    TECHNIQUE INSPECTION &CONTROLE s.a.

    API 510: Pressure Vessel Inspection Code: Maintenance Inspection, Rating, Repair, and Alteration.

    API 570: Piping Inspection Code: Inspection, Repair, Alteration, and Rerating of In-service Piping Systems.

    ASME B31-3: Process Piping.

    IEC 947 (1 to 4) : For electrical equipment

    IEEE Std C37.20.2-1993 for Metal-Clad and Station-Type Cubicle Switchgear

    ANSI/IEEE 576-1989: IEEE Recommended Practice for Installation, Termination, and Testing of Insulated Power Cable as Used

    in the Petroleum and Chemical Industry

    IEEE Std 1159-1995 Recommended Practice for Monitoring Electric Power Quality

    IEEE C62.92.2 IEEE Guide for the Application of Neutral Grounding in Electrical Utility Systems Part IIGrounding of

    Synchronous Generator Systems

    IEEE Std C62.92.1 IEEE Guide for the Application of Neutral Grounding in Electrical Utility SystemsPart I: Introduction

    IEEE Std C62.92.3 IEEE Guide for the Application of Neutral Grounding in Electrical Utility Systems, Part IIIGenerator

    Auxiliary Systems

    IEEE C62.92.4 IEEE Guide for the Application of Neutral Grounding in Electrical Utility Systems, Part IVDistribution

    IEEE Std C62.92.5 : IEEE Guide for the Application of Neutral Grounding in Electrical Utility Systems, Part VTransmission

    Systems and Sub transmission Systems

    LOLER 98

    BS EN 12077-2 Cranes safety-Requirements for health and safety-Part 2: Limiting and indicating devices

    BS EN 12644 Crane - Information for use and testing-Part 2: Marking

    BS IS0 5057 Industrial trucksInspection and repair of fork arms in service on fork-lift trucks

  • 7/31/2019 QCP for Zueitina

    3/20

    TECHNIQUE INSPECTION &CONTROLE s.a.

    BS4278: Eyebolts for lifting purposes

    BS 6994:1988 : Specification for Steel shackles for lifting and general engineering purposes: grade M(4)

    BS EN13411-1:2002 : Terminations for steel wire ropesSafetyPart 1: Thimbles for steel wire rope slings BS EN 13411-2:2001: Terminations for steel wire ropesSafetyPart 2: Splicing of eyes for wire rope slings

    BS EN 13411-4:2002: Terminations for steel wire ropesSafetyPart 4: Metal and resin Socketing

    BS 6570: 1986: The selection, care and maintenance of steel wire ropes

    BS7035:1989: Socketing of stranded steel wire ropes

  • 7/31/2019 QCP for Zueitina

    4/20

    TECHNIQUE INSPECTION &CONTROLE s.a.

    Review and approve the technical calculation,

    data sheets, drawings and design data.

    Review Material List and certificates to pressure

    vessel drawings.

    Review manufacturer Welding ProcedureSpecifications (W.P.S.) and Procedure

    Qualification Record (P.Q.R.) for the materials of

    construction.

    Review manufacturer proposed level and extent

    of Non Destructive Examination (N.D.E.)

    Review manufacturer procedure for post weld

    heat treatment (if applicable).

    Review manufacturer pressure test procedure.

    Design code An engineer NA

  • 7/31/2019 QCP for Zueitina

    5/20

    TECHNIQUE INSPECTION &CONTROLE s.a.

    Visual inspection according to approved and asbuilt drawings.

    Dimensional check

    Internal and external inspection Design codeA qualifiedinspector

    Meter,clamps

    meter &Depthgauge

    Manufacturers

    procedures

    PQ/RSC-CV/01AG

    PQ/RSC-CV/01 AG

    RQ/CRS-APP/04

    Attend and witness the test pressure:

    Make sure that the equipment withstands the

    hydrostatic test without leakage through the

    weld seam or the vessel body.

    Design codeAn authorisedpressure vessel

    inspector

    Calibratedmanometer

    Manufacture

    s procedure

    PQ/CRS-APG/01 AG

    PQ/CRS-EHV/01 AG

    RQ/CRS-APP/04CE/CRS-APP/04

  • 7/31/2019 QCP for Zueitina

    6/20

    TECHNIQUE INSPECTION &CONTROLE s.a.

    Ensure that each pressure vessel has apermanently attached nameplate showing at

    least:

    The name of the manufacturer

    The manufacturers location

    The manufacturer's serial number

    identifying the vessel

    The year builtThe internal volume

    The hydraulic test pressure;

    The date of test;

    Any statutory marking required

    Affix the T.I.C. stamp on the accepted vessel

    Manufactures

    procedureDesign code

    An authorisedpressure vesselinspector

    T.I.C Stamp..

  • 7/31/2019 QCP for Zueitina

    7/20

    TECHNIQUE INSPECTION &CONTROLE s.a.

    Review and approve the technical calculation,

    data sheets, drawings and design data.

    Review Material List and certificates to

    pressure vessel drawings.

    Review manufacturer Welding Procedure

    Specifications (W.P.S.) and Procedure

    Qualification Record (P.Q.R.) for the materialsof construction.

    Review manufacturer proposed level and

    extent of Non Destructive Examination

    (N.D.E.)

    Review manufacturer procedure for post weld

    heat treatment (if applicable).

    Review manufacturer pressure test procedure

    Review of the maintenance record book /

    Review of previous inspection reports

    Design code An engineer NA

  • 7/31/2019 QCP for Zueitina

    8/20

    TECHNIQUE INSPECTION &CONTROLE s.a.

    Visual inspection according to approved and as

    built drawings. API 510A qualified

    inspectorNA

    Manufacturers

    procedures

    PQ/RSC-

    CV/01AG

    RQ/RSC-IV/01

    Dimensional check of each pressure vessel

    according to approved and as built drawings. Design codeA qualified

    inspectorMeter

    Manufacturers

    procedures

    Check the condition of the outside surface of

    the vessel, insulation systems, painting and

    coating systems, supports, and associated

    structure

    Check for leakage, hot spots, vibration, the

    allowance for expansion and the general

    alignment of the vessel on its supports

    Particular attention should be given to weldsused to attach components (e.g. reinforcement

    plates, and clips) for cracking or other defects.

    API 510 & API571

    A qualified

    inspector

    Meter, clampsmeter & Depth

    gauge

    PQ/CRS-APG/02 AG

    PQ/CRS-APG/02AG

  • 7/31/2019 QCP for Zueitina

    9/20

    TECHNIQUE INSPECTION &CONTROLE s.a.

    Thorough check of internal pressure boundary

    surfaces for damage

    Specific N.D.E. techniques may be required by

    the inspector to find damage specific to the

    vessel or service conditions.

    For equipment not designed for entrance by

    personnel, Boroscope check techniques may aid

    the check of these equipment internal surfaces.

    API 510 & API571

    Qualifiedinspector

    meter, clampsmeter, Depthgauge, Gasdetector &Borescope

    PQ/RSC-CV/01 AGPQ/CRS-APG/02

    AG

    RQ/RSC-IV/01

    They are taken to verify the thickness of vessel

    components. This data is used to determine the

    corrosion rates and remaining life of the vessel. The

    inspector should consult with a corrosion specialist

    when the short term corrosion rate changes

    significantly from the previous identified rate to

    determine the cause. Appropriate responses to

    accelerated corrosion rates may include, additionalthickness readings, U.T. scans in suspect areas,

    corrosion/process monitoring, and revisions to the

    vessels inspection plan.

    API 510

    Qualifiedinspector

    UT inspectorLevel II

    Wall thickness

    measurement

    apparatus

    PQ/RSC-ME/01 AGPQ/NDT-UT/01

    RQ/RSC-ME/01AG

    RQ/CND-UT/01

  • 7/31/2019 QCP for Zueitina

    10/20

    TECHNIQUE INSPECTION &CONTROLE s.a.

    Attend and witness the pressure test

    .

    API 510Design code

    An API510pressure vessel

    inspector

    Calibratedmanometer

    PQ/CRS-APG/01AG

    PQ/CRS-EHV/01AG

    RQ/CRS-APP/04

    Ensure that each pressure vessel has a

    permanently attached nameplate showing at

    least:

    The name of the manufacturer

    The manufacturers location

    The manufacturer's serial number

    identifying the vessel

    The year built

    The internal volume

    The hydraulic test pressure;

    The date of test;

    Any statutory marking required

    Affix the T.I.C. stamp on the accepted vessel

    Manufacturesprocedure

    Design code

    An API 510pressure vessel

    inspector

  • 7/31/2019 QCP for Zueitina

    11/20

    TECHNIQUE INSPECTION &CONTROLE s.a.

    Review and approve the technical calculation,

    data sheets, drawings and design data.

    Review Material List and certificates to pressure

    vessel drawings.

    Review manufacturer Welding ProcedureSpecifications (W.P.S.) and Procedure

    Qualification Record (P.Q.R.) for the materials of

    construction.

    Review manufacturer proposed level and extent of

    Non Destructive Examination (N.D.E.)

    Review manufacturer procedure for post weld

    heat treatment (if applicable).

    Review manufacturer pressure test procedure.

    The code towhich thetubular

    elements werebuilt

    Authorized Piping

    Inspector NA

  • 7/31/2019 QCP for Zueitina

    12/20

    TECHNIQUE INSPECTION &CONTROLE s.a.

    Confirm all operations have been done as per

    internal mill practices and procedures

    Design code,

    client

    requirements

    Authorized Piping

    InspectorTools

    inspection and

    instrumentation

    should

    provided by the

    manufacturer

    PQ/CRS-CUT /01 AG

    PQ/CRS-CUT /02 AG

    RQ/CRS-CUT /01 AG

    or

    RQ/CRS-CUT /02 AG

    The quality control of steel used for tubes is

    conducted by means of samples taken from tubes,

    after completion of manufacturing process likely to

    modify the metals properties.

    Values measured elongation, traction resistance and

    elasticity limits must fulfil provisions of the design

    code and be at least equal to the minimal specified

    values selected for the calculation of tubular

    elements. They must be measured on samples taken

    for the basic metal.

    Design code,

    client

    requirements

    Authorized Piping

    InspectorTools

    inspection and

    instrumentation

    should

    provided by themanufacturer

    PQ/CRS-CUT /01 AG

    PQ/CRS-CUT /02 AG

    RQ/CRS-CUT /

    01 AG

    or

    RQ/CRS-CUT /02 AG

  • 7/31/2019 QCP for Zueitina

    13/20

    TECHNIQUE INSPECTION &CONTROLE s.a.

    Each pipe shall be visually inspected to detect

    surface defects: Such inspection shall be over the

    entire external surface and shall cover as much of the

    internal surface as is practical.

    Design code,

    client

    requirements

    A qualifiedinspector

    Manufacturers

    procedures

    PQ/RSC-

    CV/01AG

    RQ/RSC-IV/01

    Tests pertaining to the quality of steel shall be

    performed on samples taken at the end of tubes

    randomly chosen by the T.I.C. from each lot of tubes

    made up of elements of the same characteristics,produced by the same melt

    Destructive Examinations related to the quality of

    longitudinal or spiral welds shall be performed on

    samples randomly chosen at the end of tubes

    Design code,

    client

    requirements

    A qualifiedinspector

    Tools

    inspection and

    instrumentation

    should

    provided by the

    manufacturer

    PQ/CRS-CUT /

    01 AG

    PQ/CRS-CUT /02 AG

    RQ/CRS-CUT /

    01 AG

    or

    RQ/CRS-CUT /02 AG

    Inspection of pipe to reveal imperfections, using

    radiographic, ultrasonic or other methods that do not

    involve disturbance, stressing or breaking of the

    materials

    Design code,

    client

    requirements A qualified

    inspector levelII

    Tools

    inspection and

    instrumentationshould

    provided by the

    manufacturer

    PQ/CRS-CUT /01 AG

    PQ/CRS-CUT /02 AG

    RQ/CRS-CUT /

    01 AG

    or

    RQ/CRS-CUT /02 AG

  • 7/31/2019 QCP for Zueitina

    14/20

    TECHNIQUE INSPECTION &CONTROLE s.a.

    The pipe shall withstand the hydrostatic test without

    leakage through the weld seam or the pipe body.

    Design code,

    client

    requirements

    An Authorized

    Piping Inspector

    Tools inspectionand

    instrumentation

    should provided

    by themanufacturer

    PQ/CRS-CUT /01 AG

    PQ/CRS-CUT /02 AG

    RQ/CRS-CUT / 01AG

    CE/CRS-CUT / 01AG

    RQ/CRS-CUT / 02AGCE/CRS-CUT/02 AG

    Any fitting equipment must be subject to an

    individual hydraulic test

    Design code,

    client

    requirements

    An Authorized

    Piping Inspector Tools inspectionandinstrumentation

    should providedby the

    manufacturer

    PQ/CRS-CUT /01 AG

    PQ/CRS-CUT /02 AG

    RQ/CRS-CUT /

    01 AGor

    RQ/CRS-CUT /02 AG

    Accessory devices must be subject of in factory

    hydraulic tests under the same conditions of tubular

    elements

    Design code,

    client

    requirements

    An Authorized

    Piping Inspector Tools inspectionandinstrumentationshould provided

    by the

    manufacturer

    PQ/CRS-CUT /01 AG

    PQ/CRS-CUT /02 AG

    RQ/CRS-CUT /

    01 AGor

    RQ/CRS-CUT /02 AG

    The accessory equipment shall withstand the

    hydrostatic test without leakage through the weldseam or the body.

    Design code,

    client

    requirements

    Authorized PipingInspector

    Tools inspection

    and

    instrumentationshould provided

    by the

    manufacturer

    PQ/CRS-CUT /

    01 AG

    PQ/CRS-CUT /02 AG

    RQ/CRS-CUT /

    01 AGor

    RQ/CRS-CUT /02 AG

  • 7/31/2019 QCP for Zueitina

    15/20

    TECHNIQUE INSPECTION &CONTROLE s.a.

    Ensure that the pipe markings includes the following

    information, as applicable:

    Name or mark of the manufacturer of the pipe

    Specified outside diameter;

    Specified wall thickness;

    Pipe steel grade (steel name)

    Product specification level designation; Type of pipe

    Mark of the customer's inspection

    representative, if applicable;

    An identification number, which permits the

    correlation of the product or delivery unit (e.g

    bundled pipe) with the related inspection

    document, if applicable.

    Design codeand client

    requirements

    An Authorized

    Piping Inspector

    PQ/CRS-CUT /01 AG

    PQ/CRS-CUT /02 AG

  • 7/31/2019 QCP for Zueitina

    16/20

    TECHNIQUE INSPECTION &CONTROLE s.a.

    The pipe coating inspector shall check, the

    following points, but not limited to:

    Material coating

    The identification of each tube

    Visual inspection shall be investigated for

    surface imperfections,

    Pipe end inspection

    Heat treatment

    Control of the pipe roughness surface

    Control of the coating thickness

    Pipe final marking

    specificationrequirements

    Coating /PaintingInspector

    Tools

    inspection andinstrumentation

    should

    provided by the

    manufacturer

    PQ/CRS-CUT /01 AG

    PQ/CRS-CUT /02 AG

    PQ/RSC-CP/01AG

    RQ/RSC-CP/01

  • 7/31/2019 QCP for Zueitina

    17/20

    TECHNIQUE INSPECTION &CONTROLE s.a.

    Review and approve the technical calculation,

    data sheets, drawings and design data.

    Review Material List and certificates to pressure

    vessel drawings.

    Review manufacturer Welding Procedure

    Specifications (W.P.S.) and ProcedureQualification Record (P.Q.R.) for the materials of

    construction.

    Review manufacturer proposed level and extent of

    Non Destructive Examination (N.D.E.)

    Review manufacturer procedure for post weld

    heat treatment (if applicable).

    Review manufacturer pressure test procedure.

    The code towhich thevessel was

    built

    An Authorized

    Piping Inspector NAPQ/CRS-

    APP/02 AG

  • 7/31/2019 QCP for Zueitina

    18/20

    TECHNIQUE INSPECTION &CONTROLE s.a.

    The pipeline shall withstand a pressure test without

    failure, leakage, distress, or distortion other than

    elastic distortion at a pressure equal to the test

    pressure of the system in which it is installed,

    either before installation or during the system

    test.

    API 570An Authorized

    Piping Inspector

    Calibrated

    manometer

    Dead weight

    tester with

    accessories

    Pressure

    recorder,

    Temperature

    gauge.

    PQ/CRS-EHG /

    01 AG

    PQ/CRS-EOL /

    01 AG

    RQ/CRS-EHG/01 AG

    CE/CRS-EHG/ 01 AG

    RQ/CRS-EOL

    / 01 AG

    CE/CRS-EOL/ 01 AG

  • 7/31/2019 QCP for Zueitina

    19/20

    TECHNIQUE INSPECTION &CONTROLE s.a.

    Visual & general checks

    Insulation Measurement.

    Bonding Measurement

    Earth connection Measurement

    Infrared testing

    ANSI/IEEEStandardslisted above

    A qualified

    inspector

    Electrical tester

    Megohmmeter

    Voltage detector

    Clip-on

    ammeter

    Infrared

    Camera

    PQ/CRS-IE/01 AG

    PQ/CRS-IE/02 AG

    PQ/RSC-TIT/01 AG

    RQ/CRS-IE/01

    RQ/CRS-IE/02

  • 7/31/2019 QCP for Zueitina

    20/20

    TECHNIQUE INSPECTION &CONTROLE s.a.

    Visual inspection of the characteristics of the

    different equipments, and determination of their

    conformities with specified requirements where

    applicable, and based on professional judgement

    where general requirements apply

    Dimensional check to show that the equipment

    has neither permanent deformation, nor

    abnormality that would render it incapable of

    being used safely for its designed purpose.

    Non-destructive examination of lifting equipment

    which should be examined by Magnetic Particle

    Inspection (M.P.I.)

    Functional tests related to the safety organs Functional tests an d overload tests

    LOLER &

    British

    standards listed

    above

    Dynamometer

    Magnetic

    indicator

    Magnetic yoke