regulatory change measurement (rcm) calculating delay costs these slides available at:

24
Regulatory Change Measurement (RCM) Calculating Delay Costs These slides available at: www.dtf.vic.gov.au/betterregulation Questions to: [email protected] Version 1.0 dated June 2010

Upload: jack-chase

Post on 26-Dec-2015

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Regulatory Change Measurement (RCM) Calculating Delay Costs These slides available at:

Regulatory Change Measurement (RCM) Calculating Delay Costs

These slides available at: www.dtf.vic.gov.au/betterregulation

Questions to: [email protected]

Version 1.0 dated June 2010

Page 2: Regulatory Change Measurement (RCM) Calculating Delay Costs These slides available at:

Contact the Better Regulation Unit (BRU)

If you expect to measure the cost of delays, please contact BRU in the first instanceBRU will take you through the key steps of the methodology and agree to the methodology and formula to be usedThese slides are intended to be an introduction

Page 3: Regulatory Change Measurement (RCM) Calculating Delay Costs These slides available at:

What are delay costs?

Delay costs are the expenses and loss of income incurred by a regulated entity through:

-an application delay and/or -an approval delay

Page 4: Regulatory Change Measurement (RCM) Calculating Delay Costs These slides available at:

Application delay

This refers to the time taken by a regulated entity to complete an application (e.g. for a licence or permit)

To be counted as a delay, an application delay must:-prevent operations from commencing-not coincide with a parallel process during the course of application,

including business processes normally undertaken during that period

Page 5: Regulatory Change Measurement (RCM) Calculating Delay Costs These slides available at:

Approval delay

This refers to the average time taken by a regulator to communicate a final decision regarding the application, and includes a ‘normal’ level of re-work of the application

To be counted as a delay, an approval delay must:-prevent operations from commencing-not coincide with a parallel process during the course of application,

including business processes normally undertaken during that period-not double count parallel processes of re-work during the approval

process

Page 6: Regulatory Change Measurement (RCM) Calculating Delay Costs These slides available at:

Examples of Delay Costs

Holding costs of land while waiting to commence operations

- interest on loans for land, and-opportunity cost of capital (equity) blocked in land

Standby costs of capital (plant and machinery of machinery) not able to be used due to a regulatory process

- interest on loans for plant and machinery, -opportunity cost of equity in plant and machinery, and-rental costs

Page 7: Regulatory Change Measurement (RCM) Calculating Delay Costs These slides available at:

Examples of Delay Costs (contd)

Standby costs of labour unable to be put to use due to a regulatory process

-wages and overheads

Lost business opportunities-loss of reputation due to late deliveries-reduced flexibility to respond to market conditions-more difficult to obtain finance

Page 8: Regulatory Change Measurement (RCM) Calculating Delay Costs These slides available at:

Mapping the delays

Reference: Toolkit 1

Page 9: Regulatory Change Measurement (RCM) Calculating Delay Costs These slides available at:

Key question: Does an obligation delay the activities of a regulated entity?

Will removing a regulation or obligation allow the regulated entity to commence operations earlier?

– then such obligation could potentially be a cause of delay

To precisely identify whether the obligation causes a delay, a project management GANTT chart is useful

– Are the activities to comply with an obligation part of the critical time path of a business project?

Page 10: Regulatory Change Measurement (RCM) Calculating Delay Costs These slides available at:

Identification of delay – GANTT chart

In this figure the red dotted lines during the application process represent the actual time that could be saved by a regulated entity if the relevant obligation was removed (i.e. these portions are on the critical path)

See next slide for detailed explanation

Page 11: Regulatory Change Measurement (RCM) Calculating Delay Costs These slides available at:

Identification of delay – illustration

For example, if a building company is no longer required to prepare the building fire plan during the application process, this will remove the Regulatory Process 2 (RP2) in the figure above. However, as it must also demonstrate at the same time why its buildings meet the environmental requirements (RP1), the reduction in the length of the application process is only equal to the dark blue section of RP2.

Regulatory process 1

Regulatory process 2

Over-lapping time period with Process 1

0 1 2 TIME

Page 12: Regulatory Change Measurement (RCM) Calculating Delay Costs These slides available at:

Identification of delay – illustration (cont’d.)

Re-iteration: The reduction in the length of the application process by removing RP2 is only equal to the dark blue section

Regulatory process 1

Regulatory process 2

0 1 2 TIME

Time saved by removing Regulatory Process 2

Page 13: Regulatory Change Measurement (RCM) Calculating Delay Costs These slides available at:

Identification of delay – another illustrationIn the case below, if RP4 is removed, then re-work for RP4

is also removed. However, as this re-work is completed within the same

time as re-work for RP2 (a separate, parallel process) the length of the approval process is not reduced in this case.

Page 14: Regulatory Change Measurement (RCM) Calculating Delay Costs These slides available at:

Identification of delay – another illustrationIn the case below, if RP4 is removed, then re-work for RP4 is also

removed. However, as this re-work is completed within the same time as re-

work for RP2 (a separate, parallel process) the length of the approval process is not reduced in this case.

StartT=0

SubmitT=1

ApprovedT=2

Application Process Government Approval Process

Re-work RP2

Re-work RP3

Re-work RP5RP4

RP2

RP3

RP1

RP5

Re-work RP4

Page 15: Regulatory Change Measurement (RCM) Calculating Delay Costs These slides available at:

Calculating Delay Costs

Reference: Toolkit 2

Page 16: Regulatory Change Measurement (RCM) Calculating Delay Costs These slides available at:

RCM formula for costs

In this case this translates to:

X

Regulatory costs(total $)

Price (P) Quantity (Q)

Cost per business Number of businesses/ total ‘quantity of assets’

Delay Cost = Price × Quantity = {(costs incurred + opportunity cost) × delay period} × (population)

Page 17: Regulatory Change Measurement (RCM) Calculating Delay Costs These slides available at:

Example: Cost of delays caused by planning application process

The example below provides a formula for delays during a planning application process

Note: There can be many other examples of delay costs, and different ways to assess them

Lt

ROIDITTC

RθrτiC

12

costsDelay

Discussed in next slides

Page 18: Regulatory Change Measurement (RCM) Calculating Delay Costs These slides available at:

Price variables for delay costsThe cost incurred by each business is the holding costs of

the asset (land) minus any rents received if the asset is rented out during the period in which the project is delayed

Note: The term C x i also captures the return that could have been obtained on equity in the absence of the delay

annumper dollarsin Rents,R

processn applicatio during any) (ifout rented Proportion

annumper percent in rates, Councilr

annumper percent in tax,

interest of ratemarket at the annum,per percent in rate,interest i

hectareper cost land Total

where

C

RθrτiC

Page 19: Regulatory Change Measurement (RCM) Calculating Delay Costs These slides available at:

Price variables for delay costsThe opportunity cost – the best alternative use for the

capital (net total cost of the alternative investment over the life of the original project multiplied by the return on investment)

Time (duration) of the delay

annumper percent project, investment theof investmenton Return ROI

yearsin duration,project planned OriginallyD

counted) separatelybeen have which capitalon payments

interest (excluding project, investment on theout paid taxesandinterest TotalIT

wagesmaterial, raw capital, including project, investment theofcost TotalTC

ROI

D

ITTC

mapped as process, approval in the in timeReduction t

Page 20: Regulatory Change Measurement (RCM) Calculating Delay Costs These slides available at:

Quantity variables for delay costs

Population: refers to the number of entities affected by a particular regulatory obligation. In this case:

affectedation land/popul TotalL

Page 21: Regulatory Change Measurement (RCM) Calculating Delay Costs These slides available at:

Worked out example - delay costs from a planning processA normally efficient business wants to open a new manufacturing plant but is facing delays from the need to complete an application that requires it to document the impact of its proposed plant on the environment. These are its costs:

-the company buys ten hectares of land on which to build the plant-the total land cost per hectare is $50 000-the interest rate per annum charged by the lender is 10 per cent-the land tax per annum is 2 per cent-the council rates per annum are 2 per cent-during the application delay period the company rents out 50 per cent of its land to farmers who use it as grazing land for $4 000 per annum per hectare

Page 22: Regulatory Change Measurement (RCM) Calculating Delay Costs These slides available at:

Worked out example - delay costs from a planning process (cont’d)

Data relevant to calculating returns that the business is losing through the delay

-the total cost of the manufacturing project is $250 000 per hectare -total interest and taxes paid out on the project (excluding interest

payments on land which have been separately counted) is $100 000 per hectare

-the originally planned project duration is 20 years and the return on that investment is 7 per cent per annum

Page 23: Regulatory Change Measurement (RCM) Calculating Delay Costs These slides available at:

Worked out example - delay costs from a planning process (cont’d)

If the cause of delay is removed, the company is able to commence its operations 18 months earlierTherefore, as a result of removing that piece of regulation, the reduction in delay cost is $82 875 (see below)If this regulation affects 100 businesses, the total delay cost of this regulation is = $8 287 500 per annum (see below)

annumper 500 287, 8, $

1001812

07.020

10000025000040005.002.002.01.050000

cost Delay

12costDelay

LtROI

DITTC

RriC

Page 24: Regulatory Change Measurement (RCM) Calculating Delay Costs These slides available at:

Other examples

As indicated earlier, there can be many other examples of delay costs, and different ways to assess them

Please therefore contact BRU for a discussion of the specific methodology applicable in your case