raftelis report on siemen's contract

Upload: the-kingfish

Post on 01-Jun-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/9/2019 Raftelis Report on Siemen's contract

    1/58

    1031 S. Caldwell Street

    Suite 100

    Charlotte, NC 28203

    Phone 704 . 373 . 1199

    Fax 704 . 373 . 1113

    www.raftelis.com

    February 27, 2015

    Ms. Kishia Powell

    Director, Department of Public Works

    City of Jackson

    200 South President Street

    Jackson, MS 39201

    Re: Phase 1 Final Report – Draft Final

    Dear Ms. Powell:

    The Raftelis Financial Consultants, Inc. (RFC) Project Team (RFC, Intel Business Solutions, and SOL

    Engineering Services, LLC; and together, the Project Team) has completed our initial engagement for the

    City of Jackson (City). The initial engagement evolved to include the following tasks.

    • Task 1 – Strategic Financial Planning

    • Task 2 – Revenue Sufficiency Analysis

    • Task 3 – Billing System Data Review

    • Task 4 – Siemens Contract Review

    • Task 5 – Infrastructure Master Plan Development

    Task 6 – Additional Efforts

    We have accomplished the objectives outlined in our scope of work and have assisted on a number of 

    additional issues that have arisen during our engagement. The attached report, which consists of an

    Executive Summary and four technical memoranda, summarizes our work and findings for the various

    tasks.

    We have appreciated the opportunity to work with you and your staff. As noted in the report, there are

    a number of tasks that still need to be undertaken, and we hope to have an opportunity to continue to

    work for the City and with you and your staff. Should you have any questions regarding the report,

    please contact me at (704) 936-4433.

    Sincerely,

    Peiffer A. Brandt

    Chief Operating Officer

  • 8/9/2019 Raftelis Report on Siemen's contract

    2/58

    Draft Final ES-1

    EXECUTIVE SUMMARY

    The City of Jackson (City) engaged a project team led by Raftelis Financial Consultants, Inc. (RFC) and

    including Intel Business Solutions (IBS) and SOL Engineering (together, the RFC Project Team) to provide

    assistance with various financial and management issues which the City currently faces. There were six

    tasks included in the engagement. As the project progressed, the scope within certain tasks evolved

    from what was originally contemplated. For example, the two tasks related to the Siemens contract

    were combined into a single task. There was also an Additional Task, which included three subtasks

    associated with issues that arose during the engagement, and was incorporated accordingly. A

    summary of each task is provided below.

    TASK 1 –STRATEGIC FINANCIAL PLANNING

    The Project Team participated in two strategy sessions with City of Jackson leadership. Based on these

    sessions, we identified 37 tasks the City needs to undertake to enhance the financial and management

    sustainability of its Department of Public Works (DPW). A few of these tasks were included in the initialscope of work. We prioritized all the tasks, categorizing them as requiring attention 1) within six

    months; 2) in six months to a year; or 3) in a year plus. Of the 37 issues identified, 21 were categorized

    as needing attention within six months. We prepared a brief technical memorandum (Technical

    Memorandum 1 or TM1) summarizing our findings, which is part of this report. In addition, an Excel file

    with the matrix of prioritized tasks has been provided to DPW. We anticipate this matrix being an

    evergreen document of the City’s, with it being updated as new issues for DPW arise.

    TASK 2 – REVENUE SUFFICIENCY ANALYSIS

    The Project Team developed a financial plan for the water and sewer system. Even though the City wasable to provide most of the data needed, there were certain data that could not be provided so the

    Project Team developed assumptions as necessary. The financial plan indicates that with the current

    rates the City will just achieve necessary coverage in FY 2015 based on the assumptions made by the

    Project Team. In future years, the City’s revenues will not be sufficient to meet the necessary debt

    service coverage. The chart on the following page shows the revenue sufficiency challenge faced by the

    water and sewer system.

    The Project Team provided an overview of the financial planning model via a webinar for City staff. The

    financial planning model, which is a deliverable of the task, can be used to evaluate different capital

    plans, rate structures, levels of operating expenses, etc. Technical Memorandum 2, which is part of this

    report, summarizes the financial results and the associated assumptions.

    There is significant uncertainly regarding the level of metered consumption and magnitude of capital

    and operating costs going forward for the water and sewer system. The City needs to refine the

    assumptions used in the financial planning model as better information becomes available. Given the

    size of the revenue shortfall in the out years, the City will need to restructure and may need to raise its

    water and sewer rates, so the City should begin focusing on rate planning and structuring.

  • 8/9/2019 Raftelis Report on Siemen's contract

    3/58

    Draft Final ES-2

    Exhibit 1: Expenses versus Current Revenues

    TASK 3 – BILLING SYSTEM DATA REVIEW

    The Project Team completed an initial billing system data review. This effort commenced in late

    October with data acquisition and was carried out through a series of independent large-scale billing

    data reviews, interviews with Information Services and Customer Service staff, and on-site account-level

    data forensics. We first compiled historical data on consumption, billings, collections, and

    customers/accounts to reconcile the billing database logs with those numbers being reported to and

    used by the City. Then we turned our attention to the active metering, billing, and collections data

    stored in the legacy billing database.

    The Project Team identified one major systemic issue, the misapplication of the minimum sewer charge,

    and several inconsistencies between billing policy and data within the billing system. These included a

    variety of accounts registering consumption but not being billed, exempted accounts, and vacant

    accounts registering consumption. In an effort to review the advance metering infrastructure (AMI)

    meter installation results, the Project Team also identified new AMI meters that were stuck at or near

    zero, or were reading above a reasonable threshold. There were also large and frequent adjustments to

    accounts, as well as accounts with very old accounts receivable that raised potential concerns. For each

    of the ten categories of perceived inconsistencies or potential concerns, the Project Team developed a

    sample of accounts for detailed review within the database’s production environment.

  • 8/9/2019 Raftelis Report on Siemen's contract

    4/58

    Draft Final ES-3

    Project Team members participated in three on-site sessions to conduct detailed account-level review

    and to gain a more complete understanding of existing processes. In addition to verification of potential

    policy misapplication, the Project Team found many data quality concerns to be related to non-standard

    practices and procedures around account adjustments, estimated reads, account exemptions, and

    enforcement standards.

    Overall, the goal of this task was to identify the current revenue problems based on the symptoms

    found through the data analysis and detailed on-site analysis. Based on our efforts to date, we have

    grouped the issues identified within three classifications:

    1. Unbilled Revenues – many accounts continue to receive services and are not timely or

    routinely billed, primarily due to untimely meter shut-offs and significant water theft issue.

    2. Ghost Revenues – many accounts fail threshold exception edits primarily due to meter reading

    errors resulting in large and frequent adjustments.

    3. Uncollected Revenues – many accounts are delinquent and have significant accounts

    receivable balances. However, the city does not have an active/proactive collections process.

    Going forward, the City will need assistance in remedying the problems identified. The Project Team

    recommends implementing a series of improved standard operating procedures and oversight

    procedures for common business practices such as calculating and applying adjustments, logging and

    verifying work orders, and collections best practices. Additionally, the Project Team recommends that

    the conversion to the new CC&B billing system include measures to verify that potential process-driven

    failures identified within the existing system are not propagated into the new system. Testing for

    conversion has begun and processes for flagging or remedying these exceptions should be included in

    this exercise.

    TASK 4 –SIEMENS CONTRACT REVIEW

    The Project Team completed an in depth review of the City’s contract with Siemens and prepared a

    technical memorandum (TM4) that summarizes the key terms of the contract and provides details

    regarding the “guaranteed savings” that Siemens maintains will be realized by the City as a result of 

    work that Siemens performed under the contract. As pointed out in TM4, the majority of savings are

    stipulated, which means they are assumed to occur. Since these savings are assumed to occur, the

    contract does not identify a protocol for testing to determine if the savings are realized. The table and

    chart below show the level of stipulated savings in Annual Period 2. There is a unique amount of 

    Guaranteed Savings for each annual period. We chose to show Annual Period 2 because it represents

    the first year of full savings. As can be seen, the stipulated savings are 65% of the total savings. The

    technical memorandum also touches on the actions that must be taken by the City in order to maximize

    the benefits offered by the Siemens contract.

  • 8/9/2019 Raftelis Report on Siemen's contract

    5/58

    Draft Final ES-4

    Exhibit 2: Savings from Annual Period 2

    Once Siemens completes the projects it is performing under the contract, the City will have a state of 

    the art water metering system and a new customer service/billing system (Oracle CC&B) with additional

    capabilities. These two systems are the key drivers of the increased revenue and savings that Siemens

    has promised to the City. However, as discussed in TM4, the City must first ensure that the meters and

    billing system are properly installed and configured. Second, the City must also implement changes in

    its metering and billing processes.

    To ensure the City gets the greatest value from the contract, the City needs to enhance its oversight of 

    the Siemens contract. In addition, the City should quantify any unexpected costs or lost revenue

    associated with the Siemens’ team performance under the contract.

    TASK 5 – INFRASTRUCTURE MASTER PLAN DEVELOPMENT

    The primary objective under this task was the development of the year 1 capital improvement plan (CIP)

    for projects that may be funded using receipts from the Infrastructure Tax. The CIP must be approved

    by the Commission before any of the funds from the Infrastructure Tax are utilized on projects. The

    Project Team reviewed existing master plans for each of the utilities/assets (water, sewer, drainage,

    streets, and bridges). Unfortunately, the City does not have recent CIPs for each utility/asset group. The

    Project Team worked with City staff to prepare a draft CIP and revise the draft after comments provided

    by City staff. Originally, the City was going to take the lead on this analysis, but due to limited staff 

    resources and time constraints, the Project Team led the effort to prepare the CIP that was presented to

    the Commission in January.

  • 8/9/2019 Raftelis Report on Siemen's contract

    6/58

    Draft Final ES-5

    Another component of the task was to understand the policies and procedures associated with the

    revenue from the Infrastructure Tax. The Project Team met with the City’s Finance Department staff 

    and discussed the Infrastructure Tax. As part of this discussion, we contacted the State to gain a better

    understanding of the components of the Infrastructure Tax.

    TASK 6 – ADDITIONAL EFFORTS

    Following the initiation of the project, the City requested the Project Team to undertake three additional

    tasks.

    • Moody’s Rating Evaluation Support – Moody’s, who has rated the City’s debt in the past,

    requested an opportunity to update its ratings on the outstanding debt. As the process

    unfolded, the City asked the Project Team to help as possible because the City does not

    currently have a Financial Advisor. This assistance involved compiling and reviewing data

    requested by Moody’s, participating in internal calls and calls with Moody’s to discuss the

    situation in Jackson and the data provided, and reviewing the ratings report and helping to crafta press release.

    • Capital Funding Options Analysis – The City has significant capital needs. In order to maximize

    the capital projects undertaken, the City needs to understand various capital funding options.

    The Project Team provided a comprehensive overview of potential options available along with

    some commentary as to the relevance to the City.

    • Green Infrastructure Challenge Assistance – The Infrastructure Tax is going to provide revenue

    for needed drainage projects. The City is interested in a mixture of green and gray solutions to

    overcome drainage challenges. In an effort to leverage resources and better understand the

    potential capability of green infrastructure applications to solve drainage issues, the City would

    like to undertake a Green Infrastructure Challenge. This task involved attending meetings

    related to the Challenge and producing materials, such as flyers, to publicize the Challenge.

  • 8/9/2019 Raftelis Report on Siemen's contract

    7/58

    Draft Final TM1-1

    Technical Memorandum #1

    Strategic Planning Issues

    The Strategic Planning task was the initial task of the Project Team’s engagement to provide financial

    and management consulting to the City of Jackson (City). As part of this task, members of the Project

    Team participated in multiple strategy meetings and discussions with key City staff, which aresummarized in this technical memorandum. During the initial meetings, the City staff and Project Team

    members brainstormed about the various challenges facing the City. Primarily, the Project Team

    listened as City staff enumerated various issues. The results of these brainstorming sessions were

    captured and the Project Team aggregated issues as appropriate. Ultimately, we identified 37 issues.

    These issues were categorized into the following five groups.

    1. Financial Management

    2. Human Resources

    3. Infrastructure Investment/CIP

    4. Regulatory/Compliance5. Service

    After categorizing the issues, the Service category had the most issues (14), followed closely by Financial

    Management (13).

    The next step was to prioritize the issues. In particular, issues were grouped as needing focus 1) within

    the next six months, 2) in six to twelve months, or 3) outside of a year. The initial prioritization was

    based on the potential impact of the issue. There were 21 issues that were prioritized in the “within the

    next six months” grouping. Some issues received multiple prioritizations. The reason for multiple

    prioritizations for certain issues was the RFC Project Team believed the City needs to take some steps

    associated with the issue immediately and some steps at a later date. A good example are two of the

    Service issues related to Communications. Public outreach, for example, needs to occur to some extent

    in the near term and the City should develop a long-term approach to public outreach regarding Public

    Works issues. As the City’s situation evolves, it is likely that the prioritization may need to be modified.

    The Project Team also identified additional information that should be included in the matrix over time.

    The City should determine the fiscal impact of addressing the issue, both the direct cost of addressing it

    and the potential impact from it being addressed. For example, the fiscal impact of providing refunds to

    customers outside of the City includes the cost of calculating and dispensing the refunds and the total

    amount of the refunds. The City should also identify the person on City staff that is responsible for

    overseeing the issue (“City Staff Lead”). Being the lead for the issue does not mean that person has todo all the work resolving the issue, but that the person provides the oversight for the resolution of the

    issue and has authority consistent with the responsibility. Thirdly, the City should identify the key

    stakeholders for each issue.

    The matrix is an Excel file that was originally developed in November and has been updated from time

    to time. The worksheets from the current matrix are attached to this technical memorandum. The

  • 8/9/2019 Raftelis Report on Siemen's contract

    8/58

    Draft Final TM1-2

    Project Team recommends that the Excel file remain a living document for the Public Works

    Department. Undoubtedly, additional issues will arise and should be added to the matrix.

  • 8/9/2019 Raftelis Report on Siemen's contract

    9/58

    Category Sub-Category Issue Description

    0 - 6

    months

    6 -12

    months

    > 12

    months Fiscal Impact Status

    Key Stakeholders

    Involved

    Assgned Cty

    S taf f l ead N ot es

    Regulatory/

    Compliance Compliance

    Address storm water permit

    requirements X

    Cost of effort (staff and possibly

    consultant time) and potentially

    higher expenses DPW staff, MDEQ  

    Next permit renewal is in 2017. Addressing

    this might hinge on determining in-house

    resource that will coordinate. In addition,

    this can be addressed by Program

    Managers funded through the

    Infrastructure Master Plan.

    Regulatory/

    Compliance Compliance

    Address consent decree

    requirements X

    Cost of effort (staff and consultant

    time) and potentially higher capital

    costs

    DPW staff, MDEQ,

    Program Manager

    Addressing this might hinge on determining

    in-house resource that will coordinate. In

    addition, this can be addressed by Program

    Managers funded through the

    Infrastructure Master Plan.

    Financial

    Management

    Contract

    Management

    Need to ensure contract compliance

    and vendor invoice accuracy and

    appropriateness X X X

    Cost of effort (staff and consultant

    time), but potentially offset by

    reduced contracting costs

    Identify universe of contracts that shouldbe assessed. Need to set a limit as to how

    large a contract needs to be to focus on it.

    All large contracts (such as Siemens, United

    Water etc.) should be addressed short

    term. Other major contracts can be

    addressed mid to long term.

    Financial

    Management

    Financial

    Operations

    Infrastructure Sales Tax Analysis -

    policy, accounting and administration

    is weak or lacking X Ongoing

    RFC team and DPW

    staff 

    Included in current scope of work with RFC

    team - see executed scope for details of 

    what will be addressed

    Financial

    Management

    Financial

    Operations

    Billing Issues - need to determine

    cause of significant under collection

    relative to estimates X

    Cost of effort (staff and consultant

    time), but potentially offset by

    higher revenues Ongoing

    RFC team and DPW

    staff 

    Included in current scope of work with RFC

    team - see executed scope for details of 

    what will be addressed

    Financial

    Management

    Financial

    Operations

    Need to identify alternative revenue

    sources to ensure no obvious

    revenue gaps and to optimize

    revenue collections X X

    Cost of effort (staff and consultant

    time), but potentially offset by

    higher revenues

    Partially

    ongoing

    RFC team and DPW

    staff 

    The optimization of revenue collections is

    part of the objective of the data review that

    is ongoing. Identifying and evaluating

    alternative revenue sources should be a

    focus later once things settle down a bit.

    Financial

    Management

    Financial

    Operations

    Ensure compliance with bond

    requirements, specifically revenue

    sufficiency X Ongoing

    RFC team and DPW

    staff 

    Included in current scope of work with RFC

    team - see executed scope for details of 

    what will be addressed

    Financial

    Management

    Financial

    Operations

    Refunds to customers outside

    Jackson X

    Cost of effort (staff and consultant

    time) and cost of refunds; amount

    of refunds to be determined Amendment 2

    City needs to determine refunds to those

    customers charged at a higher rate than

    allowed by MS PSC; also need to determine

    process for "paying" refunds.

    Financial

    Management

    Financial

    Operations

    Significant Water losses - approx.

    40% X X

    Cost of effort (staff and consultant

    time) and cost of implementing

    measures to reduce water loss;

    may result in lower operating

    expenses in the future

    Consider conducting a water loss audit to

    verify and measure magnitude of water loss

    in the short-term. The audit provides the

    benchmark and then allows the City to

    determine progress towards improvement.

    Activities that will result in reductions of 

    water loss typically hinge on

    billing/metering (passive losses), upgrades

    to linear assets or response time to water

    main breaks. These strategies are typically

    implemented in long term window.

    Draft Final TM1-A1

  • 8/9/2019 Raftelis Report on Siemen's contract

    10/58

    Category Sub-Category Issue Description

    0 - 6

    months

    6 -12

    months

    > 12

    months Fiscal Impact Status

    Key Stakeholders

    Involved

    Assgned Cty

    S taf f l ead N ot es

    Financial

    Management

    Financial

    Operations

    Grants/City Contributions/Indirect

    Cost Allocations - Need to

    understand all non arms length

    transactions with the city and other

    city agencies to ensure no

    revenue/expense gaps X

    The current flow of money between the

    City, DPW and the water/sewer enterprise

    funds needs to be identified; an

    appropriate process needs to be developed

    and documented.

    Financial

    Management

    Financial

    Operati ons Opt imize debt s tructure X

    Cost of effort (staff and consultant

    time), but potentially offset by

    reduced debt service

    FA, City staff, RFC

    team

    Evaluate current debt service structure and

    discuss challenges/opportunities for future

    debt structuring

    Financial

    Management

    Operating

    Efficiency

    Need better handle on payroll costs -

    OT and benefits; headcount; pay

    rates, etc. X

    Cost of effort (staff and consultant

    time), but potentially offset by

    reduced operating expenses

    Since labor costs are the biggest

    component of operating expenses, DPW

    needs to get a better handle on its payroll

    costs.

    Financial

    Management Policies

    Review current accounting practice

    that comingles operating and capital

    costs. Implement change where

    appropriate that ensures separation

    of capital and operating costs. X

    Cost of effort (staff and consultant

    time)

    The City needs to establish guidelines for

    capital versus operating costs

    Financial

    Management Policies

    Inadequate financial and budget

    policies - Need to document/update

    where appropriate X

    The City needs to identify and document

    key financial policies to guide future

    budgeting and ratemaking.

    Human Resources Morale

    Identify and implement efforts to

    enhance employee morale X X X

    Cost of effort (staff time and

    materials) DPW Staff  

    Happy workers are more productive so

    DPW needs to focus on employee morale

    Human Resources

    Operating

    Efficiency

    Assess organizational structure to

    ensure optimized organizational

    outcomes X X

    Cost of effort (staff and possibly

    consultant time), but potentially

    lower expenses

    Need to address key position vacancies

    within the dept. There is a short-term need

    to fill some key vacancies, but a broader

    reorganization should be undertaken once

    things have settled a bit.

    Human Resources

    Recruitment and

    Retention

    Need to be able to recruit and retain

    high-quality staff  X

    Cost of effort (staff time and

    materials) DPW Staff  

    DPW should have a recruiting plan. Once

    good employees are found, it is much less

    expensive to keep them than to find new

    ones, so retention efforts are critical.

    Human Resources Staffing

    Need to identify the level of staffing

    necessary to meet the required

    service levels and to define the

    qualifications for this staff  X DPW Staff 

    With out adequate staffing levels and

    capable employees filling those roles, the

    City will not be able to maintain

    improvements.

    Human Resources Training

    Need to develop a comprehensive

    training program for DPW staff  X

    Cost of effort (staff time and

    materials), but hopefully lower

    operating expenses with a more

    efficient workforce DPW Staff  

    In order to have and retain high quality

    staff, DPW will need to identify and offer

    training opportunities

    Infrastructure

    Investment/CIP

    Operating

    Efficiency

    Need to ensure technology is

    optimally leveraged X

    Cost of effort (staff and possibly

    consultant time), but potentially

    lower expenses

    It may be possible for technological

    enhancements to ultimately reduce

    operating costs. Potential upgrades should

    be identified and evaluated in the mid to

    long term.

    Draft Final TM1-A2

  • 8/9/2019 Raftelis Report on Siemen's contract

    11/58

    Category Sub-Category Issue Description

    0 - 6

    months

    6 -12

    months

    > 12

    months Fiscal Impact Status

    Key Stakeholders

    Involved

    Assgned Cty

    S taf f l ead N ot es

    Infrastructure

    Investment/CIP Capital Program

    Need to finalize Infrastructure Master

    Plan, including: Service areas; Needs

    and Costs; time frame (phase one is

    only 1st year plan ; prioritization

    (critical, availability of funding;

    mayors demo projects etc.) X Ongoing

    RFC team and DPW

    staff 

    Included in current scope of work with RFC

    team - see executed scope for details of 

    what will be addressed. This task is

    essential for overall financial picture and

    need to be primary priority. Phase 1 will

    address immediate needs, including

    creating funding for PMs.

    Infrastructure

    Investment/CIP Capital Program

    Need to finalize Infrastructure Master

    Plan, including: Service areas; Needs

    and Costs; time frame ( 2 - 5 year

    plan in phase two); prioritization

    (critical, availability of funding;

    mayors demo projects etc.) X

    Cost of effort (staff and consultant

    time); CIP funding approaches will

    determine ultimate cost Amendment 2

    Would be addressed by Program Managers,

    once brought on board. Key component of 

    the year 1 Infrastructure Master Plan is

    getting a PM on board.

    Service Communication

    Public Outreach - need to develop

    program to effectively communicate

    rates and impacts X X X

    Cost of effort (staff and consultant

    time); level of cost is a function of 

    level of outreach

    Challenge is this needs to happen ASAP, but

    it is not included in the RFC team scope.

    The long range financial plan needs to be

    developed before fully implementing as we

    need to know what to communicate.

    However, in the short term, some general

    good practice communication tasks could

    be undertaken to start to build goodwill

    with customers and stakeholders.

    Service Communication

    Multiple stakeholders appear to want

    to wrestle control from DPW - need

    to identify, understand and respond

    timely and effectively to various

    Stakeholder Interests X X X

    Cost of effort (staff and consultant

    time); level of cost is a function of 

    level of stakeholder interaction

    Goal should be to identify who the

    stakeholders are and a plan for engaging

    each one. It may make sense to engage

    them together or we may want to engage

    some separately. In the short term, we

    need to identify the stakeholders and their

    issues. Mid term and long term activities

    can then be developed to address them, if 

    they are not already on this list.

    Service

    Contract

    Management

    Need to assess and ensure contract

    performance X X X

    Cost of effort (staff and consultant

    time), but potentially offset by

    reduced operating expenses

    Identify universe of contracts that should

    be assessed. Need to set a limit as to how

    large a contract needs to be to focus on it.

    All large contracts (such as Siemens, United

    Water etc.) should be addressed short

    term. Other major contracts can be

    addressed mid to long term.

    Service

    Contract

    Operations

    Siemens - WW facilities; contracted

    operations - ensure oversight X

    Cost of effort (staff and consultant

    time), but potentially offset by

    reduced operati ng expenses Ongoi ng

    RFC team and DPW

    staff 

    Included in current scope of work with RFC

    team - see executed scope for details of 

    what will be addressed

    Service

    Contract

    Operations

    United Water contract (contracted

    WWT operator) - ensure oversight X

    Cost of effort (staff and consultant

    time), but potentially offset by

    reduced operating expenses

    Initial thinking was the City needs to best

    manage contract until it ends in about a

    year, at which time the City would put

    contract out to bid. However, it appears

    that new and pressing issues related to

    contract may require more immediate

    action.

    Draft Final TM1-A3

  • 8/9/2019 Raftelis Report on Siemen's contract

    12/58

    Category Sub-Category Issue Description

    0 - 6

    months

    6 -12

    months

    > 12

    months Fiscal Impact Status

    Key Stakeholders

    Involved

    Assgned Cty

    S taf f l ead N ot es

    Service

    Contract

    Operations

    Siemens - Operating plan post

    Siemens X Ongoing

    RFC team and DPW

    staff 

    Included in current scope of work with RFC

    team - see executed scope for details of 

    what will be addressed

    Service

    Operating

    Efficiency

    Need to ensure cost of Production is

    in line with industry- treatment,

    collection, distribution (chemicals,

    electricity, people) X

    Cost of effort (staff and consultant

    time), but potentially offset by

    reduced operating expenses

    Chemicals and electricity are typically the

    largest costs behind labor, so these costs

    need to be evaluated. One option is to

    benchmark production costs with those of 

    peer utilities.

    Service Policies

    Ensure key operating policies and

    procedures are in place X

    Cost of effort (staff and consultant

    time), but potentially offset by

    reduced operating expenses

    DPW should develop operating policies to

    help minimize operating expenses.

    Service Service Levels Define appropriate level of service X

    Cost of effort (staff and possiblyconsultant time) and potentially

    higher expenses to meet

    appropriate service levels

    DPW Staff and City

    Council

    DPW should move towards budgetingbased on level of service. In order to do

    this, it is necessary to establish the level of 

    service the community desires.

    Service

    Wholesale

    Agreements

    Issues with agreement - West Rankin

    Utility Authority (WRUA); need to

    address United Water audit issue X

    Cost of discussions (staff and

    consultant time) and potentially

    refunds and less future revenue Ongoing

    RFC Team, DPW

    Staff, and WRUA

    Review audit performed by WRUA and

    determine what needs to be done to

    address the issues and the potential impact

    on the City

    Financial

    Management

    Wholesale

    Agreements

    Potential issue with rates currently

    assessed to utilities outside city limit X

    Cost of discussions (staff and

    possibly consultant time) and

    potentially less revenue

    DPW staff and

    Wholesale

    Customers

    There appear to be a number of issues

    between the City and its wholesale

    customers. The first issue that should be

    evaluated is the rate issue.

    Service

    Wholesale

    Agreements

    Issues with agreement - City of 

    Ridgeland X

    Cost of discussions (staff and

    possibly consultant time) and

    potentially less revenue or higher

    expenses

    DPW staff and City

    of Ridgeland

    Identifying the issues may be short to mid

    term, but typical strategies to address

    would probably be long term

    Service

    Wholesale

    Agreements

    Issues with agreement - Madison

    County X

    Cost of discussions (staff and

    possibly consultant time) and

    potentially less revenue or higher

    expenses

    DPW staff and

    Madison County

    Identifying the issues may be short to mid

    term, but typical strategies to address

    would probably be long term

    Service

    Wholesale

    Agreements Issues with agreement - Hinds County X

    Cost of discussions (staff and

    possibly consultant time) and

    potentially less revenue or higher

    expenses

    DPW staff and

    Hinds County

    Identifying the issues may be short to mid

    term, but typical strategies to address

    would probably be long term

    Service

    Wholesale

    Agreements Issues with agreement - City of Byram X

    Cost of discussions (staff and

    possibly consultant time) and

    potentially less revenue or higher

    expenses

    DPW staff and City

    of Byram

    Identifying the issues may be short to mid

    term, but typical strategies to address

    would probably be long term

    Draft Final TM1-A4

  • 8/9/2019 Raftelis Report on Siemen's contract

    13/58

    Draft Final TM2-1

    Technical Memorandum #2

    Revenue Sufficiency Analysis

    The purpose of the Revenue Sufficiency Analysis was for the Project Team to develop a financial

    planning model for the City of Jackson’s (City) water and sewer system (System) which could be used 1)

    to evaluate the System’s ability to meet debt service coverage under current assumptions and 2) to

    address the System’s potential inability to meet debt service coverage in the future. The analysis was

    required because the City did not meet its fiscal year (FY) 2013 rate covenant obligations associated with

    the issuance of revenue bonds. The revenue sufficiency analysis also addressed the deficiencies noted

    by Moody’s in their recent (November 2014) downgrade of the City’s bond rating, which were as

    follows:

    • Inability to meet debt service coverage requirements in FY 2013;

    • Undeveloped financial plan;

    • Declining unrestricted cash;

    • Limited rate raising history; and

    • Sizable consent decree which requires additional debt leveraging.

    BACKGROUND

    In 2013, the City issued revenue bonds (FY 2013 Bonds) for approximately $91 million to cover projects

    to be performed by Siemens Industry under a performance contract, specifically for the implementation

    of advanced meter infrastructure (AMI), improvements to the O.B. Curtis and J.H. Fewell water

    treatment plants, and replacement of several major sewer collection lines. At the time the FY 2013

    bonds were issued, it was projected that the City would be able to meet the obligations of the FY 2013

    revenues bonds through operational savings and revenue enhancements stipulated by the performance

    contract (totaling approximately $7.8 million per year once all the projects were finished and

    operational) combined with moderate water and sewer rate increases. However, due to various

    circumstances, as explained later in this memorandum, the City was unable to meet the obligations of 

    the FY 2013 bonds.

    STUDY APPROACH

    In order to provide a current financial picture of the Water and Sewer System, the City engaged the

    Project Team in the fall of 2014 to develop a comprehensive revenue sufficiency study. To begin the

    study, the Project Team requested and the City provided the following information:

    • FY 2015 detailed operating budgets for both the water and sewer utilities;

    • Historic data on operating expenses and revenues;

    • Detailed amortization schedules for all outstanding debt including, revenue bonds, general

    obligation bonds (GO), state revolving fund (SRF) loans, Mississippi Development Authority

    (MDA) loans, and capital leases;

    • Comprehensive annual financial reports;

  • 8/9/2019 Raftelis Report on Siemen's contract

    14/58

    Draft Final TM2-2

    • Official statements regarding bond issues;

    • Historic customer information including number of customers by location and billable water and

    sewer flow;

    • Historic data on adjustments to billable water to determine collection rates;

    • Overall consent decree project costs;

    • Capital improvement plan for FY 2015; and• Infrastructure sales tax revenue available to be applied towards the System’s anticipated capital

    improvement plan.

    The Project Team reviewed this data in detail and developed a financial planning model using the

    information obtained above. The Project Team has solicited additional information and clarification of 

    information from City staff several times throughout the development of the financial planning model.

    RFC also made several assumptions, as explained later in this memorandum that impact the Revenue

    Sufficiency Analysis.

    Study Assumptions and Results

    The Project Team projected the annual cash needs (revenue requirements) of the system for FY 2015

    through FY 2020 and compared these costs to the projected revenues under existing rates. RFC also

    calculated the debt service coverage ratios in each year to determine if the existing rates are sufficient

    to meet the debt service coverage requirements. The assumptions used in projecting the annual

    revenue requirements, revenues, and debt service coverage are explained below.

    Revenue Requirements Assumptions

    The Project Team identified the System’s annual cash needs, or revenue requirements, which include

    operations and maintenance (O&M) expenses, existing and proposed debt service, and cash-fundedcapital projects, which are explained below:

    • The detailed FY 2015 O&M budget was used to project future O&M expenses as follows:

    Most line items were escalated by 3% based on input from City staff regarding

    anticipated future costs.

    The Department of Public Works is conducting a salary study to determine the impact of 

    minimum wage rates. Because this study was not finalized as of the date of this

    memorandum, the Project Team has assumed personnel costs will increase by 10% in FY

    2016.

    In order for the City to provide the desired level of water and sewer service to its

    customers, the City will incur additional O&M costs to eliminate water loss, address

    reliability issues, and reduce the volume of leaks and breaks. Therefore, the Project

    Team assumed O&M costs would increase by $250,000 in FY 2016 for water and for

    sewer and then an additional $250,000 in FY 2017 and beyond (totaling $500,000 each

    for water and sewer by FY 2017) which represent increased operating and maintenance

    costs.

  • 8/9/2019 Raftelis Report on Siemen's contract

    15/58

    Draft Final TM2-3

    It should be noted that RFC has not assumed any operational savings from the Siemens

    performance contract in its forecast. (See explanation provided later in this

    memorandum).

    • Debt service schedules were used to identify the total annual debt service to be paid in FY 2015

     – FY 2020.

    • Because the Public Works Department is currently developing a five-year capital program, theProject Team had to estimate the capital improvement plan (CIP) and the funding sources as

    follows:

    The Project Team used the overall consent decree ($400 million over 17 years) to

    estimate a level of sewer projects ($23.5 million per year).

    The Project Team used the recently developed CIP for FY 2015 in which it identified

    approximately $8 million in water projects. This amount was assumed to continue into

    the future but will more than likely increase as the City addresses water loss issues,

    reliability issues, and leaks and breaks.

    RFC determined funding sources, which are estimates until the City engages a Financial

    Advisor. The funding sources include a portion of the Infrastructure Sales Tax, GOBonds, Mississippi Development Loans (MDA), and State Revolving Fund Loans (SRF). It

    should be noted the City does not believe that SRF Funds will be available until future

    years (FY 2019 – 2020).

    The City currently does not have an internal target regarding the level of the CIP that

    should be cash funded versus debt funded. Cash funding a portion of the CIP allows for

    stronger debt service coverage. RFC is recommending an internal target of cash

     financing 15% of the CIP by FY 2020, which is incorporated into the study results.

    Revenue Assumptions

    The Project Team estimated annual revenues including revenues from retail customers, wholesale

    customers, and miscellaneous services, as follows:

    • To estimate revenues from retail customers, RFC obtained detailed customer billing

    information for the past two years on each customer. However, due to the large discrepancy

    between the City’s billable data and the amount of money that is actually received, RFC had to

    use data on actual revenues to back into billable flow estimates. The City also provided RFC

    with information on the total dollar amount of adjustments given in each year. RFC used this

    information to estimate the City’s amount of billable flow and then the percent of uncollected

    revenues (approximately 12%). RFC has assumed that the amount of uncollected revenues will

    improve over the next few years as adjustments resulting from the meter change-out and

    other reasons decrease, as the City begins to enforce cutting-off customers for non-payment,

    etc. It is assumed that the City will achieve an uncollectable rate of 5% by FY 2020. (The

    industry average is 1%). For now, RFC has assumed that there will not be an increase in billable

    flow resulting from the Siemens performance contract (improved meter accuracy), nor has RFC

    assumed any increase in the number of water/sewer customers or growth in water/sewer

    flow. The industry trend is declining per capita consumption, which has been assumed to

    offset any increase from enhanced meter accuracy. Even though we believe this is a

  • 8/9/2019 Raftelis Report on Siemen's contract

    16/58

    Draft Final TM2-4

    conservative assumption, given the financial situation of the System, RFC believes it is prudent

    to make conservative assumptions at this time.

    • RFC estimated revenues from sewer wholesale customers by using the existing methodology of 

    each customer paying a portion of O&M, debt service, and capital costs based on their

    proportion of sewer flow.

    • RFC incorporated miscellaneous revenues from such items as cut-off fees, returned check fees,service connections, interest earnings, etc. and is assuming these revenues will remain

    constant into the future.

    Debt Service Coverage Calculation Assumptions

    The Project Team calculated the debt service coverage for each year in the forecast. The debt service

    coverage calculation is a two-pronged test which is as follows:

    The greater of:

    1) 120% (1.20) of annual debt service on Revenue Bonds +/- rate stabilization, OR

    2) 100% (1.00) of sum of:a) Annual debt service on Revenue bonds and subordinate debt (GO, SRF, MDA,

    capital leases)

    b) amounts to paid during year for Debt Service Reserve System and the

    Contingent System

    c) any other charges or liens payable out of Revenues during the fiscal year not

    otherwise provided in this subsection

    Because of the two-pronged test, “the greater of” results in the debt service coverage requirement

    being 100% of total debt (more than just revenue bonds) plus amounts required to adequately fund the

    Debt Service Reserve System and the Contingent System. The City currently does not have an internal

    target for its debt service coverage ratio. RFC is recommending an internal target of debt service

    coverage of 1.10 of total debt (revenue bonds, GO bonds, SRF loans, MDA loans, and capital leases),

    which is incorporated into the financial planning model.

    Financial Plan Results

    The City will continue to be in a detrimental financial position if current water and sewer rates remain

    unchanged. As shown in Exhibit 1, the current revenues are barely able to meet the revenue and debt

    service coverage requirements of the System in FY 2015 and debt service coverage is compromised in

    future years.

  • 8/9/2019 Raftelis Report on Siemen's contract

    17/58

    Draft Final TM2-5

    Exhibit 1: Expenses versus Current Revenues

    In order to meet the revenue requirements of the water and sewer utility, the City will need to

    implement rate adjustments. However, the level of the rate adjustments will be impacted by the

    following:

    • Level of operational savings identified in the Siemens performance contract that is actually

    achieved.

    • Ability of the City to achieve the revenue enhancements identified in the Siemens performance

    contract resulting from increased meter accuracy.

    • Ability of the City to increase its collection efforts by addressing the number of adjustments

    given to customers, enforcing the cut-off policy, etc.

    • Modifications to the rate structure based on cost of service principles to enhance equity and

    address affordability concerns.

    While the level of rate adjustments will vary based on the factors listed above, the Project Team

    recommends that the City set rates such that the City can achieve sufficient debt service coverage.

    Exhibit 2 shows an example of proposed debt service coverage targets in each fiscal year that would

    allow the City to meet the cash needs of the utility, which include O&M costs, capital costs, and debtservice targets.

  • 8/9/2019 Raftelis Report on Siemen's contract

    18/58

    Draft Final TM2-6

    Exhibit 2: Debt Service Coverage under Existing Rates and Proposed Target

    COMPARISON OF STUDY RESULTS TO ENGINEER’S PROJECTIONS

    As mentioned previously, at the time the FY 2013 bonds were issued, it was projected that the City

    would be able to meet the obligations of the FY 2013 revenues bonds through operational savings and

    revenue enhancements stipulated by the performance contract and moderate rate increases. AppendixJ of the City’s official statement (OS) for the FY 2013 Bonds included a report titled Independent 

    Consulting Engineer’s Report (Engineer’s Report) which summarized the assumptions of the operational

    savings and revenue enhancements, and provided a projection of cash flow for FY 2013 through FY

    2017. The following table is a replication of the table provided in the Engineer’s Report. It should be

    noted these represent 87% of the savings/enhancements to allow for unforeseen events (or 13%

    variability), as explained in the Engineer’s Report. As shown in Exhibit 3, once the projects were fully

    completed and operational, it was estimated that the City would achieve operational savings and

    revenue enhancements of approximately $7.8 million per year.

  • 8/9/2019 Raftelis Report on Siemen's contract

    19/58

    Draft Final TM2-7

    Exhibit 3: Replication from Engineer’s Report

    Timing Event Impact

    End of FY 2013 Most large meters installed (all meters

    to be installed by the end of December

    2013)

    Large meter and deferred

    maintenance savings of $1.5 million

    by the end of FY 2013

    End of FY 2014 All small meters installed (1/2 yearsreduction in deferred maintenance

    expense assumed)

    Large/small meter and deferredmaintenance savings of $3.4 million

    in FY 2014

    End of FY 2015 All meters installed (full year of 

    deferred maintenance expenses

    assumed)

    Large/small meter and deferred

    maintenance savings of $5.6 million

    in FY 2015

    End of FY 2016 System upgrades complete (full year of 

    deferred maintenance and operations

    expense assumed)

    Large/small meter and deferred

    maintenance and operational savings

    of $7.7 million in FY 2016

    End of FY 2017 Fully operational system Large/small meter and deferred

    maintenance and operational savings

    of $7.8 million in FY 2017

    Exhibit 3 shows the anticipated timing and the magnitude of the operational savings and revenue

    enhancements. In addition to these assumptions, the cash flow analysis in the Engineer’s Report also

    assumed the following:

    • Debt service coverage of 1.20 in each fiscal year, where debt service coverage is defined as 1.20

    of annual revenue bond debt

    • Increases in volumetric water rates of approximately 4% in FY 2015, 4.6% in FY 2016, 9.3% in FY

    2017

    • Increases in volumetric sewer rates of approximately 2.8% in FY 2015, 6.3% in FY 2016, 2.1% in

    FY 2017

    While the Engineer’s Report demonstrated the City’s ability to meet the obligations of the FY 2013

    bonds, in actuality the City failed to meet its debt service coverage in FY 2013. Recognizing its inability

    to meet coverage, the City implemented a rate increase (that went into effect on November 8, 2013) of 

    29% for the volumetric component of the water rate structure and a rate increase of 108% for both the

    fixed and volumetric components of the sewer rate structure so that the City could meet its debt service

    obligations in FY 2014. As of the date of this technical memorandum, the audit had not been completed

    to determine if these rate increases were sufficient for the City to meet coverage for FY 2014. However,

    based on RFC’s preliminary analysis, it appears the City may meet its coverage requirement for FY 2014

    and FY 2015 but not in future years. Nonetheless, Moody’s downgraded the City’s bond rating from A1to A2 in November 2014 after reviewing the City’s financial information.

    The disparity in the cash flow analysis in the Engineer’s Report versus the updated projections

    developed by RFC is explained below and is also shown in the chart that follows the explanation.

    • The timing of the project has varied significantly from the project schedule. For example, as of 

    October 2014, only 30% of the meters had been replaced which is in contrast to the initial

  • 8/9/2019 Raftelis Report on Siemen's contract

    20/58

    Draft Final TM2-8

    schedule of having all meters replaced by the end of FY 2014. As a result, this has limited the

    City’s ability to realize operational savings and revenue enhancements in FY 2013, FY 2014, and

    will continue into the future until the project is completed.

    • The debt coverage calculation in the original projections exactly met the debt coverage

    requirement of 1.20 (of the annual debt service on revenue bonds only). This means that there

    was no room for any variation in any of the assumptions (excluding the 13% allowed variabilityin the revenue enhancements or operating savings that was already incorporated in the

    calculation). As explained previously in this technical memorandum, the debt service calculation

    is a two-pronged test. RFC’s interpretation of the rate covenant is a more stringent test than

    1.20 on senior debt service.

    • The original projection escalated operating costs for water at 1% and 3% for sewer. In actuality,

    the operating costs have and will likely continue to increase at much higher levels due to:

    Higher chemical costs for water resulting from the well system shutdown and reliance

    on the surface water treatment plant which requires more chemicals than the well

    system.

    Higher chemical costs for sewer due to having maximized current treatment of plantdischarge waters. In addition, the Siemens’ contract will repair Centrifuge #1 which

    will put the discharge plant at full capacity once again. This increase in dried sludge

    output will cause an increase in the amount of chemicals being used.

    Higher electricity costs due to the surface water plant having to pump water further

    since the well system is shut down.

    Higher cost of operation at the new Presidential Hills facility.

    Additional staff needed to provide necessary level of water and sewer service.

    • The original projections did not incorporate any additional debt resulting from the City’s consent

    decree or capital improvement projects related to water system replacement projects.

    • The rate increases that were implemented (even at the much higher levels than under the

    original projections) have not resulted in revenues increasing in proportion to the rate increases

    due to a high level of adjustments to water use (some of which is attributed to the meters being

    changed out and not registering correctly) and uncollectible accounts.

    Exhibit 4: Comparison of Engineer’s Projections to RFC’s Projections

    RFC's Revenue Sufficiency Analysis Engineer's Report - Projected Cash Flow

    CAFR (1) Unaudited (2) Budget (3) Budget (3) Budget (3) Projected

    FY 2013 FY 2014 FY 2015 FY 2016 FY 2017 FY 2013 FY 2014 FY 2015 FY 2016 FY 2017

    Total Revenues 44,186,000$ 68,431,191$ 68,431,191$ 68,431,191$ 68,431,191$ (1) 51,492,722$ 53,008,927$ 55,735,686$ 57,969,391$ 60,664,138$

    Le ss: Total O&M Ex pense s ( 33, 187, 000)$ (39,203,069)$ (45,229,699)$ (47,582,084)$ (49,788,878)$ (2) (37,827,477)$ (38,200,280)$ (38,067,595)$ (36,823,253)$ (37,593,403)$

    Revenues Available for Debt Service 10,999,000$ 29,228,122$ 23,201,492$ 20,849,107$ 18,642,313$ 13,665,245$ 14,808,647$ 17,668,091$ 21,146,138$ 23,070,735$

    Revenue Bond Debt Service 12,641,000$ 12,641,000$ 14,986,710$ 17,925,216$ 19,479,741$ 11,424,804$ 11,738,238$ 14,667,492$ 17,605,999$ 19,160,524$

    Debt Service Coverage on Rev. Bonds 0.87 2.31 1.55 1.16 0.96 1.20 1.26 1.20 1.20 1.20

    Must be 1.20 

    Total Debt Service 18,382,313$ 23,467,072$ 22,778,731$ 26,222,279$ 28,789,563$

    Debt Service Coverage on Total Debt 0.60 1.25 1.02 0.80 0.65

    Must be 1.00  0.60 1.25 1.02 0.80 0.65

    (1) From the FY 2013 Comprehensive Financia l Annual Report (page 131), with the (1) Includes enhanced revenues from performance contract and rate increases o

    exception of the revenue bond f igure which is net of capital ized interest. I t should be 4%, 4.6%, and 9.3% for water and rate increases of 2.8%, 6.3%, and 2.1 % for

    noted that FY 2012 revenues were $48.2 million. sewer in FY 2015, FY 2016, and FY 2017, respectively.

    ( 2) B ased on unaudi ted i nf ormati on provi de d by Ci ty staf f and i ncl udes rate ( 2) I ncl ude s operati onal savi ngs f rom the perf ormance contract.

    increases implemented in November 2013 of 29% for water and 108% for sewe r.

    (3) Based on FY 2015 budget provided by City staff but assumes no rate adjustments.

  • 8/9/2019 Raftelis Report on Siemen's contract

    21/58

    Draft Final TM2-9

    NEXT STEPS

    • The Project Team recommends that City staff continue to use the revenue sufficiency model

    developed by RFC as a financial planning tool and incorporate updated information into the

    model as it becomes available so that debt coverage ratios can be monitored and met in future

    years, and so that rate adjustments can be identified over a long-term planning period to avoid

    rate shock. The financial planning model should be updated annually to reflect any operational

    savings and revenue enhancements from the Siemens performance contract, other factors that

    affect operational expenses such as the City’s ability to reduce water loss, etc., demand

    projections that are impacted by weather, collection efforts that are impacted by adjustments

    and cut-off policies, etc.

    • The Project Team also recommends that the City perform a comprehensive cost of service

    analysis to determine the optimal rate structure that will allow the City to balance rate

    adjustments with affordability and equity concerns. For example, the City could have a different

    rate for each customer class (residential, commercial, etc.), or tiers for residential customers

    that could include a lifeline rate for those customers with low water use. The cost of serviceanalysis could also determine the level of costs to be recovered from the fixed component of 

    the rate structure versus the volumetric component that varies by water/sewer flow.

    Depending on the results of the cost of service analysis, the rate adjustments would impact

    customers differently. A comprehensive cost of service analysis would allow the City to balance

    rate adjustments with its rate structure pricing objectives including, but not limited to,

    affordability and equity.

  • 8/9/2019 Raftelis Report on Siemen's contract

    22/58

    Draft Final TM3-1

    Technical Memorandum #3

    Billing System Data Review

    OBJECTIVE

    In recent months, the City of Jackson (City) has recognized a lower than expected level of water andsewer revenue in light of the recent rate increases. The collection rate fell significantly between 2012

    and 2014, and current revenues are materially below expected totals. The Project Team was contracted

    to perform a variety of financial support roles, one of which was to identify patterns in billing and

    collections that may explain low revenue figures using active and historical billing system data. As

    defined in the project scope regarding potential billing data inaccuracies, the Project Team sought to

    determine:

    • Who is affected?

    • How it is occurring?

    • Why it is occurring?

    • How much revenue is potentially at stake?

    The approach to this was to examine the billing data from meter readings to incoming payments to

    identify any process disconnects, data quality concerns, incorrect application of rates or billing policy,

    fraudulent activity, or other drivers behind the reduction in revenue. Armed with that data, the Project

    Team sought to find eligible revenue sources wherever possible by identifying accounts not being billed

    when they should be or not being charged the correct amount.

    The Project Team had the additional objectives of supporting financial planning with live billing data and

    determining the extent (if at all) of incorrect billing to a group of customers outside the City.

    As the City goes through conversion to automated metering infrastructure (AMI) and a new billing

    system, identification of any issues is critical to limit their perpetuation into the new environment and to

    resolve any outstanding revenue sources before those data are potentially lost in the transition. This

    transition process has been temporarily suspended, but is expected to continue. Even with an extended

    delay, improvements to data quality and data management processes can increase billing and

    collections in the current environment as well.

    PROCESS

    Data AcquisitionThis effort commenced in late October with data acquisition and interviews with Information Services,

    utility management, and Customer Service staff. The Project Team obtained an extract copy, dated

    October 17, 2014, of the legacy billing system to be restored in our Oracle environment. We also

    obtained daily history files generated on a nightly basis as a record of all changes to the billing data from

    1999 through November 7, 2014. To support review of these data, the Project Team received

    documentation including lookup codes for billing system data, entity relationship diagrams, and SQL

    scripts used by staff to perform regular and ad hoc queries against the database.

  • 8/9/2019 Raftelis Report on Siemen's contract

    23/58

    Draft Final TM3-2

    During this initial visit, the Project Team held discussions with Information Systems and Customer

    Service staff on relevant billing policy information and data structure, and learned of some known

    problems with data and processes as well as some problems already being addressed. These included:

    1. Hung accounts due to outstanding work orders;

    2. New AMI meters that are stuck;

    3. New AMI meters causing dramatic billing increases;

    4. Accounts registering consumption with no present occupants; and

    5. G/E code accounts that are exempt from enforcement actions.

    Data Structure

    The legacy billing system includes a number of tables, but only about 10 that are used to manage day-to-

    day customer, consumption, and billing data. Of these, the majority of available billing information is

    stored in the Meter Detail table, with 1,027,980 records representing the last 12 reads and bills for every

    meter. In our extract, this table included read and bill information from October 2012 to October 2014

    for most customers. The Accounts and Meters tables each have 85,665 records. Meters are related with

    accounts and customers through a series of cross-reference tables.

    The daily history files contain a wealth of information including logs of every bill generated, every

    adjustment made, every payment made, and most user edits. For reference, the following table shows

    the number of records in each of the following categories, representing transactions from 1999 through

    November 7, 2014.

    Table 1. Amount of data contained in daily history files

    TABLE NUMBER OF RECORDSADJUSTMENTS 138,554

    CHECK PAYMENTS 3,184,815

    BANK DRAFT PAYMENTS 301,415

    CASHIERING PAYMENTS 1,572,836

    USER EDITS 3,487,316

    BILLS 5,546,163

    High Level Review

    To gain a high-level understanding of utility finances, the Project Team used daily history file data

    including every bill generated and adjustment recorded. These data were used to drive the review as it

    extended back to 1999 and gives a rich history, whereas only two years are typically available in the live

    billing system data due to constraints on the system. With the daily histories of bills generated and

    adjustment activities, the Project Team pieced together long-term trends on consumption, billings,

    collections, customers/accounts. From this perspective, the Project Team was able to visualize the

    reduced revenue, seeking an obvious driver for the problem.

  • 8/9/2019 Raftelis Report on Siemen's contract

    24/58

    Draft Final TM3-3

    These data showed that the number of accounts has been decreasing slightly over time, though

    consumption is holding nearly steady. Billings, before any adjustments are applied to accounts, have

    been rising steadily over time and have steep increases aligned with the timing of rate increases. At the

    same time, adjustments have followed a similar trend, increasing drastically even normalized for rates.

    These adjustments are mostly related to water charges rather than sewer, sanitary, or meter charges.

    As a result, adjusted billings have not increased as much as expected (see Figure 1).

    Figure 1. Total Unadjusted Charges, Adjustments, and Adjusted Charges by Year 

    Payments, though increasing, have not been tracking with expectations for the past few years. This is

    especially evident with cashier payments. While it is understandable that the proportion of cashier

    payments may decrease over time as more customers use alternate payment options, the revenue from

    these other options, mailed checks and bank drafts, has not made up the difference. As a result,

    outstanding balances are on the rise and the collection rate is decreasing. Generally, increased

    adjustment activity and decreased collections are the major drivers for the reduced revenue stream.

    These figures are summarized in the table below.

     $-

     $20.00

     $40.00

     $60.00

     $80.00

     $100.00

     $120.00

    1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014

    Billings Adjustments Adjusted Bills

  • 8/9/2019 Raftelis Report on Siemen's contract

    25/58

    Draft Final TM3-4

    Table 2. Summary of High Level Data

    YEAR BILLINGS ADJUSTMENTS

    %

    ADJ

    ADJUSTED

    BILLS CHECKS DRAFTS CASH RECEIPTS

    %

    COLL

    #

    BILLED

    ACCTS

    1999 23,029,867.37 (2,326,493.71) 10% 20,703,373.66 14,383,678.49 $836,959.71 4,226,444.30 19,447,082.50 94% 65,69

    2000 48,247,048.87 (5,445,588.17) 11% 42,801,460.70 29,805,917.52 $1,867,040.39 8,915,791.76 40,588,749.67 95% 67,60

    2001 38,402,584.45 (4,497,069.42) 12% 33,905,515.03 23,591,948.94 $1,401,105.28 7,797,002.50 32,790,056.72 97% 66,95

    2002 56,753,862.31 (5,600,952.03) 10% 51,152,910.28 36,934,634.94 $1,999,840.60 12,339,446.37 51,273,921.91 100% 67,10

    2003 56,587,856.06 (8,499,363.39) 15% 48,088,492.67 33,166,028.51 $1,812,692.99 11,540,326.87 46,519,048.37 97% 66,56

    2004 56,581,223.32 (7,087,090.84) 13% 49,494,132.48 32,506,980.96 $1,954,803.87 13,201,977.92 47,663,762.75 96% 66,30

    2005 63,710,498.81 (9,073,461.72) 14% 54,637,037.09 35,234,866.46 $2,115,425.67 12,876,349.74 50,226,641.87 92% 66,04

    2006 61,422,308.90 (8,797,588.37) 14% 52,624,720.53 33,866,342.29 $2,071,952.58 16,087,833.33 52,026,128.20 99% 65,70

    2007 60,481,050.54 (8,259,673.39) 14% 52,221,377.15 31,964,535.59 $2,041,538.74 17,530,588.90 51,536,663.23 99% 64,71

    2008 67,916,162.21 (11,497,746.82) 17% 56,418,415.39 32,768,787.23 $2,111,619.58 16,956,346.66 51,836,753.47 92% 64,23

    2009 66,261,029.90 (13,871,447.53) 21% 52,389,582.37 29,398,409.67 $1,836,450.16 17,854,046.15 49,088,905.98 94% 64,38

    2010 65,101,024.67 (11,088,840.49) 17% 54,012,184.18 32,016,889.07 $1,985,247.46 17,551,258.58 51,553,395.11 95% 64,02

    2011 71,323,964.23 (14,109,562.55) 20% 57,214,401.68 36,677,896.50 $2,146,939.19 16,623,617.54 55,448,453.23 97% 63,54

    2012 73,038,101.34 (16,566,067.84) 23% 56,472,033.50 36,003,024.74 $2,026,614.66 15,291,882.30 53,321,521.70 94% 62,59

    2013 74,560,102.15 (14,932,747.34) 20% 59,627,354.81 39,001,206.03 $2,192,379.71 13,045,818.91 54,239,404.65 91% 61,90

    THRU NOV

    7, 2014  95,777,131.41 (26,773,241.38) 28% 69,003,890.03 45,061,498.44 $2,676,389.43 12,903,999.69 60,641,887.56 88% 62,81

    2014 PROJ. 110,143,701.12 (30,789,227.59) 28% 79,354,473.53 51,820,723.21 3,077,847.84 14,839,599.64 69,738,170.69 88% 62,81

  • 8/9/2019 Raftelis Report on Siemen's contract

    26/58

    Draft Final TM3-5

    Bulk Billing Data Review

    A bulk analysis of billing data in the live billing system was performed to supplement this finding with

    specific data quality concerns that could be leading to unbilled accounts or accounts requiring

    adjustments. Based on known rates, billing policies, and data structure, the Project Team used customer

    and consumption data in the billing system as of October 2014 to replicate account water and sewer

    charges before and after the November 2013 rate change. This exercise resulted in the identification of categories of accounts where the customer charges were not as expected, where bills seemed to be

    going out or not going out unexpectedly, and where poorly maintained customer information could

    result in unenforceable circumstances. These circumstances could be symptoms of a systematic

    misapplication of billing policy or simply of poor data quality and limited quality control measures. The

    results of this analysis are described further below.

    Field Audit

    Based on the bulk billing data review, RFC developed sample data for further investigation by project

    partners, IBS. This investigation took place on site over three separate visits, during which IBS staff has

    worked with City Information Systems and Customer Service staff to research individual accounts anddetermine whether the exceptions noted during bulk review were justified, or whether other similarities

    exist between accounts exhibiting the same unexpected circumstances.

    Field visits were conducted on December 9th and December 18th and 19th, 2014, and the week of January

    5th, 2015. The findings from these visits are summarized below and a detailed report is included as

    Appendix A.

    FINDINGS

    Billing Data Accuracies

    The Project Team could replicate the vast majority (approximately 97%) of water charges to accounts

    within the City. Many of those that were not replicable were not receiving bills, which is addressed

    below. This is not to say that payments are made to all correctly charged accounts, but that the Project

    Team found the billing system data related to water charges to be mostly accurate.

    Billing Data Inaccuracies

    Data Validity

    While reviewing the data in bulk, the Project Team found many instances of invalid entries throughout

    most tables and fields. For example, there are accounts within the City with both inside- and outside-city

    flags in different fields. Rates are determined based on a meter’s location (inside vs. >1 mile outside the

    city) and having conflicting information on the same account could confuse the calculation process,especially as it is converted to the new billing system.

    Similarly, there are entries that make the billing policy difficult to accurately implement. Residential

    properties with multiple units are supposed to be billed per unit. In the legacy system, there are two

    fields that denote this set-up. First, the Apartment Code should be “0” for single family properties (one

    unit) or “A” for multiple units. A subsequent field is supposed to contain the number of units where the

  • 8/9/2019 Raftelis Report on Siemen's contract

    27/58

    Draft Final TM3-6

    Apartment Code is “A.” The Project Team found 38 other unique values other than other than “0” or “A”

    included in the Apartment Code field of 173 accounts. The Project Team also found 13 instances where

    more than one unit was noted with a “0” single family residential property, and 386 instances where “A”

    multi-unit properties were listed with 0 or 1 as the number of units. All of these are invalid combinations

    that could result in the miscalculation of per unit water and sewer charges.

    Across the board, there were invalid data that hindered bill replication by the Project Team, but more

    importantly caused concern about data maintenance and data quality as it relates to correct bill

    calculation at the City.

    Adjustments

    Given that adjustments appeared to play a large role in the reduction of revenue in 2014, two groups of 

    accounts were identified to examine recent adjustments. All large adjustments, defined as a single credit

    or debit of more than $400, and all frequent adjustments, defined as four or more adjustment instances,

    over the past two years were pulled out and sampled for further review. As of November 2014, there

    were 3,391 large adjustments totaling $(41,204,999) and 141 accounts with many adjustments, totaling$(2,562,740). The project team found no systematic evidence of accounts being adjusted by values

    greater than the account balance, except in cases where payments had already been made.

    From the field audit, the root cause(s) of the adjustments issue appears to be mostly human errors from

    meter readers. The readings are fixed through a re-compute system process, but before this occurs they

    are already registered in the system incorrectly, causing an adjustment to appear on the record. Another

    root cause is meter leaks, which are addressed by a manual calculation to determine a corrected bill

    based on past consumption. In this case, only a monetary adjustment is made, and no consumption

    adjustment is done in the system.

    The City does have a leak adjustment policy and a standard process for meter error adjustments. All the

    adjustments sampled were processed in accordance with policy as described and were properly

    authorized. It appears that adjustments of any level are signed off by supervisors before being

    committed to the system.

    The Project Team noticed that in many cases, several adjustments were made to an account at a single

    time, seemingly as a series of attempts to get the calculation to end up at a desired result. That, paired

    with reported supervisory authorization for each adjustment, suggests that more stringent supervisory

    review and more carefully calculated adjustments should reduce this value. The billing system does not

    have any validation rules or checks on an adjustment before it is committed. Going forward, these are

    highly recommended. The City needs to instate a process or improve existing processes to address datainaccuracies before they go into the billing system.

    ManyAdjustments

    For the field audit, the team identified a sample of 159 accounts with more than four adjustments over

    the most recent two year time period for further analysis. Of those, the team received additional work

    order information for 52 (33%), representing adjustments of $1,011,722. 44 (85%), which were

  • 8/9/2019 Raftelis Report on Siemen's contract

    28/58

    Draft Final TM3-7

    associated with work orders to address meter reading errors, and 8 (15%), which were associated with

    work orders for meter leaks.

    LargeAdjustments

    For the field audit, the team identified a sample of 61 accounts with more than four adjustments over

    the most recent two-year time period for further analysis. Of those, the team received additional workorder information for 30 (49%), representing adjustments of $1,367,876. 16 (60%), which were

    associated with work orders to address meter reading errors, and 2 (7%), which were associated with

    work orders for meter leaks.

    AMI Meters

    City staff mentioned that the installation of new AMI meters had been causing a number of billing issues

    to be reported by customers. Primarily, the new meters either were causing no consumption to be

    billed, or dramatic increases to be caused in bills. These two issues were examined in the billing data and

    subsets of accounts were identified for detailed examination, as explained below.

    StuckAMImeters

    The issue of stuck AMI meters has been addressed in part by the meter installer through improved

    quality control measures. However, more instances than were acknowledged by the installer were

    found in the billing data. The Project Team identified a set of 283 AMI meters linked to active accounts

    with a history of steady consumption that drops drastically (to or near 0) after the meter is replaced.

    During the field audit, the Project Team found that the standard for stuck meter resolution is 8 weeks,

    though no policy or service level agreement was provided. Our review revealed that about 90% meet

    this standard based on service order notes in the sample group. As of the date of the audit, only 2

    accounts (10%) on the sample list were still unresolved. While this process seems to be improving, the

    service order process within the legacy system is open-ended and there are many opportunities for

    service orders to fall through the cracks. The service order entry and follow-up process is described

    more fully below.

    ReadingaboveThreshold 

    Another claim regarding the new AMI meters is that some appear to be miscalibrated or reading in the

    wrong unit (gallons instead of cubic feet). Theorizing that these problems could be teased from the data,

    the Project Team developed a list of 3,371 new meters whose readings after being replaced with AMI

    meters were two standard deviations above mean consumption prior to the replacement.

    During the January 2015 field audit, the Project Team discovered that DPW was experiencing a high ratethreshold exceptions, averaging approximately 53% of all billed accounts needing review. The field

    auditors sampled 30 accounts. Twenty-one (70%) of the exceptions appear to be triggered by incorrect

    meter reads due to meter reading errors and not leaks. This large exceptions rate appears to have a

    direct correlation with the high levels of adjustments discussed in the previous section.

  • 8/9/2019 Raftelis Report on Siemen's contract

    29/58

    Draft Final TM3-8

    Meter reading error rates appear to be consistent with both standard and AMI meters, thereby

    eliminating AMI as a primary driver for the high exception rates overall. There are currently no quality

    assurance standards deployed during the meter reading process (although the current handheld system

    has some built in functionality that, if used, could help). As a result, bad meter reading data is uploaded

    into the billing system and putting tremendous pressure on staff to catch large variances prior to bill

    mail out. There is an existing manual process by which daily threshold exception logs are reviewed by 3or 4 edit clerks. Once identified, the high bills are pulled prior to mail out and reviewed. The bill is then

    adjusted and estimated bills are sent out. Because of the manual process and the high volume of 

    exceptions, it is unlikely that most of the exceptions are addressed prior to mail out. A large percentage

    of customer bills are rendered incorrectly and require adjustment.

    Concurrent with the Project Team Review, the City also obtained separate information from the AMI

    meter installation contractor suggesting that a number of meters were using gallon units. The majority

    of these identified meters were installed after the time of the Project Team data extract. Those that

    were installed prior to the extract had not registered unusually high consumption.

    Misapplication of Billing Policy

    MinimumSewerCharge

    The most critical finding by the Project Team is the incorrect calculation of the minimum sewer charge.

    The City’s Code of Ordinances, Division 2, Sec. 122-235 regarding minimum monthly sewer charges

    states:

    (a) The schedule of minimum sewer service charges is as follows:

    (1) Each customer with a five-eighths-inch meter whose water consumption is 300 cubic feet or less

    shall be assessed a minimum monthly charge of $13.41.

    (2) Each customer with a one-inch meter whose water consumption is 670 cubic feet or less shall be

    assessed a minimum monthly charge of $29.95.(3) Each customer with a one and one-half or two-inch meter whose water consumption is 1,510

    cubic feet or less shall be assessed a minimum monthly charge of $67.50.

    (4) Each customer with a three-inch or larger meter whose water consumption is 2,710 cubic feet

    or less shall be assessed a minimum monthly charge of $121.14.

    Customers are billed bimonthly, and the monthly minimum sewer rate as described in the ordinance is

    in fact charged only bimonthly, meaning that all users below the minimum threshold are charged only

    half the expected amount. This lost revenue equates to at least the following levels of lost revenue

    between Nov 8, 2013 and Oct 17, 2014.

    Table 3: Lost Revenue from Billing Misapplication

    METER SIZE LOST REVENUE

    5/8” $ 630,394

    1” $ 100,546

    1 1/2” AND 2” $ 150,052

    >2” $ 35,615

  • 8/9/2019 Raftelis Report on Siemen's contract

    30/58

    Draft Final TM3-9

    TOTAL $ 916,607

    In Figure 2, below, the number of 5/8” meters charged $13.41 and the number of times each account

    received this charge between Nov 8, 2013 and Oct 15, 2014 (nearly a full year after the rate increase) is

    plotted. This amount should never be billed, but it happens thousands of times. Rather, twice the

    monthly charge, or $26.82 for 5/8” meters, should be minimum charge found on a bill.

    Figure 2. Instances of Half Minimum Sewer Charge for 5/8" Meter 

    HungAccounts

    City staff also mentioned that the billing system was set up in such a way that accounts could be set to

    non-bill status even though water service may still be available. Hung accounts are those that that are

    listed as active but have multiple instances of consumption greater than zero, and no charge for water

    and sewer. The Project Team identified 73 accounts in the legacy billing system where this happened

    continuously between January 2013 and October 2014. These accounts represented 1,374,318 cubic

    feet of unbilled consumption over this period, which based on current rates would be about $45,000.

    Upon further review during the field audit, the consultant team found most hung accounts to be

    resolved. As of the date of the audit, only 20% of accounts on the sample list were still unresolved.

    According to Information Systems staff, intensified efforts have been recently placed on resolving hung

    accounts as part of the data cleanup for conversion.

    VacantPropertieswithRegisteredConsumption

    The Project Team noticed when reviewing the billing data in bulk that there are many instances of 

    incomplete or inaccurate customer information, which could lead to unenforceable collections

    circumstances. Specifically, there are accounts where the customer is “No Present Occupant,” not

    receiving a bill, but with consumption registering regularly. The Project Team generated a list of 1,304

     -

     1,000

     2,000

     3,000

     4,000

     5,000

     6,000

     7,000

    1 2 3 4 5 6

       N   u   m    b   e   r   o    f   M   e   t   e   r   s

    Number of $13.41 sewer charges over 6 billing cycles of 2014

  • 8/9/2019 Raftelis Report on Siemen's contract

    31/58

    Draft Final TM3-10

    “No Present Occupant” accounts representing 2,850,201 cubic feet of unbilled consumption during the

    last two-month period of the legacy billing system. The time constraint on this is meant to avoid any

    issues related to a change in customer status over time, since the customer information is just a

    snapshot as of the time the Project Team obtained a copy of the billing system.

    The team identified a sample of 40 accounts and received additional information on 38 of the 40requested samples, of which only 23 (58%) were still in NPO status at the time of the field audit.

    Seventeen (74%) had been closed out as part of the standard NPO process, while 6 (26%) hadn’t been

    closed out. Twenty-one (91%) of the 23 accounts had outstanding balances, which means the vacating

    customer didn’t settle their final bill.

    Non-BilledAccounts

    There are several types of non-bill status in which an account can fall. They are:

    • Off- Customer Request

    • Customer moving (off)

    • Off- Delinquent Bill

    • Off- Bad Check

    • Off- Seasonal

    • Returned mail

    • Special Payment Plan

    These categories relate to circumstances in which a bill should not be generated because no

    consumption is allowed. However, the Project Team found 410 instances of non-bill accounts with

    consumption activity between September 1, 2014 and October 15, 2014. This activity totaled 769,734

    cubic feet of consumption or $53,417.

    The field audit included a sample of 43 accounts, from which the consultant team identified a lack of 

    follow-up on the cause of non-bill status to be the main driver. After an account has been classified as

    non-bill status, it appears that accounts go unread for upwards of a year after last billed date. It also

    appears that field actions to pull meter or tie-in also take a considerably long time. So, if an account is

    shifted to “Off- Bad Check,” for example, it could be a long time before a field technician actually shuts

    off the meter (if ever). Secondarily, the process for moving accounts to non-bill status is being exploited

    by customers. Customers that are delinquent on their payment get switched to a non-bill status and so

    stop getting billed. Since field work orders to shut off account are not closely monitored to confirm that

    actual shut off happened, customers continue to get free service for extended periods of time.

    Although, meter reads continue to confirm usage on these accounts subsequently, actions to bill orterminate service physically, still doesn’t happen for extended periods of time. Even when physi