ref.no-80212/9 th 17 nov, 2014 to, (seiaa), odisha ... date : 17 nov,2014 ocl india ltd, rajgangpur...
TRANSCRIPT
Ref.No-80212/9
17th
Nov, 2014
To,
The State Environment Impact Assessment Authority,
(SEIAA), ODISHA
Qtr. No. 5RF-2/1,
Unit - IX,
BHUBANESWAR - 751022
Sub:-Submission of six monthly compliance report for the period (April,2014 to Sept,2014) of (2 x 27 MW)
Captive Power Plant project of M/s OCL India Limited, Rajgangpur, Dist- Sundargarh,Odisha.
Ref: - Environmental Clearance letter No. : SEIAA 619 / SEIAA-128/10 dated 22 December 2010.
Dear Sir,
With reference to above letter, we enclose herewith the six monthly compliance report of conditions stipulated in the
Environmental Clearance for the above project.
Thanking you
Yours sincerely
For OCL India Limited
Ganesh W Jirkuntwar
Deputy Executive Director (Mfg) /C
Encl: As above
Copy to:
The Director (S)
Government of India
Ministry of Environment and Forest
Eastern Regional Office
A/3, Chandrasekharpur BHUBANESWAR – 751 023
SIX MONTHLY COMPLIANCE REPORT (APRIL, 2014 TO SEPTEMBER, 2014)
OF
ENVIRONMENT CLEARANCE LETTER NO.
SEIAA 619 / SEIAA-128/10 DATED 22 DEC, 2010
FOR
(2X27 MW) CAPTIVE POWER PLANT PROJECT
BY OCL INDIA LIMITED
RAJGANGPUR – 770017 DIST- SUNDARGARH
ODISHA
Date : 17th Nov,2014
OCL INDIA LTD, RAJGANGPUR Sub: Submission of Six monthly compliance report (April,2014 to Sept,2014) of conditions stipulated in
Environmental Clearance letter No. SEIAA 619 / SEIAA-128/10 dated 22 December 2010 by SEIAA,Odisha for (2x27 MW) Captive Power Plant Project of M/s OCL India Limited, Rajgangpur.
SL.No. Description of conditions Compliance status
i The applicant (Project proponent) will take necessary
measures for prevention, control and mitigation of
Air Pollution ,Water pollution, Noise Pollution and
Land Pollution including solid waste management as
mentioned by him in form-1, Final EIA reports and
Environment Management Plan (EMP) in compliance
with the prescribed statutory norms and standards.
Following Pollution control systems are installed
for prevention ,control of pollution and mitigation
of Air, Water ,Noise & Land pollution including
solid waste management -
Air Pollution Control
Two nos. high efficiency Electrostatic
Precipitator (ESP) with six fields.
Pneumatic ash conveying system
Ash storage silos with bag filter arrangement
Pneumatic ash transportation system from CPP
to our cement plant
Conveyor belt covering arrangement
8 nos bag filters are installed in Coal handling
transfer points
Water sprinkling arrangement on the road
Water Pollution Control
STP has already been commissioned and treated
water is utilized for green belt development/
plantation.
Noise Pollution Control
Compressor, TG area and ACC is acoustically
sealed to prevent noise pollution.
In steam vent line silencers are provided.
Fan and seal blower silencers arrangement made.
Solid Waste Management
Sludge from STP is utilized for green belt
development / plantation.
Solid waste (fly ash & Bottom ash) is utilized as
raw material for cement manufacturing process
in our own cement plant.
ii The applicant will take necessary steps for socio-
economic development of the people of the area on
need based assessment for providing employment
education, health care, drinking water and sanitation,
road and communication facilities etc, after a detailed
primary socio economic survey of the core zone.
A detailed socio-economic survey report has
already been submitted. As per the findings in the
report, actions are being taken.
iii The applicant will comply with the points, concerns A detailed compliance report in this regard which is
and issued raised by the people during public hearing
on 29th
May 2009 in accordance with the
commitments make by him thereon.
relating to CSR activities is enclosed herewith for
the period 2013-14 as annexure-1.
iv The applicant will take statutory clearance / approval
/ permissions from the concerned authorities in
respect of his project as and when required.
Complied.
v For post environmental clearance monitoring , the
applicant will submit half yearly compliance report in
respect of the stipulated terms and conditions of
Environmental Clearance to the State Environmental
Impact Authority (SEIAA/), Orissa on 1st June and 1
st
December of each calendar year.
The half yearly compliance report is being
submitted regularly accordingly in terms of the
stipulated conditions of the Environmental
Clearance.
vi High efficiency Electrostatic Precipitators (ESPs)
shall be installed to ensure that particulate matter
emission does not exceed 50 mg/Nm3.
Two nos. high efficiency Electrostatic Precipitator
(ESP) with six fields are installed and stack emission
is achieved below 50 mg/Nm3.
vii The proponent may use bottom ash as a supplement
for the raw material for cement production with
approved technology confirming to the relevant
standard specification.
We have established use of bottom ash in cement
manufacturing process and accordingly mix is
prepared in confirmation to the standards.
viii The unit shall be allowed to use washery rejects as
raw material having <60% ash content.
We make use of the Washery rejects as raw
material having < 60% ash content.
ix The proponent shall treat the flue gas through Flue
Gas De-sulfurisation (FGD), if SO2 emission level
exceeds the prescribed norm.
SO2 emission is very low. However, in case it is
found to exceed the maximum limit as and when
such limit is prescribed, we shall take up treatment
of flue gas accordingly.
x No ground water shall be extracted for the project
work at any stage.
Noted for compliance
xi Adequate dust extraction system such as cyclones /
bag filters and water spray system in dust areas such
as in coal handling and ash handling points, transfer
areas and other vulnerable dusty areas shall be
provided.
Adequate dust extraction systems are installed as
mentioned below-
i) 8 nos of bag filters in coal handling transfer
Points to control fugitive dust.
ii) 3 nos of bag filters in flyash silo areas to
control fugitive dust.
iii) Pneumatic fly ash transportation system from
CPP to cement plant is commissioned to
eliminate fugitive dust.
iv) Covered conveyor belts are provided for coal
transportation to eliminate fugitive dust.
xii Fly ash shall be collected in dry form and storage
facility (silos) shall be provided. 100% fly ash
utilized shall be ensured as per fly ash notification of
MoEF, Govt. of India. Unutilized fly ash and bottom
ash shall be stored in the ash pond separately through
high concentration slurry disposal method. Mercury
levels along with other heavy metals (Pb, Cr, As etc.)
should be monitored in the fly ash / bottom ash,
lechates and effluents emanating from the ash pond.
100% Fly Ash is utilized in our cement plant.
Bottom ash is stored in silo and being utilized as
raw material in cement manufacturing. Our CPP
does not have any ash pond, as it is not required in
our system.
xiii The ash pond should be constructed with impervious
lining and ash pond embankment should be stone
pitched.
Our CPP does not have any ash pond, as it is not
required in our system.
xiv The treated effluents confirming to the prescribed
standards shall be re-circulated and reused within the
The effluent after treatment conforms to the
prescribed norms. We ensure ‘zero’ discharge by
plant. There shall be no discharge outside the plant
boundary. Arrangements shall be made so that
effluents and storm water do not get mixed.
re-circulating and reusing the treated water. Care
has been taken to avoid mixing of effluent and
storm water.
xv A sewage treatment plant shall be provided and the
treated sewage shall be used for raising greenbelt /
plantation.
Sewage Treatment Plant (STP) already
commissioned and treated sewage is used for
greenbelt development / plantation.
xvi Rainwater harvesting should be adopted. Central
Groundwater Authority / Board shall be consulted for
finalization of appropriate rainwater harvesting
technology within a period of three months from the
date of clearance and details shall be furnished to the
SEIAA, Orissa.
We have already complied with the required system
accordingly. Central Groundwater Board has been
consulted for the same and report submitted.
xvii
Adequate safety measures shall be provided in the
plant area to check / minimize spontaneous fires in
coal yard, especially during summer season. Details
of these measures to be taken along with location
plant layout shall be submitted to the SEIAA, Orissa.
We have taken all required safety measures in our
a) Plant area like providing fire extinguishers, fire
alarm system provision in control room and other
associated areas.
b) Coal yard to extinguish spontaneous fires, Detail
scheme is already submitted.
xviii Storage facilities for auxiliary liquid fuel such as
LDO and / HFO / LSHS shall be made in the plant
area where risk is minimum. On site and off site
Disaster Management Plans shall be prepared to meet
any eventuality in case of an accident taking place.
Mock drills shall be conducted regularly and based
on the same, modifications required if any, shall be
incorporated in the Disaster Management Plan
(DMP). Sulfur content in the liquid fuel will not
exceed 0.5%.
This is strictly complied with, as specified and also
in terms of the guidelines under the Explosives
Rules, 2008.
xix Regular monitoring of ground water in and around
the ash pond shall be carried out, records maintained
and half yearly reports shall be furnished to the
SEIAA, Orissa.
This is not applicable to us in terms of the fact that
we store the fly ash in the fly ash silo and
compartment silo of our cement plant, as reported
above.
xx A Green belt of adequate width and density
preferably with local species along the periphery of
the plant & alongside roads etc shall be raised so as
to provide protection against particulates and noise. It
must be ensured that at least 33% of the total land
area shall be under permanent green belt throughout
the year & for this purpose they may engage
professionals in this field for creation and
maintenance of the green belt. An action plan for this
purpose shall be prepared accordingly and submitted
to the SEIAA, Orissa.
This is complied with. However we have started
developing more green belt in the earmarked area.
Year wise plantation details are enclosed as
annexure - 2
xxi First aid and sanitation arrangements shall be made
for the drives and other contract workers during
construction phase.
Complied
xxii Noise levels emanating from turbines and air
compressors shall be limited to 75 dB(A). For people
working in the high noise area, requisite personal
protective equipments like earplugs / ear muffs etc
Noise level is maintained within the permissible
limit by adopting silencers / acoustic enclosures etc.
People working in the noisy area are provided with
ear muff & other PPE as required.
shall be provided. Workers engaged in noisy areas
such as turbine area, air compressors etc. shall be
periodically examined to maintain audiometric record
and for treatment for any hearing loss including
shifting to non noisy / less noisy areas.
xxiii Regular monitoring of ground level concentration of
SO2, NOx, RSPM (PM10 & PM2.5) etc. shall be
carried out in the impact zone and records
maintained. If at any stage these levels are found to
exceed the prescribed limits, necessary control
measures shall be provided immediately. The
location of the monitoring stations and frequency of
monitoring shall be decided in consultation with
SPCB, Orissa.
Regular monitoring of SO2, NOx, RSPM (PM10 &
PM2.5) etc is being carried out as per guideline of
SPCB. Monitoring results are enclosed as
annexure-3. However, We would ensure its strict
compliance in consultation with OSPCB.
xxiv Provision shall be made for housing of construction
labours within the site with all necessary
infrastructure and facilities such as fuel for cooking,
mobile toilets, mobile STP, safe drinking water,
medical health care, crèche etc. The housing may be
in the form of temporary structures to be removed
after the completion of the project.
This has been taken care of.
xxv A separate environment management cell with
qualified staff shall be set up for implementation of
the stipulated environmental safeguards.
Environment cell has already been formed for
implementation of environmental safeguards.
xxvi Half yearly report on the status of implementation of
the stipulated conditions and environmental
safeguards shall be submitted to the appropriate
authorities.
Being complied with accordingly.
xxvii Separate fund shall be allocated for implementation
of environmental protection measures along with
item-wise break-up. These cost shall be included as
part of the project cost. The funds earmarked for the
environment protection measures shall not be
diverted for other purposes and year-wise
expenditure should be reported.
Earmarked funds have since been created and we
will ensure the same for not being diverted to some
other purpose. Details already submitted.
xxviii The need of the local people should be appropriately
addresses in the CSR activities to be undertaken by
the project proponent in the area. An action plan in
this regard should be prepared and submitted to
SEIAA, Orissa.
We have already undertaken quite a good no. of
developmental work under CSR to address the
needs of the people dwelling in the vicinity which
is being carried out continuously. An action plan on
Socio-Economic Survey is already submitted.
However, developments work under CSR for the
year 2013-14 is enclosed herewith as annexure-1
xxix The above mentioned stipulated conditions shall be
complied in time bound manner. Failure to comply
with any of the conditions mentioned above may
result in withdrawal of this clearance and attract
under the provisions of Environmental Protection
(EP) Act, 1986.
We take a note of it.
Ambient air quality monitoring report for the period April,2014 to September,2014
Location of sampling
station
SO2 (μg / m3)
NOx (μg / m3)
Particulate matter (size less than 10µm) or PM10 (μg / m3)
Particulate matter (size less than 2.5µm) or PM2.5 (μg / m3)
Ozone (O3)
(μg / m3)
Lead (Pb) (μg / m3)
CO (mg / m3)
Ammonia (NH3)
(μg / m3)
Benzene (C6H6)
(μg / m3)
Benzo(a) Pyrene (BaP) - particulate phase only (μg / m3)
Arsenic (AS)
(μg / m3)
Nickel (Ni)
(μg / m3)
WORKSHOP BUILDING
3.0
15.0 60.0 26.0 <19.6 0.42 0.36 52.0 <0.1 <0.1 <1.0 <5.0
CCR
BUILDING 6.0 21.0 77.0 300 20.0 0.44 0.36 29.0 <0.1 <0.1 <0.1 <5.0
NEAR
WATER HARVESTING AREA OF CPP
6.0 18.0 62.0 23.0 <19.6 <0.40 0.18 33.0 <0.1 <0.1 <1.0 <5.0
DITC BUILDING
8.0 25.0 79.0 31.0 34.0 0.49 0.32 57.0 <0.1 <0.1 <1.0 <5.0
Ambient Noise monitoring report for the period April,2014 to September,2014
Particulars Sampling Locations
WORKSHOP BUILDING
CCR BUILDING
NEAR WATER HARVESTING AREA OF CPP
DITC BUILDING
Noise level ( Lday) during day time 65.0 67.1 66.9 67.0
Noise level ( L night) during night
time 52.5 53.8 53.9 54.1
Annexure -2
Green Belt Development at OCL India Limited, Rajgangpur
• OCL has already developed green belt in 38 % of the total area by planting more than 1.9 lacs of trees up
to October 2014 in and around the factory and planned to increase it by massive plantation of 9000 trees
every year.
• An area is earmarked for greenbelt development / plantation in the proposed CPP project. The saplings
shall be planted @ 2500 trees per ha.
Sl. No. Year No. of saplings to be
planted (nos.)
Present Status
1 2011 500 Completed
2 2012 250 Completed
3 2013 250 Completed
4 2014 250 Completed
5 2015 250 Ground work preparation in progress
Total 1500
OCL INDIA LIMITED
Rajgangpur
In its 63 years of untiring service to Nation, OCL has always given priority to community development. In its endeavor to
uplift the conditions of poor and hapless tribal of this locality, OCL has undertaken various developmental activities in
peripheral areas of Rajgangpur and Lanjiberna. The activities are mainly focused on areas like Health, Education, Drinking
Water, Community Development, Livelihood Training, Games and Sports etc. The activities organized during the current
year i.e. 2013-14 are given below.
HEALTH :
Sl.
No.
Activity Expenses
incurred
Approx.
beneficiaries
1 Mother and Child Health Care Project (Preventive health care for preg- mothers,
lactating mothers, children 0-6 yrs, adolescent girls, eligible couples,
strengthening GKS )
741000 3000
2 Providing free treatment to villagers in Lanjiberna Dispensary 2584988 21581
3 Providing free treatment in homoeopathic dispensary at Rajgangpur and
Lanjiberna
219853
3064
4 Donation to Bharatiya Jana Seva Sansthan, New Delhi for operating a charitable
dispensary at Sonakhan
250000
4500
5 Providing treatment to villagers through Mobile Medical Unit in collaboration with
Help Age
900000
1415
6 Organised Mega Health Camp, Bone Mineral Density Camp, Physiotherapy Camp
at Lanjiberna
103119 1300
7 Organised awareness camps in villages on Save the Girl Child/ Anti Tobacco
Campaign/ HIV & AIDS/ Malaria/Dengue/Diarrhea (with street play distribution of
mosquito nets)
68189 1100
8 Helped individuals in need for medical treatment on specific surgery cases. 76402 5
Total 4, 943,551 35965
EDUCATION :
Sl.
No.
Activity Expenses
incurred
Approx.
beneficiaries
1 Running Remedial Education Centre for students of St IX & X in 3 schools
(coaching + counseling with students & parents)
163,000 183
2 Running Novodaya Coaching centre at Kheramuta village (Lanjiberna) 45,000 22
3 Running free school bus service for students of villages around mining area
(since July 2013 to Jan 2014)
538,703 140
4 Financial assistance provided to St. Mary’s Girls High school 100,000 400
5 Provided financial assistance to schools for paying remuneration to
additional teachers (Shramik High School, Bihabandha, Nodal UP School,
Lanjiberna , GEL Church High School -, centre for differently able HOPE)
165,000 595
6 Water supply provision created at Santadevi High School , Katang 71,094 450
7 Refurbishment work in Dalmia College Building, Jhagarpur 550,000 750
8 Provided financial assistance to Bharatiya Jana Seva Sansthan, New Delhi
for operating two primary schools in Goriamunda
150,000
250
9 Running 45 units of ‘Ekal Vidyalaya’ through Friends of Tribal Society
around Rajgangpur and Lanjiberna
720,000
1,100
10 Organised debate, drawing competition in 11 schools, Ekal Vidyalaya and
Nursing College with distribution of exercise books/ dictionary/ Nursing
books
79,480 935
11 Distribution of exercise books/nursing books in schools & nursing college 25,000 500
12 Electrical wiring work with supply of light and fan in Babudih UP School . 25,925 235
13 Provided financial assistance to meritorious poor children for pursuing
study.
135,000
63
Total 2,768,202 5,623
DRINKING WATER :
Sl.
No.
Activity Expenses
incurred
Approx.
beneficiaries
1 Installation of tube wells in villages 23 units 1,733,450 2450
2 Repaired tube wells and made them functional 146,760 1100
3 Created provision for drinking water in one common place at Liploi 140,000 1000
4 Arranged "Jal Chhatra" at Rajgangpur and Lanjiberna during Summer 11,240 8000
6 Developed water supply systems at Bihaband square 82,991 1400
Total 2,114,441 13950
COMMUNITY DEVELOPMENT :
Sl.
No.
Activity Expenses
incurred
Approx.
beneficiaries
1 Constructed one community toilet at Kesramal village 405,000 5000
2 Arranged repairing of village road from Kheramuta to Saliamuta 29,780 350
3 Maintained Theme Park at Sundargarh. 447,881 20335
4 Celebrated Chhat Puja and X-mass 33,839 1900
5 Construction & erection of community stage at Girjatoli 312,000 100
6 Drain cleaning work at Lanjiberna 53,880 3000
7 Renovation of recreation centre for elder people at Kunmur village 50,788 160
8 Refurbishment/Repairing work in building / structures used by community
people (Anganwadi centre/ boundary walls of school and common centre )
56,714
1300
9 Construction work of village drainage line at Dhaurada village 24,114 1350
10 Repairing of village roads & maintenance of village infrastructure 84,692 1368
11 Beautification work at Kutra Tahsil & Court premises 66,961 150
12 Distribution of blankets to destitute old people 300,948 1400
Total 1,866,597 36413
LIVELIHOOD TRAINING:
Sl.
No.
Activity Expenses
incurred
Approx.
beneficiaries
1 Organised Livelihood Training at DITI (on Mason / Driving ) 286,000 34
2 Running career counseling programme for unemployed youths and
students (of St IX to XII) through Nirmaan organization, Hyderabad
939,743 2188
3 Training programme at CTTC & Kalinga Career Academy 5,220 56
4 Running tailoring training centre in 4 location and advance training in one
location for women
202,978 127
5 Training of women on income generating projects with supply of materials
(7 events)
103,977
176
6 Capacity building training of women SHG members 58,905 635
Total 1,596,823 3216
GAMES & SPORTS :
Sl.
No.
Activity Expenses
incurred
Approx.
beneficiaries
1 Organised Inter-Village Dalmia Cup Hockey Tournament and OCL Cup
Hockey Tournament
143,528 1300
2 Initiated Hockey coaching training for 25 girls and 25 boys < 14Yrs age 25,281 50
3 Organised Inter Village Dalmia Cup Football Tournament at Rajgangpur 75,850 800
4 Provided games and sports materials to Youth Clubs in villages 55,133 485
5 Organised Inter-School Athletic Meet 92,600 1085
Total 392,392 3720
PLANTATION :
Sl.
No.
Activity Expenses
incurred
Approx.
beneficiaries
1
Organised Banamahotsav and Brukshya Mela (including procurement of
more than 6000 grafted plants )
141,533
1400
Total 141,533 1400
SUMMARY EXPENSES 2013-14
CSR Thematic Areas Expenses incurred
(Amount in Rupees)
Approx. beneficiaries
HEALTH 4,943,551 35965
EDUCATION 2,768,202 5623
DRINKING WATER 2,114,441 13950
COMMUNITY DEVELOPMENT 1,866,597 36413
LIVELIHOOD TRAINING 1,596,823 3216
GAMES & SPORTS 392,392 3720
PLANATION 141,533 1400
Contribution to CM Relief Fund 5,100,000 00
Donation to Lions Club for Relief work 200,000 1000
Setting up of OCL Eye Centre at Rgp 18,600,000 00
TOTAL 37,723,539 101287
SUMMARY OF EXPENSES INCURRED DURING LAST 3 YEARS (All amount Rupees in Lakh)
2011-12 2012-13 2013-14
Expenses Beneficiaries Expenses Beneficiaries Expenses* Beneficiaries
HEALTH 32.91 45,000 41.83 60,439 49.44 35,965
DRINKING WATER 6.94 20,000 10.28 36,015 21.14 5,623
COMMUNITY
DEVELOPMENT
12.89 3000 12.32 24,680 18.67 13,950
LIVILIHOOD TRAINING 2.79 75 4.77 82 15.97 36,413
EDUCATION 25.92 7500 30.90 7,731 27.68 3,216
PLANTATION 0.95 0.89 2,000 1.42 3,720
SPORTS 2.70 950 2.55 2,685 3.92 1,400
ACTIVITIES THROUGH
SDPDC, SUNDARGARH
33.00 500 0.00 00
CHARITY & DONATIONS
(Through Lions Club)
31.00 2.00 1,000
Contribution to CM Relief
Fund for emergency
relief)
51.00
Setting up OCL Eye
Centre at Rajgangpur
186.00
Total 116.10 76,525 136.54 1,34,132 377.24 101,287