

    Name ofImplementing Local

    Authority andDescription of Sub

    Project

    Location(Village)

    ImplementationPeriod

    TEC(Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate

    No.ofkm/Sqf.Etc.

    Community

    Com.Expenditure

    Council (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy%Total

    Expenditure

    1NELSIP/NP/J /VVUC/W/01

    Reconstruction ofKKS Road 2ndlane,Netkolu lane,Netkolu VarivarKovilfront road ,

    KerudavilNorthCluster-01

    11.05.2012 10.08.2012 1.118 5.565 0.268 0.233 0.278 0.302 5.019 5.459 100% 5.994

    2NELSIP/NP/J /VVUC/W/02

    Reconstruction ofPeriakadakkaraiRoad, Vellankaraicemetry Road,Veeramakali AmanKovil Roa d

    Thonda manaru-Cluster-02

    15.05.2012 14.08.2012 1.665 11.145 0.37 0.000 0.584 0.348 10.191 10.724 100% 11.072

    3NELSIP/NP/J /VVUC/W/03

    Reconstruction ofRetaining wall a longcoastal Area fromvady lane ac cess tomathavad y area

    Valvettiturai Northwest

    11.05.2012 10.08.2012 0.255 14.167 0.492 0.000 0.706 0.062 12.96914.067 100% 14.129

    4NELSIP/NP/J /CLG/W/02(VVUC)

    Construction o fvegetable Marketwith ShoppingComplex-packageA

    Valvettithurai town

    12.04.2013 11.12.2013 24.988 0.248 0.000 1.732 0.000 23.018 4.905 40% 4.905

    5NELSIP/NP/J /CLG/W/02A(VVUC)

    Construction o fvegetable Marketwith ShoppingComplex-packageB

    Valvettithurai town

    12.04.2013 11.08.2013 10.625 0.105 0.000 0.736 0.000 9.784 0.076 20% 0.076

    34

    Se.No Project No

    Name ofImplementing Local

    Authority andDescription of Sub

    Project

    Location(Village)

    ImplementationPeriod

    TEC(Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate

    No.ofkm/Sqf.Etc.

    Communit

    y

    Com.Expenditure

    Council

    (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy %Total

    Expenditure

    6NELSIP/NP/J /VVTUC/W/04

    Construction ofRetaining Wall atSithampa ra Co llegeplay ground -North

    VVTWest

    PreparingEstimate

    7NELSIP/NP/J /VVTUC/W/05

    Reconstruction ofKonavalai Road

    Kerudavil-East

    PreparingEstimate

    8NELSIP/NP/J /VVTUC/W/06

    Reconstruction ofAatrankarai Roadup to Field Workcentre

    ThondamanaruSouth

    PreparingEstimate

    Total 66.49 1.483 0.233 4.036 0.712 60.98 35.230 36.175

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    18/61

    Reconst. of Kerudavil North Cluster Road 1.188Km (5.459 Mn)

    35DPMU, Pura Neguma, Jaffna

    Reconst. of Thondamanaru Cluster Roads 1.665Km (10.724 Mn)

    36DPMU, Pura Neguma, Jaffna

    Reconst. of Retaining wall along coastal area 0.255Km (14.067 Mn)

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    19/61

    DPMU, Pura Neguma, Jaffna 37

    Const. of Market With Shopping Complex A (23.018 Mn)

    Const. of Market With Shopping Complex B (9.784 Mn)

    38DPMU, Pura Neguma, Jaffna

    121.29Mn

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    20/61

    39

    Se.No Project No

    Name ofImplementing

    Local Authority andDescription of Sub

    Project

    Location(Village)

    ImplementationPeriod

    TEC(Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate

    No.ofkm/Sqf.Etc.

    Communit

    y

    Com.Expenditur

    e

    Council

    (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy %Total

    Expenditure

    1NELSIP/NP/J /C hPS/W/06(ChPS-1)

    Reconst. OfMirusuvil HospitalFront Veethy

    Mirusuvil 2.8.2011 2.12.20111.000

    6.485 0.210 0.235 0.219 0.147 6.056 4.302 100% 4.684

    2NELSIP/NP/J /C hPS/W/07(ChPS-2)

    Reconst. OfAmmakadaiVeethy

    Karampai Kurce

    2.8.2011 2.12.20111.000

    6.646 0.218 0.144 0.265 0.162 6.163 4.744 100% 5.050

    3NELSIP/NP/J /C hPS/W/08(ChPS-3)

    Reconst. OfNavalkuli WestKoolarupitty Roa d

    Navalkuli 2.8.2011 2.12.20111.000

    6.876 0.259 0.259 0.219 0.150 6.398 4.356 100% 4.765

    4NELSIP/NP/J /ACLG/ W/01 -CHPS

    Reconstruction ofKarampakamVidaththatpalaiRoad

    Vidaththatpalai

    01.07.2012 01.11.20122.009

    24.928 0.795 0.698 1.355 0.823 22.77818.164 100% 19.685

    5NELSIP/NP/J /C hPS/W/05

    Mettaling & TarringAmmakada i Road2nd Stage

    Karampakurichchi

    23.07.2012 21.10.2012 0.970 10.946 0.335 0.335 0.554 0.511 10.057 7.125 100% 7.971

    40

    Se.No Project No

    Name ofImplementing Local

    Authority andDescription of Sub

    Project

    Location

    (Village)

    ImplementationPeriod

    TEC(Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate

    No.ofkm/Sqf.Etc.

    Communit

    y

    Com.Expenditure

    Council

    (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy%Total

    Expenditure

    6

    NELSIP/NP/J /

    ACLG/W/04(CHPS)

    Mettaling & Tarring

    Mirusuvil HospitalFront Road 2nd Stage Mirusuvil 11.02.2013 11.06.2013 2.280 23.850 0.716 0.000 1.213 1.145 21.92 8.019 100% 9.164

    7NELSIP/NP/J /ChPS/W/06

    Re.Con of ManthuvilKudiyetta thiddaRoad

    Manthuvil

    Preparing Estimate

    8NELSIP/NP/J /ChPS/W/07

    Re.Con of SarasalaiIyanar Road

    Sarasalai-South

    Preparing Estimate

    9NELSIP/NP/J /ChPS/W/08

    Re. Con of KaithadyNorth NavapuramMadduvil Sivan KovilRd

    Kaithady North,Kaithady East

    Preparing Estimate

    Total 8.259 79.731 2.533 1.671 3.825 2.938 73.37 46.710 51.319

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    21/61

    Reconstruction of Mirusivil Hospital Front Road 1.00 Km (4.302 Mn)

    41

    Reconstruction of Ammakadai Road 1.00 Km(4.744 Mn)

    Reconst. of Karampakam Vidaththalpalai Road 2.009Km (18.164 Mn)

    42

    Reconst. of Kularupiddy Road 1.00 Km (4.356 Mn)

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    22/61

    Reconst. of Ammakadai Road (2nd Stage) 0.970Km (7.125 Mn)

    43

    Reconst. of Hospital Front Road (2nd Stage) 2.280Km (21.92 Mn)

    44

    99.81 Mn

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    23/61

    45

    Se.No Project No

    Name ofImplementing Local

    Authority andDescription of Sub

    Project

    Location(Village)

    ImplementationPeriod

    No.ofkm/Sqf.Etc.

    TEC(Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate

    Communit

    y

    Com.Expenditur

    e

    Council

    (LA)

    Council

    Expenditur

    e

    PuraNeguma

    PuraNeguma

    Expenditur

    e

    Phy%TotalExpenditure

    1NELSIP/NP/J /DELPS/W/29(DELPS-1)

    Reconst. Of SouthSudalaiVigaravadiVeethy

    Delft West2.8.20112.12.20111.500

    5.351 0.218 0.000 0.299 0.029 4.834 3.422 100% 3.451

    2

    NELSIP/NP/J /DELPS/W/30(DELPS-2)

    Reconstruction ofJ agapparKovilKalamunaiConcrete Veethy

    Kalamunai

    2.8.20112.12.2011 2.000 7.130 0.29 0.000 0.399 0.027 6.441 1.883Termination(35%)

    1.910

    PN/NP/ J /DELPS/W/07

    05.06.13 04.09.13 1.100 7.044 0.200 0.000 0.373 0.000 6.471 0.041 55% 0.041

    3

    NELSIP/NP/J /DELP

    S/W/31(DELPS-3)Reconstruction ofMurukan KovilKopalapiddyConcrete Veethy

    Kopalapiddy

    2.8.20112.12.2011 0.800 2.854 0.116 0.000 0.16 0.018 2.578 1.430 100% 1.448

    PN/NP/ J /DELPS/W/08

    05.06.13 04.09.13 0.275 1.655 0.049 0.000 0.092 0.000 1.514 0.000 50% 0.000

    46

    Se.No

    Project No

    Name ofImplementing Local

    Authority andDescription of Sub

    Project

    Location(Village)

    ImplementationPeriod

    No.ofkm/Sqf.Etc.

    TEC(Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate Comm

    unity

    Com.Expenditure

    Council (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy %Total

    Expenditure

    4NELSIP/NP/J /DE

    LPS/W/04

    Co nstruction o fChildren's Reading

    and Trainig Hall

    Mannalt

    hurai

    19.10.2012 19.05.2013 432m2 25.326 0.515 0.000 1.066 0.000 23.74 12.016 90% 12.016

    5NELSIP/NP/J /DELPS/W/07

    Reconstruction ofThomayar Veethy

    DelftDocumentationwork for Tender

    6NELSIP/NP/J /DELPS/G/01

    Supplying of boat DelftTender Ca lled

    7NELSIP/NP/ J /DELPS/W/08

    Reconstruction ofHospital EastManalthurai Rd

    DelftDocumentationwork for Tender

    Total 5.675 49.360 1.388 0.000 2.389 0.074 45.58 18.793 18.866

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    24/61

    47

    Reconst. of Jakapar Kovil Kalmunai Road - 2.0Km (8.354 Mn)

    48

    Const. of Reading & Training Hall (23.74 Mn)

    Reconst. Of Murugan Kovil Koppalapiddy Road 0.8Km ( 2.944 Mn)

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    25/61

    49

    93.78 Mn

    50DPMU, Pura Neguma, Jaffna

    Se.No

    Project No

    Name ofImplementing Local

    Authority andDescription of Sub

    Project

    Location(Village)

    ImplementationPeriod

    No.ofkm/Sqf.Etc.

    TEC(Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate

    Communi

    ty

    Com.Expenditure

    Council (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy%Total

    Expenditure

    1

    NELSIP/NP/J /KR

    PS/W/ 32(KRPS-1)

    Reconst. Of O oriMurukan Kovil Veethy

    Oori 2.8.2011 2.12.20111.500

    12.583 0.379 0.379 0.480 0.334 11.724 7.766 100% 8.479

    2NELSIP/NP/J /KRPS/W/02

    Reconstruction ofSampalodai Road

    Sampaloda i

    21.03.2012 20.06.2012 1.130 7.431 0.464 0.464 0.464 0.209 6.530 5.445 100% 6.118

    3NELSIP/NP/J /KRPS/W/03

    Reconstruction ofPalaiyakandy SivanKovil Roa d

    Palaiyakandy

    21.03.2012 21.06.2012 2.00 15.024 0.471 0.471 0.892 0.470 13.661 10.826 100% 11.767

    4NELSIP/NP/J /ACLG/W/06(KRP

    S)

    Metalling &TarringThoppukkadu

    vairavar Kovil Veethy

    Thoppukadu

    20.02.2013 20.06.2013 1.420 21.062 0.634 0.634 1.054 0.085 19.374 15.058 100% 15.777

    5NELSIP/NP/J /KRPS/W/04

    Metalling &TarringKovalamMaruthapuram 1st

    joing veethy

    Maruthapuram

    02.08.2012 31.10.2012 2.070 12.527 0.59 0.590 0.639 0.247 11.298 9.631 100% 10.468

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    26/61

    51DPMU, Pura Neguma, Jaffna

    Se.No

    Project No

    Name ofImplementing Local

    Authority andDescription of Sub

    Project

    Location(Village)

    ImplementationPeriod

    No.ofkm/Sqf.Etc.

    TEC(Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate

    Community

    Com.Expenditure

    Council (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy%Total

    Expenditure

    6NELSIP/NP/J /ACLG/W/05(KRPS)

    Meta lling &TarringPaththarkeniyRoad& Drainage

    keniyady20.02.201

    320.06.201

    31.620 21.466 0.804 0.804 1.106 0.160 19.556 15.562 100% 16.526

    7NELSIP/NP/J /ACLG/W/07(KRPS)

    Reconstruction ofSubramaniam Road

    Karainagar

    Documentationwork for Tender 2.05 22.554

    8NELSIP/NP/J /KR

    PS/W/05

    Reconstruction ofThannai

    SuntharamoorthyRoad

    Karainag

    ar

    Tender Called0.86 8.857

    Total 9.740 90.093 3.342 3.342 4.635 1.505 82.14 64.288 69.135

    Reconst. of Oori Murugan Kovil Veethy 1.5Km (7.766 Mn)

    52DPMU, Pura Neguma, Jaffna

    Reconst. of Sampalodai Road 1.13Km (5.445 Mn)

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    27/61

    53DPMU, Pura Neguma, Jaffna

    Reconst. of Thoppukadu Vairavar Kovil Veethy 1.42Km (19.374 Mn)

    Reconst. of Palayakandy Sivan Kovil Road 2.0Km (10.826 Mn)

    54

    Reconst. of Kovalam Maruthapuram Veethy 2.07Km (9.631 Mn)

    Reconst. of Paththar Kerniy Road 1.62Km (19.556 Mn)

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    28/61

    55

    95.03 Mn

    56DPMU, Pura Neguma, Jaffna

    Se.No

    Project No

    Name ofImplementing Local

    Authority andDescription of Sub

    Project

    Location

    (Village)

    ImplementationPeriod

    No.ofkm/Sqf.Etc.

    TEC(Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate

    Community

    Com.Expenditure

    Council (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy%Total

    Expenditure

    1NELSIP/NP/J/KYPS/W/33

    (KYPS-1)

    Reconst. OfMelingimunai Main

    Road

    Melingimunai

    2.8.2011 2.12.20110.830

    6.430 0.232 0.232 0.348 0.145 5.850 3.628 100% 4.005

    2NELSIP/NP/J/KYPS/W/34(KYPS-2)

    Reconst. OfAnalaidivu KadaiyadiCross Roa d

    Analaidivu

    2.8.2011 2.12.20110.850

    5.748 0.244 0.244 0.264 0.133 5.240 3.704 100% 4.081

    3NELSIP/NP/J/KYPS/W/03

    Reconst. Of CampRoad

    Kayts 23.03.2012 23.06.2012 1.06 7.441 0.237 0.237 0.384 0.363 6.820 5.243 100% 5.843

    4NELSIP/NP/J/KYPS/W04

    Reconst. OfSeddiyanthodda

    Road

    Naranthanai

    North

    05.04.2012 05.07.2012 0.985 7.341 0.212 0.212 0.352 0.040 6.777 5.319 100% 5.571

    5NELSIP/NP/J/KYPS/W/05

    Reconst. OfSooriyawathai Road

    Sooriyawathai

    23.03.2012 23.06.2012 0.978 12.416 0.374 0.374 0.619 0.061 11.423 9.522 100% 9.957

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    29/61

    57DPMU, Pura Neguma, Jaffna

    Se.No

    Project No

    Name ofImplementing Local

    Authority andDescription of Sub

    Project

    Location(Village)

    ImplementationPeriod

    No.ofkm/Sqf.Etc.

    TEC(Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate

    Community

    Com.Expenditure

    Council (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy%Total

    Expenditure

    6NELSIP/NP/ J /ACLG/W/ 10(KYPS)

    Metalling &TarringNaranthai Sinnamadu1st &2 nd Road &Drainage

    Sinnamadu

    13.08.2012 11.12.2012 1.323 19.37 0.603 0.603 0.993 0.141 17.774 14.134 100% 14.878

    7NELSIP/NP/ J /KYPS/W/06

    Metalling &TarringNaranthaiUtharappiddy Road

    NaranthannaiNorth

    01.08.2012 30.10.2012 1.1 9.318 0.488 0.488 0.521 0.064 8.309 8.830 100% 9.382

    8NELSIP/NP/ J /ACLG/W/ 09(KYPS)

    Metalling &TarringPuliyankoodal NorthRoad

    Pulliyankoodal

    10.09.2012 08.01.2013 1.557 20.938 0.696 0.696 1.051 0.064 19.191 15.789 100% 16.549

    9NELSIP/NP/ J /KYPS/W/08

    Metalling &TarringNaranthanaiGanesha school Rd

    Naranthannai

    01.08.2012 30.10.2012 1.323 12.031 0.607 0.607 0.666 0.053 10.758 11.170 100% 11.830

    10NELSIP/NP/ J /KY

    PS/W/07

    Reconstruction of

    Koththikula veethykayts 01.08.2012 30.10.2012 1.004 9.28 0.481 0.481 0.499 0.064 8.300 8.759 100% 9.304

    11NELSIP/NP/ J /KYPS/W/09

    Reconstruction ofUppukula Road andLink Road

    Karampan North

    Preparing Estimate

    Total 110.31 4.174 4.174 5.697 1.128 100.4486.097 91.400

    Reconst. of Kaddaiyadi Cross Road 0.85Km (3.704 Mn)

    58

    Reconst. of Melinchimunai Main Road 0.830Km (3.628 Mn)

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    30/61

    Reconst. of Camp Road 1.06Km (5.243 Mn)

    59

    Reconst. of Seddiyanthodda Road 0.985Km (5.319 Mn)

    60

    Reconst. of Sooriyawattai Road 0.978Km (9.522 Mn)

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    31/61

    61DPMU, Pura Neguma, Jaffna

    Reconst. of Naranthanai Utharappiddy Road 1.1Km (8.830 Mn)

    Reconst. of Puliyankoodal North Road 1.557Km (19.191 Mn)

    62

    Reconst. of Naranthanai Ganesha School Road1.323Km (11.170 Mn)

    Reconst. of Koththikula Road 1.004Km (8.759 Mn)

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    32/61

    63

    96.30 Mn

    64

    Se.No Project No

    Name ofImplementing Local

    Authority andDescription of Sub

    Project

    Location

    (Village)

    Implementation Period

    TEC(Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate

    No.ofkm/Sqf.Etc.

    Communit

    y

    Com.Expenditure

    Council

    (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy%Total

    Expenditure

    1NELSIP/NP/J /NaPS/W/05(NaPS-1)

    Reconstruction ofAriyalai South EastManipuri Veethy

    Ariyalai 2.8.2011 2.12.20111.000

    8.074 0.252 0.252 0.367 0.208 7.455 5.324 100% 5.784

    2NELSIP/NP/J /

    NaPS/W/02

    Const. of Kerniyady

    Road

    Kokuvil 16.05.2012 15.08.2012

    1.476

    7.005 0.211 0.000 0.335 0.023 6.459 4.720 100% 4.743

    3NELSIP/NP/J /NaPS/W/03

    ReconstructionManippuri jointVeethy & Manippuri8th CrossVeethy

    Ariyali 01.07.2012 01.10.20121.343

    18.894 0.581 0.000 0.977 0.052 17.33613.219 100% 13.271

    4NELSIP/NP/J /CLG/W/03(NAPS)

    Co nstruction o fChildren indoorgames,Trainingcentre & Cultural Hall

    Kokuvil 17.04.2013 04.02.2014 55.977 0.780 0.000 3.735 0.041 51.462 8.443 25% 8.484

    5NELSIP/NP/J /NaPS/W/03

    Reconstruction ofNamakalVeethy

    KokuvilDocumentation work

    for Tender2.19 14.08

    6NELSIP/NP/J /NaPS/W/04

    Reconstruction ofKoddukkinaru PilaiyarKovil Veethy atAriyalai - East

    AriyalaiEast

    Documentation workfor Tender

    0.33 4.50

    Total 89.950 1.824 0.252 5.414 0.324 82.71231.706 32.282

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    33/61

    Reconst. of Ariyalai South East Manipuri Road 1.0Km (5.324 Mn)

    65

    Reconst. of Manipuri & 8th Cross Road 1.343Km (13.219 Mn)

    66

    Reconst. of Kerniyadi Road 1.476Km (6.459 Mn)

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    34/61

    67

    Construction of children indoor games, Training centre & cultural hall (51.462 Mn)

    68

    127.48 Mn

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    35/61

    69

    Se.No Project No

    Name ofImplementingLocal Authority

    and Description ofSub Project

    Location(Village)

    ImplementationPeriod

    TEC(Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate

    No.ofkm/Sqf.Etc.

    Community

    Com.Expenditure

    Council (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy%Total

    Expenditure

    1NELSIP/NP/J /PPPS/W/09(PPPS-1)

    Reconst ofUruththiravattaiSchool Veethy

    Uruththiravattai

    2.8.2011 2.12.20111.370

    8.865 0.268 0.240 0.477 0.269 8.120 5.567 100% 6.076

    2NELSIP/NP/J /PPPS/W/10(PPPS-2)

    Reconst. OfThikkam SchoolVeethy

    Thikkam 2.8.2011 2.12.20110.750

    5.909 0.205 0.195 0.204 0.205 5.500 3.706 100% 4.106

    3NELSIP/NP/J /PPPS/W/03

    Reconst. OfKampavaththaiinternal Roads

    Puloly 16.04.2012 15.07.20121.000

    9.092 0.282 0.322 0.485 0.463 8.325 8.479 100% 9.264

    4NELSIP/NP/J /PPPS/W/05

    Reconstruction ofPoomaga l road

    Polikandy 16.04.2012 15.07.20121.150

    9.908 0.354 0.414 0.608 0.490 8.946 8.943 100% 9.847

    5NELSIP/NP/J /PPPS/W/06)

    Reconstruction ofPeriyathevanaththai Road

    Periyathevanaththai

    16.04.2012 15.07.20121.050

    8.371 0.258 0.288 0.472 0.365 7.641 6.649 100% 7.302

    6NELSIP/NP/J /PPPS/W/04

    Reconstruction ofKudakkamparaiinternal Road

    Kudakkamparai

    16.04.2012 15.07.20121.150

    9.145 0.286 0.334 0.498 0.418 8.361 7.606 100% 8.358

    70

    Se.No Project No

    Name ofImplementingLocal Authority

    and Description ofSub Project

    Location(Village)

    ImplementationPeriod

    TEC(Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate

    No.ofkm/Sqf.Etc.

    Communit

    y

    Com.Expenditure

    Council

    (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy%Total

    Expenditure

    7NELSIP/NP/J /PPPS/W/07

    Mettaling &Tarring KerudavilAmman KovilRoad

    Kerudavil 03.08.201201.11.2012 1.234 9.854 0.313 0.226 0.576 0.378 8.965 7.589 100% 8.193

    8NELSIP/NP/J /ACLG/W/14(PPPS)

    Construction o fShoppingcomplex

    Manandi 10.04.201307.10.2013 29.671 0.585 0.000 1.844 0.086 27.242 4.313 50% 4.400

    9NELSIP/NP/J /CLG/W/01(PPPS)

    Construction o fMarket atmanthikai

    Manthikai 17.04.201314.10.2013 26.103 0.453 0.000 1.154 0.086 24.496 3.660 40% 3.746

    10NELSIP/NP/J /PPPS/W/08

    KaddaikaduNithiyaveddaiRoad

    Preparing Estimate

    11NELSIP/NP/ J /PPPS/W/09

    Saveriyar KovilRoad (ChurchRoad)

    Preparing Estimate

    Total 7.704 116.918 3.004 2.019 6.318 2.760 107.5956.514 61.292

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    36/61

    Reconst. of Thikkam school Road 0.75Km (3.706 Mn)

    71DPMU, Pura Neguma, Jaffna

    Reconst. of Urithiravthai School Road 1.370Km (5.567 Mn)

    Reconst. of Kudakkamparai internal Road 1.15Km (7.606 Mn)

    72DPMU, Pura Neguma, Jaffna

    Reconst. of Kampavaththai internal Road 1.0Km (8.479 Mn)

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    37/61

    73DPMU, Pura Neguma, Jaffna

    Reconst. of Poomahal Road 1.15Km (8.943 Mn)

    Reconst. of Periyathevanaththai Road 1.05Km (6.649 Mn)

    Reconst. of Kerudavil amman Kovil Road 1.230Km (7.589 Mn)

    74

    Const. of Manaandy Market & Shopping Complex (27.242 Mn)

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    38/61

    75DPMU, Pura Neguma, Jaffna

    Const. of Manthikai Market & Shopping Complex (24.496 Mn)

    76

    101.35 Mn

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    39/61

    77DPMU, Pura Neguma, JaffnaDPMU, Pura Neguma, Jaffna

    Se.No

    Project No

    Name ofImplementing

    Local Authority andDescription of Sub

    Project

    Location(Village)

    ImplementationPeriod

    TEC(Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate

    No.ofkm/Sqf.Etc.

    Community

    Com.Expenditure

    Council (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy%Total

    Expenditure

    1NELSIP/NP/ J /VdSWPS/W/11(VdSWPS-1)

    Reconst of Kulana iVeethi

    Thunnalai 1.8.2011 1.12.20110.900

    6.317 0.211 0.236 0.475 0.584 5.631 3.885 100% 4.705

    2NELSIP/NP/ J /VdSWPS/W/12(VdSWPS-2)

    Reconsto f MiththilSempadu Veethy,

    ThunnalaiCentre

    1.8.2011 1.12.20111.800

    12.739 0.398 0.415 0.854 0.157 11.487 8.068 100% 8.640

    3NELSIP/NP/ J /VDSWPS/W/03

    Reconst. ofMaththonipublicmarket Road

    Maththoni 21.03.2012 20.06.20120.650

    3.996 0.144 0.144 0.228 0.204 3.624 2.840 100% 3.188

    4NELSIP/NP/ J /VdSWPS/W/04

    Reconstruction ofSrinaratha Veethy

    KaraveddyWest

    17.01.2013 17.04.2013 0.805 3.578 0.118 0.112 0.177 0.0700 3.283 2.637 100% 2.819

    5NELSIP/NP/ J /VdSWPS/W/05

    Reconstruction ofAlvai ManokaraVeethy(Samananthurai)

    Alvai 17.01.2013 17.04.2013 0.800 5.762 0.171 0.166 0.290 0.1590 5.301 3.909 100% 4.234

    78DPMU, Pura Neguma, JaffnaDPMU, Pura Neguma, Jaffna

    Se.No

    Project No

    Name ofImplementing Local

    Authority andDescription of Sub

    Project

    Location(Village)

    ImplementationPeriod

    No.ofkm/Sqf.Etc.

    TEC (Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate

    Community

    Com.Expenditure

    Council (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy%Total

    Expenditure

    6NELSIP/NP/ J /VdSWPS/W/06

    Reconstruction ofNesavusalai Veethy

    Udupiddy

    17.01.2013 17.04.2013 1.070 6.345 0.183 0.000 0.326 0.0710 5.836 3.326 100% 3.397

    7NELSIP/NP/ J /VdSWPS/W/07

    Reconstruction ofKavilkerai VellavaikalVeethy

    Karanavai East

    17.01.2013 17.04.2013 1.400 8.546 0.258 0.000 0.432 0.0710 7.856 5.021 100% 5.092

    8NELSIP/NP/ J /VdSWPS/W/08

    Reconstruction ofManiyakaran

    Thodda Veethy

    Karanavai South

    17.01.2013 17.04.2013 0.860 11.124 0.316 0.000 0.572 0.0710 10.236 5.901 100% 5.972

    9NELSIP/NP/ J /VdSWPS/W/09

    Reconstruction ofKalaimahalCommunity CenterVeethy

    Imaiyannam

    17.01.2013 17.04.2013 1.131 7.496 0.231 0.227 0.372 0.2010 6.893 4.916 100% 5.344

    10

    NELSIP/NP/ J /C

    LG/W/05(VdPS)

    Construction o f

    Market Complex atNelliady

    Nelliyad i Prepa ring Estimate

    Total 9.416 65.903 2.030 1.300 3.726 1.588 60.14740.503 43.391

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    40/61

    Reconst. of Kulanai Road 0.9Km (3.885 Mn)

    79DPMU, Pura Neguma, Jaffna

    Reconst. of Mithilsempadu Road 1.80Km (8.068 Mn)

    Reconst. of Maththoni Public Market Road 0.65Km (2.840 Mn)

    DPMU, Pura Neguma, Jaffna

    Reconst of Manokara Samanathurai Rd.866Km (3.909 Mn)

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    41/61

    81DPMU, Pura Neguma, Jaffna

    Reconstruction of Srinaratha Road.805Km (2.637 Mn)

    82DPMU, Pura Neguma, Jaffna

    Reconstruction of Nesavusalai Road 1.040Km (5.836 Mn)

    Reconstruction of maniyakaran Road.886Km (10.236 Mn)

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    42/61

    Reconst of kalaimagal community Rd1.135Km (5.916 Mn)

    83DPMU, Pura Neguma, Jaffna

    Recont of Kavilkirai Road.1.4Km (7.856 Mn)

    84DPMU, Pura Neguma, Jaffna

    110.46 Mn

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    43/61

    85DPMU, Pura Neguma, Jaffna

    Se.No

    Project No

    Name ofImplementing Local

    Authority andDescription of Sub

    Project

    Location(Village)

    ImplementationPeriod

    No.ofkm/Sqf.Etc.

    TEC(Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate

    Community

    Com.Expenditure

    Council (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy%Total

    Expenditure

    1NELSIP/NP/J /VEPS/W/16(VEPS-1)

    Reconst. Of KopayKiluvana i Veethy

    Kopay 2.8.2011 2.12.20111.750

    9.901 0.310 0.311 0.428 0.416 9.163 8.100 100% 8.827

    2NELSIP/NP/J /VEPS/W/17(VEPS-2)

    Reconst .ofThanipanaiyaddiVeethy

    Achelu 2.8.2011 2.12.20111.500

    8.179 0.254 0.254 0.351 0.341 7.574 6.695 100% 7.289

    3NELSIP/NP/J /VEPS/W/18(VEPS-3)

    Reconst. OfVanniyasingamVeethy

    Awarankal west

    2.8.2011 2.12.20112.000

    11.208 0.350 0.350 0.483 0.469 10.375 9.177 100% 9.996

    4NELSIP/NP/ J /VEPS/W/04

    Reconst. Of o ld postoffice veethy

    KopaiSouth

    03.4.201203.7.20121.500

    10.899 0.327 0.327 0.546 0.448 10.026 7.411 100% 8.186

    Total6.750 40.187 1.241 1.242 1.808 1.674 37.138 31.382 34.298

    Reconst. of Killuvanai Veethy 1.75Km (8.100 Mn)

    86

    Reconst. of Thanipanaiyadi Veethy 1.5Km (6.695 Mn)

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    44/61

    Reconst. of Old Post Office Road 1.5Km (7.411 Mn)

    87

    Reconst. of Vanniyasingam Veethy 2.0Km (9.177 Mn)

    88

    104.20 Mn

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    45/61

    89

    Se.No

    Project No

    Name ofImplementing Local

    Authority andDescription of Sub

    Project

    Location(Village)

    ImplementationPeriod

    No.ofkm/Sqf.Etc.

    TEC(Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate

    Community

    Com.Expenditure

    Council (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy%Total

    Expenditure

    1NELSIP/NP/J /VNPS/W/22(VNPS-2)

    Reconst. OfPonnaiya Veethy

    Pannalai 2.8.2011 2.12.20110.960

    5.902 0.189 0.189 0.277 0.202 5.436 4.157 100% 4.548

    2NELSIP/NP/J /VNPS/W/22(VNPS-2)

    Reconst.Kuddiyapulamveethy

    Kuddiyapulam

    2.8.2011 2.12.20110.970

    5.788 0.190 0.190 0.178 0.160 5.420 4.300 100% 4.650

    3NELSIP/NP/J /VNPS/W/03

    Reconst. OfPonnipulam Road

    Tellipalai 22.03.2012 21.06.20121.070

    8.698 0.335 0.336 0.601 0.358 7.762 6.734 100% 7.428

    4NELSIP/NP/J /VNPS/W/04

    Reconst. Ofvellijampathy Road

    Alaveddy East

    22.03.2012 21.06.20121.030

    6.894 0.210 0.210 0.349 0.036 6.335 5.584 100% 5.830

    5NELSIP/NP/ J /VNPS/W/05

    Reconst. OfKooththancheemaRoad

    Alaveddy North

    22.03.2012 21.06.20121.390

    9.991 0.300 0.300 0.526 0.041 9.165 7.943 100% 8.284

    90

    Se.No

    Project No

    Name ofImplementing Local

    Authority andDescription of Sub

    Project

    Location(Village)

    ImplementationPeriod

    No.ofkm/Sqf.Etc.

    TEC(Mn)

    Progress Up to 30th of June 2013

    StartDate

    EndDate

    Community

    Com.Expenditure

    Council (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy%Total

    Expenditure

    6NELSIP/NP/J /VNPS/W/06

    Reconstruction ofKernipiddyveethy(Periya KinnaththadyVeethy)

    Alaveddy East

    20.08.2012

    19.11.2012

    1.174 9.958 0.299 0.299 0.531 0.0200 9.128 6.638 100% 6.957

    7NELSIP/NP/J /VNPS/W/07

    Mettaling & TarringPeriya KanakarvalavuRoad

    Mallagam South

    20.08.2012

    19.11.2012

    1.430 14.764 0.394 0.394 0.652 0.140 13.718 10.809 100% 11.343

    8NELSIP/NP/J /VNPS/W/08

    Mettaling & TarringKuruvalai veethy

    Mallagam South

    20.08.2012

    19.11.2012

    1.130 14.642 0.488 0.488 0.770 0.278 13.384 9.866 100% 10.632

    9NELSIP/NP/J /VNPS/W/09

    Mettaling & TarringThammalai Veethy

    Allaveddy West

    20.08.2012

    19.11.2012

    1.490 12.512 0.358 0.359 0.622 0.019 11.532 9.365 100% 9.743

    10NELSIP/NP/ J /VNPS/W/10

    Mettaling & TarringSoda Company Rd

    MallakamCentre

    20.08.2012

    19.11.2012

    1.235 8.449 0.266 0.267 0.469 0.019 7.714 6.202 100% 6.488

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    46/61

    91

    Se.No

    Project No

    Name ofImplementing Local

    Authority andDescription of Sub

    Project

    Location(Village)

    ImplementationPeriod

    No.ofkm/Sqf.Etc.

    TEC(Mn)

    Progress Up to 30th of June 2013

    StartDate

    EndDate

    Community

    Com.Expenditure

    Council (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy%Total

    Expenditure

    11 NELSIP/NP/ J /VNPS/W/11

    Reconstruction ofPaddikkadavai Road

    Kollankaladdi

    Documentationwork for Tender

    1.47 11.61

    12NELSIP/NP/ J /VNPS/W/12

    Reconstruction ofMurungayappulamRoad and Link Road

    AlaveddiWest

    Documentationwork for Tender

    1.05 14.41

    13NELSIP/NP/ J /VNPS/W/13

    Reconstruction ofCemetery Road

    Vasavilan-West

    Documentationwork for Tender

    1.07 11.85

    14NELSIP/NP/ J /VNPS/W/14

    Reconstruction ofAppachchippilaiRoad

    AlaveddiSouth

    Documentationwork for Tender

    0.71 3.47

    Total 11.87 97.598 3.029 3.032 4.975 1.273 89.59 71.597 75.903

    Reconst. Of Ponnaiya Road 0.96Km (4.157 Mn)

    92

    Reconst. of Kudiyappulam Cemetery Road 0.970Km (4.300 Mn)

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    47/61

    Reconst. of Ponnipulam Road 1.070Km (6.734 Mn)

    93

    Reconst. of Velliyampathy Road 1.03Km (5.584 Mn)

    94

    Reconst. of Koothanseema Road 1.39Km (7.943 Mn)

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    48/61

    Reconst. of Periyakinatradi Veethy 1.174Km (6.638 Mn)

    95

    Reconst. of Kanakar Valavu Part Road 1.43Km (10.809 Mn)

    Reconst. of Kuruvalai Veethy 1.13Km (9.866 Mn)

    96

    Reconst. of Thammalai Veethy 1.49Km (9.365 Mn)

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    49/61

    97

    Reconst. of Sodacompany Road 1.235Km (6.202 Mn)

    98

    101.35 Mn

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    50/61

    99

    Se.No

    Project No

    Name ofImplementingLocal Authorityand Descriptionof Sub Project

    Location(Village)

    ImplementationPeriod

    No.ofkm/Sqf.Etc.

    TEC(Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate

    Community

    Com.Expenditure

    Council (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy%Total

    Expenditure

    1NELSIP/NP/J /VSPS/W/13(VSPS-1)

    Reconst. ofMalvam 3rdCross Road

    Uduvil 2.8.2011 2.12.20110.820

    4.778 0.147 0.151 0.181 0.113 4.450 3.047 100% 3.310

    2NELSIP/NP/J /VSPS/W/14(VSPS-2)

    Reconst. ofKadakarampaiCemetry Road

    Kuplan 2.8.2011 2.12.20111.150

    6.830 0.221 0.224 0.209 0.201 6.400 4.921 100% 5.346

    3NELSIP/NP/J /VSPS/W/15(VSPS-3)

    Reconst. KaliKovil Veethy

    Ellalai 2.8.2011 2.12.20111.000

    4.475 0.137 0.137 0.249 0.109 4.089 2.837 100% 3.083

    4NELSIP/NP/J /VSPS/W/04

    Reconst.ofSabapathipillaiRoad

    Chunakam North

    18.06.2012 17.09.20120.810

    13.089 0.394 0.394 0.668 0.468 12.027 9.276 100% 10.138

    5NELSIP/NP/J /VSPS/W/05

    Reconst. OfSellappaManiyakaaranVeethy

    PunnalaikadduvanSouth

    18.06.2012 17.09.20122.030

    11.865 0.367 0.368 0.602 0.484 10.895 9.102 100% 9.955

    100

    Se.No Project No

    Name ofImplementing Local

    Authority andDescription of Sub

    Project

    Location(Village)

    ImplementationPeriod

    No.ofkm/Sqf.Etc.

    TEC(Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate

    Community

    Com.Expenditure

    Council (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy %Total

    Expenditure

    6NELSIP/NP/J /VSPS/W/06

    Mettaling & TarringNagathampiranVeethy

    Eveni 22.8.201220.11.2012 1.810 14.867 0.488 0.488 0.736 0.546 13.643 11.959 100% 12.973

    7 NELSIP/NP/J /ACLG/W/11(VSPS)

    Mettaling & TarringKantharoodaiCemetry Veethy

    Chunnakam

    04.9.201202.01.2013 2.000 21.109 0.644 0.645 1.06 0.980 19.405 18.776 100% 20.401

    8NELSIP/NP/J /VSPS/W/07

    Reconstruction ofSingathinKaladdY Veethy atInuvil

    InuvilDocumentationwork for Tender

    1.9 26.41

    9NELSIP/NP/J /VSPS/W/08

    Reconstruction ofMangalamanVeethy at Evinai

    EvinaiDocumentationwork for Tender

    1.85 20.67

    10NELSIP/NP/J /V

    SPS/W/09

    Reconstruction ofKuppilan AnnamarVeethy at Kuppulan

    Elzalai

    East

    Documentation

    work for Tender0.85 11.47

    Total 9.620 77.013 2.398 2.407 3.705 2.901 70.90959.918 65.206

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    51/61

    Reconst. of Malvam 3rd cross Road 0.82 Km (3.047 Mn)

    101

    Reconst. of Kadakkadampai Road 1.15Km (4.921 Mn)

    102

    Reconst. of Kaalikovil Road 1.0Km (2.837 Mn)

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    52/61

    Reconst. of Sellappamaniyakaran Road 2.030km (9.102 Mn)

    103

    Reconst. of Sabapathippillai Road 0.810km (12.027 Mn)

    Reconst. of Cemetry Road 2.0Km (18.776 Mn)

    104

    Reconst. of Nagathampiran Road 1.81Km (11.959 Mn)

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    53/61

    105

    108.18 Mn

    106

    Se.No

    Project No

    Name ofImplementing Local

    Authority andDescription of Sub

    Project

    Location(Village)

    ImplementationPeriod

    No.ofkm/Sqf.Etc.

    TEC(Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate

    Community

    Com.Expenditure

    Council (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy%Total

    Expenditure

    1NELSIP/NP/ J /VSWPS/W/23(VSWPS-1)

    Reconst. OfSinnappa Veethy

    Mannipay 2.8.2011 2.12.20111.300

    7.696 0.255 0.255 0.331 0.171 7.110 4.901 100% 5.327

    2NELSIP/NP/ J /VSWPS/W/24(VSWPS-2)

    Reconst. ofAlankulai Lane

    Mannipay 2.8.2011 2.12.20111.390

    7.529 0.247 0.247 0.322 0.170 6.960 4.800 100% 5.217

    3NELSIP/NP/ J /VSWPS/W/25(VSWPS-3)

    Reconst. CemetryVeethy, Ilavalai

    Mannipay 2.8.2011 2.12.20111.610

    6.121 0.185 0.186 0.236 0.229 5.700 4.773 100% 5.188

    4NELSIP/NP/ J /VSWPS/W/26(VSWPS-4)

    Reconst. OfUtchc hiodai Veethi

    Mannipay 2.8.2011 2.12.20111.240

    5.362 0.166 0.167 0.216 0.179 4.980 3.971 100% 4.317

    5NELSIP/NP/ J /VSWPS/W/05

    Reconst. OfUnthupalaikaddaiVeethy

    Sillalai 04.04.201204.07.2012 1.030 9.700 0.358 0.358 0.499 0.562 8.843 7.808 100% 8.728

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    54/61

    107

    Se.No

    Project No

    Name ofImplementing Local

    Authority andDescription of Sub

    Project

    Location(Village)

    ImplementationPeriod

    No.ofkm/Sqf.Etc.

    TEC(Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate

    Community

    Com.Expenditure

    Council (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy%Total

    Expenditure

    6NELSIP/NP/J /VS

    WPS/W/06

    Reconstruction of

    Nallunni Veethy

    Kiraamp

    atu

    Documentation

    work for Tender

    1.4 16.86

    7NELSIP/NP/J /VSWPS/W/07

    Reconstruction ofArasady AavalaiVeethy linkKompanipulamVeethy

    Sandilipay-North

    Documentationwork for Tender

    2.22 24.80

    8NELSIP/NP/J /VSWPS/W/08

    Reconstruction ofMaa vadi Veethy(Old Schools Veethy)

    Suthumalai-South

    Documentationwork for Tender

    1.425 15.84

    9NELSIP/NP/J /VSWPS/W/09

    Reconstruction ofAnantha Veethy linkvairavar Kovil Veethy

    Manippai-East

    Documentationwork for Tender

    1.35 10.58

    10NELSIP/NP/J /VSWPS/W/10

    Reconstruction ofMathagal vilanVeethy

    Mathakal,Vilan

    Documentationwork for Tender

    2.6 33.01

    Total6.570 36.408 1.211 1.213 1.604 1.311 33.593 26.253 28.777

    Reconst. Of Sinnappah Veethy 1.3Km (4.901 Mn)

    108

    Reconst. of Allankulai Lane 1.39Km (4.800 Mn)

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    55/61

    Reconst. of Cemetry Veethy 1.61Km (4.773 Mn)

    109

    Reconst. of Uchchiyodai Veethy 1.24Km (3.971 Mn)

    Reconst. of Unthusanthai Unthupalakai Road 1.03Km (7.808 Mn)

    110

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    56/61

    111

    100.38 Mn

    112

    Se.No

    Project No

    Name ofImplementingLocal Authority

    and Description ofSub Project

    Location

    (Village)

    ImplementationPeriod

    No.ofkm/Sqf.Etc.

    TEC(Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate

    Community

    Com.Expenditure

    Council (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy%Total

    Expenditure

    1NELSIP/NP/J /VWPS/W/19(VW

    PS-1)

    Reconst.Chulipuram Periya

    Thampiran Veethy

    Chulipur

    am

    2.8.2011 2.12.2011

    1.300

    10.973 0.334 0.000 0.494 0.468 10.145 6.111 100% 6.579

    2NELSIP/NP/J /VWPS/W/19(VWPS-2)

    Reconst ofNochchiampathyPatchanthaiVeethy

    Nochchiampathy

    2.8.2011 2.12.20111.500

    13.164 0.410 0.000 0.595 0.509 12.159 9.003 100% 9.512

    3NELSIP/NP/J /VWPS/W03

    Re-Construction ofPallasuddi Road

    Chulipuram

    23.04.2012 22.07.20122.250

    15.380 0.817 0.000 0.907 0.587 13.656 11.962 100% 12.549

    4NELSIP/NP/J /VWPS/W04

    Reconstruction ofChankanai VallaiRoad 1st Lane,VickneswaraRoad , J affna-Ponna lai 1st Lane

    Chankanai

    Preparing Estimate

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    57/61

    113

    Se.No

    Project No

    Name ofImplementing Local

    Authority andDescription of Sub

    Project

    Location(Village)

    ImplementationPeriod

    No.ofkm/Sqf.Etc.

    TEC(Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate

    Community

    Com.Expenditure

    Council (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy%Total

    Expenditure

    5NELSIP/NP/J /VWPS/W05

    Reconstruction ofMoo lai SaivaoirakasaVidyalaya Road

    Moo lai Preparing Estimate

    6NELSIP/NP/J /VWPS/W06

    Reconstruction ofVaddukkoddaiKalainager RoadMalavarayar Rd

    Vaddukkoddai

    Preparing Estimate

    Total5.050 39.517 1.561

    -1.996 1.564

    35.9627.077 28.640

    Reconst. of Periyathampiran Road 1.3Km (6.111 Mn)

    114

    Reconst. Of Nochiyampathy Road 1.5Km (9.003 Mn)

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    58/61

    Reconst. of Pallasuddy Road 2.25Km (11.962 Mn)

    115

    116

    103.33 Mn

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    59/61

    117

    DPMU, Pura Neguma, Jaffna

    Se.No

    Project No

    Name ofImplementing Local

    Authority andDescription of Sub

    Project

    Location(Village)

    ImplementationPeriod

    No.ofkm/Sqf.Etc.

    TEC(Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate

    Community

    Com.Expenditure

    Council (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy%Total

    Expenditure

    1NELSIP/NP/

    J /VLPS/W/27(VLPS-1)

    Reconst. OfRasaiya Veethy

    Kurikaduvan

    2.8.2011 2.11.20112.600

    10.211 0.338 0.338 0.594 0.092 9.279 5.896 100% 6.326

    2NELSIP/NP/

    J /VLPS/W/28(VLPS-2)

    Reconst ofSangaththa KeniVeethy

    Pungudutheevu

    2.8.2011 2.12.20111.500

    10.659 0.321 0.321 0.545 0.100 9.793 4.822 100% 5.243

    3NELSIP/NP/

    J /VLPS/W/03

    Reconst. ofPerunkulam veethy& Const. ofretaining wall

    Nainathivu 11.04.2012 11.08.20120.670

    14.030 0.423 0.423 0.704 0.118 12.903 11.455 100% 11.995

    4

    NELSIP/NP/

    J /VLPS/W/04

    Construction o fMarket Thuraiyoor 19.09.2012 16.02.2013 11.370 0.000 0.000 0.000 0.000 11.370 5.555 90% 5.555

    5NELSIP/NP/

    J /VLPS/W/04A

    Construction o fthuraiyoor fishmarket -Accessroad a t velanai

    Thuraiyoor 21.03.2013 19.07.2013 10.179 0.810 0.000 1.255 0.722 8.114 3.270 100% 3.992

    118

    Se.No

    Project No

    Name ofImplementingLocal Authorityand Descriptionof Sub Project

    Location(Village)

    Implementation Period

    No.ofkm/Sqf.Etc.

    TEC(Mn)

    Progress Up to 31stJuly 2013

    StartDate

    EndDate

    Community

    Com.Expenditure

    Council (LA)

    Council

    Expenditure

    PuraNeguma

    PuraNeguma

    Expenditure

    Phy%Total

    Expenditure

    6NELSIP/NP/J /ACLG/W/12(VLPS)

    Construction o fMarket -

    Muththaveli

    Punguduthivu

    09.11.2012 08.05.2013 17.631 0.859 0.000 0.999 0.024 15.773 0.116 40% 0.140

    7NELSIP/NP/J /ACLG/W/08(VLPS)

    Const.of Suda laiVeethy

    Mandativu

    09.08.2012 07.12.2012 1.600 18.500 0.557 0.000 0.966 0.847 16.977 11.236 100% 12.083

    8NELSIP/NP/J /VLPS/W/05

    Construction o fModern Market

    Velanai Preparing Estimate

    9NELSIP/NP/J /VLPS/W/06

    Reconstruction ofVenpuraviRoad

    Alaipiddi

    Preparing Estimate

    Total 6.370 92.580 3.308 1.082 5.063 1.903 84.209 42.35 45.335

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    60/61

    Reconst. of Rasaiah Road 2.6Km (9.279 Mn)

    119

    Reconst. of Sankatharkerny Road 1.5Km (9.793 Mn)

    Reconst. of Sudalai Road 1.60Km (11.236 Mn)

    120

    Const. of Market at thuraiyoor 11.370 Mn)

  • 7/29/2019 Pura Neguma Project (NELSIP) - Jaffna

    61/61

    121DPMU, Pura Neguma, Jaffna

    Const. of Vegitable Market at Muthathuveli (15.773 Mn)