racecourse cogeneration project

19
Racecourse Cogeneration Project John Hodgson, Des Sievers and Bryan Lavarack ISSCT Workshop 2015 1/19

Upload: others

Post on 05-Jan-2022

10 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Racecourse Cogeneration Project

Racecourse Cogeneration Project

John Hodgson, Des Sievers and Bryan Lavarack

ISSCT Workshop – 2015

1/19

Page 2: Racecourse Cogeneration Project

Project Overview

150 t/h HP bagasse boiler and 38 MW cogen plant at Racecourse Mill.

25 MW export supplies 30% of Mackay electricity needs year-round.

Operates 49 weeks each year

Supplies steam and electricity to mill and refinery.

Extended bagasse storage facilities: ~130,000 tonnes bagasse is stored for 13 weeks operation in the non-crush

Coal burned in remaining 14 weeks of the non-crush.

200,000 tpa GHG abatement.

A$120m project was approved in January 2010.

Completed on-time and within budget with commissioning and performance tests completed in March 2013.

Australian Gov 20% RET Power Purchase Agreement 2/19

Page 3: Racecourse Cogeneration Project

Major plant items

Power Plant: 150 t/hr, 80 bar, 525°C steam boiler & de-aerator 38 MW condensing extraction steam turbine generator 80 t/h condenser, cooling tower and pumps Coal plant and moving grate 11kV / 66kV transformer

Auxiliary Plant: New condensate system Improved evaporator steam efficiency measures New control and switchrooms Switchyard and 66kV interconnection (5.5km) Extra bagasse storage facility (45,000 t.

160,000 t. total)

Project Management: Mackay Sugar (AE&E insolvent 11m into 3 year $90m+

contract) MSL took over contract and employed 26 ex-AE&E

people

3/19

Page 4: Racecourse Cogeneration Project

No.2Boiler

Crushing season steam flowsheet

HP Steam

17 bar(g)

HP/LP ID Fans T/As Shredder Mills Misc.

LP Steam

1.5 bar(g)

To 3E & 3W

LP/V1

Vapour System

0.7 bar(g)

Refinery Sugar Mill

PE1A

PE1B

(Old

1E&

1W

MillPans

Pans #1 Mill

Pan

2E&

2W

Melters

No.3Boiler

CogenBoiler

Condensor

LP Reheater

38MW STG

VHP Steam

VHP/IP

IP Steam5 bar(g)

80 bar(g)

Deaerator

COGENERATION

No.2Boiler

LP Steam

1.5 bar(g)

2 bar(g)

Steam Transformer

4/19

Page 5: Racecourse Cogeneration Project

Non-crushing season steam flowsheet

VHP Steam

80 bar(g) Condensor

38MW STG

VHP/IP

IP Steam

5 bar(g) LP Reheater

LP Steam

1.5 bar(g)

2 bar(g)

Vapour System

0.7 bar(g)

Deaerator Steam Transformer

COGENERATION Refinery Sugar Mill

PE1A

Pans #1 Mill

Pan

CogenBoiler

Melters

No.3Boiler

No.2Boiler

5/19

Page 6: Racecourse Cogeneration Project

Innovative project features

High steam pressure / temp maximise generation.

Operates 49 weeks/yr high plant capacity factor & PPA certainty.

Coal firing ensures reliable steam and electricity outputs.

Supplies refinery energy in non-crush full year cogeneration maximises site energy efficiency.

Re-use existing chimney, bagasse plough points and milling building for STG hall to reduce capital costs.

No flue gas airheater; uses large economiser with water pass-out for SA and UGA airheaters, reducing dewpoint corrosion at low load.

Pre-evaporator boils ESJ during the crush, and re-boils refinery condensate during non-crush, segregating quality steam from process.

Two pre-primary juice heaters use final effet vapour to improve efficiency.

Pressurised feedwater system on #3 Boiler for energy and water effic.

Condensate from the STG is pre-heated using factory waste hot water.

6/19

Page 7: Racecourse Cogeneration Project

Feedwater Tank

Feedwater Pumps No2 Switchroom

No2 Transformer

Boiler Controlroom

Roller Lathe

Cogen Boiler STG Hall

7/19

Page 8: Racecourse Cogeneration Project

STG

Polishing Plant

Heater / Effet modifications

Switchroom

Boiler

Power lines to Switchyard

11kV/66kV Transformer

Cooling Tower

Bagasse Pad at Marian

8/19

Page 9: Racecourse Cogeneration Project

Cogeneration Operations

Marian Farleigh

Racecourse @ 500TCH

4.0 MW

Bagasse

130,000 t

0 t

25 MW

Crush

80,000 t 50,000 t

Non-Crush

Coal

25.0 MW – Bagasse (13.0W)

20.0 MW – Coal (peak price)

10.0 MW – Coal (off-peak price)

30,000 t

Racecourse

9/19

Page 10: Racecourse Cogeneration Project

Outputs of the Cogeneration Project

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May

Power plant operates at MCR: • 150 t/h steam at 80 bar to STG • 15 t/h passout at 5 bar • 70 t/h passout at 1.5 bar • 65 t/h to condensor.

Power plant operates at near MCR: • 140 t/h steam at 80 bar to STG • 15 t/h passout at 5 bar • 45 t/h passout at 1.5 bar • 80 t/h to condensor.

Peak elec. price: • 125 t/h steam to STG • 15 t/h passout at 5 bar • 45 t/h passout at 1.5 bar • 65 t/h to condensor.

Off-peak elec. Price • 75 t/h steam to STG • 15 t/h passout at 5 bar • 45 t/h passout at 1.5 bar • 10 t/h to condensor

10/20

Page 11: Racecourse Cogeneration Project

Contractors

143 contracts in total: o 123 Power Plant contracts (novated from AE&E) o 20 Balance-of-plant contracts o 413,000 contractor man-hours worked @ Racecourse o Max site workforce was 180 personnel o 5.5 km Ergon powerline o Site planning crucial for cut-ins: Rac boilers

down for 2 weeks pa. Injuries:

o 1 lost time o 8 medical treatments o 31 first aid

Project spend: o 50.2% Mackay based businesses o 4.3% Other QLD based businesses o 27.1% Other Australian based businesses o 18.4% Overseas businesses 11/19

Page 12: Racecourse Cogeneration Project

Boiler design – 3D model

12/19

Page 13: Racecourse Cogeneration Project

Grate Combustion System: Detroit Stoker, USA

Steam Turbine Generator: Shin Nippon, Japan / Brush, Netherlands

Boiler Fabrication: Suzhou Hailu Heavy Industry, China

Economizer: Greens Power, UK

Hot Water Air Heater: Jord, Australia

Heat Exchangers: GEA, Germany / Daewoo , Korea

Wet Scrubber: Mikropul, Australia

Fan Package: Ebara Hamada, Japan

Pump Package: KSB, Australia

Electrical and I&C Package: ABB, Australia

Control Valves: KSB, Australia

Transformer: ABB, Vietnam

Major power plant sub-contractors

13/19

Page 14: Racecourse Cogeneration Project

Components manufactured worldwide

14/19

Page 15: Racecourse Cogeneration Project

STG rotor – Shin Nippon works

15/19

Page 16: Racecourse Cogeneration Project

20 YEAR DIVERSIFICATION PLAN

Boiler pressure parts – China supply

16/19

Page 17: Racecourse Cogeneration Project

Project site – Before and after

17/19

Page 18: Racecourse Cogeneration Project

Conclusions for a successful project

Cost control: Detailed estimates based on accurate work scopes Re-use existing mill infrastructure where possible Compile detailed specifications (technical and

commercial) Source competitive tenders from competent

contractors, incl o/seas Weekly reviews of cost and progress reports

Program: Initiate connection agreement enquiry well before

project start Detailed program compiled before awarding contracts Include as much float as possible for large supply

items (eg STG) Effective control of multiple site contractors

Best returns: Operate beyond crush (preferably year-round) Fuel: source quality fuel (eg bagasse from nearby

mills) for non-crush Co-locate a process that requires energy year-

round cogeneration Long-term PPA matched to project outputs

18/19

Page 19: Racecourse Cogeneration Project

Acknowledgements

The Senior Executive and Board of Mackay Sugar Limited who supported this project from conceptual stage in 1998 through to commissioning in 2013.

Queensland Government which provided a $9.0m grant

through the Queensland Renewable Energy Fund. Staff from Wilmar Pioneer Mill and NSW Sugar

Milling Cooperative for their advice following large cogeneration projects.

The dedicated MSL in-house Cogen Project Team.

19/19