qa supervision from10 to 35 - procon.me · particular conditions as part of rfp 6 have ... project...
TRANSCRIPT
Question no.10:
The Tenderer shall with his Tender submit a copy of this page as well as of all
the pages of the Particular Conditions, duly initialled by the person authorised
to sign the Tender.
In those six submitted files we didn’t received Particular conditions, can you
submit them?
Answer no.10:
Particular conditions as part of RFP 6 have been now issued (Attached File: Addenda 1 Particular
conditions). Appendix 1 to 4 will be drafted based information already contained in the Term of
Reference.
Question no.11:
In compliance with General instructions to Consultants – RFP 2, paragraph 2.2 and 2.3, we would
appreciate your answers to the following questions:
1. Are there any minimal requirements for association/consortium/joint venture members if the
Prime consultant by himself complies with financial criteria stated in RFP 1 par 6 point B ?
Answer: all financial requirements for association/consortium/joint venture members are defined in
RFP 2, clause 1.5
2. Are there any minimal requirements for association/consortium/joint venture members if the
Prime consultant by himself complies with technical criteria stated in RFP 1 par 6 point C?
Answer: all technical requirements for association/consortium/joint venture members are defined
in RFP 2, clause 1.6. Clarification is also contained in answer no. 2
Question no.12:
What is a planned distribution of 5 weight points among criteria listed in RFP 4 point 4. Other factors ?
Answer no.12:
Criterions are clearly indicated in the table (local participation, local presence, back-up capacity,
environmental certifications, training/transfer of know how)
Question no.13:
Are there any criteria and/or requirements for Consultant companies and experts regarding licences in
accordance with the Montenegrin Law in Planning and Construction? If there is, how will these be
evaluated?
Answer no.13: Supevision of works has to be performed in line with requirements of montenegrin Law,
certification included. Neverthless Experts and Consultants from abroad are not obliged to present
licences in accordance with Montenegrin Law. Other liceses/habilitation, different by those released by
Montenegrin Bodies, but equivalent in accordance to the legislation of their Countries of origin, will be
deemed accettable
Question no.14:
In ToR RFP 5 paragraph 6.1.3. Resident Engineers it is stated that: ’’Two Resident are expected to be in
this Project’’ while table 5 in RFP 5 and table d3) in RFP 1 lists only 1 (one). What is a correct number of
Resident Engineers required for this project?
Answer no.14:
Only one Resident Engineer
Question no.15:
Will the expert’s experience in construction of WWTP and sewerage networks be accepted as required
qualification or it is limited to assignments in design and/or supervision.
Answer no.15:
Evaluation will be in line with indicatation in table Evaluation Criteria and Methodology - RFP 4 .
Anyway, as provided by answer 31, also assignments as Contractor’s Representative in Design & Build
Project of WWTP according to FIDIC YELLOW BOOK provisions.
Question no.16:
The consultant kindly requests to recive the particular conditions as presented in RFP6.
Answer no.16:
Please refer to answer no.10
Question no.17:
Answer no.17:
Yes, it is mandatory.
Tender Guarantee is a standard document whose format is available by any banks and shall be
completed in accordance to “Uniform Rules for Demand Guarantees, published as number 458 by the
International Chamber of Commerce” therefore the format has bot been provided before.
However we attached hereinafter a general form which is reputed acceptable by this Contracting
Authority.
Question no.18:
We would like to clarify a doubt that we have after read the tender documentation:
In the initial document “INVITATION FOR TENDERS” it was written: All tenders must be accompanied by
a tender guarantee of 20.000 € (twenty thousand Euro). However now, we don't see any mention to this
subject in the tender documentation.
Our questions it’s:
It’s need to present a tender guarantee?
Answer no.18:
Please refer to Answer 17.
Question no.19:
WITH REFERENCE TO RFP 5, PAR 6.6. TABLE 5, THE MINIMA WORKING DAYS FOR PROJECT MANAGER
(PM) ARE 500.
CONSIDERING THAT THE PM NORMALLY PERFORMS PERIODIC VISIT ON SITE, WHILE HE IS SUPPORTED
BY THE RESIDENT, THAT IS ALMOST PERMANENTLY ON SITE, WE THINK THAT THE MINIMA WORKING
DAYS FOR THE PM SHOULD BE EFFECTIVELY REDUCED.
Answer no.19:
Minimal man days for project manager is 150 days, not 500 days .
Question no.20:
WITHE REFERENCE TO RFP 5, PAR 5.2 TABLE 1, SUPERVISION WORKS CONTRACT TAKES 16 MONTHS
AND THE END OF MONTH IS ESTABLISHED AT MONTH 21.
BUT, PROVIDED THAT AFTER PERMITS ACHIVEMENT THE WORKS CAN START, IF ALL PERMITS ARE
READY AT MONTH 4, WORKS SUPERVISION SHOULD END AT MONTH 20 (4+16=20), INSTED OF MONTH
21.
THEN, IF NO DEFECTION PERIODO TAKES 12 MONTHS, IT SHOULD END AT MONTH 32 (20+12), INSTEAD
OF MONTH 36.
FINALLY, WHY DO THE TEST ON COMPLETION END BEFORE WORKS SUPERVISION?
WE THINK THAT SOME CALCULATION MISTAKES HAVE BEEN DONE IN THE ABOVE MENTIONED TABLE
Answer no.20:
Sequence of Principal Events during Contract for WWTP design and build has been amended. Due to
that fact following table related to Indicative schedule of implementation has been changed:
End Month
Project commencement
Inception Report 1
Supervision Manual 1
Design Review and Permits 4
Supervision of works contract (including test on completion and pre-
commissioning) 26
Trial operation 38
Defect Notification Period 50
Final Report 51
Question no.21:
WITHE REFERENCE TO RFP 5, PAR 5.2 TABLE 2.
PROVIDED THAT AFTER PERMITS ACHIVEMENT THE WORKS CAN START, AND THAT PERMITS ARE
ACHIEVED AT MONTH 3, WHY DO THE SUPERVISION OF WORKS (DURATION 8 MONTHS) END AT
MONTH 12, INSTEAD THAN MONTH 11 (3+8=11)? DO WE HAVE TO SUPPOSE THAT WWTP D&B
CONTRACT AND SEWERAGE NETWORK D&B CONTRACT WILL START TOGETHER (4+8=12)?
WHY DO THE TEST ON COMPLETION END SIX MONTHS LATER THAN WORKS SUPERVISION?
PROVIDED THAT TEST ON COMPLETION START AS SOON AS SUPERVISION OF WORKS END, WE THINK
THAT 6 MONTHS ARE TOO MUCH FOR TEST ON COMPLETION OF SEWERAGE NETWORK.
WE THINK THAT SOME CALCULATION MISTAKES HAVE BEEN DONE IN THE ABOVE MENTIONED TABLE
Answer no.21:
Please, refer to the following table:
Question no.22:
WITH REFERENCE TO RFP 5, PAR 6.1.4.
1. SENIOR EXPERT, FORTH BULLET:
2. JUNIOR EXPERT, FORTH BULLET
3. TECHNICIANS, SURVEYORS, FORTH BULLET
DO YOU DEEM ACCETTABLE , INSTEAD OF “SAME POSITION”, DIFFERENT BUT HIGHER POSITION?
EXAMPLE 1 : IN ORDER TO COVER THE POSITION OF SURVEYOR/INSPECTOR DO YOU DEEM ACCETTABLE
THE CV OF AN EXPERT THAT HAS EXPERIENCE AS SITE MANAGER/SUPERVISOR?
EXAMPLE 2 : IN ORDER TO COVER THE POSITION OF SITE MANAGER DO YOU DEEM ACCETTABLE THE CV
OF AN EXPERT THAT HAD EXPERIENCE AS PROJECT MANAGER/RESIDENT ENGINEER?
Answer no.22:
Yes, it’s acceptable. The fact that an expert has covered higher position (respect to that one he is
proposed for), gives guarantee about his competencies in the assignment.
Indicative Schedule of Implementation SEWERAGE NETWORK Duration
(End of Month)
Project Commencement
Inception Report 1
Supervision Manual 1
Permits 3
Supervision of works contract (8 months construction ) 12
Test on Completion (3 months) 15
Defect Notification Period (10 months) 25
Draft Final Report 24
Final Report 25
Question no.23:
WITH REFERENCE TO RFP 5, PAR 6.1.1, CAN THE DEGREE IN CHEMICAL ENGINEERING BE CONSIDERED
EQUIVALENT TO THE EDUCATION PROFILE IN TABLE 5? WE THINK THAT THE EQUIVALENCE OF
EDUCATION PROFILE SHOULD DEPEND ON THE SYSTEM OF LICENCE (FOR ENGINEERING SERVICES) THAT
IS RECOGNIZED BY THE LEGISLATION OF THE COUNTRY WHERE THE EXPERT HAS ACHIEVED THE
UNIVERSITY DEGREE.
Answer no.23:
All the degrees that, according to the legislation of the country where they are achieved and the
relevant foreseen license, allow to design/supervision of Project in the water sector (WWTP and
sewerage network) are deemed equivalent to the education profile in table 5.
Question no.24:
WITH REFERENCE TO RFP 5, PAR 6.1.2:
- PROJECT MANAGER: REGARDING THE “SPECIFIC PROFESSIONAL EXPERIENCE IN LAST 10
YEARS”CAN THE PROJECT VERIFICATION/REVISION BE DEEMED ACCETTABLE IN ORDER TO
COVERT THE MINIMUM 5 ASSIGNMENTS IN DESIGN AND/OR SUPERVISION OF WWTP AND
SEWERAGE NETWORK?
- RESIDENT ENGINEER: REGARDING THE “SPECIFIC PROFESSIONAL EXPERIENCE IN LAST 10
YEARS”CAN THE PROJECT VERIFICATION/REVISION BE DEEMED ACCETTABLE IN ORDER TO
COVERT THE MINIMUM 5 ASSIGNMENTS IN DESIGN AND/OR SUPERVISION OF WWTP AND
SEWERAGE NETWORK?
- SENIOR EXPERT, THIRD BULLET: CAN THE PROJECT VERIFICATION/REVISION BE DEEMED
ACCETTABLE IN ORDER TO COVERT THE MINIMUM 5 ASSIGNMENTS IN DESIGN AND/OR
SUPERVISION OF WWTP AND/OR SEWERAGE NETWORK?
- JUNIOR EXPERT, THIRD BULLET: CAN THE PROJECT VERIFICATION/REVISION BE DEEMED
ACCETTABLE IN ORDER TO COVERT THE MINIMUM 2 ASSIGNMENTS IN DESIGN AND/OR
SUPERVISION OF WWTP AND/OR SEWERAGE NETWORK?
- TECHNICIANS, SURVEYOR, THIRD BULLET: CAN THE PROJECT VERIFICATION/REVISION BE
DEEMED ACCETTABLE IN ORDER TO COVERT THE MINIMUM 5 ASSIGNMENTS IN DESIGN
AND/OR SUPERVISION OF WWTP AND/OR SEWERAGE NETWORK?
Answer no.24:
YES, revision/verification assignments are acceptable. In the scope of the contract, the Engineer
shall carry out design review activities. Therefore, for the expert proposed in the Team, any
experience in this field is qualifying for the Tender.
Question no.25:
Answer no.25:
Fidic conditions do not provide terms such as resident or others.
Site manager, resident, surveyor represent a common terminology identified by the client for the
positions deemed necessary to comply with the contracts goals.
Since the description of detailed activities to be assigned to each role is part of the technical offer (see
rfp 3.5), no further clarification can be given.
Question no.26:
Answer no.26:
Correct, only 1 resident Engineer.
Question b.
Question c.
Question d.
Question e.
Answer 27 (a to e):
“Each expert can be proposed for more than one position until the proposal is compatible with timing
and scheduling of activities”.
This means that an expert that, according to GANNT (rfp 3.5),” is assigned on day “n” to position “a”,
cannot be assigned on the same day “n” to position “b”.
Provided that this principle is complied with, all the bids will be comparable and the working days
won’t be less than the minimal established by tor.
Furthermore, if any expert would be proposed for more than one position, the evaluation committee
will assess that the solution proposed by the bidder was not in conflict with the principle above
mentioned.
Since the above topic is part of the technical offer (see rfp3.4, rfp 3.5), no further clarification can be
given.
Question no.28 (a and b)
Question a.
Question b.
Answer 28 (a and b)
Site surveyor/inspector is intended to be a quantity surveyor, also in charge to supervise the quality of
works (inspection).
Since the description of detailed activities to be assigned to each role is part of the technical offer (see
Rfp 3.4), no further clarification can be given.
For question b, see also answer to question 21.
Question no.29:
Answer no.29:
The Candidate is free to propose junior or senior profile for experts at par 6.1.4.The Committee will
evaluate the adequacy of their profile.
Question no.30:
Answer no.30:
Technician/surveyor has not a university degree, but a technical education. The lower level in education
is offset by experience. Please, not that only for short term expert is allowed “technical education”,
further than the “university degree”.
Question no.31:
Answer no.31:
Yes, are acceptable, provided that the experience in relevant to D&B contract under FIDIC conditions.
See also answer 15.
Question no.32:
Answer no.32:
Yes, are acceptable provided that the experience in relevant to D&B contract under FIDIC conditions.
Question no.33:
Answer no.33:
Please refer to Answer 17
Question no.34:
In the pag 3, from RFP1, d3) it’s written:
d3) The candidate shall guarantee the following Key experts:
Position Number
Long Term Key Experts Resident Engineer 1
Short Term Key Experts
In the pag 12, from RFP5, point 6.1.1 it’s written:
Table 5 Experts’ working days
Position Education profile N° Minima
working
days
Long
Term Key
Experts
Resident Engineer
WWTP and sewerage
network
civil, construction, hydraulic, environmental engineer or equivalent,
1 500
In the pag 13, from RFP5, point 6.1.3 it’s written:
Resident Engineers
(…)
Two Resident are expected to be in this Project:
Resident for WWTP and sewerage network .
(….)
Our questions it’s:
• How many Resident Engineers we need to guarantee in order to fulfill the Tender
requirements?
Answer no.34:
Only one Resident Engineer . Pag 13, from RFP5, point 6.1.3 contains a typing mistake.
Question no.35:
In the pag 3, from RFP1, d1) it’s written:
d1) The candidate should have at least 6 stable engineers; stable engineers means that the
work relationship with the company shall be longer than 1 year, continuous and not occasional.
In the pag 5, from RFP2, point 3.6 it’s written:
(…)
• it is mandatory that 4 of the key experts proposed, have an extended
and stable working relationship with the Candidate;
from this, we understand:
Our questions it’s:
• It’s correct our reasoning?
Answer no.34:
No the reasoning is incorrect.
The coorect explanation is the following:
The requirements at page 3, from RFP1, d1) is referred in general to the staff of the
Candidate; this requirement aims at demonstrating the organizational and technical capacity
(in terms of technical staff) of the Candidate, independently from the team that he will
propose for the assignment.
The requirement at page 5, from RFP2, point 3.6 is referred to the key experts, that means
to the Supervision Team that is proposed in the Tender.
In conclusion, this means that at least 4 key expert of the Supervision Team (RFP 5, page
12, par 6.1.1 table 5) shall be chosen among the stable (6 or more) engineers that
constitute the permanent staff of the Candidate.
Question no.35:
Answer no.35:
Correct.