7/27/2019 Quality Audit for Diesel Loco POH Workshop(1) http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 1/104 Page 1 of 104 Quality Audit of Diesel Loco POH Workshop Quality Audit of Diesel Loco POH Workshops CHECK SHEET Item Description Reference Documents, Annexures, Further details on check sheet etc. General Compliance of POH Schedule: Schedule of standard examinations: MP-Misc-140/141 (for Alco locos). Quality of POH: -do- Load Test records:  HP  SFC  EGT  Peak Firing Pressure Load Test MI No MP.MI-10 (Rev 0.02), Aug 2003. (for Alco locos). Methodology of collection of failures on locos turned out by shops, failure investigation, analysis and preventive action.  Display of work instructions on shop floor  Training of staff  Status of record keeping  Calibration of gauges/ instruments Safety items a. Speed recorder/Indicator Section b. Wheel (Wear adapted profile) profile & other defects. c. Brake adjustment, release & and application timings. d. Headlight focus adjustment e. Horn maintenance f. Undergear safety brackets g. Gauging of Couplers h. Vertical offset between Side bearer and centre pivot a. OEM’s maintenance manual. b. Drg No SKDL-2561 Alt 8. c. Standard test scheme as per MP.TP-029/87 (Rev 02) Oct 2008 for Air Brake, and, as per MP.TP-019/81 (Rev 02) Nov 08 for dual brake locos. d. IB No MP.IB.EC.01.08.06 (Rev 0) December 06. f. MI No MP.IB.BD.02.16.01 (Rev 01) December 09. g. CBC Manual No G 76 Sept 87. h. MI No MP.IB.VL.02.11.10 (Rev 00) February 10.

Upload: satyanarayanaboddul

Post on 14-Apr-2018

273 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 1/104

Page 1 of 104 Quality Audit of Diesel Loco POH Workshop

Quality Audit of Diesel Loco POH WorkshopsCHECK SHEET

Item Description Reference Documents, Annexures, Further details on check sheet

etc.

General

Compliance of POH Schedule: Schedule of standard examinations: MP-Misc-140/141 (for Alco

locos).Quality of POH: -do-

Load Test records:

 HP

 SFC

 EGT

 Peak Firing Pressure

Load Test MI No MP.MI-10 (Rev 0.02), Aug 2003. (for Alco locos).

Methodology of collection of failures on locos turned out by shops,

failure investigation, analysis and preventive action.

 Display of work instructions on shop floor

 Training of staff  Status of record keeping

 Calibration of gauges/ instruments

Safety items

a.  Speed recorder/Indicator Section

b.  Wheel (Wear adapted profile) profile & other defects.

c.  Brake adjustment, release & and application timings.

d.  Headlight focus adjustment

e.  Horn maintenance

f.  Undergear safety brackets

g.  Gauging of Couplers

h.  Vertical offset between Side bearer and centre pivot

a.  OEM’s maintenance manual.

b.  Drg No SKDL-2561 Alt 8.

c.  Standard test scheme as per MP.TP-029/87 (Rev 02) Oct

2008 for Air Brake, and, as per MP.TP-019/81 (Rev 02) Nov

08 for dual brake locos.

d.  IB No MP.IB.EC.01.08.06 (Rev 0) December 06.

f.  MI No MP.IB.BD.02.16.01 (Rev 01) December 09.g.  CBC Manual No G 76 Sept 87.

h.  MI No MP.IB.VL.02.11.10 (Rev 00) February 10.

Page 2: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 2/104

Page 2 of 104 Quality Audit of Diesel Loco POH Workshop

Quality of 

Subassembly

repairs

(important

items)

a. Expressor/Compressor

b. Air Brake Section

c. Bogie section

d. Rotating Machines Section

e. Turbo section

f. Engine Block, Crankshaft and Main bearings

g. Cylinder Head , Piston and Valve section

h. Radiator section.

i. FIP/Injector Section

 j. Governor Section

k. Electrical Control Section

l. Battery Section

m.  Under-frame, side buffers, cow catcher,

couplers, superstructure/Upper-frame, roof,

driver cabin, hand rails, fuel tank, loco

painting/marking/stencilling etc.

a.  Further details of check sheet covered in Annexure 1.

b.  -do-

c.  Further details of check sheet covered in Annexure 2.

d.  Further details of check sheet covered in Annexure 3.

e.  Further details of check sheet covered in Annexure 4.

f.  -do-

g. 

h.  -do-

i.  -do-

 j.  Further details of check sheet covered in Annexure 5.

k.  -do-

l.  -do-

m.  Further details of check sheet covered in Annexure 6.

Implementation

of modifications

As per modification sheets/Instruction Bulletin’s issued by RDSO/DLW/HQ.  

Material  Availability of critical items

 Procurement from unapproved sources, if any.

Any other itemAs decided by the auditing authority

Page 3: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 3/104

Page 3 of 104 Quality Audit of Diesel Loco POH Workshop

Annexure-1

CHECK LIST FOR

TECHNICAL AUDIT AT POH WORKSHOPS (BRAKE ITEMS)

S.No. Item Parameter Observ ations 

1. Whether all the items

prescribed in the schedule isbeing followed for brakeequipment, compressor /Expressor & air dryer or not

 As per Schedule of standard examinations

(No. MP.Misc.-140 & 141, Rev-01,September’2006) 

`

1. Whether maintenance is done as per RDSOMIs or manufacturers MI mentioned inMP.Misc.-140 & 141.

2. Maintenance facilities are available or not.2. Functioning of VCD Whether functioning of VCD is being checked in

every POH schedule.

3. Test benches and rigs 1. Whether the required test bench and rigs areavailable or not viz. AB test rack for brakevalves, air dryer test bench, compressor/

Expressor test bench etc.2. Whether, testing is done on above test

benches.3. Calibration of test benches and rigs is being

done periodically or not.

4. Test on Loco after POH Whether brake system check is done on loco asper test programme no. MP.TP-029 (for air brakeloco) & MP.TP-019 (For dual brake loco).

5. Infrastructure facilities (a) Whether dust proof and controlledtemperature environment for maintenance,assembly and testing of brake valves is

available.(b) Availability of compressed air (in test

benches.(c) Availability of compressor in air lines.(d) Whether air dryer provided in test benches/

air lines.(e) Reservoir pressure is being checked or not(f) Washing facilities

Page 4: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 4/104

Page 4 of 104 Quality Audit of Diesel Loco POH Workshop

(g) Painting facilities(h) Technical Cell(i) Metrology lab(j) Store(k) Tool room(l) Fire extinguishers(m)Material handling facilities for movement of 

material and components.

6. Storage of material Whether dust/damp proof environment withcontrolled temperature is available for storage of brake equipment and rubber components.Whether rubber components are being stored asper guidelines mentioned in this office letter no.SD.DEV.RBC dated 28.02/07.03.2007 circulatedto all Zonal Railways.

7. Availability of Material Any Chromic shortage of material for maintenance

8. Human Resourcedevelopment

Whether periodic training is being imparted tomaintenance staff to make them conversant withthe maintenance practices.

9. Any other observation

Page 5: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 5/104

Page 5 of 104 Quality Audit of Diesel Loco POH Workshop

Annexure-2

CHECK SHEET FOR

CONDUCTING TECHNICAL AUDIT OF BOGIE AT POH WORKSHOP (ALCO LOCOMOTIVE)

SN Activity Loco Type Reference Details Observations

1. Overhauling/Inspection Alco Series

RDSO report Misc. No. Misc-164,MP.MI-71/78 and SK.DL-3370 to befollowed

  Cleaning of bogie frame

   Alignment of bogie frame (includingtramming)

a)  Wheel base spacingb) Transverse pedestal spacingc)  Longitudinal pedestal spacingd) Pedestal bottom alignmente) Motor nose suspension lug

squareness & spacing

  Crack detection, repair & heattreatment (Stress relieving)

  Replacement of manganese liners andbrake rigging bushes

WDM2, WDM3A, WDG3A, &

WDM3D/E/F

2. Axle box & journal bearings

  Cleaning of Axle box & bearings

  Inspection bearing components

  Overhauling as per the referred MP.MI

MP.MI-04.004

3. Suspension Springs ( As per MI ) 

 Cleaning of springs

 Free height of springs

 Working height of springs

 Grouping / colour code of springs 

 100% replace of spring pads ( HappyPads) 

WDM2, WDM3A, WDG3A, &

WDM3D/E/F

 As per relevant drawing,MP.IB.VL- 04.19.01 (Rev.01),

MP.IB.VL- 04.19.01 (Rev.01) for 

WDG3A & MP.MI-31 for 

WDM3D/E/F

4. Friction Snubber Assembly

 Disassemble snubber (See SK.DL- 1505for instructions)

 Check the inside diameter of the frictionsleeve with a “No Go” gauge FigureSK.DL- 3127

Details as per Drawing SK.DL-2089A, SK.DL- 1505, SK.DL- 3127,SK.DL-3126, SK.DL- 1512 , SK.DL-1513

Page 6: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 6/104

Page 6 of 104 Quality Audit of Diesel Loco POH Workshop

 Check the dimensions of the shoes asindicated in figure SK.DL-3126

 Replace worn or broken parts. For assembly refer SK.DL- 1512 &1513

 Re-assembly of snubber 

 Height measurement and checking for damping characteristics

5. Hydraulic damper 

  Check the Capacity / Rating of dampers  Damper overhauling 

  Testing 

 As per drawings No. SK.VL-295,

SK.VL-328 and SK.VL-387 &overhauling as per MP.IB.VL. 05.39.10 (Rev.00)

6. Side Bearer (Rubber spring)

 Free Height of rubber spring 

 Working height of rubber spring

 Permanent set of rubber spring

 Rubber crack length/ de-bonding 

WDG3A, & WDM3D/E/F As per drawings No. SK.Vl-127 &

133 &

MP.IB.VL. 04.30.08 (Rev.01)

7. Equaliser Beams

  Checking for cracks

  Reclamation of hard face as per MC-43

and 92 

WDM2, WDM3A, M&C document no. MC – 43 & MC-92

8. Wheel & Axle Assembly

  Wheel wear measurement i.e. Rootwear, Tread wear, Flange wear, wheelflat, visual inspection for any defectlike crack, wheel flat, shelling, spalingetc. ,wheel reprofiling.

  Wheel gauge (1596+3/-0.5 mm)

  Deference in tread diameter of wheelson same axle, same bogie & sameloco

  Ultrasonic testing of axles 

WDM2, WDM3A,WDG3A, &

WDM3D/E/F

Wheel wear managementInstruction Bulletinno.MP.IB.BD.0216.01 (Rev-1) & MPMI71/78 & MP.MI-31

RDSO procedure MC-71

Page 7: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 7/104

Page 7 of 104 Quality Audit of Diesel Loco POH Workshop

9.  Brake rigging

   Abnormal wear of brake hangers

  Replacement of Brake blocks, Pins &Bushes

  Replace brake head, tie rod, brakeshoe key, top & bottom slack adjusters

(condition basis) and friction armspring, if found damaged. 

MP.MISC – 141

1. Centre Pivot & Loading Pads

 Load Pad to Centre Pivot HeightDifference to be maintained. 

2.  Floating type Pivot assembly:Dismantle complete assembly

 Clean of the metal component exceptrubber bush

 Inspect for wear, tear and cracks

 Reassemble pivot block assembly withchange centre pivot bush.

 In case non-metallic pivot block, 100%replacement may be carried out. 

WDM2, WDM3A

WDG3A, & WDM3D/E/F

MP.IB.VL.02.11.10

SK.VL-128

SK.VL-501, RDSO Modification

sheet no. 03.10.09

10. Lateral Stopper, lifting chain and other fasteners and brackets are to be 100%replaced.

WDG3A, & WDM3D/E/F SK.VL-134

11. Re-assembly of bogieMaintain all running gear clearance as per the MI’s Maintain the Lateral clearances between

 Axle Box and Pedestals

(Ensure attention to wheel and axleassembly as per S.N. 8)

WDM2, WDM3AWDG3A, & WDM3D/E/F

MP.MI-71/78, VL.Mi-02/96 &MP.MI-31

MP.IB.VL.03.04.06 (WDM2 &

WDM3A)

MP.IB.VL.01.02.06 (WDG3A)

Page 8: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 8/104

Page 8 of 104 Quality Audit of Diesel Loco POH Workshop

12. Availability of Tools And Test Stands WDM2, WDM3A,WDG3A, &

WDM3D/E/FOver head Crane 

Hydraulic Jacks 

Cleaning vat 

Bogie frame manipulator  

Crack reclamation facility like gouging,

grinding & welding facility etc.Stress relieving furnace

DPT, MPT & UT testing facilities

Surface table for measurement

Spring load-deflection testing machine

Hydraulic damper testing machine

Torque wrench, Go/No Go Gauges

Height gauges

Inside and Outside Calliper, Vernier Caliper, Height Gauge, Cleaning Tank,

Painting facilitiesWheel wear measuring gauge SK.DL-3592

Elecrode heating oven

Facility to measure pre-heat temperature

13. Availability Of Instructions Etc

 Availability of WI including criticaldimensions

Training of staff including qualification of welders

Maintenance manual and check sheets

Record keeping of tools and measuringinstruments

Calibration of measuring instruments

14. Record Keeping For Traceability

Page 9: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 9/104

Page 9 of 104 Quality Audit of Diesel Loco POH Workshop

Annexure-3

CHECK SHEET FOR

QUALITY AUDIT OF TRACTION MOTOR PINION & GEAR ASSLY. AT POH WORKSHOPS

During the audit, activities should be checked with regard to the Clause/Para/Item of the reference documents. Wherever the activities are

not performed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded:

S.N REQUIREMENTS LOCO TYPE MAKE OF SUB-ASSEMBLY

REFERENCEDETAILS

CLAUSE/PARA/

ITEM

DETAILS

OBSERVATION

1 MEASUREMENT

Alco (WDM2,

WDM3A,WDM3D)

MP-IB.EM.10.31.08dated

24.10.2008

1.1  TRACTION GEAR & PINION 

Gear Ratio 18 : 65

Pinion Drg. No. 18 teeth, SKDP3624

Pinion Bedding In ColdCondition

Not less than 95 %

Pinion Advance 2.25 TO 2.45MM

Heating Temperature 190ºC + AMB TEMP.

Span Size On New Pinion Over 3 teeth88.595 /88.722MM

Condmning Limit On Basis Of Span Size Of Pinion

Over 3 teeth86.995MM

Gear Drg. No. 65 teeth SKDP3623& SKDP3775

Span Size On New Gear  Over 7 teeth223.989/223.798MM

Condmning Limit On Basis Of Span Size Of Gear  Over 7 teeth220.800MMPermissible Backlsh With NewSet

0.266 - 0.664MM

Condemning Limit On BasisOf Backlash

1.04MM

Crack detection MPMI or Zyglo test

Page 10: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 10/104

Page 10 of 104 Quality Audit of Diesel Loco POH Workshop

1.2 TRACTION GEAR & PINION

WDG3ATraction Motor Pinion & Gear  Assly. of Alco

Loco

MP-MI 129/86July ‘1986 

MP-MI 5

Gear Ratio 18 : 74

Pinion Drg. No. 18 teeth, SKDP3443

Pinion Bedding In ColdCondition

Not less than 95 %

Pinion Advance 2.30 TO 2.45MM

Heating Temperature 185ºC + AMB TEP.Span Size On New Pinion Over 3 teeth 81.976

/82.093MMCondmning Limit On Basis Of Span Size Of Pinion

Over 3 teeth80.366MM

Gear Drg. No. 65 teeth SKDP3444 &SKDP3546

Span Size On New Gear  Over 8 teeth231.36/231.177

Condmning Limit On Basis Of Span Size Of Gear 

Over 8 teeth 228.140

Permissible Backlsh With NewSet

0.243 - 0.608MM

Condemning Limit On BasisOf Backlash

1.00MM

Crack detection MPMI or Zyglo test

1.3 TA FAN ASSEMBLY

All ALColocos

MP-IB.EM.01.02.10dated 11.01.2010.

Outer diameter of TA fan

1387.25/1387mm

Bore diameter of TA stator 1392mm

Bore diameter of TA fan 600.00 / 600.03mm

Diameter of fan seating area onbarrel. 

600.03 / 600.06mm

Width of fan seating at bore 9+1 mmDepth of counter sunk bolts hole 4.5 - 5.5 mm

Bolt head width 12.3mm

Bolt head height above fan plateafter final assembly should not bemore than

6- 7mm

Circumferentially Fan gap on TA 2.50 – 2.75mm

Tightening torque and wire lockingprocess

28 – 30Kg-m

Page 11: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 11/104

Page 11 of 104 Quality Audit of Diesel Loco POH Workshop

Tightening torque of M30(coupling bolt)

170 – 180 kg-m.

Oil catcher thickness (at bottomside)

53.90 to 54.10mm

Bolts strength properties grade R8.8.

Sunk type M20 bolts can be used in place of fullythreaded M20 bolts

M20 & M30 bolts should be

replaced

 After 4 – 5 years

service of TAFan bore area should be heated(for shrink fit).

150 to 170 °С 

Re-used or old bolts and barrelthread condition should bechecked by

GO & NO GO threadring or plug gauge

Threaded portion of barrel & boltsshould be free from varnish or paint or dust deposits.

Visual inspection isrequired

TA fan should be mounted on thebarrel by “shrink fit “

In place of (bolts)press fit.

TA fan bolts locking wire endsshould not be come out of the bolthead(projected)

 As shown in photo

Proper alignment of TA fan shouldbe checked by inserting filler gauge circumferentially

Clearance betweenthe fan (back side)and barrel of TA (asshown in attachedphoto)No clearance isallowed.

 After Final assembly of TA fan,visual inspection is required on

Tightening torque,wire locking & fanback clearance withbarrel(by filler gauge(circumferentially)

TA Gear train assembly Backlash at Steelplate

All ALColocos 

MP.IB.EM.02.12.0

0dated 10-4-2000.TA GEAR 102T AG/EG PINION 43T

PTU PINION - 43T

0.60mm to 1.40mm0.05mm to 0.12mm

on shaft

Page 12: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 12/104

Page 12 of 104 Quality Audit of Diesel Loco POH Workshop

2 Carbody cables and Traction Motor cables

All ALColocos 

MP.IB.EM.02.03.08,dated 24-01-2008

And

MP.IB.EM.03.04.08,dated 24-01-2008 

Ensure the following:

Control cables should be replaced fully irrespective of 

the condition after every 8 years. Power cables

should be replaced on condition basis. During POH

power cables, which are exposed to oil should be

critically examined and replaced if any symptoms of 

bulging, softening or perishing of insulation at the

cable terminals are noticed. 

3 AVAILABILITY OF TOOLS AND TEST STANDSAll ALColocos 

MP.IB.EM.02.03.08,dated 24-01-2008

And

MP.IB.EM.03.04.08,

dated 24-01-2008 

2.1 Vernier Callipers

2.2 Disc Mike

2.3 Filler Gauge

4 INSTRUCTION

3.1 Display Chart

3.2 Training of Staff 

3.4Record keeping of tools and measuring

instruments

5 TRACEABILITY

6 MATERIAL AVAILABILITY

5.1 Vital Spare -NA

5.2 Must change items -NA

Page 13: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 13/104

Page 13 of 104 Quality Audit of Diesel Loco POH Workshop

CHECK SHEET FOR

QUALITY AUDIT OF TRACTION MOTORS AT POH WORKSHOPS

During the audit, activities should be checked with regard to the Clause/Para/Item of the reference documents. Wherever the activities are

not performed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded:

SN REQUIREMENTS LOCO TYPE MAKE OF SUB-

ASSEMBLY

REFERENCE

DETAILS

CLAUSE/

PARA/

ITEM DETAILS

OBSERVATI

ON

1 MEASUREMENT

Alco Locos

Traction Motors

of Alco Loco

MP.MI-2,

MP.MI-6 &

Maintenance

manual issued

by OEMs viz.

BHEL / CGL.

1.1 PRE-INSPECTION

i) Record IR of 

a) Armature (Shall be > 10 MΩ) 

b) Inter Pole (Shall be > 10 MΩ ) 

c) Main Pole (Shall be > 10 MΩ) 

ii) Record ovality of commutator (Limit – 0.001”) 

1.2 AFTER DIS-MANTLING 

i) Pinion to be sent for Magna flux test / Zyglo test

ii) Visual examination of Armature banding. If found

beyond repair, rewind it.

iii) Check commutator dia. for condemning size.

Replace commutator, if condemning size reached.

If commutator is retained, then check millivolt

drop to ensure health of tig welding/bar to bar

shortening. If required, repair it.

iv) Check commutator surface roughness. If found >

0.05  mm or any cut mark is observed,

commutator to be grind on machine.

v) Ensure that there is no damage on armature

seating area & armature shaft. If any damaged is

noticed, re-metalize it to reqd. size.

vi) Ensure cleaning of magnet frame with cleaning

solvent to RDSO spec. MP.0.8000.01 Rev.02

Oct.’2007. 

Page 14: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 14/104

Page 14 of 104 Quality Audit of Diesel Loco POH Workshop

vii) Bake the magnet frame in oven at 120 + 10 °C &

record it.

viii) Apply insulation varnish as per RDSO MP.MI

153/92 (latest revision)

ix) Check IR after renewal of glass epoxy laminate,

GMGS & Nomex insulation for inter poles & main

poles (Shall be > 100 MΩ )

x) Ensure tightening of pole bolts during assembly of 

magnet frame and maintain IP & MP bores as per

OEM manual.

xi) Joints may be brazed & insulated, if required with

RDSO approved Silicon elastomer tape.

xii) Check IR of main pole & inter pole assemblies &

record it. (Shall be > 100 MΩ )

xiii) High potential test of inter pole & main pole at

1.3 KV for 15 sec. shall pass the test.

xiv) Ensure spray cleaning of armature with cleaning

solvent to RDSO spec. MP.0.8000.01 Rev.02

Oct.’2007. 

xv) Bake the armature in oven at 120 + 10 °C &

record it.

xvi) Spray varnish paint protecting the shaft &

commutator & cure it.

xvii) Ensure mica cutting. & chamfering as per OEM’s

manual

xviii) Ensure cleaning & baking of brush arms as perOEM’s manual. 

xix) Measure IR of brush arm (Shall be > 100 MΩ). If 

less, replace the brush arm

xx) Ensure the spring tension. (Lt. 4.5 Kg to 5.5 Kg) 

Page 15: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 15/104

Page 15 of 104 Quality Audit of Diesel Loco POH Workshop

xxi) Ensure the replacement of PTFE sleeve of brush

arm.

xxii) Ensure painting of support arm with red becktol

varnish.

xxiii) Conduct high potential test as per OEM’s manual 

1.3 ASSEMBLY

i) Motor assembly as per OEM’s manual 

ii) Measure the final Insulation Resistance = 10

Mega ohm

a) Armature (Shall be > 100 MΩ) 

b) Inter Pole (Shall be > 100 MΩ ) 

c) Main Pole (Shall be > 100 MΩ) 

iii) Measure the end float (Lt. = 0.006” to 0.012”) 

iv) Check the nose plate condition. If found damaged

or wear out, shall be replaced.

v) Conduct the light run test at low, medium & highrpms on assembled motor & observe for unusual

sound using listening rod.

vi) Check the bearing temperature after stabilisation

during light un test. (Shall not be > 60 °C) 

vii) Apply brush seater on the commutator to seat

the carbon brushes on the commutator properly.

viii) Ensure tag welding / welding of stays on main

pole & compole fixing bolts.

ix) Apply recommended sealant to avoid ingress of 

water etc.x) Apply a coat of paint on motor.

Page 16: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 16/104

Page 16 of 104 Quality Audit of Diesel Loco POH Workshop

2 AVAILABILITY OF TOOLS AND TEST STANDS

2.1 1000V Megger

2.2 Filler gauge

2.3 HV tester

2.4 Dial gauge

2.5 Tachometer / Speedometer2.6 Pyrometer

2.7 Inside & Outside micrometer /calliper

3 INSTRUCTION

3.1 Display Chart

3.2 Training of Staff 

3.3 Record keeping of tools & measuring instruments

4 TRACEABILITY

5 MATERIAL AVAILABILITY & STORAGE (AC/non-

AC)

5.1 Vital Spares

5.2 Must change items

Page 17: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 17/104

Page 17 of 104 Quality Audit of Diesel Loco POH Workshop

CHECK SHEET FOR

QUALITY AUDIT OF TRACTION ALTERNATOR AT POH WORKSHOPS

During the audit, activities should be checked with regard to the Clause/Para/Item of the reference documents. Wherever the activities are

not performed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded:

SN REQUIREMENTS LOCO TYPE MAKE OF SUB-

ASSEMBLY

REFERENCE

DETAILS

CLAUSE/

PARA/ITEM

DETAILS

OBSERVATIO

N

1 MEASUREMENT

ALCO locos TractionAlternator

of Alco loco 

BHEL’s 

Maintenance

Manual forElectrical

Equipment of 

ALCO loco

(Volume-II)

a)Check tightness of all mechanical and

electrical connections. Check slip rings and

brushes for sparking.

b)BRUSH GEAR

Spring pressure- 1.36 to 2.2 kgs (adjustable) to

be adjusted to 1.8 kgs.Minimum length of brush at which brush

become inoperative – 35mm.

Clearance between brush holder & slip ring- 2

to 3 mm.

c)SLIP RING

Diameter (New) – 520 mm

Minimum worn out dia – 510 mm

Slip ring run our (max) – 0.1 mm

Slip ring ovality (max) – 0.1 mm

Page 18: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 18/104

Page 18 of 104 Quality Audit of Diesel Loco POH Workshop

d)ROTOR

Diameter- 1003 mm

Air gap at pole center – 6 mm

Rotor bearing - NU330 EM/C4/D150mm x65

mm x 320mm O/D

Bearing housing dimension – 320-0.005 mm.where outer race sites - - 0.025 mm

Radial clearance of free bearing when new – 

0.165 to 0.215 mm

Fit between outer race & bearing housing-

0.035 mm clearance, 0.025 mm interference

Shaft bearing seating dia – 150 + 0.055 mm

+ 0.035 mm

Fit between inner race & shaft – 0.035 to 0.08

mm interferenceDiametrical slackness of free bearing – 0.15 to

0.18 mm

Min. permissible racial clearance when

assembled - 0.03 to 0.13 mm

Min. diametrical clearance when assembled in

the machine – 0.051 mm

Bull gear wheel I/D – 149.098 + 0.025 mm

+ 0.0 mm

Shaft bull gear seating dia –149.098 + 0.162 mm

+ 0.152 mmGear box oil capacity – 2.6 litres approx.

Lubricant type – SAE 40 or equivalent 

Page 19: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 19/104

Page 19 of 104 Quality Audit of Diesel Loco POH Workshop

e)TIGHTENING TORQUE KG.M

Exciter to gear box – 15

Aux-gen to gear box – 15

PTU to gear box – 15

Gear box to end shield – 15

(write locked)Gear box to end shield – 1

(at pads)

Fan to rotor shaft – 25/27

(write locked)

Rotor shaft extension to barrel – 25

Rotor pole bolts – 170/190

Slip ring to shaft extn. – 15

f) RESISTANCE AT 25°C-

Stator- 0.002156 ohm (Line to Line)

Rotor- 0.312 ohm (at slip ring)

g) IR TESTS

Stator (check with 1000V magger) : 2M Ohms

Rotor(check with 1000V magger) : 2M Ohms

2 AVAILABILITY OF TOOLS AND TEST STANDS

a.  Bearing retaining ring

b.  Clamping ring

c.  Shaft adaptor

d.  Guide sleevee.  Frame lifting fixture

f.  Extractor for bull gear

g.  Lifting tackle

h.  Forcing screws

i.  Guiding studs

 j.  Spacers

k.  S.K.F. Oil Pump

Page 20: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 20/104

Page 20 of 104 Quality Audit of Diesel Loco POH Workshop

l.  Studs

m.  protection sleeves

n.  Extractor for bearing inner race

o.  Extractor foe bearing outer race from

bearing housing

3 INSTRUCTION

3.1 Display Chart3.2 Training of Staff 

3.4Record keeping of tools & measuring

instruments

4 TRACEBILITY

5 MATERIAL AVAILABILITY

5.1 Vital Spare

5.2 Must change items

Page 21: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 21/104

Page 21 of 104 Quality Audit of Diesel Loco POH Workshop

CHECK SHEET FOR

QUALITY AUDIT OF TRACTION MOTOR BEARING & ASSLY. COMPONENTS AT POH WORKSHOPS

During the audit, activities should be checked with regard to the Clause/Para/Item of the reference documents. Wherever the activities are

not performed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded:

S.N REQUIREMENTS LOCO TYPE MAKE OF SUB-

ASSEMBLY

REFERENCE

DETAILS

CLAUSE/

PARA/ITEM

DETAILS

OBSERVATION

1 MEASUREMENT

All ALColocos fitted

with TM4907/C1001

Traction Motor Bearing & Assly.Components of 

 Alco Loco

MP-IB.EM.14.50.08

dated20.02.2009

1.1  Verticality of Outer race

1.2 Verticality of Inner race

1.3 Max. deviations allowed in above cases:

Side Inner race Outer race

Pinion End 0.075 mm 0.25 mm

Commutator End 0.065 mm 0.20 mm

1.4 Radial Clearances of bearings

a) For New Bearings

Bearing Radial clearancebefore mounting

(mm)

Radial clearanceafter mounting (mm) 

NU 330 0.165 - 0.215 0.100 – 0.170

NH 320 0.105 – 0.140 0.060 – 0.100

b) In addition to above, max. service radialclearance 

NU 330 0.300 mm max. 0.250 mm max.

NH 320 0.190 mm max. 0.150 mm max.

c) Flinger - PEBore Dia. 153.130 to 153.155 mm

Total Width 12.65 to 12.70 mm

d) Retaining collar - PE

Bore Dia. 146.015 to 146.040 mm

Total Width 12.65 to 12.70 mm

Outer Dia. 253.225 to 253.290 mm

Page 22: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 22/104

Page 22 of 104 Quality Audit of Diesel Loco POH Workshop

Hub Outer dia. 177.040 to 177.090 mm

Outer dia. on 2n

Groove 210.610 to 210.670 mm

Groove width 8.00 to 8.05 mm

Total width 44.4 to 44.6 mm

e) End shield - PE

Bore dia. 319.975 to 319.995 mm

f) End shield - CE

Bore dia.  214.980 to 215.00 mmg) Seat diameter on armature shaft

For brg.-PE, Bore dia. 150.035 to 150.055 mm

For brg.-CE, Bore dia. 100.025 to 100.040 mm

For retaining collar PE 146.130 to 146.150 mm

For bearing sleeve PE 153.220 to 153.240 mm

For inner brg. wiper CE 101.600 to 101.620 mm

h) End Float on Traction motor (TM 4907) CE

Limit – 0.50 mm Aim – 0.42 mm

1.5 Fits & Clearances (BG TM)

i) Pinion end bearing

Interferences (Diametrical) Clearances (Diametrical

Brg. Sleeveto shaft

0.020 to0.065 mm

Brg.Sleeve toinner brg.cap

0.635 to0.750 mm

Flinger toshaft

0.065 to0.110 mm

Retainingcollar toouter brg.cap

0.25 mm(min.)

Inner race toshaft

0.035 to0.080 mm

--------------- -------------- 

Retainingcollar to shaft

0.090 to0.135 mm

-------------- -------------- 

Page 23: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 23/104

Page 23 of 104 Quality Audit of Diesel Loco POH Workshop

ii) Commutator end bearing

Interferences (Diametrical) Clearances (Diametrical

Brg. Sleeveto shaft

0.020 to0.065 mm

Inner brg.Cap tosleeve

0.635 to0.750 mm

Flinger toshaft

0.065 to0.110 mm

--------------- -------------- 

Inner brg.

Race to shaft

0.025 to

0.060 mm

-------------- -------------- 

1.6 Heating temp. of brg. & assly. components

Item Heating temp.

Bearing inner race PE 100 - 110 ºC

Bearing inner race CE 100 -110 ºC

Sleeve (PE) 100 -130 ºC

Sleeve (CE) 100 -130 ºC

Flinger (PE) 100 -120 ºC

End shield (PE) 120 -130 ºC

End shield (CE) 120 -130 ºC

Retaining collar (wiper) 120 -130 ºC

2 AVAILABILITY OF TOOLS AND TEST STANDS

2.1 Dial gauge3 INSTRUCTION

3.1 Display Chart

3.2 Training of Staff 

3.3Record keeping of tools and measuring

instruments

4 TRACEABILITY

5 MATERIAL AVAILABILITY

5.1 Vital Spare - NA

5.2 Must change items - NA

Page 24: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 24/104

Page 24 of 104 Quality Audit of Diesel Loco POH Workshop

Annexure-4 

CHECK SHEET FOR

QUALITY AUDITOF TURBO SECTION (POH)

During the audit, activities should be checked with regard to the Clause/Para/Item/chapter of the reference document as per applicability. Wherever the

activities are not performed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded.

Workshop/Rly: Audited by: Date of audit:

SN Requirements Loco Type Make Of 

Subassembly

Reference

Details

Clause/Para/It

em Details

Observations

1.

Balancing, measurementsetc

Balancing:

1.1 Bladed shaft, range 31-257 gmm.

1.2 Rotor, range 157-470 gmm.

5.6

5.6.2.5

5.6.2.5

Rotor Shaft Dimensions:

1.3 Bearing position OD A 39.98 – 40.00 mm

Alco ABB VTC 304

Turbocharger

ABB-Exhaust

Gas

Turbocharge

r VTC 304 A

Comprehensi

ve Manual

for Indian

Railways

issued by

M/s ABB

Para 5.2.4.13

&

details in5.4.2.1

1.4 Bearing position OD B 50.987--51.000 mm

1.5 Bearing position OD C 56.10-56.20 mm

1.6 Piston ring recess S 2.58-2.85 mm

Wheel Bush

1.7 Compressor wheel set OD A 56.10 -56.20 mm

Para 5.2.4.13

&

details in

5.4.2.2

1.8 Piston ring recess S 2.58-2.85 mm

1.9 Plain bearing (CE) ID A 54.00-54.06 mm Para 5.2.4.13

&

details in

5.4.2.3

1.10 Bearing housing bore ID A 65.00-65.07 mm Para 5.2.4.13

&

details in

5.4.2.4

Page 25: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 25/104

Page 25 of 104 Quality Audit of Diesel Loco POH Workshop

1.11 Floating bush ID (CE) 40.011-40.05 mm Para 5.2.4.13

&

details in

5.4.2.5

Floating bush OD (CE) 53.80-53.86 mm

1.12 Floating bush OD (TE) 64.82-64.84 mm

1.13 Floating bush ID (TE) 51.022-51.07 mm

1.14 Thrust bearing width 10.39-10.50 mm Para 5.2.4.13

&

details in5.4.2.6

1.15 Axial bearing width 16.76-16.88 mm Para 5.2.4.13

&

details in

5.4.2.7

1.16 Piston ring width 2.00-2.49 mm Para 5.2.4.13

&

details in

5.4.2.8

1.17 Thrust bearing press fit measure(K) 170.5-170.63 Para 5.2.4.13

&details in

5.4.2.9

1.18 Axial clearance A 0.11-0.32 mm Para 5.2.4.13

&

details in 5.7

1.19 Radial clearance B 0.47-0.93 mm

2.

 Availability of Tools, Test Stands etc.

Alco do do

2.1 Balancing machine

2.2 Zyglo testing machine

2.3 Casing hydraulic test stand

2.4 Bearing puller (CE & TE)

2.5 Torque wrench up to 250 psi

2.6 micrometer 2”-3” & 0-4” 

2.7 Go-NoGo gauge for checking fix nozzle ring

3

 Availability of instructions etc.

3.1 Display Chart

3.2 Training of staff 

3.3 Maintenance manual and check sheets

3.4 Record keeping of tools and measuring instruments

Page 26: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 26/104

Page 26 of 104 Quality Audit of Diesel Loco POH Workshop

4 Record Keeping For Traceability 

5

Material Availability 

5.1 Vital Spares

5.2 Must change items

1

Measurements etc

1.1 Nozzle ring and gas inlet casing 0.022-0.032”DiaClearance (Cl)

Alco Alco 720

Instruction

Manual

ALCO

ALCo MI

11126

1.2 Turbine blade and gas inlet casing 0.060-0.092”Dia CI 

1.3 Nozzle ring and turbine disc 0.124” cold CI 

1.4 Intermediate casing and impeller 0.017-0.065”

longitudinal Clearance (long Cl)

1.5 Impeller and Blower inlet 0.035-0.075” long CI 

1.6 Blower casing end blower inlet measure with bolt

loose. Scatting with back of diffuser at lease to 80%(This

is only in case when we apply a new diffuser) 0.005-

0.020” Long CI (Gap) 

1.7 Turbine disc and intermediate casing 0.008-0.016”Long CI

1.8 Bearing and thrust collar (Blower end) with surface

by approx 0.003 less when oil. 0.007-0.018” Thrust CI 

1.9 Inducer and blower casing 0.091-0.101”Dia CI 

1.10 Thurst collar and oil seal Blower End 0.014-

0.036”Dia CI 

1.11 Interference between bearing and intermediate

casing (blower & Turbine end ) 0.0005-0.0015” DiaCl 

1.12 Rotor shaft and oil seal (turbine end) 0.006-0.008”

Dia CI

1.13 Gas inlet casing and intermediate casing insidemeasurement 0.090-0.098” Dia CI 

1.14 Impeller and intermediate casing 0.125-0.127” Dia

CI

1.15 Max allowable clearance between Gas inlet casing

& Nozzle ring 0.005” clearance 

Page 27: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 27/104

Page 27 of 104 Quality Audit of Diesel Loco POH Workshop

2

 Availability of tools, Test Stands etc.

AlcoAlco 720 Instruction

Manual

ALCO

2.1 Balancing machine

2.2 Zyglo machine

2.3 Casing hydraulic test stand

2.4 Oil gallery flushing test stand

2.5 Bearing puller (CE & TE)

2.6 Sand blast machine for rotor cleaning2.7 Torque wrench up to 250 psi

2.8 micrometer 2”-3” & 0-4” 

2.9 Go-NoGo gauge for checking fix nozzle ring

3

 Availability of instructions etc .

3.1 Display Chart

3.2 Training of staff 

3.3 Maintenance manual and check sheets

3.4 Record keeping of tools and measuring instruments

4 Record Keeping For Traceability 

5

Material Availability 

5.1 Vital Spares

5.2 Must change items

Page 28: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 28/104

Page 28 of 104 Quality Audit of Diesel Loco POH Workshop

CHECK SHEET FOR

TECHNICAL AUDIT OF ENGINE BLOCK, MAIN BEARING (POH)

During the audit, activities should be checked with regard to the Clause/Para/Item/chapter of the reference document as per applicability. Wherever the

activities are not performed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded.

Workshop/Rly: Audited by: Date of audit:

SN Requirements LocoType

Make/classOf 

Subassembly

ReferenceDetails

Clause/Para/Item/Chapter Details

Observations

1 Removal of Cyl Block

a)  Removal of Cylinder liner.

b)  Removal of cylinder liner sleeve.

Alco

Conventional

ALCO MI

11079 D

Chapter on Maintenance,

Instruction of Cylinder Block

.

2 Maintenance and Inspection

DPT for cracks/signs of leaks/ other

damage,

2.1 Check sizes of Main Brg. Bore.

a)  New MB bore dia. 9.0355" -9.0370"

b)  Worn MB bore dia. 9.0350" -

9.0385"

c)  Cyl. Liner bore.

2.2 a)Out of roundness checking at planes

A,B,C,D, E & F (max. 0.0035”). 

b) Check taper

i)  At vertical planes A and D (0.001”). 

ii)  At 45° from vertical between

planes B & F and C & E (0.003”).

a)  Horizontal misalignment limit – (i)  Two adjacent bores – 0.002” 

(ii)  Two non-adjacent bores 0.004” 

b)  Vertical misalignment limit – 

(i)  Three adjacent bores-0.0015” 

(ii)  Two non-adjacent bores-

0.003”. 

Page 29: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 29/104

Page 29 of 104 Quality Audit of Diesel Loco POH Workshop

Torque values for Cylinder head stud 100-

120 ft pound.

4.

Availability of tools and test

a)  Plate, lifting

b)  Compound, gasket

c)  Turning plate, free end & gen. end.

d)  Fixture for checking distortion of Cyl,

block and cyl. liner to Cyl. block seat

e)  Sleeve tool, upper and lower.f)  Mandrel

g)  Magnaflux

h)  Feeler gauge

i)  Vernier caliper

 j)  Torque wrench

5.

Availability of instruction

a)  Display chart.

b)  Training of staff 

c)  Maintenance manual and check

sheets.

d)  Record keeping of tools andmeasuring instruments.

6.Record keeping traceability

.

7.

Material availability

(i). Vital spares.

(ii). Must change item

Page 30: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 30/104

Page 30 of 104 Quality Audit of Diesel Loco POH Workshop

TECHNICAL AUDIT OF CRANK SHAFT (POH)

During the audit, activities should be checked with regard to the Clause/Para/Item/chapter of the reference document as per applicability. Wherever the

activities are not performed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded.

Workshop/Rly: Audited by: Date of audit:

SN Requirements Loco

Type

Make/class

Of 

Subassembly

Reference

Details

Clause/Para/

Item/Chapter Details

Observations

1 Removal of Crank Shaft

a)  Removal of Oil

catcher/pipes/engine parts/main

brgs caps/shells & split gears.

b)  Checked Crank shaft thrust

(i) Using Main brg shell 0.010”-

0.017” 

(ii) Using Thrust collar 0.012”-

0.021” 

c)  Apply grease and wrap journals

and crankpins. Alco

Conventional

ALCO MI

11069 E

Chapter on Maintenance,

Instruction of Cylinder Block.2 Maintenance and Inspection

a)  Cleaning

b)  Magnaflux test for

cracks/other damage,

c)  Roughness and burrs (limit 25

RMS max).

d)  Check M/Brgs saddle bore

2.1 Check Crank shaft.

a) MB Journal dia. 8.498" – 8.500"

b) Out of roundness limit 0.002” 

c) Run out for 16 cyl-0.008” max 

d) MB Journal eccentricity limit

0.001”

d) Crank pin dia 5.998”- 6.000” 

e) Crank pin out of roundness limit

0.002” 

Page 31: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 31/104

Page 31 of 104 Quality Audit of Diesel Loco POH Workshop

2.2 Split Gear

a) Removal of gears.

b) Inspect gear teeth (ALCo MI 11030).

2.3 Check Split gear

a) Key Interference fit- 0.0000”-0.0005” 

b) Gear side clearance-0.007”-0.023” 

c) Split line clearance limit- 0.0015” 

d) Torque for gear cap screw in ft-lbs – 

i) Preliminary torque- 50 ft-lbsii) Final torque – 300 ft-lbs.

ALCO MI

11067 C

ALCO MI

11069 E &

11067C4.

Availability of tools and test

a)  Lifting block

b)  Lapping tool

c)  Deflection guage.

d)  Feeler gauge

e)  Soft hammer

f)  Torque wrench

5.

Availability of instruction

a)  Display chart.

b)  Training of staff c)  Maintenance manual and

check sheets.

d)  Record keeping of tools and

measuring instruments.

6. Record keeping traceability.

7.

Material availability

(i). Vital spares.

(ii). Must change item

Page 32: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 32/104

Page 32 of 104 Quality Audit of Diesel Loco POH Workshop

CHECK SHEET FOR

TECHNICAL AUDIT OF CYLINDER HEAD SECTION (POH)

During the audit, activities should be checked with regard to the Clause/Para/Item/chapter of the reference document as per applicability. Wherever the

activities are not performed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded.

Workshop/Rly: Audited by: Date of audit:

SN Requirements LocoType

Make Of Subassembly

Reference Details Clause/Para/Item/chapter Details

Observations

1

Cleaning, measurements etc.

1.1 Cleaning of cylinder head

ALCo --

DLW

Maintenance

Instruction

Manual

Chapter on cylinder

head

1.2 Cy head leak test at 70 PSI with hot water

1.3 Inspect head for cracks using Magnaflux

1.4 Valve guide to head int 0.002” -0.0005” 

1.5 yoke to guide int 0.002” -0.0005” 

1.6 Yoke guide ( press in dim) 3.210” -3.272” 

1.7 Valve guide ( press in dim) 2.25” 

1.8 Valve to guide cl 0.003 – 0.0045” 

1.9 Cy head nuts torquing value 550ft/lbs

2

 Availability of tools , Test Stands etc.

2.1 Valve seat reconditioning machine

2.2 Hydraulic test stand

2.3 Nozzle hole sleeve tube expander(Bottom & Top)

2.4 Nozzle sleeve extractor

2.5 Nozzle sleeve holder

2.6 Feeler gauge

2.7 Magna flux

3

 Availability of instructions etc.

3.1 Display Chart3.2 Training of staff 

3.3 Maintenance manual and check sheets

3.4 Record keeping of tools and measuring instruments

4 Record Keeping For Traceability 

5Material Availability 

5.1 Vital Spares

5.2 Must change items

Page 33: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 33/104

Page 33 of 104 Quality Audit of Diesel Loco POH Workshop

CHECK SHEET FOR

TECHNICAL AUDIT OF PISTON SECTION (POH)

During the audit, activities should be checked with regard to the Clause/Para/Item/chapter of the reference document as per applicability. Wherever the

activities are not performed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded.

Workshop/Rly: Audited by: Date of audit:

SN Requirements LocoType

Make Of Subassembly

Reference Details Clause/Para/Item/chapter Details

Observations

1

Cleaning, inspection, measurements etc.

1.1 cleaning of piston

ALCo--

DLW

Maintenance

Instruction

Manual

Chapter on piston and

con rod

1.2 Inspect visually piston skirt and body for scoring or

scuffing

1.3 Inspect piston crack using Magnaflux

1.4 Zyglo test for checking surface crack

1.5 (a) Groove width top ring, 2nd

ring and 3rd

ring

0.1902”- 0.1950”(conventional) 

(b) Groove width top ring & 2nd

 ring 0.1900”-0.195”(3RV) 

1.6 (a) Side clearance in above rings 0.0052” -0.012”

(conventional)

(b) Side clearance in above rings 0.0054” -0.012”

(3RV)

1.7 (a) Groove width of oil scraper ring 0.3140” – 

0.3165” (conventional) 

(b)Groove width of oil scraper ring 0.2377” – 0.0.241”

(3RV)

1.8 (a) Side clearance in oil ring 0.002”- 0.006”

(conventional)

(b) Side clearance in oil ring 0.002”- 0.0064” (3RV) 

1.9 Piston pin to bushing clearance running 0.003” – 

0.0075” 

1.10 Piston pin to snap ring total clearance 0.076” – 

0.118” 

Page 34: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 34/104

Page 34 of 104 Quality Audit of Diesel Loco POH Workshop

2.

 Availability of tools , Test Stands etc.

2.1 Feeler gauge

2.2 Zyglo testing machine

2.3 Magna flux

2.4 Vernier caliper

2.6 Piston ring groove gauge

3

 Availability of instructions etc3.1 Display Chart

3.2 Training of staff 

3.3 Maintenance manual and check sheets

3.4 Record keeping of tools and measuring instruments

4 Record Keeping For Traceability 

5

Material Availability 

5.1 Vital Spares

5.2 Must change items

Page 35: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 35/104

Page 35 of 104 Quality Audit of Diesel Loco POH Workshop

CHECK SHEET FOR

QUALITY AUDIT OF AIR & EXHAUST VALVE MAINTENANCE (POH)

During the audit, activities should be checked with regard to the Clause/Para/Item/chapter of the reference documents. Wherever the activities are not

performed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded:

Workshop/Rly: Audited by: Date of audit:

SN Requirements Loco Type Make of 

Subassembly

Reference

Details

Clause/Para/

Item details

Observations

1

Measurements etc:

Alco--

Alco Instruction

Manual (MI-

11020G)

Chapter on

Cylinder

Heads

1.1 Stem dia. of valves 0.6205-0.6195 (New).

1.2 Groove fillet radii 0.025-0.031R.

1.3 Valve disk thickness: for C and F type valve

of 450:

(a) 0.1562” (new) and (b) 0.0625”

(condemning Limit).

1.4 Valve disk thickness (for E type valve 300)

0.1750” (new). And, 0.0937” (condemning

Limit).

2

 Availability of tools, test stands etc:

2.1 Depressor, Spring etc

2.2 Grinder

3

 Availability of instructions etc:

3.1 Display Chart etc.

3.2 Training of Staff 

3.3 Record keeping of tools and measuring

instruments

4 Record keeping for traceability:

5

Material Availability:

5.1 Vital Spare

5.2 Must change items

Page 36: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 36/104

Page 36 of 104 Quality Audit of Diesel Loco POH Workshop

CHECK SHEET FOR

TECHNICAL AUDIT OF RADIATOR SECTION (POH)

During the audit, activities should be checked with regard to the Clause/Para/Item/chapter of the reference document as per applicability. Wherever the

activities are not performed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded.

Workshop/Rly: Audited by: Date of audit:

SN Requirements Loco

Type

Make/class

Of 

Subassembly

Reference

Details

Clause/Para/

Item/Chapter Details

Observations

1 Leakage testing

AlcoConventional

Alco MI

Chapter on Maintenance,

Radiators.

2 Reconditioning of Radiator Chapter on LOCOMOTIVE

INSPECTION,

MAINTENANCE AND

LUBRICATION 

MI 17003 A

2.1 Dismantling2.2 Cleaning of the core

2.3 Changing of gaskets

2.4 Assembly

2.5 Testing

Chapter on Maintenance,Radiators.

3 Cleaning etc

Alco ConventionalAlco MI

Chapter on Maintenance,

Radiators.

3.1 cleaning details

4

 Availability of tools, Test Stands etc.

4.1 Torque wrench up to 140 ft-lb.

4.2 Hydraulic testing machine 0-10 Kg/Cm2

4.3 Radiator stand4.4 Fin combing tool

4.5 Radiator immersion tank for cleaning

Page 37: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 37/104

Page 37 of 104 Quality Audit of Diesel Loco POH Workshop

5

 Availability of instructions etc.

5.1 Display board etc

5.2 Training of staff 

5.3 maintenance manual and check sheets

5.4 Calibration facility for tools and measuring

instruments

6 Record Keeping for Traceability 

7.

Material Availability:

5.1 Vital spares

5.2 Must change Item

Page 38: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 38/104

Page 38 of 104 Quality Audit of Diesel Loco POH Workshop

CHECK SHEET FOR

QUALITY AUDIT OF FUEL INJECTION PUMP (POH)

During the audit, activities should be checked with regard to the clause/Para/Item of the reference document. Wherever the activities are not performed

correctly, the method adopted should be indicated or the nature of non-compliance should be recorded.

Workshop/Rly: Audited by: Date of audit:

SN Requirements Loco type Make of 

subassembly

Reference

details

Clause/Para/Item details Observation

1. Dis-assembly /Measurement/Assembly etc

Alco Bosch 17 mm Bosch repair

and testing

manual

Para on Dis-assembly

Para on Inspection of parts

Para on Inspection of parts

Para on Inspection of parts

Para on Inspection of parts

Para on assembly

Para on Calibration values

1.1  Dis-assembly

1.2  Inspection of parts

1.3  Replace plunger guide cup if the indentation

on the Plunger and tappet seating surface is

more than 0.125 mm (0.005”) 

1.4  Clearance between control rack and bushing

within 0.5 mm (0.020”) 

1.5  Control rack movement – within 0.38 mm

(0.015”).

1.6  Range control bush dia – 18.25 mm (0.7185”)

 – 18.27 mm (0.7192”) 

1.7  BDC Dimension ‘a’ – 6.5 ± 0.05 mm.

2.  Availability of Tools ,Test Stands etc.

1.1  Depth gauge for checking of BDC dimension

‘a’ on test bench. 

1.2  Nut torque wrench, 450 lbs – 500 lbs.

1.3  Bush reamer.

1.4  Micrometer, 16 – 20 mm.

1.5  Assembly and dis-assembly fixture

1.6  Pump calibration test stand

1.7  Calibration oil – Servo Calib-5

Page 39: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 39/104

Page 39 of 104 Quality Audit of Diesel Loco POH Workshop

3.  Availability of instructions etc.

3.1 Display of charts etc

3.2 Training of staff.

3.3 Maintenance manual and check sheet etc

3.4 Record keeping of tools and measuring

instruments.

4. Record keeping for traceability: 5. Material availability :

5.1 Vital Spares

5.2 Must change items

Page 40: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 40/104

Page 40 of 104 Quality Audit of Diesel Loco POH Workshop

CHECK SHEET FOR

QUALITY AUDIT OF INJECTOR (POH)

During the audit, activities should be checked with regard to the clause/Para/Item of the reference document. Wherever the activities are not performed

correctly, the method adopted should be indicated or the nature of non-compliance should be recorded.

Workshop/Rly: Audited by: Date of audit:

SN Requirements Locotype Make/Class/Name

of 

subassembly

Referencedetails Clause/Para/Item details Observations

1. Dis-assembly /Measurement/Assembly etc:

Alco Bosch 17 mm Bosch repair

and testing

manual

Para on Dis-assembly

Para on Inspection of Parts

Para on Inspection of Parts

Para on Assembly

Para on Assembly

Para on Assembly

1.1 Dis-assembly

1.2 Inspection of parts

1.3 Replace Intermediate disc if found cracked or

if indentation at the nozzle seating end exceeds

0.125 mm.

1.4 Opening pressure – 3700 to 3800 psi ( 260-270

kgf/cm

2

) for Overhauled nozzle1.5 Nozzle cap nut tightening torque 130-150 Nm

(13-15 kgf.m or 94-109 lbs-ft)

1.6 Repetition (chatter) and spray pattern test

2.  Availability of Tools, Test Stands etc:

List on Service Tools for

Injector

2.1 Nozzle needle lift gauge

2.2 Feeler gauge

2.3 Dial gauge

2.4 Nozzle cleaning sleeve

2.5 True running gauge

2.6 Nozzle tester

2.7 Fixture for injector2.8 Socket wrench

2.9 Test oil

Page 41: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 41/104

Page 41 of 104 Quality Audit of Diesel Loco POH Workshop

3.  Availability of instructions etc:

3.1 Display of chart

3.2 Training of staff 

3.3 Maintenance manual and check sheet

3.4 Record keeping of tools and measuring

instruments

4. Record keeping for traceability: 5. Material availability:

5.1 Vital spares

5.2 Must change items

Page 42: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 42/104

Page 42 of 104 Quality Audit of Diesel Loco POH Workshop

CHECK SHEET FOR

TECHNICAL AUDIT OF PTLOC SECTION (POH)

During the audit, activities should be checked with regard to the Clause/Para/Item/chapter of the reference document as per applicability. Wherever the

activities are not performed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded.

Workshop/Rly: Audited by: Date of audit:

SN Requirements Loco

Type

Make Of 

Subassembly

Reference Details Clause/Para/Ite

m/chapter

Details

Observations

1

Dis-assembly /Measurement/Assembly/Test etc.

1.1 Overhauling procedure

1.2 Plate Pack Length

1.3 Hydraulic Test

Plate Type Lube

Oil Cooler

(PTLOC)

MPMI-24, Nov. 2004

& MP.IB.ES.01.07.08

DLW Drawing No.

TPL-8515, DLW Part

No. 11457260

Para on

Overhaul

procedure

Outline – Lube

Oil Cooler

2 Availability of tools , Test Stands etc.2.1 Ratchet spanner

3

 Availability of instructions etc.

3.1 Display Chart

3.2 Training of staff 

3.3 Maintenance manual and check sheets

3.4 Record keeping of tools and measuring instruments

4 Record Keeping For Traceability 

5

Material Availability 

5.1 Vital Spares

5.2 Must change items

Page 43: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 43/104

Page 43 of 104 Quality Audit of Diesel Loco POH Workshop

Annexure-5

CHECK SHEET FOR

TECHNICAL AUDIT OF POH WORKSHOP

Item: Electrical control MBCS + MCBG + E type

During the audit, activities should be checked with regard to the Clause/Para/Item of the reference document as per applicability. Wherever theactivities are not performed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded.

Workshop/Rly:  Audited by: Date of audit:

SN Requirements LocoType

Make Of Sub

assembly

Reference Details Clause/Para/Item Details

Observation

1. No. of Trained personnel withexperience

MBCS trained personnel

2. Record keeping practices after thetests in relay control room for E typecontrol

Shed doc

3. Practices for Handling of the electronic

cards and storing

 ALCo Doc No:IM 53 for MBCS

Medha4. Availability of crimping tool & connector 

pin details ALCo Doc No. :IM 53 for MBCS

Medha

5. Maintenance practices of MicroProcessor Based Control System MEP660

DLW/Alco/AMC (micro)/01

6. Maintenance practices of MicroController Based Governor (MCBG)MEG 601

 ALCo Doc No:IM-11 Rev. 0.0Date Jan 2009 of Medha

7. Practices followed for Fault dataanalysis for identifying the faulty

components and failure.

 ALCoContract agreement no.DLW/ALCO/MCBG/Medha

8. Standard (OEM recommended) list of spares, consumable & tools ALCo 

Contract agreement no.DLW/ALCO/MCBG/Medha

9. Measurement 

11.1 Standards for load box examination of D E locomotives

MP MI -10 (Rev.0.02) August, 2003

11.2 Practices as per BHEL CommissioningTest schedule (Electrical equipment)

BHEL docs: TNE -2/2105/97/DELCTS Date

Page 44: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 44/104

Page 44 of 104 Quality Audit of Diesel Loco POH Workshop

for 3100/2750 HP BG DE loco for ‘E’type control

Sept 1997

11.3 Test procedure for MBCS loco controlsystem MEP660 for retrofitted D E loco

 ALCo IM-59

11.4 Preventive maintenance schedule DLW/Alco/AMC (micro)/01Inspection and test report of MPreventive Maintenance schedSF-1405 (0)

11.5 Check working of safety and critical

items identified asECS operation check, GR operationcheck, Eng. Stop button check, OSTopen check, MUSD stop switch check,LWS check, GFOLR operation check(E type), Governor dry run check,Flasher light lights, Alerter, lamp, alarmand reset, Flasher lights switch panelGR, GRCO1/2, Indication panels,

 Attendant call bell, Head light,Classification light, Horn, Sanders ,Directional check, Cab light andexterior lights,

 ALCo Schedule inspection of shed

and items covered under DLW/Alco/AMC (micro)/01 for MBCS locos

11.6 Check set value of engine rpm,transition speed, LOPS, Engine water Temp., 1st notch current, DBparameters (field and armaturecurrent), loco over speed through user settable parameters,

User settable parameters asper RDSO MBCSspec.MP.0.2400.26

11.7 Check ground circuit leakage current -do-

11.8 Check mv drop test of WSR (E type)

12 Availability Of Tools And Test Stands For MBCS locos- Test standsare not provided by MBCS

supplier. Items are coveredunder AMC.

13 Display Chart Important instruction for trouble shooting like action tobe taken during wheel slip etcto be available on the cab

13.1 Display of DOS and DONTS,TROUBLE SHOOTING Chart,

 As per OEM manual

Page 45: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 45/104

Page 45 of 104 Quality Audit of Diesel Loco POH Workshop

DISPLAYCHART & FLOW CHART

14 Maintenance manual and check sheets As provided by the MBCSmanufacturer*

15 Instruction Bulletin / Modification sheet/Hand book/ Trouble shooting charts asprovided by RDSO/ CAMTECH andimplementation by MBCS vendor 

MBCS spec.MP.0.2400.26,Modification sheetNo.MP.MOD.EC.05.27.10(Rev. 00) Date 26.03.2010,Instruction Bulletinno.MP.IB.EC.04.21.10 Date

30.04.2010.CAMTECH/2010/M/MPBCS/1.0 March 2010 (IntroductionHand book on MBCS MP660fitted on diesel locomotives).CAMTECH/2000/DSL/1.0(Trouble shooting charts for drivers of WDM2 locomotive)

Medha 

1. Operational manual for drivers Doc.No.IM-38 Rev 3.0 July 072. Maintenance Instruction manual Doc. No.IM-53 Rev 0.0 Sept’2008 

3. System Manual Doc. No. IM-08 Rev.3.0 March 20084. Troubleshooting Manual Doc.No. IM-51 Rev.2.0 Oct.20085. WDG3A Control wiring Drg. no.ED 10356. WDG3A Power. ED 10377. WDG3A Schematics Drg. no.ED Wiring Drg. no 10348. WDG3A TB wiring Drg. no.ED 10369. WDM3D Control wiring Drg. no.ED 103110. WDM3D Power Wiring Drg. no.ED 103311. WDM3D Schematics Drg. no.ED 103012. WDM3D TB wiring Drg. no.ED 1032 

Siemens 

1. KM DIREKT scheme no. DRG. No. 3FZE-009612. SIM CONTROL scheme no. DRG. No. 4SIM-200509

3. SIMCONTROL Operator’s Instructions &Guidelines user manual ver.2.00 dated 10.12.09 

4. Trouble shooting manual of Siemens WDG3A and fault category of Siemens

Page 46: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 46/104

Page 46 of 104 Quality Audit of Diesel Loco POH Workshop

CHECK SHEET FOR

TECHNICAL AUDIT OF CONTROL GEAR SECTION FOR GENERATOR FIELD CONTACTOR (ALCo)

During the audit, activities should be checked with regard to the Clause/Para/Item of the reference document as per applicability. Wherever the activities are notperformed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded.

Workshop/Rly: Audited by: Date of audit:

SN Requirements LocoType

Make Of Subassembly

ReferenceDetails

Clause/Para/ItemDetails

Observations

1. Measurement 

1.1  Control voltage 72+1 VDC All DieselElectricLocomotives(ALCo)

Drawing No.EL/PT/0640/

Altr R3Part

No 12145439

Technical detailsgiven in the

drawing

1.2  Max pick up volt 48v ,1.3  Main contact gap12-14.5mm,

1.4  Wipe 8-10 mm,

1.5  Contact pressure( kgf) initial 1.82-2.95,final 5.45-7.25,

1.6  Operating coil resistance at 20 deg c 104 -116ohm, (approx.),

1.7  Interlock (gpr type : 9-41n, 3no+3nc)1.8  Contact gap 9.5-10.5 mm,

1.9  Interlock contact pressure 220-300g.

1.10  Contact impression (should be min 80%) Spec No.MP.0.04.00.08

(Rev-01),May’10 

3.10.e

1.11  IR Value between(i)  Main contacts(ii)  Coil and magnet frame(iii)  Interlocks and coil shorted together and earth.

IEC60571

as per clause10.2.9

Page 47: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 47/104

Page 47 of 104 Quality Audit of Diesel Loco POH Workshop

SN Requirements LocoType

Make Of Subassembly

ReferenceDetails

Clause/Para/ItemDetails

Observations

(iv)  Contacts of interlocks(v)  Interlocks and coil shorted together and main

contacts shorted together (vi)  shorted main contacts and shorted interlocks, coil

and earth2.0  Availability of tools and stands

2.1  Multimeter with proper calibration2.2  Vernier calipers with valid calibration

2.3  Go- No gauge suiting to different cantactors

2.4  Dial gauge of different scale and resolution assuited to respective contactor  

2.5  Source which can provide minimum current atrespective voltage (24 V – 72 V DC)

2.6  Variac

2.7  Meggar 

2.8  Oscilloscope

2.9  Screw Driver, Plier, Spanner Set, etc.

3. Availabili ty Of Instructions etc.3.1  Display Chart

3.2  Flow Chart3.3  Training of staff 

3.4  Proper Display of Do’s and Don’t 3.5  Maintenance manual and check sheets3.6  Record keeping of tools and measuring

instruments

3.7  Instruction Bulletin issued by RDSO3.8  Maintenance Manual of Manufacturer 

3.9  Specification4. Compliance of Instruction Bulletin

5. Follow of Maintenance Manual of Manufacturer 6 Record Keeping For Traceability

4.1  Proper Register is maintained for Contactors withdetails of Manufacturer’s Brand Name, Date of 

Page 48: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 48/104

Page 48 of 104 Quality Audit of Diesel Loco POH Workshop

SN Requirements LocoType

Make Of Subassembly

ReferenceDetails

Clause/Para/ItemDetails

Observations

Manufacture, Type, Sl. No., Date of Attending,Repair/Overhauling activity details, Loco No. towhich fitted.

4.2  Proper record should be maintained for eachcontactor with the measurement of Parameters as

in Sl. No.1 prior to Fitment to Loco after overhauling/maintenance with date and remarks, if any.

7. Material Availability

7.1  Vital Spares

7.2  Must change items

7.3  Consumables8. Disposal

8.1  Segregation of Workable and Non-Workable equipments and proper house keeping

8.2  Proper Disposal of Materials including recyclingfollowing relevant environmental norms

Page 49: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 49/104

Page 49 of 104 Quality Audit of Diesel Loco POH Workshop

CHECK SHEET FOR

TECHNICAL AUDIT OF CONTROL GEAR SECTION FOR CRANKING CONTACTOR (ALCo)

During the audit, activities should be checked with regard to the Clause/Para/Item of the reference document as per applicability. Wherever the activities are notperformed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded.

Workshop/Rly: Audited by: Date of audit:

SN Requirements LocoType

Make Of Subassembly

ReferenceDetails

Clause/Para/ItemDetails

Observations

1. Measurement 

1.1  Short time control voltage -72+1v dc, All DieselElectricLocomotives(ALCo)

Drawing No.EL/PT/0641/

Altr R3Part

No 121410510

Technical detailsgiven in the

drawing

1.2  Control voltage -24vdc,1.3  Max pick up volt 24v

1.4  Main contact gap12-14.5 mm,

1.5  Wipe 8-10 mm,,1.6  Contact pressure( kgf) initial 1.82-2.95, final 5.45-

7.25,1.7  Operating coil resistance at 20 deg c 18.5-

20.5ohm,1.8  Interlock (gpr type : 9-41n, 3no+3nc)

1.9  Contact gap 9.5-10.5 mm,1.10  Interlock contact pressure 220-300 gm ,1.11  .)

1.12  Contact impression (should be min 80%) Spec No.MP.0.04.00.08

(Rev-01),May’10 

3.10.e

Page 50: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 50/104

Page 50 of 104 Quality Audit of Diesel Loco POH Workshop

1.13  IR Value between(i)  mMain contacts(ii)  Coil and magnet frame(iii)  Interlocks and coil shorted together and earth.(iv)  Contacts of interlocks(v)  Interlocks and coil shorted together and main

contacts shorted together (vi)  Shorted main contacts and shorted interlocks, coiland earth

as per IEC60571

clause 10.2.9

2.0  Availability of tools and stands2.10  Multimeter with proper calibration

2.11  Vernier calipers with valid calibration2.12  Go- No gauge suiting to different contactors

2.13  Dial gauge of different scale and resolution assuited to respective contactor  

2.14  Source which can provide minimum current atrespective voltage (24 V – 72 V DC)

2.15  Variac

2.16  Megger 

2.17  Oscilloscope

2.18  Screw Driver, Plier, Spanner Set, etc.

3. Availabili ty Of Instructions etc.3.10  Display Chart

3.11  Flow Chart3.12  Training of staff 

3.13  Proper Display of Do’s and Don’t 

3.14  Maintenance manual and check sheets3.15  Record keeping of tools and measuring

instruments

3.16  Instruction Bulletin issued by RDSO3.17  Maintenance Manual of Manufacturer 

3.18  Specification

Page 51: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 51/104

Page 51 of 104 Quality Audit of Diesel Loco POH Workshop

4. Compliance of Instruction Bulletin

5. Follow of Maintenance Manual of Manufacturer 6 Record Keeping For Traceability

4.3  Proper Register is maintained for Contactors withdetails of Manufacturer’s Brand Name, Date of Manufacture, Type, Sl. No., Date of Attending,

Repair/Overhauling activity details, Loco No. towhich fitted.

4.4  Proper record should be maintained for eachcontactor with the measurement of Parameters asin Sl. No.1 prior to Fitment to Loco after overhauling/maintenance with date and remarks, if any.

7. Material Availability

7.4  Vital Spares7.5  Must change items

7.6  Consumables8. Disposal

8.3  Segregation of Workable and Non-Workable equipments and proper house keeping

8.4  Proper Disposal of Materials including recyclingfollowing relevant environmental norms

Page 52: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 52/104

Page 52 of 104 Quality Audit of Diesel Loco POH Workshop

CHECK SHEET FOR

TECHNICAL AUDIT OF CONTROL GEAR SECTION FOR CRANKING CONTROL CONTACTOR (ALCo)

During the audit, activities should be checked with regard to the Clause/Para/Item of the reference document as per applicability. Wherever the activities are notperformed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded.

Workshop/Rly: Audited by: Date of audit:

SN Requirements LocoType

Make Of Subassembly

ReferenceDetails

Clause/Para/ItemDetails

Observations

1. Measurement 

1.1  Short time control voltage 72+1 v dc, All DieselElectricLocomotives(ALCo)

Drawing No.EL/PT/0639/

Altr R3Part

No 12141100

Technical detailsgiven in the

drawing

1.2  Control voltage 24vdc,1.3  Max pick up volt 24 v

1.4  Main contact gap 6-7.5mm,1.5  Wipe 0.8-1.6 mm,1.6  Contact pressure(gmf) initial 80-150, final 180.-

280,1.7  Operating coil resistance at 20 deg c 55+5%

ohm(52 to 58 ohms),

1.8  Contact impression (should be min 80%) Spec No.MP.0.04.00.08

(Rev-01),May’10 

3.10.e

1.9  IR Value between(i)  fixed contact to movable Contacts(ii)  coil to frame

IEC 60571 clause 10.2.9

Page 53: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 53/104

Page 53 of 104 Quality Audit of Diesel Loco POH Workshop

2.0  Availability of tools and stands

2.19  Multimeter with proper calibration

2.20  Vernier calipers with valid calibration

2.21  Go- No gauge suiting to different contactors

2.22  Dial gauge of different scale and resolution assuited to respective contactor  

2.23  Source which can provide minimum current atrespective voltage (24 V – 72 V DC)

2.24  Variac

2.25  Megger 

2.26  Oscilloscope

2.27  Screw Driver, Plier, Spanner Set, etc.

3. Availabili ty Of Instructions etc.

3.19  Display Chart3.20  Flow Chart

3.21  Training of staff 

3.22  Proper Display of Do’s and Don’t 

3.23  Maintenance manual and check sheets

3.24  Record keeping of tools and measuringinstruments

3.25  Instruction Bulletin issued by RDSO

3.26  Maintenance Manual of Manufacturer 

3.27  Specification4. Compliance of Instruction Bulletin

5. Follow of Maintenance Manual of Manufacturer 

Page 54: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 54/104

Page 54 of 104 Quality Audit of Diesel Loco POH Workshop

6 Record Keeping For Traceability

4.5  Proper Register is maintained for Contactors withdetails of Manufacturer’s Brand Name, Date of Manufacture, Type, Sl. No., Date of Attending,Repair/Overhauling activity details, Loco No. towhich fitted.

4.6  Proper record should be maintained for eachcontactor with the measurement of Parameters asin Sl. No.1 prior to Fitment to Loco after overhauling/maintenance with date and remarks, if any.

7. Material Availability

7.7  Vital Spares7.8  Must change items

7.9  Consumables8. Disposal

8.5  Segregation of Workable and Non-Workable equipments and proper house keeping

8.6  Proper Disposal of Materials including recyclingfollowing relevant environmental norms

CHECK SHEET FOR

Page 55: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 55/104

Page 55 of 104 Quality Audit of Diesel Loco POH Workshop

CHECK SHEET FOR

TECHNICAL AUDIT OF CONTROL GEAR SECTION FOR FUEL PUMP CONTACTORS (ALCo LOCO)

During the audit, activities should be checked with regard to the Clause/Para/Item of the reference document as per applicability. Wherever the activities are notperformed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded.

Workshop/Rly: Audited by: Date of audit:

SN Requirements LocoType

Make Of Subassembly

ReferenceDetails

Clause/Para/ItemDetails

Observations

1. Measurement 

1.1  Max pick up volt 48v All DieselElectricLocomotives(ALCo)

Drawing No.EL/PT/0629/

Altr R3Part

No 12141033

Technical detailsgiven in the

drawing1.2  Main contact gap 11-13 mm,1.3  Wipe 3.5-4.7mm,

1.4  contact pressure( kgf) initial 0.68-0.9kgf, final 0.9-1.4kgf.,

1.5  operating coil resistance at 20 deg c 169-195 ohm ,

1.6  Contact impression (should be min 80%) Spec No.

MP.0.04.00.08

(Rev-

01),May’10 

3.10.e

1.7  IR Value as per clause 10.2.9 of IEC60571 between

(i)Main contacts of contactor 

(ii) Coil and magnet frame

IEC60571

as per clause10.2.9 

2.0  Availability of tools and stands2.28  Multimeter with proper calibration

2.29  Vernier calipers with valid calibration2.30  Go- No gauge suiting to different cantactors

SN R i t L M k Of R f Cl /P /It Ob ti

Page 56: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 56/104

Page 56 of 104 Quality Audit of Diesel Loco POH Workshop

SN Requirements LocoType

Make Of Subassembly

ReferenceDetails

Clause/Para/ItemDetails

Observations

2.31  Dial gauge of different scale and resolution assuited to respective contactor  

2.32  Source which can provide minimum current atrespective voltage (24 V – 72 V DC)

2.33  Variac

2.34  Meggar 

2.35  Oscilloscope

2.36  Screw Driver, Plier, Spanner Set, etc.

3. Availabili ty Of Instructions etc.

3.28  Display Chart3.29  Flow Chart

3.30  Training of staff 3.31  Proper Display of Do’s and Don’t 

3.32  Maintenance manual and check sheets3.33  Record keeping of tools and measuring

instruments3.34  Instruction Bulletin issued by RDSO

3.35  Maintenance Manual of Manufacturer 3.36  Specification

4. Compliance of Instruction Bulletin5. Follow of Maintenance Manual of Manufacturer 

6 Record Keeping For Traceability4.7  Proper Register is maintained for Contactors with

details of Manufacturer’s Brand Name, Date of Manufacture, Type, Sl. No., Date of Attending,Repair/Overhauling activity details, Loco No. to

which fitted.

4.8  Proper record should be maintained for eachcontactor with the measurement of Parameters asin Sl. No.1 prior to Fitment to Loco after overhauling/maintenance with date and remarks, if any.

SN Requirements Loco Make Of Reference Clause/Para/Item Observations

Page 57: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 57/104

Page 57 of 104 Quality Audit of Diesel Loco POH Workshop

SN Requirements LocoType

Make Of Subassembly

ReferenceDetails

Clause/Para/ItemDetails

Observations

7. Material Availability7.10  Vital Spares

7.11  Must change items7.12  Consumables

8. Disposal8.7  Segregation of Workable and Non-

Workable equipments and proper house keeping8.8  Proper Disposal of Materials including recycling

following relevant environmental norms

CHECK SHEET FOR

Page 58: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 58/104

Page 58 of 104 Quality Audit of Diesel Loco POH Workshop

CHECK SHEET FOR

TECHNICAL AUDIT OF CONTROL GEAR SECTION FOR RADIATOR FAN CONTACTOR (ALCo)

During the audit, activities should be checked with regard to the Clause/Para/Item of the reference document as per applicability. Wherever the activities are notperformed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded.

Workshop/Rly: Audited by: Date of audit:

SN Requirements LocoType

Make Of Subassembly

ReferenceDetails

Clause/Para/ItemDetails

Observations

1. Measurement 

1.1  control voltage 72+1v dc,1.2  Max pick up volt 48 v

 All DieselElectricLocomotives(ALCo)

Radiator Fancontactor 

Drawing No.EL/PT/0638/

Altr R3Part

No 12140235

Technical detailsgiven in the

drawing

1.3  Main contact gap 6-7.5mm, Drawing No.EL/PT/0638/Par 

t1.4  Wipe 0.8-1.6 mm, No 12140235

1.5  Contact pressure( gmf) initial 80-150, final 180.-280,

Altr R3 

1.6  Operating coil resistance at 20 deg c -388ohm±5% (368 to 408 ohms),

Drawing No.EL/PT/0638/Par 

t1.7  Contact impression (should be min 80%) Spec No.

MP.0.04.00.08(Rev-

01),May’10 

3.10.e

1.8  IR Value between(i)  fixed contact to movable Contact(ii)  coil to frame

IEC 60571 clause 10.2.9

2.0  Availability of tools and stands

2.37  Multimeter with proper calibration2.38  Vernier calipers with valid calibration

2.39  Go- No gauge suiting to different cantactors

SN Requirements Loco Make Of Reference Clause/Para/Item Observations

Page 59: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 59/104

Page 59 of 104 Quality Audit of Diesel Loco POH Workshop

SN Requirements LocoType

Make Of Subassembly

ReferenceDetails

Clause/Para/ItemDetails

Observations

2.40  Dial gauge of different scale and resolution assuited to respective contactor  

2.41  Source which can provide minimum current atrespective voltage (24 V – 72 V DC)

2.42  Variac

2.43  Meggar 

2.44  Oscilloscope

2.45  Screw Driver, Plier, Spanner Set, etc.

3. Availabili ty Of Instructions etc.

3.37  Display Chart3.38  Flow Chart

3.39  Training of staff 3.40  Proper Display of Do’s and Don’t 

3.41  Maintenance manual and check sheets3.42  Record keeping of tools and measuring

instruments3.43  Instruction Bulletin issued by RDSO

3.44  Maintenance Manual of Manufacturer 3.45  Specification

4. Compliance of Instruction Bulletin5. Follow of Maintenance Manual of Manufacturer 

6 Record Keeping For Traceability4.9  Proper Register is maintained for Contactors with

details of Manufacturer’s Brand Name, Date of Manufacture, Type, Sl. No., Date of Attending,Repair/Overhauling activity details, Loco No. to

which fitted.

4.10  Proper record should be maintained for eachcontactor with the measurement of Parameters asin Sl. No.1 prior to Fitment to Loco after overhauling/maintenance with date and remarks, if any.

SN Requirements Loco Make Of Reference Clause/Para/Item Observations

Page 60: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 60/104

Page 60 of 104 Quality Audit of Diesel Loco POH Workshop

SN Requirements LocoType

Make Of Subassembly

ReferenceDetails

Clause/Para/ItemDetails

Observations

7. Material Availability7.13  Vital Spares

7.14  Must change items7.15  Consumables

8. Disposal8.9  Segregation of Workable and Non-

Workable equipments and proper house keeping8.10  Proper Disposal of Materials including recycling

following relevant environmental norms

CHECK SHEET FOR

Page 61: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 61/104

Page 61 of 104 Quality Audit of Diesel Loco POH Workshop

CHECK SHEET FOR

TECHNICAL AUDIT OF CONTROL GEAR SECTION FOR FIELD SHUNTING CONTACTOR (ALCo)

During the audit, activities should be checked with regard to the Clause/Para/Item of the reference document as per applicability. Wherever the activities are notperformed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded.

Workshop/Rly: Audited by: Date of audit:

SN Requirements LocoType

Make Of Subassembly

ReferenceDetails

Clause/Para/ItemDetails

Observations

1. Measurement 

1.1  Control voltage 72+1v dc, AllDieselElectricLocomotives(ALCo)

Drawing No.EL/PT/0614/

Altr R4Part

No 12140491

Technical detailsgiven in the

drawing

1.2  max pick up volt 48v,1.3  Main contact gap12-14.5mm,

1.4  wipe 8-10 mm,1.5  contact pressure( kgf) initial1.6  1.82-2.95,final 5.45-7.25,

1.7  operating coil resistance at 20 deg c 104 -116ohms,

1.8  interlock (GPRelay type- 9-41n, 3no+3nc) contactgap 9.5-10.5

1.9  Interlock contact mm pressure -220-300gm.,

1.10  Contact impression (should be min 80%) Spec No.MP.0.04.00.08

(Rev-01),May’10 

3.10.e

1.11  IR Value between(i)  Main contacts(ii)  Coil and magnet frame(iii) Interlocks and coil shorted together and earth.(iv) Contacts of interlocks(v)  Interlocks and coil shorted together and main

as per IEC60571

clause 10.2.9

SN Requirements Loco Make Of Reference Clause/Para/Item Observations

Page 62: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 62/104

Page 62 of 104 Quality Audit of Diesel Loco POH Workshop

SN Requirements LocoType

Make Of Subassembly

ReferenceDetails

Clause/Para/ItemDetails

Observations

contacts shorted together (vi) shorted main contacts and shorted interlocks, coil

and earth2.0  Availability of tools and stands

2.46  Multimeter with proper calibration2.47  Vernier calipers with valid calibration

2.48  Go- No gauge suiting to different cantactors2.49  Dial gauge of different scale and resolution as

suited to respective contactor  2.50  Source which can provide minimum current at

respective voltage (24 V – 72 V DC)

2.51  Variac

2.52  Meggar 

2.53  Oscilloscope

2.54  Screw Driver, Plier, Spanner Set, etc.

3. Availabili ty Of Instructions etc.3.46  Display Chart3.47  Flow Chart

3.48  Training of staff 3.49  Proper Display of Do’s and Don’t 

3.50  Maintenance manual and check sheets3.51  Record keeping of tools and measuring

instruments3.52  Instruction Bulletin issued by RDSO3.53  Maintenance Manual of Manufacturer 

3.54  Specification

4. Compliance of Instruction Bulletin5. Follow of Maintenance Manual of Manufacturer 

Page 63: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 63/104

Page 63 of 104 Quality Audit of Diesel Loco POH Workshop

6 Record Keeping For Traceability

4.11  Proper Register is maintained for Contactors withdetails of Manufacturer’s Brand Name, Date of Manufacture, Type, Sl. No., Date of Attending,Repair/Overhauling activity details, Loco No. towhich fitted.

4.12  Proper record should be maintained for eachcontactor with the measurement of Parameters asin Sl. No.1 prior to Fitment to Loco after overhauling/maintenance with date and remarks, if any.

7. Material Availability

7.16  Vital Spares7.17  Must change items

7.18  Consumables8. Disposal

8.11  Segregation of Workable and Non-Workable equipments and proper house keeping

8.12  Proper Disposal of Materials including recyclingfollowing relevant environmental norms

CHECK SHEET FOR

Page 64: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 64/104

Page 64 of 104 Quality Audit of Diesel Loco POH Workshop

CHECK SHEET FOR

TECHNICAL AUDIT OF CONTROL GEAR SECTION FOR EP CONTACTORS (ALCo)

During the audit, activities should be checked with regard to the Clause/Para/Item of the reference document as per applicability. Wherever the activities are notperformed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded.

Workshop/Rly: Audited by: Date of audit:

SN Requirements LocoType Make Of Subassembly ReferenceDetails Clause/Para/ItemDetails Observations

1. Measurement  ALCo Drawing No.EL/PT/0630/

Altr R4Part

No 12141008

Technical detailsgiven in the

drawing1.1  Contact gap 15-17 mm

1.2  Wipe 25.4-28.6 mm

1.3  Knuckling spring pressure(without lever) initial 4.5-6.3 kgf, final 12.2-18.2 kgf,

1.4  Normal air pressure 4.9 kg/cm2

1.5  Interlock gap 2.5-3.95mm,1.6  Interlock pressure 500-900g.

1.7  Interlock rated current 10 A,1.8  Magnet valve coil resistance at 20degC 615+5%

ohm.for BHELTYPE: M5027MV21.9  ROTEX TYPE: 3118AV1-3 coil resistance at

20degC 526 to 594 Ohms,1.10  Contact impression (should be min 80%) Spec No.

MP.0.04.00.08

(Rev-01),

May’10 

3.10.e

1.11  IR Value between

a)  main contactsb)  interlocks and MVc)  interlocks and MV shorted together and earthd)  contacts and interlockse)  Interlocks and MV shorted together and main

contacts shorted together.f)  Main contacts shorted together and earth

shorted with MV and interlocks.

IEC 60571 as per clause

10.2.9 

SN Requirements Loco Make Of Reference Clause/Para/Item Observations

Page 65: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 65/104

Page 65 of 104 Quality Audit of Diesel Loco POH Workshop

SN Requirements LocoType

Make Of Subassembly

ReferenceDetails

Clause/Para/ItemDetails

Observations

2.0  Availability of tools and stands2.55  Multimeter with proper calibration

2.56  Vernier calipers with valid calibration2.57  Go- No gauge suiting to different cantactors

2.58  Dial gauge of different scale and resolution assuited to respective contactor  

2.59  Source which can provide minimum current atrespective voltage (24 V – 72 V DC)

2.60  Variac

2.61  Lever of 122.5 mm for measuring initial and finalpressure.

2.62  Compresor with air reservoir 

2.63  Megger 

2.64  Oscilloscope

2.65  Screw Driver, Plier, Spanner Set, etc.

3. Availabili ty Of Instructions etc.3.55  Display Chart3.56  Flow Chart

3.57  Training of staff 3.58  Proper Display of Do’s and Don’t 

3.59  Maintenance manual and check sheets3.60  Record keeping of tools and measuring

instruments

3.61  Instruction Bulletin issued by RDSO3.62  Maintenance Manual of Manufacturer 

3.63  Specification

4. Compliance of Instruction Bulletin5. Follow of Maintenance Manual of Manufacturer 

Page 66: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 66/104

Page 66 of 104 Quality Audit of Diesel Loco POH Workshop

6 Record Keeping For Traceability

4.13  Proper Register is maintained for Contactors withdetails of Manufacturer’s Brand Name, Date of Manufacture, Type, Sl. No., Date of Attending,Repair/Overhauling activity details, Loco No. towhich fitted.

4.14  Proper record should be maintained for eachcontactor with the measurement of Parameters asin Sl. No.1 prior to Fitment to Loco after overhauling/maintenance with date and remarks, if any.

7. Material Availability

7.19  Vital Spares7.20  Must change items

7.21  Consumables8. Disposal

8.13  Segregation of Workable and Non-Workable equipments and proper house keeping

8.14  Proper Disposal of Materials including recyclingfollowing relevant environmental norms

CHECK SHEET FOR

Page 67: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 67/104

Page 67 of 104 Quality Audit of Diesel Loco POH Workshop

C C S O

TECHNICAL AUDIT OF CONTROL GEAR SECTION FOR 6M REVERSER (ALCo)

During the audit, activities should be checked with regard to the Clause/Para/Item of the reference document as per applicability. Wherever the activities are notperformed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded.

Workshop/Rly: Audited by: Date of audit:

SN Requirements LocoType Make Of Subassembly ReferenceDetails Clause/Para/ItemDetails Observations

1. Measurement

1.1   Auxiliary contacts 4, change over type,   ALCo Drawing No.EL/PT/0649/

Altr R5Part

No 12310372

Technical detailsgiven in the

drawing1.2  Control voltage 72+1 V DC,1.3  Operating air pressure 4.9 kg/cm2,

1.4  Min operating air pressure 3.85 kg/cm2,

1.5  Main contact gap19.05+1.6mm,

1.6  Main contact outside pressure (with lever) 4.0-4.5kgf, inside pressure 5.8-6.5kgf,

1.7  Contact impression (should be min 80%)

1.8   Auxiliary contact pressure 0.68-2.0kgf,

1.9   Auxiliary contact gap 31.75mm (min), ,1.10  Magnet valve coil resistance at 20degC 615+5%

ohm.for BHEL type: 5027MV2

1.11  ROTEX TYPE: 3118AV1-3 coil resistance at20degC-526 to 594 Ohms.

1.12  Contact impression (should be min 80%) Spec No.

MP.0.04.00.08

(Rev-

01),May’10 

3.10.e

SN Requirements Loco Make Of  Reference Clause/Para/Item Observations

Page 68: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 68/104

Page 68 of 104 Quality Audit of Diesel Loco POH Workshop

qType Subassembly Details Details

1.13  IR Value between(i)  Main contacts and frame(ii)  Frame and all live parts connected

together (wth main cxontacts closed)(iii)  Terminals of both side, terminals shorted

together on each side (Main contacts

open)(iv)   All control and Aux. circuit 

IEC 60571 as per clause10.2.9 

2.0  Availability of tools and stands2.66  Multimeter with proper calibration

2.67  Vernier calipers with valid calibration2.68  Go- No gauge suiting to different cantactors

2.69  Dial gauge of different scale and resolution assuited to respective contactor  

2.70  Source which can provide minimum current atrespective voltage (24 V – 72 V DC)

2.71  Variac2.72  Lever of 122.5 mm for measuring initial and final

pressure.

2.73  Compresor with air reservoir 

2.74  Megger 

2.75  Oscilloscope

2.76  Screw Driver, Plier, Spanner Set, etc.

3. Availabili ty Of Instructions etc.3.64  Display Chart

3.65  Flow Chart3.66  Training of staff 3.67  Proper Display of Do’s and Don’t 

3.68  Maintenance manual and check sheets3.69  Record keeping of tools and measuring

instruments

3.70  Instruction Bulletin issued by RDSO

SN Requirements Loco Make Of  Reference Clause/Para/Item Observations

Page 69: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 69/104

Page 69 of 104 Quality Audit of Diesel Loco POH Workshop

Type Subassembly Details Details

3.71  Maintenance Manual of Manufacturer 3.72  Specification Spec No.

MP.0.04.00.08

(Rev-

01),May’10 

4. Compliance of Instruction Bulletin5. Follow of Maintenance Manual of Manufacturer 

6 Record Keeping For Traceability4.15  Proper Register is maintained for 6 M Reverser 

with details of Manufacturer’s Brand Name, Date of Manufacture, Type, Sl. No., Date of Attending,Repair/Overhauling activity details, Loco No. towhich fitted.

4.16  Proper record should be maintained for each 6 MReverser with the measurement of Parameters asin Sl. No.1 prior to Fitment to Loco after overhauling/maintenance with date and remarks, if any.

7. Material Availability7.22  Vital Spares7.23  Must change items

7.24  Consumables8. Disposal

8.15  Segregation of Workable and Non-Workable equipments and proper house keeping

8.16  Proper Disposal of Materials including recyclingfollowing relevant environmental norms

CHECK SHEET FOR

Page 70: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 70/104

Page 70 of 104 Quality Audit of Diesel Loco POH Workshop

TECHNICAL AUDIT OF CONTROL GEAR SECTION FOR 6 M BKT CONTACTORS (ALCo LOCO)

During the audit, activities should be checked with regard to the Clause/Para/Item of the reference document as per applicability. Wherever the activities are notperformed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded.

Workshop/Rly: Audited by: Date of audit:

SN Requirements LocoType Make Of Subassembly ReferenceDetails Clause/Para/ItemDetails Observations

1. Measurement 

1.1   Auxiliary contacts 4 change over type, AllDieselElectricLocomotives(ALCo)

Drawing No.EL/PT/0648/

Altr R5Part No

12310300

Technical detailsgiven in the

drawing1.2  Control voltage 72+1 V DC,1.3  operating air pressure 4.9 kg/cm2,1.4  Min operating air pressure 3.85 kg/cm2 ,

1.5  Main contact gap19.05+1.6mm,1.6  Main contact - outside pressure (with lever)1.7  4.0-4.5kgf, inside pressure 5.8-6.5kgf,

1.8   Auxiliary contact pressure 0.68-2.0 kgf,

1.9   Auxiliary contact gap 31.75mm (min),1.10  Magnet valve coil resistance at 20degC1.11  615+5% ohm. for BHELTYPE : M5027MV2

1.12  ROTEX TYPE: 3118AV1-3 coil resistance at20degC 526 to 594 Ohms

1.13  Contact impression (should be min 80%) Spec No.

MP.0.04.00.08

(Rev-01),

May’10 

3.10.e

1.14  IR value between(i)  Main contacts and frame(ii)  Frame and all live parts connected together 

(wth main cxontacts closed)(iii)  Terminals of both side, terminals shorted

together on each side (Main contacts open)(iv)   All control and Aux. circuit

IEC60571

as per clause10.2.9 

2.0 Availabili ty of tools and stands

Page 71: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 71/104

Page 71 of 104 Quality Audit of Diesel Loco POH Workshop

2.77  Multimeter with proper calibration2.78  Vernier calipers with valid calibration

2.79  Go- No gauge suiting to different cantactors2.80  Dial gauge of different scale and resolution as

suited to respective contactor  

2.81  Source which can provide minimum current atrespective voltage (24 V – 72 V DC)

2.82  Variac2.83  Lever of 122.5 mm for measuring initial and final

pressure.

2.84  Compresor with air reservoir 

2.85  Meggar 

2.86  Oscilloscope

2.87  Screw Driver, Plier, Spanner Set, etc.

3. Availabili ty Of Instructions etc.3.73  Display Chart

3.74  Flow Chart3.75  Training of staff 

3.76  Proper Display of Do’s and Don’t 3.77  Maintenance manual and check sheets

3.78  Record keeping of tools and measuringinstruments

3.79  Instruction Bulletin issued by RDSO

3.80  Maintenance Manual of Manufacturer 3.81  Specification

4. Compliance of Instruction Bulletin

5. Follow of Maintenance Manual of Manufacturer 

Page 72: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 72/104

Page 72 of 104 Quality Audit of Diesel Loco POH Workshop

6 Record Keeping For Traceability

4.17  Proper Register is maintained for Contactors withdetails of Manufacturer’s Brand Name, Date of Manufacture, Type, Sl. No., Date of Attending,Repair/Overhauling activity details, Loco No. towhich fitted.

4.18  Proper record should be maintained for eachcontactor with the measurement of Parameters asin Sl. No.1 prior to Fitment to Loco after overhauling/maintenance with date and remarks, if any.

7. Material Availability

7.25  Vital Spares

7.26  Must change items

7.27  Consumables

8. Disposal8.17  Segregation of Workable and Non-

Workable equipments and proper house keeping

8.18  Proper Disposal of Materials including recyclingfollowing relevant environmental norms

CHECK SHEET FOR

Page 73: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 73/104

Page 73 of 104 Quality Audit of Diesel Loco POH Workshop

TECHNICAL AUDIT OF CONTROL GEAR SECTION FOR GENERAL PURPOSE RELAY (ALCo LOCO)

During the audit, activities should be checked with regard to the Clause/Para/Item of the reference document as per applicability. Wherever the activities are notperformed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded.

Workshop/Rly: Audited by: Date of audit:

SN Requirements LocoType Make Of Subassembly ReferenceDetails Clause/Para/ItemDetails Observations

1. Measurement 

1.10  Nominal operating voltage (50-80 V) All DieselElectricLocomotives(ALCo)

BHEL, AAL andIEI

Spec No.MP.0.400.03

(Rev-01) Nov’08 

Clause 3.1.1

1.11  Pick up voltage (Must Operate), max 48V Clause 3.2 (ii) 1.12  Drop out Voltage Min 7.5 V

1.13   Auxiliary make rating 7.5 A at 72 V1.14  Resistance of the coil at 20 deg C 445±5%, Clause 3.2 (v) 1.15  Contact Pressure 100-250 g Clause 3.2 (vi) 

1.16  Over travel (1.6 mm) with over travel gauge inposition 0.0 to 0.1

Clause 3.2 (vii) 

1.17  Min contact gap 2.7 mm Clause 3.2 (viii) 1.18   Armature gap 4.7 to 6.6 Clause 3.2 (ix) 1.19  Ensure that no distortion or corrosion of any

componentsClause16.1.9.2

1.20  IR Value between1.20.1  Open contacts1.20.2  Contacts and metal parts1.20.3   Adjacent contacts1.20.4  Coil and earth

as per IEC60571

Clause 10.2.9

2.0  Availability of tools and stands

2.88  Multimeter with proper calibration2.89  Vernier calipers with valid calibration2.90  Go- No gauge

2.91  Dial gauge

SN Requirements LocoT

Make Of S b bl

ReferenceD t il

Clause/Para/ItemD t il

Observations

Page 74: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 74/104

Page 74 of 104 Quality Audit of Diesel Loco POH Workshop

Type Subassembly Details Details

2.92  Source which can provide minimum current atrespective voltage (72 V DC)

2.93  Variac

2.94  Meggar 

2.95  Screw Driver, Plier, Spanner Set, etc.

2.96  Sufficient set of tool and gauges provided bymanufacturer 

3. Availabili ty Of Instructions etc.

3.82  Display Chart3.83  Flow Chart

3.84  Training of staff 3.85  Proper Display of Do’s and Don’t 

3.86  Maintenance manual and check sheets3.87  Record keeping of tools and measuring

instruments

3.88  Instruction Bulletin issued by RDSO

3.89  Maintenance Manual of Manufacturer 3.90  Specification Spec No.

MP.0.400.03(Rev-01) Nov’08 

4. Compliance of Instruction Bulletin5. Follow of Maintenance Manual of Manufacturer 

6 Record Keeping For Traceability4.19  Proper Register is maintained for GP Relay with

details of Manufacturer’s Brand Name, Date of Manufacture, Type, Sl. No., Date of Attending,Repair/Overhauling activity details, Loco No. towhich fitted.

4.20  Proper record should be maintained for GP Relaywith the measurement of Parameters as in Sl. No.1prior to Fitment to Loco after overhauling/maintenance with date and remarks, if any.

SN Requirements LocoT pe

Make Of S bassembl

ReferenceDetails

Clause/Para/ItemDetails

Observations

Page 75: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 75/104

Page 75 of 104 Quality Audit of Diesel Loco POH Workshop

Type Subassembly Details Details

7. Material Availability7.28  Vital Spares

7.29  Must change items8. Disposal

8.19  Segregation of Workable and Non-Workableequipments and proper house keeping

8.20  Proper Disposal of Materials including recyclingfollowing relevant environmental norms

CHECK SHEET FOR

Page 76: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 76/104

Page 76 of 104 Quality Audit of Diesel Loco POH Workshop

TECHNICAL AUDIT OF POH WORKSHOP OF ELECTRICAL CONTROL FOR DC-DC CONVERTER (500 W)-TWIN BEAM HEAD LIGHT(ALCo LOCO)

During the audit, activities should be checked with regard to the Clause/Para/Item of the reference document as per applicability. Wherever the activities are notperformed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded.

Work shop/Rly: Audited by: Date of audit:

SN Requirements LocoType

Make Of Subassembly

ReferenceDetails

Clause/Para/ItemDetails

Observations

1. Measurement :2.1 Visual Inspection – check finish , material , sound

quality of workman ship etc

 ALCo

RDSOspecification No.ELRS/SPEC/DC-DC Converter /0021 ,Rev.01

Sept 2004

Clause No.6.3.1

2.2 Functional Check –ON/OFF properly RDSOspecification No.ELRS/SPEC/DC-DC Converter /0021 ,Rev.01

Sept 2004

2.3  Available output regulated Voltage 25.5 ± .1% VDC with the variation of input voltage 50-85 V DC

RDSOspecification No.ELRS/SPEC/DC-DC Converter 

/0021 ,Rev.01Sept 2004

Clause No. 2.2and 2.3

2.Availability Of Tools And Test Stands  ALCo

3.1 Multimeter with Valid Calibration

SN Requirements LocoType

Make Of Subassembly

ReferenceDetails

Clause/Para/ItemDetails

Observations

Page 77: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 77/104

Page 77 of 104 Quality Audit of Diesel Loco POH Workshop

Type Subassembly Details Details

3.2 Test stand for measurement and testing.

3.3 Screw Driver, Plier, etc.

3.4 Fire Extinguisher of proper class

3

Availability Of Instructions etc.

3.91  Display Chart

3.92  Flow Chart

3.93  Training of staff 

3.94  Proper Display of Do’s and Don’t 

3.95  Maintenance manual and check sheets

3.96  Record keeping of tools and measuringinstruments

3.97  Instruction Bulletin issued by RDSO NA

3.98  Maintenance Manual of Manufacturer 

3.99  Specification

4. Compliance of Instruction Bulletin

5. Follow of Maintenance Manual of Manufacturer 

6. Record Keeping For Traceability

4.21  Proper Register is maintained for DC-DCConverter (500 W) with details of Manufacturer’sBrand Name, Date of Manufacture, Type, Sl. No.,

SN Requirements LocoType

Make Of Subassembly

ReferenceDetails

Clause/Para/ItemDetails

Observations

Page 78: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 78/104

Page 78 of 104 Quality Audit of Diesel Loco POH Workshop

Type Subassembly Details Details

Date of Attending, Repair/Overhauling activitydetails, Loco No. to which fitted.

4.22  Proper record should be maintained for each DC-DC Converter 

4.23  500 W DC-DC Converter with themeasurement of Parameters as in Sl. No.1 prior to Fitment to Loco after overhauling/maintenancewith date and remarks, if any.

7.

Material Availability7.30  Vital Spares

7.31  Must change items

7.32  Consumables

8. Disposal

8.1 Segregation of Working and Non-Workingequipment and Proper House Keeping

8.2 Safe Disposal including recycling followingrelevant environmental norms.

CHECK SHEET FOR

Page 79: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 79/104

Page 79 of 104 Quality Audit of Diesel Loco POH Workshop

TECHNICAL AUDIT OF POH WORKSHOP ELECTRICAL CONTROL FOR LED FLASHER LIGHT (ALCo LOCO)

During the audit, activities should be checked with regard to the Clause/Para/Item of the reference document as per applicability. Wherever the activities are notperformed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded.

Workshop /Rly: Audited by: Date of audit:

SN Requirements LocoType

Make Of Subassembly

Reference Details Clause/Para/Item Details

Observations

1. Measurement :2.1 Visual Inspection – check finish , material , sound

quality of workman ship , water tightness etc

 ALCo

RDSO specificationNo.

ELRS/SPEC/LFL/0017 Rev 1 Sept 04

ClauseNo.6.3.

2.2 Functional Check –ON/OFF properly RDSO specificationNo.

ELRS/SPEC/LFL/0

017 Rev 1 Sept 042.3 Lux Value- The lux measured in axial directionshall not be less than 500 lux at 1 meter and 55lux at 3 meters for amber clour LED of 120 Nos

RDSO specificationNo.

ELRS/SPEC/LFL/0017 Rev 1 Sept 04

Clause No.2.3.3

2.4 Flashes per Minute (40±5) RDSO specificationNo.

ELRS/SPEC/LFL/0017 Rev 1 Sept 04

Clause No.2.4.1

2.5  Output regulated Voltage RDSO specificationNo.

ELRS/SPEC/LFL/0017 Rev 1 Sept 04

Clause No.2.4.5

2.6  Check Repeater indication properly RDSO specificationNo.

ELRS/SPEC/LFL/0017 Rev 1 Sept 04

ClauseNo.2.4.3.1

2. Availability Of Tools And Test Stands  ALCo

SN Requirements LocoType

Make Of Subassembly

Reference Details Clause/Para/Item Details

Observations

Page 80: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 80/104

Page 80 of 104 Quality Audit of Diesel Loco POH Workshop

Type Subassembly em Details

3.1 Voltmeter with Valid Calibration3.2   Ammeter with Valid Calibration

3.3 Lux Meter with proper Calibration

3.4 Test stand for measurement and testing.

3.5 Stop Watch

3.6 Screw Driver, Plier, etc.

3.7 Fire Extinguisher of proper class

3

Availability Of Instructions etc.

3.1 Display Chart

3.2 Flow Chart

3.3 Training of staff 

3.4 Proper Display of Do’s and Don’t 

3.5 Maintenance manual and check sheets

3.6 Record keeping of tools and measuringinstruments

3.7  Instruction Bulletin issued by RDSO

3.8 Maintenance Manual of Manufacturer 

3.9 Specification RDSO specificationNo.

ELRS/SPEC/LFL/0017 Rev 1 Sept 04

SN Requirements LocoType

Make Of Subassembly

Reference Details Clause/Para/Item Details

Observations

Page 81: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 81/104

Page 81 of 104 Quality Audit of Diesel Loco POH Workshop

Type Subassembly em Details

4. Compliance of Instruction Bulletin

5. Follow of Maintenance Manual of Manufacturer 

6. Record Keeping For Traceability

4.1 Proper Register is maintained for LED Flasher Light with details of Manufacturer’s Brand Name,Date of Manufacture, Type, Sl. No., Date of 

 Attending, Repair/Overhauling activity details,Loco No. to which fitted.

4.2 Proper record should be maintained for each LEDFlasher Light

4.3  LED Flasher Light with the measurement of Parameters as in Sl. No.1 prior to Fitment to Locoafter overhauling/maintenance with date andremarks, if any.

7.

Material Availability7.1 Vital Spares

7.2 Must change items

7.3 Consumables such as fuses , toggle switches etc

8. Disposal

8.1 Segregation of Working and Non-Working

equipment and Proper House Keeping

8.2 Safe Disposal including recycling followingrelevant environmental norms.

CHECK SHEET FOR

Page 82: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 82/104

Page 82 of 104 Quality Audit of Diesel Loco POH Workshop

TECHNICAL AUDIT OF POH WORKSHOP ELECTRICAL CONTROL FOR LED MARKER LIGHT (ALCo LOCO)

During the audit, activities should be checked with regard to the Clause/Para/Item of the reference document as per applicability. Wherever the activities are notperformed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded.

Workshop /Rly: Audited by: Date of audit:

SN Requirements LocoType

Make Of Subassembly

ReferenceDetails

Clause/Para/ItemDetails

Observations

1. Measurement :2.7 Visual Inspection – check finish , material , sound

quality of workman ship , water tightness etc.

 ALCo

RDSOspecification No.ELRS/Spec/PR/

0022 (REV-1Oct -2004)

Clause No.6.3.

2.8 Functional Check –ON/OFF properly RDSO

specification No.ELRS/Spec/PR/0022 (REV-1Oct -2004)

2.9 Lux Value- for all input voltage range 45V-90 V

Lamp Lux level at 1

Meter 

Lux level at 3

Meters 

RED 75 LUX 7 LUX

WHITE 75 LUX 7 LUX

RDSOspecification No.ELRS/Spec/PR/

0022 (REV-1Oct -2004)

Clause No. 2.4.3

2.

Availability Of Tools And Test Stands3.8  Multimeter with Valid Calibration ALCo3.9 Lux Meter with proper Calibration

3.10  Test stand for measurement and testing.

SN Requirements LocoType

Make Of Subassembly

ReferenceDetails

Clause/Para/ItemDetails

Observations

Page 83: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 83/104

Page 83 of 104 Quality Audit of Diesel Loco POH Workshop

Type Subassembly Details Details

3.11  Screw Driver, Plier, etc.

3.12  Fire Extinguisher of proper class

3

Availability Of Instructions etc.

3.10  Display Chart

3.11  Flow Chart

3.12  Training of staff 

3.13  Proper Display of Do’s and Don’t 

3.14  Maintenance manual and check sheets

3.15  Record keeping of tools and measuring

instruments3.16  Instruction Bulletin issued by RDSO

3.17  Maintenance Manual of Manufacturer 

3.18  Specification

4. Compliance of Instruction Bulletin

5. Follow of Maintenance Manual of Manufacturer 

6. Record Keeping For Traceability

4.4 Proper Register is maintained for LED Marker Light with details of Manufacturer’s Brand Name,Date of Manufacture, Type, Sl. No., Date of 

 Attending, Repair/Overhauling activity details,Loco No. to which fitted.

SN Requirements LocoType

Make Of Subassembly

ReferenceDetails

Clause/Para/ItemDetails

Observations

Page 84: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 84/104

Page 84 of 104 Quality Audit of Diesel Loco POH Workshop

yp y

4.5 Proper record should be maintained for each LEDMarker Light

4.6  LED Marker with the measurement of Parameters as in Sl. No.1 prior to Fitment to Locoafter overhauling/maintenance with date andremarks, if any.

7.

Material Availability

7.4 Vital Spares

7.5 Must change items

7.6 Consumables such as fuses , toggle switches etc

8. Disposal

8.1 Segregation of Working and Non-Workingequipment and Proper House Keeping

8.2 Safe Disposal including recycling followingrelevant environmental norms.

CHECK SHEET FOR

TECHNICAL AUDIT OF CONTROL GEAR SECTION FOR STICK TYPE / IMPROVED STICK TYPE MASTER CONTROLLER

Page 85: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 85/104

Page 85 of 104 Quality Audit of Diesel Loco POH Workshop

TECHNICAL AUDIT OF CONTROL GEAR SECTION FOR STICK TYPE / IMPROVED STICK TYPE MASTER CONTROLLERFOR POH WORKSHOPS IN REFERENCE TO POH OF ALCo DIESEL LOCOMOTIVES

During the audit, activities should be checked with regard to the Clause/Para/Item of the reference document as per applicability. Wherever the activities are notperformed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded.

Workshop/Rly: Audited by: Date of audit:

SN Requirements LocoType

Make Of Subassembly

Reference Details Clause/Para/Item Details

Observations

A. Stick Type / Improved Stick type Master controller 

1.  Measurement:  

1.1  Visual checking ALCo

M/s BHEL, Asian Plastic,M/s Kaysons

(AMC/R2)Make

BHEL Testprogrammedocument no. 865476dt

Clause 1.1

Drawing of Improved

stick type Master Controller EL-PT-0633-R3 dt.29.12.2007.

1.2  Contact gap,  BHEL Testprogrammedocument no. 865476dt 24.04.99 and

Clause 1.2

1.3  Contact pressure,

1.4  Cam sequence and1.5  Mechanical interlocking

1.6  Working of Throttle handle Clause 1.3

2. Test : 

2.1  Insulation Resistance test: BHEL Testprogramme

document no. 865476

Clause 5.0

2.2  Continuity Test DLW Drg. No.35900030031Rev. 04

Page 86: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 86/104

Page 86 of 104 Quality Audit of Diesel Loco POH Workshop

2.

Availability Of Tools And Test Stands

 ALCoM/s BHEL,

 Asian Plastic,

M/s Kaysons(AMC/R2)

Make

3.13  Voltmeter with Valid Calibration3.14  Venier Caliper with Valid Calibration3.15  Megger with Valid Calibration

3.16  Digital Multimeter with Valid Calibration3.17  Potentiometer with Valid Calibration

3.18  Height gauge with Valid Calibration3.19  High Voltage Tester with Valid Calibration

3.20  Bore Dial gauge with Valid Calibration3.21   Ammeter with Valid Calibration

3.22  GO and NO GO Gauge3.23  Screw Driver, Plier, Required spanner set etc.

3.24  Test stand for measurement and testing.

3.25  Fire Extinguisher of proper class

3

Availability Of Instructions etc.

3.19  Display Chart

3.20  Flow Chart

3.21  Throttle sequence chart

3.22  Mechanical interlocking Chart

3.23  Training of staff 

3.24  Proper Display of Do’s and Don’t 

3.25  Maintenance manual and check sheets

3.26  Record keeping of tools and measuringinstruments

Page 87: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 87/104

Page 87 of 104 Quality Audit of Diesel Loco POH Workshop

3.27  Instruction Bulletin issued by RDSO

3.28  Maintenance Manual of Manufacturer 

3.29  Specification

4. Compliance of Instruction Bulletin

5. Follow of Maintenance Manual of Manufacturer 

6. Record Keeping For Traceability

4.7 Proper Register is maintained for EMD Master Controller checking with details of Manufacturer’sBrand Name, Date of Manufacture, Type, Sl. No.,Date of Attending, Repair/Overhauling activitydetails, Loco No. to which fitted.

4.8 Proper record should be maintained for each

4.9  EMD Master Controller with the measurement of Parameters as in Sl. No.1 prior to Fitment to Locoafter overhauling/maintenance with date andremarks, if any.

7.

Material Availability7.7 Vital Spares

7.8 Must change items

7.9 Consumables like OTTO Switches, Reverser Handle), Terminal Lugs, 28-Pin Coupler, M/s.Radiant make cables. etc.

8. Segregation of Working and Non-Working equipment and

Proper House Keeping

CHECK SHEET FOR

TECHNICAL AUDIT OF POH WORKSHOP ELECTRICAL CONTROL FOR TWIN BEAM HEAD LIGHT (ALCo LOCO)

Page 88: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 88/104

Page 88 of 104 Quality Audit of Diesel Loco POH Workshop

TECHNICAL AUDIT OF POH WORKSHOP ELECTRICAL CONTROL FOR TWIN BEAM HEAD LIGHT (ALCo LOCO)

During the audit, activities should be checked with regard to the Clause/Para/Item of the reference document as per applicability. Wherever the activities are notperformed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded.

Workshop /Rly: Audited by: Date of audit:

SN Requirements LocoType

Make Of Subassembly

ReferenceDetails

Clause/Para/ItemDetails

Observations

1. Measurement :2.10  Visual Inspection – check finish , material , sound

quality of workman ship etc

 ALCo

RDSOspecification No.ELRS/SPEC/PR/0024 ( Rev-1,

Sept 2004)

Clause No.6.3.1

2.11  Functional Check –ON/OFF properly

2.12  Type of Bulbs used – H4 P45 T(IR), Twin Filament IB NO.

MP.IB.EC.01.08.06 DATE:27-12-06

Clause No. 4.A.1

2.13  Model of Bulbs –Halonix and AutoPal Only IB NO.MP.IB.EC.01.08.06 DATE:27-12-06

Clause No. 4.A.2 

2.14  Voltage Rating -24 V IB NO.MP.IB.EC.

01.08.06 DATE:27-12-06

Clause No. 4.A.3 

2.15  Wattage Rating of Bulbs -100/90 W, Bright/Dimfilament at 24 V

IB NO.MP.IB.EC.01.08.06 DATE:27-12-06

Clause No. 4.A.4 

SN Requirements LocoType

Make Of Subassembly

ReferenceDetails

Clause/Para/ItemDetails

Observations

Page 89: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 89/104

Page 89 of 104 Quality Audit of Diesel Loco POH Workshop

2.16  Lumen Out put -2600/1770 ± 15 % Lumen of Bright/Dim Filament at 24 V

IB NO.MP.IB.EC.01.08.06 DATE:27-12-06

Clause No. 4.A.5 

2.17  Lux output with Twin Beam Head Light for eachreflector minimum 2400 Lux at a distance of 8 Mtand 24.5± 0.1 V DC terminal Voltage at LampHolder 

IB NO.MP.IB.EC.01.08.06 DATE:27-12-06

Clause No. 4.A.6 

2.18  Procedure to check correctness of bulb’s f ilamentin test room

IB NO.MP.IB.EC.01.08.06 DATE:27-12-06

Clause No. 4 B

2.19  Checking illumination intensity of head light

assembly when both bulbs are working

IB NO.

MP.IB.EC.01.08.06 DATE:27-12-06

Clause No.6

2.

Availability Of Tools And Test Stands3.26  Voltmeter with Valid Calibration

3.27  1.A standard portable lux measuringequipment ‘Lux meter’ like T.E.S. model TES –1330 shall be used. Lux Meter should be of range0-20000 lux with least count of 0.01 Lux with validcalibration

3.28  Focusing Stand IB NO.MP.IB.EC.01.08.06 DATE:27-12-06

3.29  Screw Driver, Plier, etc.

SN Requirements LocoType

Make Of Subassembly

ReferenceDetails

Clause/Para/ItemDetails

Observations

Page 90: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 90/104

Page 90 of 104 Quality Audit of Diesel Loco POH Workshop

3.30  Test stand for measurement and testing.

3.31  Fire Extinguisher of proper class

3

Availability Of Instructions etc.

3.30  Display Chart

3.31  Flow Chart

3.32  Training of staff 

3.33  Proper Display of Do’s and Don’t 

3.34  Maintenance manual and check sheets

3.35  Record keeping of tools and measuringinstruments

3.36  Instruction Bulletin issued by RDSO IB NO.MP.IB.EC.01.08.06 DATE:27-12-06

3.37  Maintenance Manual of Manufacturer 

3.38  Specification RDSOspecification No.ELRS/SPEC/PR/0024 ( Rev-1,

Sept 2004)

4. Compliance of Instruction Bulletin

5. Follow of Maintenance Manual of Manufacturer 

6. Record Keeping For Traceability

SN Requirements LocoType

Make Of Subassembly

ReferenceDetails

Clause/Para/ItemDetails

Observations

4 10 P R i i i i d f T i

Page 91: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 91/104

Page 91 of 104 Quality Audit of Diesel Loco POH Workshop

4.10  Proper Register is maintained for TwinBeam Head Light with details of Manufacturer’sBrand Name, Date of Manufacture, Type, Sl. No.,Date of Attending, Repair/Overhauling activitydetails, Loco No. to which fitted.

4.11  Proper record should be maintained for 

each Twin Beam Head Light4.12  Twin Beam Head Light /Bulbs with the

measurement of Parameters as in Sl. No.1 prior to Fitment to Loco after overhauling/maintenancewith date and remarks, if any.

7.

Material Availability7.10  Vital Spares

7.11  Must change items

7.12  Consumables like bulbs , Reflector 

8.

Disposal

8.1 Segregation of Working and Non-Workingequipment and Proper House Keeping

8.2 Safe Disposal of Bulbs/reflector includingrecycling following relevant environmental norms.

CHECK SHEET FOR

TECHNICAL AUDIT OF BATTERY SECTON LEAD ACID BATTERY CHECK SHEET FOR POH

Page 92: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 92/104

Page 92 of 104 Quality Audit of Diesel Loco POH Workshop

TECHNICAL AUDIT OF BATTERY SECTON LEAD ACID BATTERY CHECK SHEET FOR POHWORKSHOPS IN REFERENCE TO POH OF ALCo DIESEL LOCOMOTIVES

During the audit, activities should be checked with regard to the Clause/Para/Item of the reference document as per applicability. Wherever the activities are notperformed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded.

Workshop/Rly: Audited by: Date of audit:

SN Requirements LocoType

Make Of Subassembly

Reference Details Clause/Para/Item Details

Observations

1. Measurement :2.20  Physical Examination

 ALCo

2.21   Air Pressure Spec. No.DEL/SPN/193 July’98 

Clause 8.5 

2.22   Ampere Hour Capacity Spec. No.DEL/SPN/193 July’98 

Clause 8.6 

2.23  Watt Hour Efficiency Spec. No.DEL/SPN/193 July’98 

Clause 8.7 

2.24   Ampere Hour Efficiency Spec. No.DEL/SPN/193 July’98 

Clause 8.7 

2.25  Internal Resistance Spec. No.DEL/SPN/193 July’98 

Clause 8.8

2.26  Initial Cranking Current Spec. No.DEL/SPN/193 July’98 

Clause 8.9 

2.27  Electrolyte Level Spec. No.DEL/SPN/193 July’98 

Clause 6 

2.28  Polarity and absence of Short Circuit

2.

Availability Of Tools And Test Stands

 ALCo

3.32  Battery Room Suitable size with sufficient area for movement of forklift, Storing of Acid Mixing tank,and Suitable battery test benches with sufficientExhaust fans.

3.33  Electrolyte mixing tank-Motorized type preferred3.34  Voltmeter with Valid Calibration

3.35  Thermometer with Valid Calibration

SN Requirements LocoType

Make Of Subassembly

Reference Details Clause/Para/Item Details

Observations

3 36 H d t ith V lid C lib ti

Page 93: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 93/104

Page 93 of 104 Quality Audit of Diesel Loco POH Workshop

3.36  Hydrometer with Valid Calibration3.37   Ammeter with Valid Calibration

3.38  Multi meter with Valid Calibration3.39  Clamp Meter 

3.40  Rubber syringe3.41  Battery Charger(Preferred Constant Current

Chargers)3.42  Battery Discharger (Preferred Electronic type)

3.43  Required Lab for testing of Acid and DM water 3.44  Screw Driver, Plier, Spanner Set etc.

3.45  Test stand for measurement and testing (ConcretePlatform covered with Acid Resistant FRPsheets/coating for keeping batteries –charge/Discharge.)

3.46  D.M.Water Plant

3.47  Proper earthing facility for switch gear and Battery

charging Panel.3.48  Fire Extinguisher of proper class

3.49  Fork Lift

3.50  Hand trolley

3.51  Battery lifting crane on test bench

3.52  Plastic Pallet for storing Battery

3.53  Rubber Apron

3.54  Rubber Gloves

3.55  Goggles

3 Availability Of Instructions etc.

SN Requirements LocoType

Make Of Subassembly

Reference Details Clause/Para/Item Details

Observations

3 39 Displa Chart

Page 94: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 94/104

Page 94 of 104 Quality Audit of Diesel Loco POH Workshop

3.39  Display Chart

3.40  Flow Chart

3.41  Training of staff 

3.42  Proper Display of Do’s and Don’t 

3.43  Maintenance manual and check sheets

3.44  Record keeping of tools and measuringinstruments

3.45  Instruction Bulletin issued by RDSO MP. IB. EC.01.02.05(Rev.01), Dec. 2008

3.46  Maintenance Manual of Manufacturer 

3.47  Specification Spec. No.DEL/SPN/193 July’98 

4. Compliance of Instruction Bulletin

5. Follow of Maintenance Manual of Manufacturer 

6.

Record Keeping For Traceability

4.13  Proper Register is maintained for Battery checkingwith details of Manufacturer’s Brand Name, Dateof Manufacture, Type, Sl. No., Date of Attending,Repair/Overhauling activity details, Loco No. towhich fitted.

4.14  Proper record should be maintained for eachbattery with the measurement of Parameters as inSl. No.1 prior to Fitment to Loco after overhauling/maintenance with date and remarks, if any

SN Requirements LocoType

Make Of Subassembly

Reference Details Clause/Para/Item Details

Observations

MaterialAvailability

Page 95: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 95/104

Page 95 of 104 Quality Audit of Diesel Loco POH Workshop

7.

Material Availability7.13  Vital Spares

7.14  Must change items

7.15  Consumables like Distilled Water,

Sulphuric Acid (for Lead Acid Battery), Lugs,Rubber Mat etc.

8.

Disposal

8.1 Segregation of Working and Non-Workingequipment and Proper House Keeping

8.2 Safe Disposal of Battery including recyclingfollowing relevant environmental norms.

CHECK SHEET FOR

TECHNICAL AUDIT OF GOVERNOR SECTON (ALCo LOCO) FOR POH WORKSHOPS

Page 96: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 96/104

Page 96 of 104 Quality Audit of Diesel Loco POH Workshop

TECHNICAL AUDIT OF GOVERNOR SECTON (ALCo LOCO) FOR POH WORKSHOPSIN REFERENCE TO POH OF ALCo DIESEL LOCOMOTIVES

During the audit, activities should be checked with regard to the Clause/Para/Item of the reference document as per applicability. Wherever the activities are notperformed correctly, the method adopted should be indicated or the nature of non-compliance should be recorded.

Workshop/Rly: Audited by: Date of audit:

SN Requirements LocoType

Make Of Subassembly

Reference Details Clause/Para/Item Details

Observations

1. Dis Assembly and Assembly  ALCo Maintenancemanual of Woodward 

Section 5 of Maintenance

Manual 2. Measurement :

2.29  Physical Examination

 ALCo

Wood WardGovernor Test

Record Format No.TSP/F8572-828

and Maintenancemanual of Woodward

Section 6 of Maintenance

Manual 

2.30  Barometer Reading

2.31  Pressure Test

2.32  Hydraulic Seals, needle valve seat and buffer piston bypass in both direction2.33  Needle Valve setting

2.34  Speed Setting2.35  Normal Shut Down

2.36  Pressure Requirement2.37  Speed Setting timing

2.38  Lube Oil Shutdown2.39   Air Box Pressure Fuel Limiting

2.40  Load Control2.41  Vane Servo Timing

2.42  Excitation Resistor 2.43  General

2.44  Verification with Cover Installed

3.

Availability Of Tools And Test Stands  ALCo3.56  Test Stand for Wood Ward Governor 

3.57  Multimeter with valid Calibration3.58  Screw Driver, Plier, Allen Key, Spanner,

SN Requirements LocoType

Make Of Subassembly

Reference Details Clause/Para/Item Details

Observations

etc

Page 97: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 97/104

Page 97 of 104 Quality Audit of Diesel Loco POH Workshop

etc.3.59  Fire Extinguisher of proper class

4.

Availability Of Instructions etc.3.48  Display Chart

3.49  Flow Chart3.50  Training of staff 

3.51  Proper Display of Do’s and Don’t 

3.52  Display of Trouble Shooting Chart MaintenanceManual

Section 4

3.53  Maintenance manual and check sheets

3.54  Record keeping of tools and measuringinstruments

3.55  Instruction Bulletin issued by RDSO NA

3.56  Maintenance Manual of Manufacturer 

3.57  Specification NA

5. Compliance of Instruction Bulletin NA

6. Follow of Maintenance Manual of Manufacturer 

7. Record Keeping For Traceability

4.15  Proper Register is maintained for Governor testing with details of Manufacturer’s

Brand Name, Date of Manufacture, Type, Sl. No.,Date of Attending, Repair/Overhauling activitydetails, Loco No. to which fitted.

SN Requirements LocoType

Make Of Subassembly

Reference Details Clause/Para/Item Details

Observations

4 16 Proper record should be maintained for

Page 98: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 98/104

Page 98 of 104 Quality Audit of Diesel Loco POH Workshop

4.16  Proper record should be maintained for each Governor with the measurement of Parameters as in Sl. No.1 prior to Fitment to Locoafter overhauling/maintenance with date andremarks, if any.

8.

Material Availability

7.16  Vital Spares

7.17  Must change items

7.18  Consumables like Lub Oil, Cotton wool,etc.

9.

Disposal

9.1 Segregation of Working and Non-Workingequipment and Proper House Keeping

9.2 Safe Disposal of scrap and waste including

recycling following relevant environmental norms.

Annexure-6 

Check sheet for Quality Audit of Railway Workshop

Page 99: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 99/104

Page 99 of 104 Quality Audit of Diesel Loco POH Workshop

Check sheet for Quality Audit of Railway Workshop

(Underframe/cattle guard/ fuel tank/ loco painting/ cab/ battery box/ superstructure/ CBC/ side buffers)

Sl.N

o.

Activity Clause/ Reference Observations

Underframe

01 Underframe to be kept on trestle at lifting lugs.

02 Proper cleaning & washing of U/F with detergents & water,.

03 Use of manipulator for carrying out repair work by down hand welding.

04 i.  Visual inspection of buffer beam, striker block for any crack or damage,

accordingly repair/weld properly

ii.  Check the buffer base bolt holes for size, centers & ovality. Remove the

ovality by welding and redrill if necessary

05 i.  Check the cattle guard/rail guard by visual inspection, if any crack/ damage

found then it should be repaired/replaced accordingly

ii.  Ensure minimum clearance of cattle guard from R/L to be 178 mm

iii.  Ensure minimum clearance of rail guard from R/L. to be 115 mm

iv.  Modify/ change cattle guard and its support arrangements to plate type on

WDM3A locomotive

RDSO’s Drg. No. 

SK.DL-4533/4535 and

DMW’s Drg. No.

2DMW/SK-938

06 Visual inspection of welding of gussets/ stiffeners in back of buffer beam 

transferring buffing force from buffers to maintain longitudinal box section. If any

crack /damage is found, it shall be repaired accordingly.

07 Visual inspection of Footstep for welding crack/damage and shall be repaired by

welding properly or replaced.

Page 100: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 100/104

Page 100 of 104 Quality Audit of Diesel Loco POH Workshop

08 i.  Visual inspection of welding of Hand rails to underframe. If there is any

crack or damage in weld then reweld it properly.

ii.  All fasteners are used for securing hand rail, clamp, hand rail support should

be properly tighten

09 The coupler pocket shall be examined closely for welding cracks/damage in ribs andinspection of welding with underframe. If any crack or wear is found, shall be

repaired or replaced properly.

10 Visual inspection of welding of ECC mounting stool. If there is any welding

crack/damage then it should be rewelded or replaced properly.

11 i.  If abnormal vibration noted modify compressor mounting area of WDM3D

locomotive under frame

ii.  Visual inspection of welding of expressor/ compressor mounting stool. If 

there is any welding crack/damage then it should be rewelded or replaced

properlyiii.  Clean the threads of mounting block on stool by tapping it properly.

MP.MOD.LD.01.02.11

dated 09.03.2011

12 i.  Visual inspection of welding of engine mounting block. If there is any weld

defect carryout required welding or replace it

ii.  Check/Clean the threads of mounting block by tapping.

13 i.  Inspection of air duct gallery for all traction motors cutout for any leakage

or cracks

ii.  Filling water/hydraulic test in the gallery carried out

iii.  If any leakage is found, shall be repaired accordingly.

14 i.  Visual inspection of battery box below side sill/bottom plate for corrosion &

welding cracks in wear plate, end plates & support plate. If there is any crack

or corrosion then it should be rewelded or replaced it

RDSO’s letter

No.SD.DMG.32 Dated

30 07 1996 and SK DL 4436

Page 101: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 101/104

Page 101 of 104 Quality Audit of Diesel Loco POH Workshop

p

ii.  End plate of battery box with fuel tank end shall be modified as per RDSO

Drg. no. SK.DL-4436.

iii.  Mounting block, nut & bolt should be properly secured and tighten

iv.  Wooden spacer properly placed between the battery

v.  All hinges, locks should be in working

vi.  Cover assly. properly secured & locked with battery box.

30.07.1996 and SK.DL-4436

15 i.  Ensure proper cleaning & washing of fuel tank to remove dirt, sludge

deposited inside the tank.

ii.  Inspection of fuel tank for any leakage or cracks.

iii.  Inspection of drain valve, glow rod and for any crack repair by welding or

replace if found beyond repair.

iv.  Mounting block, nut & bolt should be properly secured and tighten

v.  Fuel gauge should not be broken and in working condition

vi.  Fuel gauge mounting bracket, filler cap, vent pipe should be in good

condition

RDSO’S Investigation

Report No.

MP-473/83 February, 1983

16 Visual inspection of underframe box section and side sill welding. If there is any

crack or damage, weld it properly with low hydrogen welding electrode.

RDSO’S Investigation

Report No.

MP.INV-8

December, 1995

17 i.  Carefully examine the welding around the both center pivots for crack and

also check the surface with magnaflux or die-penetrant method to identify

cracks, if any, which is not visible to naked eyes.

ii.  If any crack is found, weld it properly with down hand welding.

RDSO’Drg. No. 

SK.DL-2069

18 i.  Carefully examine the welding around side load bearers for crack and also

check the surface with magnaflux or die penetrant method to identifycracks, if any, which is not visible to naked eyes.

ii.  side load bearer shall be repaired

RDSO’s spec. No. MP.MI-

140/88, Sep’1988 and 

RDSO’Drg. No. 

SK.DL-2069

19 Loco painting, marking, stenciling;

Apply epoxy primer and PU paint before stenciling

As per extent colour

scheme

Page 102: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 102/104

Page 102 of 104 Quality Audit of Diesel Loco POH Workshop

20 Center buffer coupler & Draft Gear

Check compliance of RDSO instructions for inspection and maintenance

Modify uncoupling arrangement to make it top operated

G-80

MP.MOD.LD.05.10.11

dated 18.07.2011

21 Side Buffers

Check compliance of RDSO instructions for inspection and maintenance

MP.MI-116/82, Rev.02

22 Loco Cab Railway Board’s letter

No.2000/M(L)/466/9 dated

05.01.2005

23.

1

Driver/Pilot seat

i.  Base mounting nut/ bolt and other fasteners should be properly tighten

ii.  Motion and its adjuster/locking arrangement/ Ver. & rotational motion

should be in functioning

iii.  Cushion & upholstery should be in good condition

23.

2

Side sash / window

i.  Sliding glass should freely slide and not cracked

ii.  Locking arrangement properly in fuction

iii.  Guide rail, weather rubber & glazing rubber should be in good condition

iv.  Rear view mirror if applied properly secured with frame and its rotational

movement checked. Mirror should be in good condition

23.

3

Cab door

i.  Lock, hinges should be in function

Page 103: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 103/104

Page 103 of 104 Quality Audit of Diesel Loco POH Workshop

ii.  Glass, weather strip should be in good condition and door properly sealed in

closed condition

iii.  Assistant seat properly secured and in good working condition

iv.  Wiper motors should be in working

23.

4

Cab floor

i.  Flooring mat & trim should be in good conditionii.  Steel structure/ panel sheet of cab should not be corroded or broken

23.

5

Cont. Comp door, short hood door & Cab inner trim

i.  Lock, hinge and weather sealings should be in working condition

ii.  Perforated aluminium sheet , insulating material, fasteners should be in

good condition

23.

6

Cab light and fan

i.  Switches, regulators and connections are properly in function

23.

7

Fire Extinguisher

i.  Mounting bracket should be in good condition and refilling facilities should

be available

23.

8

Air condition (if applied)

i.  Switches, regulator and water drainage properly in function

23.

9

Token pick up arrangement

i.  Token pickup rod properly joint with cab and should be in function (closing

& opening)

ii.  Cushion pad frame properly welded with cab and cushion mat condition

should be good23.

10

Front look out glass

i.  Glass & weather strip should be scratches free and properly sealed with

front structure

ii.  Covering grill glass properly cover with hinged grill

24 Superstructure

i.  Check the condition of sheets and repair if possible otherwise change

Page 104: Quality Audit for Diesel Loco POH Workshop(1)

7/27/2019 Quality Audit for Diesel Loco POH Workshop(1)

http://slidepdf.com/reader/full/quality-audit-for-diesel-loco-poh-workshop1 104/104

ii.  Check hinges and door locks for proper working and repair if possible

otherwise change

iii.  Check for water leakage at various joints and renew weather stripes/ceilings

iv.  Door panel-sheet should not bend and properly close 

25 Radiator compartment & Expansion tank

i. 

Gauge, vent, vacuum valve, low water alarm should function

ii.  Expansion tank plate should not be corroded

iii.  Funnel grating, foot step, hand- rail, inspection door properly secured with

rad. Comp. Structure.