Rancho Mission Viejo Pavilion Project Winter Design Review 2020 Acknowledgements LPS Engineering would like to thank both Professor Lanning and Professor Bucknam for guiding our group through the planning process. LPA, Inc. | LPS Engineering | Team G-2 Industry Advisor - Andrea Echeverria, P.E. Project Manager - Justin Liu Abstract The Rancho Mission Viejo Pavilion project is a 1.6 acre site with a proposed joint-use facility between the community and the adjacent K-8 school. During the school day, the neighboring K-8 school will have access to the recreational facilities. After school hours, the community will have access to the gymnasium for basketball, volleyball, and other community events. This will be a central recreational facility for the village of Esencia that all members of the community will have access to. Given the architectural layout from LPA, Inc, LPS Engineering was tasked with establishing the grading layout of the site and Best Management Practices (BMPs) within the site. Design Approach Iterative approach to grade and re-grade the site that ultimately complies with American Disabilities Act of 1990 (ADA) standards using AutoCAD Partitioning of site Drainage Management Areas (DMAs) Following Orange County Public Works Best Management Practices (BMPs) to design vegetated and proprietary bioswales Preliminary Design Results Establish spot elevations and grading slopes throughout the surrounding site Determine a Finished Floor Elevation (FFE) for the main pavilion structure Design of a vegetated swale and a modular wetlands unit Sectioning 10 drainage management areas Topographic contours LPS Engineering Consultants Future Steps The next stage of this project will be focused on the following: Refining site drainage system Modular Wetland Vegetation Swale Designing pipe system Citations Title 24, Part 2. (2018). California Access Compliance Advisory Reference Manual. Division of the State Architect. BIO-2: Vegetated Swale. (2011). OC Watershed Technical Guidance Document. Orange County Public Works. Worksheet D. (2013). Orange County Watershed Best Management Practices. Orange County Public Works. Design Constraints & Considerations ADA Compliance Orange County Public Works BMP Compliance Pre-existing grades Existing hydrological flow Contain and manage all water capture within the site Preservation of native Heritage Oak Trees Client design requests Preliminary Site Design Existing Site Conditions Modular Wetlands Vegetated Bioswale Design Team (Left to Right): Timothy Lee, Christopher Lu, Justin Liu, Kenny Suryadinata, Daniel Pena

Upload: others

Post on 29-Mar-2022

3 views

Category:

Documents


0 download

TRANSCRIPT

Rancho Mission Viejo Pavilion ProjectWinter Design Review 2020

AcknowledgementsLPS Engineering would like to thank both Professor Lanning and Professor Bucknam for guiding our group through the planning process.

LPA, Inc. | LPS Engineering | Team G-2Industry Advisor - Andrea Echeverria, P.E.

Project Manager - Justin Liu

AbstractThe Rancho Mission Viejo Pavilion project is a 1.6

acre site with a proposed joint-use facility between the community and the adjacent K-8 school. During the school day, the neighboring K-8 school will have access to the recreational facilities. After school hours, the community will have access to the gymnasium for basketball, volleyball, and other community events. This will be a central recreational facility for the village of Esencia that all members of the community will have access to. Given the architectural layout from LPA, Inc, LPS Engineering was tasked with establishing the grading layout of the site and Best Management Practices (BMPs) within the site.

Design Approach● Iterative approach to grade and re-grade the site that

ultimately complies with American Disabilities Act of 1990 (ADA) standards using AutoCAD

● Partitioning of site Drainage Management Areas (DMAs)● Following Orange County Public Works Best

Management Practices (BMPs) to design vegetated and proprietary bioswales

Preliminary Design Results● Establish spot elevations and grading slopes throughout the surrounding site● Determine a Finished Floor Elevation (FFE) for the main pavilion structure● Design of a vegetated swale and a modular wetlands unit● Sectioning 10 drainage management areas● Topographic contours

LPS Engineering Consultants

Future StepsThe next stage of this project will be focused on the following:● Refining site drainage system

○ Modular Wetland○ Vegetation Swale

● Designing pipe system

CitationsTitle 24, Part 2. (2018). California Access Compliance Advisory Reference Manual. Division of the State Architect.

BIO-2: Vegetated Swale. (2011). OC Watershed Technical Guidance Document. Orange County Public Works.

Worksheet D. (2013). Orange County Watershed Best Management Practices. Orange County Public Works.

Design Constraints & Considerations● ADA Compliance● Orange County Public Works BMP Compliance● Pre-existing grades● Existing hydrological flow● Contain and manage all water capture within the site● Preservation of native Heritage Oak Trees● Client design requests