remanufacturing in wind power: a multi ...1463409/...wind turbine manufacturing; figure 1 is a...

59
REMANUFACTURING IN WIND POWER: A MULTI CRITERIA DECISION ANALYSIS APPROACH Dissertation in partial fulfilment of the requirements for the degree of MASTER OF SCIENCE WITH A MAJOR IN WIND POWER PROJECT MANAGEMENT Uppsala University Department of Earth Sciences, Campus Gotland Graeme Robertson 05.06.20

Upload: others

Post on 27-Sep-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

REMANUFACTURING IN WIND POWER:

A MULTI CRITERIA DECISION ANALYSIS APPROACH

Dissertation in partial fulfilment of the requirements for the degree of

MASTER OF SCIENCE WITH A MAJOR IN WIND POWER

PROJECT MANAGEMENT

Uppsala University

Department of Earth Sciences, Campus Gotland

Graeme Robertson

05.06.20

Page 2: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

REMANUFACTURING IN WIND POWER:

A MULTI CRITERIA DECISION ANALYSIS APPROACH

Dissertation in partial fulfilment of the requirements for the degree of

MASTER OF SCIENCE WITH A MAJOR IN WIND POWER PROJECT MANAGEMENT

Uppsala University

Department of Earth Sciences, Campus Gotland

Approved by:

Supervisor: Sanna Mels

Examiner: Jens Nørkær Sørensen

05.06.20

Page 3: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

Abstract

Due to the rapid growth of the wind energy market over the last decade, the future of the

industry will consequently see the dismantling of many wind turbines, both due to wind

turbines reaching the end of their service life and to make way for surpassing technology,

leaving behind a large amount of material that must be dealt with. Furthermore, due to the

advancing technology of wind turbines, there has been a decline in the number of medium

sized wind turbines being manufactured. This study aims to address the problem of future

waste mitigation, whilst attempting to capture the medium scale market. As such, the study

has looked at the idea of transitioning towards a circular economy, in which wind turbines

are not considered as waste at the end of their service life, but rather an opportunity to

recapture value through remanufacturing. This was approached by identifying the driver

and barriers of remanufactured products, utilising knowledge from other industries with

developed remanufacturing sectors.

A Multi-Criteria Decision Analysis (MCDA) has been performed using the PROMETHEE II

method with the objective of drawing a comparison of three scenarios, enveloped by a

theoretical wind turbine selection project. The scenarios were created by the author and

considered the implementation of a new wind turbine and remanufactured wind turbines.

Upon examining the results of the multi criteria decision analysis, it was seen that the

benefits of implementing remanufactured turbines were preferred by the majority of

the stakeholders involved.

Page 4: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

Acknowledgements

This thesis has been written as the closing chapter of the master’s course in Wind Power

Project Management at Uppsala University and I would like to express my gratitude to

everyone who has helped me during the process.

To the Wind Energy department, thank you for one of the most interesting and challenging

years of my life. The dedication from all the lecturers throughout the year has allowed me to

leave with a wealth of knowledge, which I can take forward with me throughout my career.

Thank you to my supervisor Sanna Mels for your patience, advice and kind words.

To all my classmates, what a year it has been and what a pleasure it was to spend it with

you all! Thanks to Esma, Jim, Jason, Marc and Andis for all your help and positivity.

Finally, I would like to thank my family for all their support throughout my studies.

Page 5: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

NOMENCLATURE

MCDA Multi Criteria Decision Analysis

EOSLWT’s End of Service Life of Wind turbines

NREL National Renewable Energy Laboratory

LCA Life Cycle Analysis

NGO Non-Governmental Organisation

NPV Net Present Value

Page 6: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

6

Contents 1. Introduction ...................................................................................................................................... 8

1.2. Waste Material ........................................................................................................................ 10

1.3. Potential for a Circular Economy ............................................................................................. 11

1.4. Objectives................................................................................................................................. 11

1.5. Structure of the Report ............................................................................................................ 11

2. Literature Review ............................................................................................................................ 13

2.1. Sustainability ............................................................................................................................ 13

2.2. Triple Bottom Line .................................................................................................................... 14

2.3. Product Lifetime ....................................................................................................................... 15

2.4. End of service life of wind turbines (EOSLWT’s) ...................................................................... 15

2.5. Legislation and guidelines ........................................................................................................ 16

2.6. Circular economy ..................................................................................................................... 18

2.7. Economic potential of circular economy ................................................................................. 20

2.8. End of Life Operations.............................................................................................................. 21

2.9. Remanufacturing...................................................................................................................... 23

2.10. Remanufacturing in wind industry ......................................................................................... 24

2.11. Benefits of Remanufacturing in the wind industry ................................................................ 25

2.12. Introduction to MCDA ............................................................................................................ 27

3. Methodology ................................................................................................................................... 29

3.2. Microsoft Excel ......................................................................................................................... 31

3.3. PROMETHEE II .......................................................................................................................... 31

4. Project Description .......................................................................................................................... 34

4.2. Case Study ................................................................................................................................ 34

4.3. Life Cycle Analysis Review ........................................................................................................ 34

4.4. Scenarios .................................................................................................................................. 36

5. Stakeholder Selection ..................................................................................................................... 37

5.1. Investor .................................................................................................................................... 37

5.2. Developer ................................................................................................................................. 37

5.3. Public ........................................................................................................................................ 38

5.4. Environmental NGO ................................................................................................................. 38

5.5. Manufacturers ......................................................................................................................... 38

5.6. Governmental body ................................................................................................................. 38

6. Evaluation Criteria ........................................................................................................................... 39

6.1. Economic Criteria ..................................................................................................................... 39

6.1.1. Manufacturing Costs ............................................................................................................. 39

6.1.2. Net Present Value ................................................................................................................. 40

Page 7: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

7

6.1.3. Environmental Criteria .......................................................................................................... 40

6.1.4. Material Circularity Indicator ................................................................................................ 40

6.1.5. Energy to Manufacture ......................................................................................................... 42

6.1.6. Co2 to Manufacture .............................................................................................................. 43

6.2. Technical Criteria ..................................................................................................................... 43

6.2.1. Availability ............................................................................................................................. 43

6.2.2. Risk ........................................................................................................................................ 44

6.2.3. Lead Time .............................................................................................................................. 44

6.2.4. Product Development ........................................................................................................... 45

6.3. Social Criteria ........................................................................................................................... 45

6.3.1. Perceived Quality .................................................................................................................. 46

6.4. Summary of Criteria ................................................................................................................. 46

7. MCDA Results .................................................................................................................................. 48

8. Discussion ........................................................................................................................................ 52

8.2. Analysis .................................................................................................................................... 52

8.3. Limitations................................................................................................................................ 53

9. Conclusion ....................................................................................................................................... 54

9.1. Summary of the study .............................................................................................................. 54

9.2. Future Research ....................................................................................................................... 55

10. References .................................................................................................................................... 56

Page 8: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

8

List of Figures Figure 1:Top 10 onshore turbine manufacturer’s, 2016 (GW)(BNEF, 2016) ____________________________ 10Figure 2:Adaptation of waste hierarchy, taken from Ellen McArthur Foundation (ellenmcarthurfoundtion.org, 2017) ___________________________________________________________________________________ 17Figure 3:Illustration of linear economy's 'take-make-dispose' nature (ellenmcarthurfoundation.org 2017). __ 19Figure 4:Material flow in a circular economy (ellenmcarthurfoundation.org 2017) _____________________ 20Figure 5:Case studies of companies utilizing closed loop supply chain (Ellen McArthur Foundation, 2014) ___ 21Figure 6: Illustrative flow chart of the methodology ______________________________________________ 30Figure 7: Preference of Investor ______________________________________________________________ 48Figure 8: Preference of Developer ____________________________________________________________ 48Figure 9: Preference of Public ________________________________________________________________ 49Figure 10: Preference of Environmental NGO ___________________________________________________ 49Figure 11: Preference of Manufacturer ________________________________________________________ 50Figure 12: Preference of Governmental Body ___________________________________________________ 50Figure 13: Summary of preferred scenarios _____________________________________________________ 51

Page 9: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

9

List of Tables Table 1: Criteria Weighting. _________________________________________________________________ 32Table 2:Summary of components and average mass from LCA’s reviewed. ____________________________ 35Table 3:Summary of materials and average material mass from LCA's reviewed. _______________________ 35Table 4: Scale of Turbine Availability __________________________________________________________ 44Table 5: Scale of Encouragement of Sustainable Design ___________________________________________ 45Table 6: Scale of Perception of Quality _________________________________________________________ 46Table 7: Summary of Criteria ________________________________________________________________ 47

Page 10: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

10

1. Introduction 1.1. Growth of Wind Power

Recent years have seen the commitment of EU countries to an energy agreement which aims

to reduce greenhouse gas emissions by 40%, whilst increasing the consumption of renewable

energy to at least 27%. In 2016, wind power in Europe accounted for 10.4% of energy

consumption and 51% of the total installed power generation; globally however, it was China

that were making the biggest movement in the market, taking a 42.8% share of the global

installed market for the same year. With an increase in market growth, comes the increase in

wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind

turbine manufacturers.

Figure 1 is a representation of the manufacturing market leaders in 2016 with Vestas, GE

and Goldwind commanding the market of the installed capacity and the 2017 merger of

Siemens and Gamesa will result in the big three, becoming the big four.

1.2. Waste Material

The decommissioning of modern wind turbines is a relatively new process, but due to the

rapid growth of the market over the last decade, the future of the industry will consequently

see the dismantling of many wind turbines, both due to wind turbines reaching the end of

their service life and to make way for surpassing technology, leaving behind a large amount

of material that must be dealt with. Some estimates show that total waste material will

Figure 1:Top 10 onshore turbine manufacturer’s, 2016 (GW)(BNEF, 2016)

Page 11: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

11

increase an average of 12% per year between 2014 and 2026 and 41% per year between 2026

and 2034 (Anderson et al). To minimise the footprint on the earth, there are several ways in

which material can be handled; coupled with government legislation, wind turbine owners

have greater responsibility to handle the material in an environmentally sound manner. This

is resulting in a transition from a product life cycle which is linear, make, use, dispose, to a

more circular life cycle, in which the product remains in use either in full form or as a separate

product.

1.3. Potential for a Circular Economy

Circular economy is a concept which envelops the ideas and processes that are designed to

create a continuous improvement of today’s society, with the aim of utilizing the potential of

all products, components and materials, resulting in a reduction in the amount of material

and energy that is wasted to meet current human demand. Aside from the environmental

benefits a circular economy can provide, there is also the potential for companies to strive

economically, and products or services to be developed towards a more sustainable future.

1.4. Objectives

The objective of this report is to address the future waste issue within the wind energy

industry and seek for options to minimise its impact on the environment. The author aims to

look towards remanufacturing as a potential resolution to the problem by assessing the

drivers and barriers of remanufactured wind turbines; through the creation of a theoretical

project, a MCDA (Multi criteria decision analysis) will be carried out to make an evaluation of

the selection process between a remanufactured wind turbine and a new wind turbine. This

has led to the following research questions:

What are the driving factors for remanufacturing within the wind energy industry?

Using MCDA, how do these factors affect the outcome of the turbine selection process?

1.5. Structure of the Report

Chapter 2 of this paper presents a literature review deemed relevant to the end of service life

of wind turbines (EOSLWT’s) and the future potential of sustainability within the wind energy

industry as well as the implementation of MCDA in sustainable energy projects. This review

has enabled a better understanding of the benefits and barriers regarding the sustainable

Page 12: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

12

management of decommissioned wind turbines as well as identifying an appropriate tool to

compare the authors findings. Chapter 3 presents the methodology for the study, giving an

insight to the approach taken by the author with a description of the tools used, including

detailed description of the MCDA method PROMETHEE II. Chapter 4 outlines the theoretical

case study which the author has developed to compare the findings of the literature review.

The results from the study will be provided in chapter 5 before a conclusion and discussion of

the study, including potential future research in chapter 6.

Page 13: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

13

2. Literature Review

There are an increasing number of publications arising which reflect on EOSLWTs and the

issues involved. This literature review was carried out with the intention of reviewing

publications that cover several topics that are both directly linked to EOSLWTs and future

waste material, as well as the end of life opportunities that are currently available such as

reuse, recycling and remanufacturing. Furthermore, publications that explore the idea of

working towards an altogether more sustainable, circular economy were also reviewed.

2.1. Sustainability

Humans, per capita, are filling land fill sites at a faster rate than the planet can accommodate

and are consuming more resources than the planet can reproduce, notably more so in

Northern industrialised countries as well as large cities in Southern countries (Princen 1999).

Humanity’s Ecological Footprint is a measurement, which aims to compare human

consumption of renewable resources and ecological services against natures ability to supply

them (Rees, 1996) a recent study has calculated that it had exceeded the Earth’s total bio-

capacity, the regenerative ability of nature’s resources, by more than 60 percent in 2012

(WWF, 2012). Alongside growing population and technology, rising consumption is one of the

three major causes of changes in the global environment which provoke warning signs of the

potential for even larger footprints in the future (Princen, 1999).

The need to take responsibility and combat this problem has been growing over the past

few decades, leading to the concept of sustainable development, which was first coined

in the Brundtland Report in 1987, with the following definition;

‘development that meets the needs of the present without compromising the ability of

future generations to meet their own needs’ (WCED, 1987).

Following its release in 1987 there has been a plethora of modified definitions of

‘sustainability’ and ‘sustainable development’, with an estimated three hundred definitions

currently existing within the disciplines that are either directly or indirectly related (Johnston

et al, 2007). This is due to imprecise designation and recognition of sustainable development

terminology as well as different term usage depending on geographical area (Glavič et al,

2007). However, amongst the many interpretations of sustainability and what

Page 14: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

14

it encompasses, there are two recurring themes throughout the literature; the first theme,

introduced in the Brundtland (1987) report, is the theory that sustainable development is

allowing today’s generation to meet their needs without affecting future generations ability

to meet theirs. The second theme, also present in the report is that if progress is to be truly

sustainable it must address environmental, economic and social aspects simultaneously to

succeed. Incorporating both themes for a combined interpretation would suggest the

following definition: Addressing economic, environmental and social factors to meet the

needs of today, without affecting future generation’s ability to meet theirs. Such terminology

has ultimately lead to the development and creation of the term ‘triple bottom line’ or, the

‘three pillars’ of sustainability.

2.2. Triple Bottom Line

Triple Bottom line is a term developed in 1994 by Elkington (1998) due to the

understanding that to make real environmental progress the social and economic

dimensions, which had been flagged in the Brundtland Report previously, would have to

be addressed in a more integrated way (Henriques 2004). In the first chapter of Enter the

Triple Bottom Line, written by Elkington, he states that the term of TBL came about

through no single moment of realisation “...instead, in 1994 we had been looking for new

language to express what we saw as an inevitable expansion of the environmental agenda

that sustainability had mainly focused upon to that point”.

The concept is based on the idea that an organisations performance should be measured in

relation to all stakeholders, including local communities and governments, not just the

stakeholders with whom it has direct relations with, such as employees, suppliers and

customers (Hubbard, 2009). It is believed that many organisations find the concept of TBL

untoward, as it suggests that the common company responsibilities go much further than

simply producing products and services that customers want for economic benefit, by

incorporating social and environmental aspects as well (Hubbard, 2009). However, the Triple

Bottom Line suggests that when economic, environment and social performance intersect,

the company has the ability to have a beneficial effect on society and the natural environment

whilst simultaneously achieving long term economic benefits, as well as providing a

competitive advantage over other companies (Carter et al, 2008).

Page 15: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

15

2.3. Product Lifetime

The definition of the life time of a product can be unclear with the exact beginning and

end of a products lifetime proving to be a grey area. The lifetime of a wind turbine is more

commonly referred to as the ‘service life’ due to the nature of the products function. The

definition of service life can be defined as follows: ‘the period from when a product is

acquired until the moment it is disposed of’ (Cooper, 1994).

2.4. End of service life of wind turbines

For wind turbine’s the product lifetime refers to the moment of commissioning until the

moment of decommissioning. Cooper et al (2010) distinguishes further definitions which

are appropriate to the wind energy industry:

1. The technical lifetime being the maximum period a product has the physical

threshold to function.

2. The replacement or economic lifetime being the period from initial sale to the point

where the owner buys a replacement regardless of the product functioning or not

(Cooper, 2010).

As a turbine nears its end of life, its performance begins to deteriorate, due to mechanical,

environmental and technological ageing and therefore, in most cases, it becomes

uneconomical for it to continue operating. It is at this stage where the owner/operator has a

responsibility to decommission the turbine(s) as part of their ongoing commitment to its

initial development. It has become customary practice to have decommissioning plans

submitted as part of the initial project plan and environmental impact assessment, where

financial security for the decommissioning project must be established through a bond, which

will cover all or part of the costs; it is noted that the sum required, as well as who is responsible

for its management, varies between and within countries (Alden et al, 2014). The UK Energy

Act (2008) requires developers to demonstrate that payment to the decommissioning fund is

evident in the annual returns, ensuring transparency and minimising risk to the tax payer

(Scottish Government, 2008)

Full or partial decommissioning, for both onshore and offshore wind turbines, must be

considered by the owner, where the former involves returning the site back to its previous

state, and the latter can result in components, such as foundations or cables, remaining on

Page 16: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

16

site, under conditions that it causes minimal disruption to the surrounding environment and

habitat. In either case, it is important to consider the way the site is decommissioned, and the

decommissioning plan should consist of habitat and protected species surveys as performed

in pre-development environmental impact assessments. The subsequent dismantling of the

wind turbine(s) of course leads to an inventory of components and material which the

responsible party must manage.

Many current publications express the concern regarding the growth of the wind industry and

relative inexperience when it comes to end of service life (EOSL) (Andersen et al, 2016.,

Andersen et al, 2007., Ortegon et al, 2013., Topham et al, 2016). However, there is a distinct

lack of research on the technological, environmental, and economic issues associated with the

EOSLWT’s, because of its past subservience. It is noted that this is due to the relative infancy

of the industry, resulting in next to no historical data available for use (Ortegon et al, 2013).

The publication by Andersen et al (2016) attempts to address these concerns by quantifying

future waste material, expressing the importance of ensuring there is sufficient recycling

capacity. The study is specific to the growth of the wind industry in Sweden and the

subsequent increase in wind turbine waste over the next two decades; it estimates that total

waste material will increase an average of 12% per year between 2014 and 2026 before taking

a dramatic spike to an average of 41% per year between 2026 and 2034. This increase in

estimated waste is relevant to the growth of the wind industry around a decade before now,

which resulted in the annual increase of installed capacity.

2.5. Legislation and guidelines

There are several legislations and guidelines that developers must adhere to when deciding

how to manage the material accumulated from decommissioning, and developers are obliged

to create a site waste management plan as part of these requirements (Scottish Government,

2008). An example of such is when in 2010, the Scottish Government published its Zero Waste

Plan, intended to provide guidance through a waste, economic

and resource strategy in support of their aim of achieving a ‘zero waste’ society. It envelops

22 actions that will help to deliver the Zero Waste vision of Scotland:

Page 17: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

17

• ‘where everyone – individuals, the public and business sectors - appreciates the

environmental, social and economic value of resources, and how they can play

their part in using resources efficiently;

• reducing Scotland’s impact on the environment, both locally and globally, by

minimising the unnecessary use of primary materials (materials in their first life

cycle; raw materials), reusing resources where possible, and recycling and

recovering value from materials when they reach the end of their life;

• about helping to achieve the targets set in the Climate Change (Scotland) Act 2009 of

reducing Scotland’s greenhouse gas emissions by 42% by 2020 and 80% by 2050;

• to contribute to sustainable economic growth by seizing the economic and

environmental business and job opportunities of a zero waste approach’ (Scottish

Government, 2010).

Multiple countries have adopted similar regulations in an attempt to coerce organisation’s

into taking more responsibility for the impact they are having on the environment. It

encourages the idea of sustainable development as aforementioned in Chapter 2.1.

This concept is further echoed by ‘The waste hierarchy’, which refers to the ranking system,

set out by the European Waste Framework Directive, for the management of waste material

(European Parliament 2008/98/EC), and can be considered the foundations of which the

Scottish Government sets its waste regulations on. It is intended to have a positive impact on

waste prevention and reduce the amount of waste that is being sent to landfill. Figure 2

represents the waste hierarchy in ascending order.

Figure 2:Adaptation of waste hierarchy, taken from Ellen McArthur Foundation (ellenmcarthurfoundtion.org, 2017)

1. Prevention of waste: A factor that aims to directly reduce the amount of material

entering circulation. This can be done through the design of product which require

less material, and the use of less hazardous materials.

Page 18: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

18

2. Preparing for reuse: Involves the inspection, cleaning, repairing and refurbishment

of products or components, to be re-entered into the product life cycle in a

functional condition.

3. Recycling: The action of turning waste material in to a substance or new product,

effectively giving the material a new life.

4. Other recovery: Such as energy recovery is where the material can no longer be

used for practical purposes and therefore is processed by means of gasification or

pyrolysis to produce fuel, heat and power as an energy source.

5. Disposal: When the material has no further potential, and is sent to landfill or

incinerated without recovery, and is the last resort is regards to the waste hierarchy.

Similar plans have been developed throughout Europe and the planning of wind

power projects must adapt to these and further changes in legislation that will no

doubt arise in years to come (ellenmcarthurfoundation.org 2017).

2.6. Circular economy

The Circular economy is a concept which envelops the ideas and processes that are designed to

create a continuous improvement of today’s society, with the aim of utilising the potential of all

products, components and materials, resulting in a reduction in the amount

of material and energy that is wasted to meet current human demand. Its emergence is owed

to the flawed linear ‘take-make-dispose’ model, represented in Figure 3, which society has

adopted, where continuous, copious amounts of energy and resources are used to create

consumables which are disposed of when there are deemed unfit for purpose.

Page 19: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

19

Figure 3:Illustration of linear economy's 'take-make-dispose' nature (ellenmcarthurfoundation.org 2017).

Stahel (1998) addresses this linear model adding that terms such as ‘value added’, the point of

production, ‘value write off’, the depreciation of value after sale and ‘waste’, the end of the

product life, only amplify the need for a change in the way we operate as responsibility for the

product does not leave ‘the factory gate’. A circular economy addresses these issues by creating

an industry which is ‘restorative and regenerative by design’. It is noted that there is no single

origin of the concept of a circular economy however it began gaining more recognition for its

implementation on the modern economic systems and industrial processes during the 1970’s

(Ellen McArthur Foundation, 2017).

The Ellen McArthur Foundation is an organisation founded by Dame Ellen McArthur, which

aims at promoting this concept, describing it as ‘a potential way for our society to increase

prosperity, while reducing dependence on primary materials and energy” (Ellen McArthur

Foundation, 2015). Figure 4 shows the cyclic model which is an adaptation of the drawing from

McDonough et al (2002) book “Cradle to Cradle”. It illustrates the three principles

considered to be essential to a circular economy, looking at both the biological and technical

material flow through what is labelled the “value circle” as seen in Figure 4 below.

Page 20: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

20

Figure 4:Material flow in a circular economy (ellenmcarthurfoundation.org 2017)

2.7. Economic potential of circular economy

Further to the environmental benefits of a circular economy, there are publications that look

at the potential economic opportunity which lies within products that can have recoverable

value. Closed loop supply chains refer to the recovery of products or their components within

one system to reuse for further value. A definition of this can be considered as “the design,

control, and operation of a system to maximize value creation over the entire life cycle of a

product with the dynamic recovery of value from diverse types and volumes of returns over

time. (Guide and Van Wassenhove 2006, Managing product returns for remanufacturing).”

The reason for such potential of recoverable value is detailed in the publication Towards

the Circular Economy 3: Accelerating the Scale (2014), which suggests that economies,

companies and consumers will all benefit from such a strategic shift. It further describes

that the reduction in material and energy costs as well as a more stable hand on material

volatility and supply chain risks would see economies flourish. Companies would benefit from

secondary markets and “competitive advantage”, whilst consumers would reap the benefits

of improved choice and better service quality”. The publication further emphasises the

potential to create more resilient economies through better material productivity, and the

evolution from the current low skilled “mass production” labour to one with a much higher

skill set, which will signify a move that would make it harder to revert to the linear economy.

Page 21: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

21

The publication by Atasu (2008) takes a broader look at the economic benefits of a closed

loop supply chain, explaining that many publications simply assume that product retrieval and

its reusable quality thereafter, is often considered a formality. Geyer et al (2007) further state

that even with the quality of the product remaining at the standard of its first life, there are

many other factors that are required for a closed loop system to be profitable, such as a

steady used product collection rate, durability and product life cycle.

Towards the Circular Economy 3: Accelerating the Scale Up gives recognition to the

importance of collection and reverse logistics to improve material productivity and provides

case studies of companies that have successfully been able to use a closed loop system to

their benefit economically (Ellen McArthur Foundation, 2014). An example of the case studies

is provided as reference in Figure 3.

Figure 5:Case studies of companies utilizing closed loop supply chain (Ellen McArthur Foundation, 2014)

2.8. End of Life Operations

Reuse, recycling, repair, reconditioning and remanufacturing are the five general terms

encompassing techniques which can help achieve sustainable development (Ijomah, 2010).

Ijomah (2010) categorises remanufacture, reconditioning and repair as ‘addition’ processes

that use components from used products, also known as; component reuse, product recovery

Page 22: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

22

or secondary market; since they typically involve some degree of disassembly they are further

referred to as disassembly processes. These processes are generally preferable to recycling,

which is the process of collecting, sorting and processing discarded materials to use in the

production of new products. The paper elaborates further, listing the advantages that product

recovery strategies have over recycling. These include; bringing products back to working

order through product recovery, which is adding value to waste whereas recycling reduces

products to its raw materials. Product recovery also attempts to keep products as whole as

possible, which reduces the overall energy and resources. When recycling, all the energy and

resources are lost from the initial manufacture with potential to use significantly more energy

in raw material extraction, transportation and processing of these reclaimed raw materials

to make new products. Product recovery retains the energy used in the initial

manufacture (King et al, 2006). Considering the reuse at the end of life of a product whilst

designing can allow producers to effectively meet the environmental, legislative and

competitive needs through the following:

• Increasing product life, meaning it takes longer before the product is discarded.

• Enabling servicing of products at the end of use, so that they can be used again.

• Enabling materials of the product to be recycled and used to make new ones if not

suitable for product recovery or reuse.

• Enabling used components to be used in new products.

Ijomah et al (2004) hypothesised that the ambiguity surrounding the definition of

remanufacturing and the inability to differentiate between the strategies was a major barrier

that was impeding the uptake of product recovery and re-use processes in industry. The

research conducted produced a robust definition as well as establishing the distinct differences

between remanufacturing, reconditioning, repair and recycling including the work content

required. The concluding definitions of the research are detailed:

“Recycling: Reducing a used product to the value of its component material, though

complete disassembly and processing.

Remanufacture: Returning a used product to original or improved specification with a

warranty that matches or is greater than the new component; through inspection,

disassembly, cleaning, reprocessing, reassembly and testing.

Page 23: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

23

Reconditioning: Returning a used product to satisfactory condition through the

replacement of faulty or worn components. Commonly with a warranty less than that

of the new equivalent.

Repair: Fixing identified fault within a product to return it to working condition.

Warranties generally only cover the repaired part and are less than that of new

equivalent products.”(Ijomah et al. 2004)

2.9. Remanufacturing

Throughout the literature relating to sustainable manufacture, the concept that presents

itself most often is remanufacture. The publication by Andersen et al (2007) notes that the

future handling of material is unclear, suggesting that recycling will be the more prominent

process. As can be seen in the waste hierarchy (Figure 1), this disregards the potential there

is for a more sustainable handling of the material through prevention and reuse. Multiple

authors agree that remanufacturing is the preferable end of life process as it adds value to

products that may have been scrapped; helps to reduce landfill; reduces the level of required

virgin materials as well as reducing the energy levels required in the manufacturing phase

(Ijomah et al.,2004; Hatcher et al., 2011; King et al. 2004). Cooper (2010) adds that with the

aim of reducing the amount of material used within a process as well as energy demands, an

approach which doesn’t rely on recycling and instead, encourages product life extension,

should be applied. Hazen et al (2016) describes remanufacturing as “the ultimate form of

recycling”. A common understanding of the need for a clear definition of remanufacturing is

prominent throughout the literature reviewed (Ijomah et al, 2004., Ortegon et al, 2014). As

a reminder the definition of remanufacturing implies that a product that has been used and

therefore, considered to be at the end of its useful life cycle, is given a new life which

emulates the quality of its previous life through the dismantling, cleaning, repairing and

replacement of components and reassembly. This also means that after testing, it should

have a warranty that matches the product in its first life.

Many publications acknowledge Xerox as being a prime example of how companies can

effectively use remanufacturing to their advantage (Statham, 2006., King et al, 2006). The

company initially delved in to a new project they called “asset recovery” in 1987 by creating

Page 24: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

24

an entirely different subsidiary to their plant in the Netherlands, which had the aim of

retrieving old photocopying machines from the waste stream and to then process these

machines for resale. A successful venture which saw 75% of the machines being

remanufactured within a decade and even though the remanufactured machines were

competing on the market with the new machines that Xerox were producing, a saving of

$95M over the decade was made. A further example of successful remanufacturing, which

was depicted in Figure 3 Is that of Caterpillar, who have had an involvement in

remanufacturing since the 1970’s. They now claim to “provide customers with lower-cost

products, shorter downtime and quick, dependable service options”. It is not just the benefits to

customers and their business which has driven the company to expand their remanufacturing

programs, stating “we make one of the greatest contributions to sustainable development—

keeping non-renewable resources in circulation for multiple lifetimes.” This is a fitting example

of a company’s early embodiment of a circular economy.

2.10. Remanufacturing in wind industry

As the market for remanufacturing stands in wind power just now, companies who specialise

in remanufacturing look to procure used wind turbines before remanufacturing and selling

for profit. While there are used turbines currently available on the market, the process has

somewhat more uncertainty to it, as the original manufacturer is not simply collecting the

used turbine at the end of service life. This is not to say that the big players are not getting

involved in remanufacturing. Vestas and Caterpillar came to an agreement in 2011, which

would see the remanufacturing giants do what they do best on wind turbine components.

This allows Vestas to then sell their remanufactured components as part of their “spares and

repairs” department which is a positive move towards a circular economy

(windpowermonthly.com, 2017).

The study by Ortegon et al (2014), notes the potential for the medium size turbines market,

stating that this usually consists of turbines between 500kw-1500kw, however the study by

Walton and Parker (2008) suggests that the production of medium scale wind turbines has

slowed significantly due to the industry’s continuous scaling up where the focus is on

designing larger wind turbines with the main aim of creating larger profit margins.

Nonetheless, they predict that the market will become more prominent, with an estimated

Page 25: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

25

2000 units per year coming available by 2024. The main sectors that would consume this

market are those who are looking to make significant electricity cost savings, such as

communities, farmers, industrial plants and schools; all of which have already began to look

to wind power as a resolution (Parker et al, 2008).

2.11. Benefits of Remanufacturing in the wind industry

While the studies suggest there is the potential for remanufacturing to flourish with in the

industry, it is important to understand the benefits it would provide. Although the

ideologies of remanufacturing, such as the reduction in raw material usage and waste

prevention, are presented in previous sections of this literature review, the specific

impacts that it would have within the wind industry must be clarified.

Parker et al (2008), state that significant cost savings could be made from remanufacturing a

wind turbine rather than the purchase of a new unit. This is primarily down to the potential

saving in initial investment which is a key driver to the development of a wind power project.

Due to the lack of practice, or more specifically, research, on the economic benefits of

remanufacturing within the wind industry, it is difficult to provide detailed economic data on

the reduction in manufacturing costs; Ortegon et al (2014) notes that the current supply of

remanufactured turbines cost between 30-50% of that of a new turbine, a saving which can be

presumed to be down to the cost savings made from the processing of raw materials and

manufacturing of components. Further economic benefit can be found from the difference in

lead times to produce a remanufactured turbine to that of a new one. A report from NREL

(2004) state that the lead times for new wind turbines can be anything from 12 to 16 months,

where some remanufacturers are promoting a lead time of less than three months

(repoweringsolutions.org, 2017., PES Wind, 2017). The author has noted that this lead time

could be down to the high demand of new wind turbines compared to the low demand of

remanufactured wind turbines and this would most likely have to be reassessed as a benefit

should the remanufacturing market increase. However, the potential for reduced project

duration would be a key driver for the medium scale market.

As aforementioned, there are many industries which have a well-developed remanufacturing

sector and so potential energy savings of remanufacturing are somewhat better researched.

A study by Sutherland et al (2008) compares the energy intensities between the

Page 26: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

26

manufacturing and remanufacturing of diesel engines and reports energy savings of almost

90% compared to an engine manufactured from virgin material. Other literature based on

remanufacturing from multiple industries provide an overall average energy consumption

value of around 50% of that of a manufactured product. It is worth

noting that due to the high-performance requirements of wind turbines, there are several

components which will experience a high level of wear and tear during the lifetime of a wind

turbine. Any component which is exposed to the environment, such as the blades, will fall in

to this category as well as all moving parts that undergo an almost continuous amount of

stress such as the gearbox (PLATE, 2017). The study by Ortegon et al (2014) states that regular

maintenance of wind turbines will help to substantially reduce the risk of failure, while

bringing down maintenance costs and downtime.

There is room for improvement when it comes to the design of wind turbines. Inheriting a

design which makes maintenance or replacement of components a much simpler task would

be beneficial in further reducing financial risk of a wind turbine failing. The study by Charter et

al (2008) concluded that it is the design stage of a products lifespan which will have the

greatest impact on the cost, manufacturing and end of life possibilities.

Growth Within: A Circular Economy Vision for a Competitive Europe presents the idea that

such design activities would be further developed if companies were to share their

product information, ultimately leading to greater utilisation of products, development of

secondary markets and driving the markets economy and competitiveness. In turn, the

greater utilisation of products would lead to an optimisation of material circularity and

improvement on product design. The study concludes these thoughts by posing two

questions for companies:

If your products were designed for take-back, how much value could you

recapture from products sold?

If you had to take back all the products you sell, how would that affect design and

production?

This displays a perfect example of how the rethinking of the way products are designed could

prove beneficial to a company’s, and an industry’s economic growth. (Ellen McArthur

Foundation, 2015). As previously noted, remanufactured products are considered to emulate

the quality of its first life, however, multiple studies note that consumers, retailers

Page 27: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

27

and even remanufacturers do not perceive equality between them, suggesting that their

behaviour towards remanufactured product is altered (Hazen 2016.; Smith et al, 2008). Hazen

(2011) provides explanation by saying the consumers may see the remanufacturing process as

ambiguous, with particular uncertainty in the products past life as well as the necessary actions

required to bring the product back to original quality. Hazen et al (2016) goes on to note that

the perceived quality of a product is a multidimensional concept, which takes in to

consideration the products lifespan, features, performance and serviceability. Due to this

uncertainty on the product, studies on consumers “willingness to pay” have been conducted,

and it was concluded that when a remanufactured products cost is more than 70% of a new

product, the consumer would opt to buy the latter (Gan et al 2017).

2.12. Introduction to MCDA

As development of sustainable energy grows, many developers are turning to multi-criteria

decision analysis (MCDA) tools to help with the decision-making process of their projects. As

Wang et al (2009) notes, “MCDA is a form of integrated sustainability evaluation” and the reason

for its rise in popularity in the development of renewable energy is due to “the multi-

dimensionality of the sustainability goal and the complexity of socio-economic and biophysical

systems”. The study supports its use due to its ability to minimise the difficulty of the decision-

making process through comparison of influential, yet conflicting criteria, that have differing

data and perspectives. Georgopoulou et al (1997) goes on to express that the conflicting

criteria doesn’t simply show the multicriteria nature of sustainable energy, but also the need

to account for the interest of multiple stakeholders. This is echoed by Georgopoulou et al

1997., Mateo 2012) who notes that every new stakeholder that is involved will result in the

addition of new criteria and subjective opinions, which must be considered. He notes that the

stakeholders involved vary from investors, individuals, institutions, authorities, environmental

groups and governing bodies, all of which may have interests which directly or indirectly affect

the process of decision making. The aim of this study is to draw an outcome from one decision

within such projects, the selection of a wind turbine, with the focus on the reduction of waste

material through the utilisation of remanufactured turbines by comparing the economic,

environmental, technical and social criteria that would affect the decision-making process.

Page 28: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

28

There are several MCDA tools that have been used in the sustainable energy planning, which the

study by Watrobski et al (2016) have outlined in their study. They concluded that analytical

hierarchy process (AHP) was the most common tool used with analytical network process (ANP),

a generalised version of AHP also present. The study noted that these tools only allow for

qualitative data to be analysed, with the evaluation of quantitative data being sacrificed. Other

methods used were Technique for Order of Preference by Similarity to Ideal Solution, Simple

Additive Weighting or Ordered Weighted Averaging Aggregator (OWA) as well as the preference

ranking organization method for enrichment evaluation (Behzaidan et al, 2010). PROMETHEE II

is a further developed method from its predecessor PROMETHEE I which is said to be a more

comprehensive approach to decision making (Brans & Vincke, 1985).

Behzadian et al (2010) presents PROMETHEE II as a means of providing a ranking, from a finite

set of alternatives from the most preferred to the least. The fundamental working of

PROMETHEE II is to make pairwise comparisons of the alternatives against each of the

selected criterion (Behzaidan et al, 2010). PROMETHEE II has been used in this study on the

basis that it has been well implemented in previous studies which look at the development of

renewable energy projects; this is owed to its ability to relay conflicting economic,

environmental, social and technical data to decision makers, who may not be well rehearsed

in MCDA techniques, in a clear and concise manner (poladitis 2006, georgopulou). Further

description of the tool can be found in section 3.3.

Page 29: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

29

3. Methodology

3.1. Introduction

This chapter provides a description of the methodology used to complete the study with

further detailed description of the tools. The aim of this study is to assess the possibilities for

minimising the amount of material that will be wasted from future decommissioned wind

turbines through alternative end of life strategies. From the literature studied it was noted

that there was potential for developing a remanufactured market within the wind energy

industry. Upon this finding the author has decided to compare the driving factors of selecting

a remanufactured wind turbine rather than a new wind turbine. The focus is on the potential

for minimising the environmental effects that the industry in the future and the criteria of this

study reflect this. The MCDA tool which has been used is PROMETHEE II after research

showed that it has been successfully implemented in to projects within sustainable energy.

Furthermore, its straightforward application and comprehensive comparison of results

provide a clear outcome.

The wind energy industry is continuously seeing the improvement of wind turbine

performance; a noticeable attribute of recent technology is the physical growth of the

wind turbines. This has led to the depleted manufacturing of medium scale wind turbines

even though there is an ever-increasing market that would benefit from them, such as

communities, farmers and industrial companies. Furthermore, the market for

decommissioning wind turbines is set to rise drastically over the next few decades as we

see initial wind energy projects near the end of their service life meaning that there will

be a substantial amount of material that must be dealt with.

In an attempt to address both of these problems comparison of a wind turbine selection

process will be carried out and from the information gathered on the subject of

remanufacturing, and its potential implementation in to the wind energy sector, three

scenarios have been created. The identification of all the stakeholders that are affiliated

with a wind power project are considered before further refinement applied to suit the

objective of the study.

With thought given to the stakeholders involved, a list of possible criteria is created. This list

concentrates of driving factors that would directly impact the decision between the scenarios

Page 30: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

30

and therefore are relatable to manufacturing and remanufacturing. The criteria can be

divided in to four categories; economic, environmental, technical and social. Following this,

the data collected for the criteria as well as the preference of all stakeholders can be

processed using PROMETHEE II with the outcome being the understanding of the preferred

scenario for each stakeholder. A representation of this methodology can be seen in figure 4

Figure 6: Illustrative flow chart of the methodology

Page 31: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

31

3.2. Microsoft Excel

Data for many of the criterion was collected from several studies which had researched

the topic of remanufacturing. To apply the information gathered to this study, the author

has used Microsoft Excel to carry out calculations for some of the qualitative criteria. More

details of the relevant calculations can be found in Section 6.

3.3. PROMETHEE II

As Behzadian (2010) presents, the aim of PROMETHEE II is to provide a ranking from a finite

set of alternatives from the most preferred to the least. The fundamental working of

PROMETHEE II is to make pairwise comparisons of the alternatives against each of the

selected criterion. In this study he breaks down the working of PROMEETHEE II in to five clear

steps and so this study will follow the same approach. Before entering data in to the

PROMETHEE II method, the user must have assigned weighting to each of the criterion

selected. Ideally, the weighting of assumptions would involve the stakeholders input,

however, due to the lack of stakeholder availability, and for continuity, the author has decided

to weight the criteria based on assumptions, focusing on their main goals when considering

a project such as this. As can be seen in Table 1, the weighting of the criteria was created

using 100 points for each stakeholder across the 7 criteria. Each stakeholder’s preferences

differ and so the weighting of the points is solely based on their input, with no influence on

other stakeholders. This means that while stakeholder A may find a criterion 1 more

important than stakeholder B, Stakeholder A may also consider multiple other criteria of high

importance, which could lead to stakeholder B having a higher point score for criterion 1. A

list of the selected criteria and their weighting for the following study can be found in table 1.

Page 32: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

32

Table 1: Criteria Weighting.

Criteria Direction Investor Developer Public

Environmental NGO's

Manufacturers Governmental Body

Manufacturing Cost Min 22 16 17

2 18 8

NPV Max 23 15 13 2 3 2

MCI Max 2 3 8 23 13 14

Energy to Manufacture Min 2 5 8

20 11 17

Co2 to Manufacture Min 2 5 10

22 11 17

Availability Max 6 13 2 4 7 7

Risk Min 18 15 13 3 2 16

Lead Time Min 8 16 2 4 18 6

Product Development Max 2 4 8

18 10 7

Perceived Quality Max 15 8 19

2 7 6

Total 100 100 100 100 100 100

As aforementioned, the first step of the PROMETHEE II calculation is to perform the pairwise

comparisons, as denoted by Equation 1.

��(�, �) = ��(�) − ��(�)

Where ��(�, �) denotes the difference between the evaluations of actions �

and � for criterion �� (Behzadian, et al, 2010).

Step 2 is to application of the preference functions of each criterion. This allows for differing

criteria values to be calculated as a preference degree, through the Equation 2.

��(�, �) = �����(�, �)� � = 1, … ,�

Where �� is the preference of the alternative � compared to the alternative � for each criterion

� as a function of ��(�, �) (Behzadian, et al., 2010).

Following this, PROMETHEE II then calculates the overall performance index using Equation 3.

Page 33: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

33

∀�, � ∈ �, �(�, �) = ∑ ��(�, �)�����

Where �(�, �) of � over � (from 0 to 1) is defined as the weighting sum for each criterion and

� is the weight associated with the �th criterion. (Behzadian, et al., 2010)

Step 4 sees the tool calculate the positive and negative outranking flows. In the case of the

positive ranking flows, the calculation considers how much scenario � is preferred over the other scenarios. The negative ranking flow calculates how much the other scenarios are

preferred to scenario � (Haralambopoulos et al, 2003). The following equations illustrate this, respectively.

�(�) =�

���∑ �(�, �)�∈� and Ø�(�) =

���∑ �(�, �)�∈�

Where �(�)denotes the positive outranking flow and �(�) denotes the negative

outranking flow for each alternative (Behzadian, et al., 2010).

The ultimate step is to calculate the difference between the positive outranking flow and the

negative outranking flow to obtain the net outranking flow. This is shown in the Equation 6

Ø(�) = Ø + (�) − Ø − (�)

Where Ø(�) denotes the outranking flow for each alternative (Behzadian, et al., 2010.

Page 34: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

34

4. Project Description

4.1. Introduction

To evaluate the benefits and barriers of remanufactured turbines, the author has decided to

use the MCDA tool PROMETHEE II to compare multiple scenarios which include new and

remanufactured turbines. This tool was selected due to its ability to evaluate conflicting

quantitative and qualitative criteria, as well as utilising a straightforward method, resulting in

a clear outcome. The aim is to make use of the information gathered in the literature review

and draw a conclusion on whether there is potential for remanufactured wind turbines within

the wind energy industry as well as assessing MCDA as a decision-making tool. This chapter

presents a theoretical case study in which the project is solely based around the selection of a

wind turbine which could provide a solution to the future decommissioned material within the

industry as well as the need for medium scale wind turbines.

4.2. Case Study

As the focus of this project is based around the turbine selection process, there was no need

to choose a specific site, instead some boundaries that have been assumed for all scenarios

have been selected by the author, based on research of literature and available data. The

medium scale market usually consists of wind turbines with a capacity ranging from 500kW

to 1.5MW, however, this study will investigate a turbine of 2MW capacity, as this is the most

commonly presented in Life Cycle Analysis (LCA) literature.

4.3. Life Cycle Analysis Review

The first step of the project was to access multiple LCA’s of 2MW turbines, with the aim of

gathering a clearer picture on the average figures in focused areas. Six publications were

reviewed and a description of the information gathered is presented below (Garrett et al, 2012.,

Martinez et al, 2010., Vargas et al, 2015., Guezuraga et al, 2012., Ghenai, 2012., Vesta 2011).

• Performance: a clearer picture on the overall performance of a 2MW wind turbine was

required so that the author could make an accurate assumption on electricity

generation. Whilst it is understood there is an abundance of factors contributing to

Page 35: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

35

the performance of a wind turbine, this project simply requires a best guess figure

for consistency throughout.

Average lifetime: an understanding of the average service life of the wind turbines

in the LCA’s was required.

Bill of components: a list of the major components considered in LCA’s was then

required.

Bill of materials: a list of the material type as well as the average mass of material

in the LCA’s was calculated.

Once all the necessary information was gathered, a table of the averages of the data sets

listed was created; this is represented in Tables 2 and 3.

Table 2:Summary of components and average mass from LCA’s reviewed.

Capacity (MW)

Lifetime (Years)

Components Sub-component

Component Mass (Tonnes)

2 20 Rotor Three blades 22

Hub 9

Tower - 153.6

Nacelle Main Shaft 9.05

Transformer 7.5

Generator 8.25

Others 8.75

Gearbox 18

Nacelle Cover 3

Table 3:Summary of materials and average material mass from LCA's reviewed.

Material Material Mass (Tonnes)

Mass %

Steel 202.35 72%

Cast Iron 39.25 14%

Copper 5.25 2%

Fiberglass 18.11 6%

Resin 13.08 5%

Aluminium 2 1%

TOTAL 280.04 100%

Page 36: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

36

4.4. Scenarios

The aim of this project is to compare the implementation of a remanufactured wind turbine

against that of a new wind turbine and as a result the author has created three scenarios

which is felt best suit the study, taking in to consideration the information gained from the

literature review. A list of these scenarios can be found below:

Scenario 1: A new wind turbine of 2MW capacity.

Scenario 2: A remanufactured turbine of 2MW capacity, with cost of remanufactured

components set at 50% of the manufacturing cost, energy needed remanufacture

components set at 50% of energy to manufacture, and Co2 produced during remanufacturing

set at 50% of Co2 produced during manufacturing. The values for this scenario were assumed

in relation to the literature reviewed on remanufactured products from multiple industries

(Kerr et all, 2001., Golinska et al, 2011., Li et al, 2013., Sutherland et al, 2008., Seitz, 2007).

Scenario 3: A remanufactured turbine of 2MW capacity, with cost of remanufactured

components set at 70% of the manufacturing cost, energy needed remanufacture

components set at 70% of energy to manufacture, and Co2 produced during remanufacturing

set at 70% of Co2 produced during manufacturing. (reference). This

scenario was created to offset the assumptions gained from the literature in scenario 1; the

cost to remanufacture was chosen due to literature which concluded that a new product

would be preferred over a remanufactured product if costs were to exceed 70% of the new

one.

Several factors which remain constant throughout the scenarios for consistency are as

follows:

• A service life of 20 years.

• AEP of 4660 MWh per year, using a capacity factor of 26.6% (Renewable UK, 2017).

• O&M costs of 2% of the initial turbine investment.

• The components for remanufacturing are tower, rotor, nacelle cover and bedframe.

• The components to be replaced are the gearbox, generator, transformer and main

shaft.

• Full recycling of materials of components which can be recycled at end of service life.

Page 37: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

37

5. Stakeholder Selection The stakeholder selection process considered those who would have a significant role in

the consideration of both scenarios, direct or indirect, and the possible influence that they

may have on the outcome. The selection of the stakeholders was conducted based on the

authors assumptions as a result of the literature review conducted. A list of the selected

stakeholders is provided below and an explanation of their involvement in the sub-

sections that follow.

1. Investor

2. Developer

3. Public

4. Environmental NGO

5. Manufacturer

6. Governmental Body

5.1. Investor

Investors involvement in development of wind power is paramount as they are the main

source of financial input. They will usually be consulted with all decisions regarding the

development of the project and their focus is on the economic aspect. When considering the

wind turbine options they are looking for performance and reliability, essentially looking for

a minimal risk and maximum profit.

5.2. Developer

The developer’s role is to complete a project to a high standard in the shortest possible time-

frame and although the focus of the developer is to meet such targets, they must also

consider all other impacts that a project can have, both socially and environmentally. The

choice of turbine will inevitably come down to their decision, however they are inclined to

keep all parties involved happy throughout the project and therefore must carefully consider

their opinions.

Page 38: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

38

5.3. Public

As the case scenario is not specifically tied to one site, the public are not being constrained to

a scale. Instead they will be used as a general opinion for the two scenarios, with the author

understanding that they would need to be considered and informed of such a decision in

most relevant cases. Their focus will be on lower electricity price as well as an overall concern

for the environment effects of the decision.

5.4. Environmental NGO

In this case, the environmental NGO is a charitable body that aims for continuous improvement

of sustainability. Although they have no direct input to a single wind power project, they do

have a strong voice within renewable energy, so it seems appropriate to consider them when

undertaking this MCDA. Their focus is to inspire the re-thinking of product design aiming for

sustainability through the minimisation of waste, minimisation of Co2 needed to produce the

product, and reduction on energy usage. The Ellen McArthur Foundation has been mentioned

previously in this paper and can be referred to for an example.

5.5. Manufacturers

The manufacturers are focused on maximising their own profit on sale whilst also aiming

for continual improvement and growth of the market. They also have a duty to minimise

the effects their process has on the environment through legislation, so this will be of

concern to them.

5.6. Governmental body

The concern of the Governmental Body is to ensure a projects outcome is best suited to

all the stakeholders involved. Aiming to build upon a sustainable society through the

economic, social and environmental planning whilst adhering to energy policies and

striving to meet the targets that are set out. This stakeholder can easily be applicable to

the EU-wide 2030 targets.

Page 39: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

39

6. Evaluation Criteria

One of the main benefits of using MCDA, is the ability to compare data on a level form in ways

that may not have been attainable otherwise; this allows the author to evaluate multiple

factors, which is beneficial when attempting to provide as thorough a conclusion as possible.

This report looks at the key drivers in sustainable development, which are the economic,

environmental and social factors. Due to the nature of wind power, and for the purpose of

this report, the author has decided to include technology as a fourth factor which will attempt

to compare the criteria which is deemed to be important to the topic of remanufacturing

specifically, thus, making it more scientifically beneficial. The author has gone on to select

sub-criteria within each category, making it relevant to the research.

6.1. Economic Criteria

The economic criterion is comprised of the sub-criteria Manufacturing Costs and Net Present

Value. Further details on these sub-criteria is explained in the following sections.

6.1.1. Manufacturing Costs

As the focus of this paper is on the comparison of using a new wind turbine against a

remanufactured turbine in wind power development, it is important to consider the

respective costs for each. The data for this has been sourced from the multiple Life Cycle

Analysis papers the author has reviewed.

The manufacturing costs take in to consideration the extraction of material, cost of

transportation and the cost to process the material, and is calculated in EURO (€). The total

cost for a 2MW turbine was assumed to be €321,000 taken from the NREL (2015) report. The

percentage of total cost to manufacture a wind turbine are estimated in the NREL (2015)

report and so the value of 71% to manufacture a new turbine was used for this paper. For the

remanufactured turbine, the research conducted for this study presented an average cost

saving of 50% and so this was used in the calculation of scenario 2. As Scenario 3 looks at the

possibility of a higher cost to remanufacture, a value of 70% was chose by the

author in accordance with the research that suggested a new product will be preferred if

the remanufactured product costs more than 70% of a new product (Gan et al 2017).

Page 40: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

40

6.1.2. Net Present Value

Net Present Value (NPV) is the variance in all income and expenditures of the lifetime of a

project. In order for the project to be considered profitable, the NPV must be positive and it

is therefore preferred for this value to be as high as possible. Since NPV has been widely used,

author has chosen Excel to calculate the NPV of the scenarios presented in this paper and the

lifetime was assumed to be 20 years in all scenarios for consistency.

6.1.3. Environmental Criteria

The environmental criterion looks at various impacts that are deemed important to consider

when evaluating both scenarios. The sub-criteria consist of: Material Circularity Indicator,

Energy to Manufacture and Co2 to Manufacture. Further details on these sub-criteria is

explained in the following sections.

6.1.4. Material Circularity Indicator

Material Circularity Indicator is a tool developed by the Ellen MacArthur (2015), which aims

to measure the minimisation of a products linear flow and maximise its restorative flow for

all the component materials. This provides a clearer indication of the sustainability of a

product by looking at how much of the material is virgin, reused or recycled. It is presented

as a quantitative figure between 0 and 1, with a maximum output preferred.

The calculation measures a products MCI by considering the percentage of virgin material,

percentage of unrecoverable waste and the utility factor of the product, which is the product

lifetime and intensity its of its use. For a new wind turbine, it is assumed that the product is

made up entirely of virgin material, however, for all virgin materials a recycling fraction is

incorporated; this is an estimation of the proportion of a material in use worldwide has been

recycled and allows. It is also considered that all materials in the new turbine which can be

effectively recycled at the end of the products life, will be with relative efficiency. The

remanufactured turbine is comprised of both new and reused material, therefore to account

for this, the fraction of materials which are used in new components will be considered in the

same way as the new turbine. All reused materials will therefore

Page 41: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

41

have maximum MCI. To get an overall MCI for the product, an aggregate of the MCI for

the mass of each component is calculated. Firstly, the virgin material of the product is

calculated using the following equation:

� = �(1 − �� − ��)

Where � is the mass of finished product ��, is the fraction of feedstock obtained from

recycled sources and is the fraction of feedstock obtained from reused sources.

As all scenarios of this study are assumed to be collected for recycling where possible;

unrecoverable waste, �� , from the recycled material is calculated as:

�� = ��(1 − ��)

Where � is the mass of the �th material and �� is the recycling efficiency of the nth

material.

As it is assumed that a fraction of the feedstock material was obtained from recycled

sources, the calculation of unrecoverable waste, ��,is as follows:

�� = ��

(1 − ��)

��

When calculating the total mass of unrecoverable waste, adding �� and , would result in

some of the unrecoverable waste being double counted. To avoid this the following equation

is necessary:

�� = (�� − ��)

2

The next step is to calculate the Linear Flow Index (LCI), which takes in to consideration how

much material is flowing in a linear take-make-dispose fashion, as described in section 2.6. LFI

is presented with a value between 0 and 1, where 1 is an entirely linear flow. The equation

for LFI is as follows:

��� = � − �

2� +(�� − ��)

2

Finally, the Material Circularity Indicator can be obtained:

Page 42: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

42

��� = 1 − ���(�(�))

Where � is the function of utility . As this study only considers one service lifetime of a

wind turbine, F(X) = 1.

6.1.5. Energy to Manufacture

The processes used to manufacture a turbine require a great deal of energy; as we aim to

become more sustainable in the way we produce products it is important to consider how

much energy is needed to do so, striving for efficiency. It is easy to overlook the energy used

to manufacture a turbine as it has the benefit of being able to “payback” this energy during

its lifetime. This criterion considers the energy used solely on the

manufacturing/remanufacturing process. Using information provided from the LCA’s

researched from this paper a calculation of the energy needed was conducted by considering

the mass of the materials used and their relative embodied energy; the energy consumed by

all processes necessary for production. The indirect energy, the energy needed for

manufacturing, was then calculated and provided in MJ, with a minimum value preferred. The

total energy to manufacture, ��, is described in the equation:

�� = ����� + ����� + ⋯

Where EE is the embodied Energy for the nth material and m is the materials mass for the

nth material.

Due to the lack of research conducted on remanufacturing of wind turbines, the author has

turned to research papers of other remanufactured products such as automotive engines,

printing cartridges and electronic components. Similar findings were also published in the

paper by Ortegon et al 2012, which has been used as further reference to the calculations.

From this, an average of 50% of energy used was used for the components that are to be

remanufactured in Scenario 2 and Scenario 3. Similar consideration was taken for the

components which go through a high amount of wear and tear during the first life of the

wind turbine. These components are paramount to the reliability of the turbine and so for

the purpose of this paper they will be replaced. These components are the gearbox,

generator, transformer and main shaft.

Page 43: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

43

6.1.6. Co2 to Manufacture

Co2 is inevitable when manufacturing new product but as the global outlook is focused on

reducing the Co2 levels and governments are aiming to meet targets, it is important to access

the levels we produce as a by-product. This criterion has been selected to evaluate the

significance in both scenarios. In principle, the Co2 to manufacture is calculated in the same

way as energy to manufactured but its provided in kgCo2, with a minimum value preferred.

The same assumptions for the replacement of certain components will be transferred to

these calculations. The total Co2 to manufacture is described in the following equation, where

EC1 is the embodied Co2 for the nth material and m is the materials mass for the nth material.

� = ������ + ����� + ⋯

6.2. Technical Criteria

The Technical criterion has been introduced to gain an understanding of its significance

on the development of a wind project. The sub-criteria consist of Availability, Risk and

Lead Time.

6.2.1. Availability

The increase in wind power development must be met with an increase in wind turbine

manufacturing; developers have a magnitude of turbine options when it comes to selecting one

and although there are many aspects to consider when doing so, namely performance at an

individual site, the availability of the turbine is paramount to ensure a smooth and fast project.

Whilst there is an abundance of new turbines, making availability less of a concern, this criterion

has been selected to consider the effect that the current availability and

variety of remanufactured turbines may pose of the selection process. As noted in the

literature, although there is a market potential for medium scale turbines, the production has

depleted due to the development of new turbine technology (Ortegon et al, 2012., Parker et

Page 44: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

44

al, 2008). Due to the lack of quantitative data available to the author regarding wind turbine

availability, this criterion will not present the estimated value of how many 2MW wind

turbines are available for each scenario. Instead, the unit will be scaled between 1-10 with

the authors judgement on the current availability with a maximum value preferred.

Table 4: Scale of Turbine Availability

Scale Availability

1-2 Few

3-5 Few to Some

6-7 Some to Widespread

8-10 Widespread

6.2.2. Risk

All wind power projects will undergo multiple risk analyses throughout the project. The main

aim of these assessments is to minimise the economic risk of a project which can happen for

many reasons such as delays, change in project value (i.e. drop in electricity price or subsidy

cuts), or social and environmental impacts. When considering the turbine selection itself, a risk

analyses is much harder to predict and mitigate. The main problem lies within the performance

of the turbine throughout its lifetime. Although a deterioration in turbine performance is

expected, it is the failing or radical underperforming risk that can cause great problems.

Manufacturers offer warranty as well as operation and maintenance packages to ensure their

turbines reliability and this criterion has been selected to address the grey area of the risk of

remanufactured turbines. A scaled value between 1-10 has been selected by the author, taking

in to consideration the performance, reliability, warranty, maintenance. A minimum value is

preferred.

6.2.3. Lead Time

The lead time is the length of time between the initiation and completion of the product. For

manufacturing of a new turbine, this relates to the time taken This includes the extraction and

processing of the raw materials, transportation to the site, manufacturing and assembly of the

wind turbines components. The lead time for remanufacturing differs as it involves the

transportation of used turbine, disassembly, inspection, cleaning, remanufacturing or

Page 45: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

45

replacement and assembly. It should be noted that although lead time could also fall under one

of the previous two criteria, the author has chosen it as a separate criterion as a result of the

literature review conducted. It is suggested that the lead time for a remanufactured turbine is

less than three months (repoweringsolutions.org, 2017., PES Wind, 2017) whereas a new

turbine can be anything from 12 to 16 months NREL (2004). The unit for this criterion is months

and a minimum value is preferred.

6.2.4. Product Development

The current development of wind turbines focuses on the improvement of performance; this

is not only evident in the increase in size of wind turbines over the years but also the

development of blade efficiency and the durability of components to meet varying

environmental demands. However, as this paper is focused on the sustainability of wind

energy, this criterion has been selected as a way of applying the findings which suggest

remanufacturing would encourage product design through greater product utilisation taking

in to consideration factors such as life extension, design for disassembly and design for repair

(Ellen McArthur Foundation 2015., Charter et al, 2008). A qualitative scale between 1-10 has

been used for this criterion, with a maximum value preferred.

Table 5: Scale of Encouragement of Sustainable Design

Scale Encouragement of Sustainable Design

1-2 Little

3-5 Little to Some

6-7 Some to Great

8-10 Great

6.3. Social Criteria

As the main aim of this paper is to consider the options of comparing the benefits of a

new turbine against that of a remanufactured one, there are fewer social aspects that are

relevant. One that does stand out however, is the perceived quality of a wind turbine in

both scenarios and this sub-criterion is explained in below.

Page 46: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

46

6.3.1. Perceived Quality

The author has researched papers that involved the perception of the remanufacturing process

and its effect on decision making. As for now, the ambiguity of the remanufacturing process is

thought to have an adverse effect on consumer’s perception, resulting in them not seeing

equality between new and remanufactured products (Hazen 2016., Keoleian, 2004). Although

the other sub criteria may have a more important impact on the development of wind energy,

it is important to consider the stakeholders’ perception in all scenarios, as this would no doubt

play a significant role in the outcome of a project. Again, this is provided as a qualitative 1-10

scale with a maximum value preferred.

Table 6: Scale of Perception of Quality

Scale Perception of Quality

1-2 Very Low

3-5 Low to Medium

6-7 Medium to High

8-10 Very High

6.4. Summary of Criteria

Table 7 presents the results from the calculations carried out for each criterion as mentioned

in Section 6.

Page 47: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

Table 7: Summary of Criteria

Criteria Sub-Criteria Unit Direction Scenario 1 Scenario 2 Scenario 3

Economic criteria

Manufacturing Cost

€ Min 2,279,100 1,139,550 1,595,370

NPV € Max 542,522.64 1,617,569.81 322,852.52

Environmental criteria

MCI Qualitative Scale 1-10

Max 6.6 9.5 9.5

Energy to Manufacture

[MJ] Min 13,750.25 6,875.12 6,875.12

Co2 to Manufacture

KgCo2 Min 1,068.08 534.04 534.04

Technical Criteria

Availability Qualitative Scale 1-10

Max 10 3 3

Risk Qualitative Scale 1-10

Min 2 7 8

Lead Time Months Min 36 6 6

Product Development

Qualitative Scale 1-10

Max 2 9 9

Social criteria Perceived Quality

Qualitative Scale 1-10

Max 10 3 2

Page 48: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

7. MCDA Results

In this chapter a graphical representation of the results from the MCDA are presented, with

each graph illustrating the preference of its respective stakeholder.

Firstly, the results of the investor are presented in Figure 7, which shows that their preference

is towards Scenario 2, with scenario 3 being least preferred.

Figure 8 represents the preference of the developer and in this case, scenario 1 is most

preferred and scenario 3 the least.

12

3

-1.000

-0.800

-0.600

-0.400

-0.200

0.000

0.200

0.400

0.600

0.800

1.000

Net

flo

w P

RO

MET

HEE

Scenarios

Investor

12

3

-1.000

-0.800

-0.600

-0.400

-0.200

0.000

0.200

0.400

0.600

0.800

1.000

Net

flo

w P

RO

MET

HEE

Scenarios

Developer

Figure 7: Preference of Investor

Figure 8: Preference of Developer

Page 49: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

The results for the public, in figure 9 show that the preferred scenario is scenario 2, with

scenario 1 being least preferred.

In figure 10, the preference of the Environmental NGO can be seen. Whilst scenario 2 is the

most preferred, it’s worth noting that scenario 1 was the least preferred by a large margin.

1 23

-1.000

-0.800

-0.600

-0.400

-0.200

0.000

0.200

0.400

0.600

0.800

1.000N

et f

low

PR

OM

ETH

EE

Scenarios

Public

1

23

-1.000

-0.800

-0.600

-0.400

-0.200

0.000

0.200

0.400

0.600

0.800

1.000

Net

flo

w P

RO

MET

HEE

Scenarios

Environmental NGO

Figure 9: Preference of Public

Figure 10: Preference of Environmental NGO

Page 50: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

In the case of the manufacturer, the preferred scenario is scenario 2, with 3 being least

preferred. This can be seen in figure 11.

The preference of the governmental body is presented in figure 12, with scenario 3 being

most preferred and scenario 1, the least preferred.

1 23

-1.000

-0.800

-0.600

-0.400

-0.200

0.000

0.200

0.400

0.600

0.800

1.000

Net

flo

w P

RO

MET

HEE

Scenarios

Manufacturer

12 3

-1.000

-0.800

-0.600

-0.400

-0.200

0.000

0.200

0.400

0.600

0.800

1.000

Net

flo

w P

RO

MET

HEE

Scenarios

Governmental Body

Figure 11: Preference of Manufacturer

Figure 12: Preference of Governmental Body

Page 51: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

Finally, Figure 13 is a representation of the preferred scenario when considering all the

stakeholders involved. As can be seen Scenario 2 was the most preferred and scenario 1 the

least.

Figure 13: Summary of preferred scenarios

Page 52: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

8. Discussion

8.1. Introduction

In this chapter, the results presented in chapter 7 will be discussed. Focus will be placed

on the reason behind each stakeholder’s preferred scenario with similarities between the

stakeholders considered.

8.2. Analysis

From the results, it is noted that four out of six stakeholders preferred scenario 2, which was

the remanufactured turbine, which would be remanufactured at 50% of the cost, energy and

Co2 produced. Scenario 1, the newly manufactured turbine, was preferred by one

stakeholder and scenario 3, the wind turbine remanufactured at 70% of the cost was also

preferred by one stakeholder. On initial review, the reduced costs and environmental benefits

have been the reason behind the preference of scenario 1, however it must be noted that the

one stakeholder’s preference towards scenario 3 was unanticipated and suggest some

inconsistency with the other results.

The investors preferred scenario was scenario 2, which suggest that the potential for a smaller

initial investment, met by a greater net present value were the main factors in the outcome.

However, the margin between scenarios was minor, and with scenario 1 being the second

preference, this indicates that there has been an influence of ‘willingness to pay’ from the

investor, where the risk of investment was maybe not met by the value of return and perceived

quality may have been the deciding criterion. The developer preferred scenario 1 which is most

likely down to the concern about the current availability of remanufactured wind turbines,

which could pose a threat to the time scale of their project. Less concern for the reduction in

energy and Co2 during manufacture is another reason why Scenario 1 has come out on top. It

is fair to note that while the public have a growing concern for the impact we have having on

our environment, the main pull for them when it comes to energy generation is the reduction

in electricity costs; Scenario 2 was the preferred scenario for the public due to the reduced

project costs and while that does not necessarily imply that electricity costs will be reduced, it

certainly shows potential for doing so. Scenario 3 was given higher preference than scenario 1,

suggesting that the 70% cost to remanufacture

Page 53: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

met the ‘willingness to pay’ bracket as suggested by the studies presented in the literature

review (Gan et al 2016). The results for the Environmental NGO were unsurprising with

Scenario 2 being preferred. The reduction in energy and Co2 during manufacture are

influential factors, but the Scenarios tendency towards a more circular economy, product

lifetime extension and product development, were certainly the driving factors for this

stakeholder. The manufacturer also took preference to Scenario 2, likely due to the potential

for larger profit margins; a reduction in manufacturing costs allow for economic growth and

driving a more competitive market. The shorter lead time for remanufactured turbines was

also important to the manufacturer, allowing for higher turnover of business. The reduction

of energy and Co2 to manufacture would allow for the manufacturer to meet any

environmental targets set out by the company or the municipality. Finally, the results of the

Governmental body show that scenario 3 would be the preferred scenario, which displays

some irregularity in the results. Scenario 3 was chosen this study to act as a variance of the

cost assumptions made, with the intention that it would define a range in which

remanufactured wind turbines would be accepted. It was not expected that it would achieve

a higher preference than scenario 2 from any of the stakeholders and so suggest some

inconsistency. Nonetheless, the preference towards remanufacturing would suggest that

high importance is placed on the reduction in environmental impact of the wind energy

industry, with EU targets being the focus for this stakeholder.

8.3. Limitations

To carry out this study, the author has had to make number of assumptions. Due to the lack

of research directly involving remanufacturing of wind turbines, studies from other

remanufacturing industries have been used. The weighting of the criteria for each stakeholder

was created by the author as there was a lack of information available from stakeholders in

the field, and for consistency is was deemed appropriate to make all assumptions. Any

assumptions of data have been provided in the relevant sections.

Page 54: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

9. Conclusion

9.1. Summary of the study

Due to the rapid growth of the wind energy market over the last decade, the future of the

industry will consequently see the dismantling of many wind turbines, both due to wind

turbines reaching the end of their service life and to make way for surpassing technology,

leaving behind a large amount of material that must be dealt with. It is estimated that total

waste material will increase an average of 12% per year between 2014 and 2026 and 41% per

year between 2026 and 2034 (Andersen et al, 2016). Furthermore, due to the advancing

technology of wind turbines, there has been a decline in the number of medium sized wind

turbines being manufactured. This aim of this study was to address the problem of future waste

mitigation, whilst attempting to capture the medium scale market. As such, the study has

looked at the idea of a circular economy, in which wind turbines are not considered as waste at

the end of their service life, but rather an opportunity to recapture value through

remanufacturing. This was approached by identifying the driver and barriers of remanufactured

products, utilising knowledge from other industries with developed remanufacturing sectors.

From this a Multi-Criteria Decision Analysis has been performed using the PROMETHEE II

method. The aim was to draw a comparison of three scenarios, enveloped by a theoretical wind

turbine selection project. The scenarios were created by the author and considered the

implementation of a new wind turbine and remanufactured wind turbines, with the criteria

selected to address the need to reduce waste within the wind energy industry whilst capturing

the medium scale market potential. The study has shown that there is great potential for

remanufacturing within the wind industry, not only due to the economic potential of

developing the secondary market within the industry and driving competition, but as a means

of developing wind energy whilst focusing on the most important reason for its

implementation, the growth towards a sustainable future. Throughout the study it has been

noted that remanufacturing costs are estimated to be, on average, 50% of the cost to

manufacture a new turbine. However, the development of wind turbine technology is driving

the reduction in wind turbines costs annually whilst the cost to remanufacture will most likely

not decrease unless the market grows substantially. This could lead to further implications for

its development as most developers of wind would

Page 55: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

opt for new wind turbines, rather than remanufactured models. However, the need for

medium size turbines is still relevant and many factors, including restrictions on wind turbine

size at specific sites, could allow for the development of remanufacturing to be achieved. It is

worth noting that whilst legislation for waste management is being implemented, it is currently

more of a guideline procedure on how to minimise the impact waste has on the environment.

If there is to be a drive towards an economy which is circular, then further legislative action

should be implemented to put greater responsibility on those who are designing,

manufacturing and buying products. In the case of wind energy, this responsibility should

stretch back to the manufacturer; currently a wind turbine manufacturers responsibility, and

subsequent handling of the material is absorbed by the customer once the product has been

delivered, leaving the manufacturer with less incentive to design a product which can be reused

or remanufactured easily. The competitive nature of the industry can also be a barrier, as

manufacturers are very secretive of the technology they have, and are developing. Whilst this

is understandable in a market that is growing the way wind energy is, it somewhat suffocates

the potential for overall development.

9.2. Future Research

As this study attempted to look at the potential for remanufacturing within the wind energy

industry, it was noted that there are multiple areas that must be researched for its

development. Firstly, a greater understanding of the remanufacturing process of a wind

turbine, including all components which are suitable for remanufacturing should be

researched thoroughly. In turn this would allow for accurate data regarding the costs to

remanufacture and energy saving made. With more accurate data available, the use of an

MCDA to compare new and remanufactured turbines could be improved. Studies in to the

perceived quality of remanufactured wind turbines would help identify barriers that would

need to be addressed for the development of a secondary market. Finally, research in to the

design of wind turbines which aim at extending the lifetime of materials and components

would benefit the transition towards a more circular economy.

Page 56: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

10. References • Aldén, L., Ansén Nilsson, M., Barney, A., & Ekman, M. E. (2014). Nedmontering av • Andersen, N., Eriksson, O., Hillman, K. and Wallhagen, M. (2016). Wind Turbines’ End-

of-Life: Quantification and Characterisation of Future Waste Materials on a National Level. Energies, 9(12), pp.1-24.

• Andersen, P., Borup, M. and Krogh, T. (2007). Managing long-term environmental aspects of wind turbines: a prospective case study. International Journal of Technology, Policy and Management, 7(4), pp.339-354.

• Atasu, A., Guide, V. and Van Wassenhove, L. (2008). Product Reuse Economics in Closed-Loop Supply Chain Research. Production and Operations Management, 17(5), pp.483-496.

• Behzadian, M., Kazemzadeh, R., Albadvi, A. & Aghdasi, M., 2010. PROMETHEE: A comprehensive literature review on methodologies and applications. European journal of Operational research, 200(1), pp. 198-215.

• Bloomberg New Energy Finance. (2017). BNEF 2016 wind turbine manufacturers ranking. [online] Available at: https://about.bnef.com/blog/vestas-reclaims-top-spot-annual-ranking-wind-turbine-makers/ [Accessed 21 Nov. 2017].

• Brans, J., Vincke, P., Mareschal, B., 1986. How to select and how to rank projects: The PROMETHEE method. European journal of operational research, 24(2), pp. 228-238.

• Carter, C.R. & Rogers, D.S., 2008. A framework of sustainable supply chain management: moving toward new theory. International Journal of Physical Distribution & Logistics Management, 38(5), pp.360–387

• Caterpillar.com. (2017). The Benefits of Remanufacturing. [online] Available at: https://www.caterpillar.com/en/company/sustainability/remanufacturing/benefits .html [Accessed 25 Nov. 2017].

• Charter, M., Gray, C., 2008. Remanufacturing and product design. International. Journal of Product Development 6 (3e4), pp. 375-392.

• Climate Action - European Commission. (2017). 2030 climate & energy framework - Climate Action - European Commission. [online] Available at: https://ec.europa.eu/clima/policies/strategies/2030_en [Accessed 21 Nov. 2017].

• Cooper, T. (1994). Beyond recycling: the longer life option. London, New Economics Foundation. P.5.

• Cooper, T. (2010). Longer Lasting Products: Alternatives To The Throwaway Society. UK: Gower Publishing. P.9

• Elkington, J. (1998). Cannibals with forks: The triple bottom line of 21st century business. Gabriola Island, BC Canada: New Society Publishers.

• Ellen Mcarthur Foundation (2014) Towards the Circular Economy 3: Accelerating the Scale Up. Available at: https://www.ellenmacarthurfoundation.org/publications

• Ellen McArthur Foundation (2015) Growth Within: A Circular Economy Vision for a Competitive Europe. Available at: https://www.ellenmacarthurfoundation.org/publications

• Ellenmacarthurfoundation.org. (2017). Circular Economy - UK, USA, Europe, Asia & South America - The Ellen MacArthur Foundation. [online] Available at: https://www.ellenmacarthurfoundation.org/ [Accessed 25 Nov. 2017].

• Gan, S., Pujawan, I., Suparno and Widodo, B. (2017). Pricing decision for new and remanufactured product in a closed-loop supply chain with separate sales-channel. International Journal of Production Economics, 190, pp.120-132.

Page 57: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

• Garrett, P. and Rønde, K. (2012). Life cycle assessment of wind power: comprehensive results from a state-of-the-art approach. The International Journal of Life Cycle Assessment, 18(1), pp.37-48.

• Georgopoulou, E., Lalas, D., Papagianakis, L. (1997) A Mullticriteria decision aid approach for energy planning problems: the case of renewable energy option. European Journal of Operational Research 103, 483-500.

• Ghenai, C., 2012. Life Cycle Analysis of Wind Turbine, Sustainable Development - Energy, Engineering and Technologies - Manufacturing and Environment, Prof. Chaouki Ghenai.

• Glavič, P. & Lukman, R., 2007. Review of sustainability terms and their definitions. Journal of Cleaner Production, 15(18), pp.1875–1885.

• Green Energy and Technology, pp. 7-10. • Guezuraga, B., Zauner, R. and Pölz, W. (2012). Life cycle assessment of two different 2

MW class wind turbines. Renewable Energy, 37(1), pp.37-44. • Guide, V. D. R. and van Wassenhove, l. N. (2001), Managing Product Returns for

Remanufacturing. Production and Operations Management, 10: 142–155. • Haralambopoulos, D., Polatidis, H., 2003. Renewable energy projects: structuring a

multi-criteria group decision-making framework. Renewable energy, 28(6), pp. 961-973.

• Hatcher, G., Ijomah, W. and Windmill, J. (2011). Design for remanufacture: a literature review and future research needs. Journal of Cleaner Production, 19(1718), pp.2004-2014.

• Hazen, B.T., 2011. Strategic reverse logistics disposition decisions: from theory to practice. International Journal of Logistics Systems and Management 10 (3), 275– 292.

• Hazen, BT., Boone, C., Wang, Y., Khor, KS. (2016). Perceived Quality of Remanufactured Products: Construct and Measure Development. Journal of Cleaner Production, pp. 716-726.

• Henriques, A. and Richardson, J. (2005). The triple bottom line, does it all add up?. London: Earthscan, p.1.

• Hubbard, G., 2009. Measuring organizational performance: beyond the triple bottom line. Business Strategy and the Environment, 18(3), pp.177–191.

• Ijomah, Winifred L., 2010. The application of remanufacturing in sustainable manufacture. Proceedings of the ICE - Waste and Resource Management, 163(4), pp.157–163. Available at:

• Ijomah, WL., Childe, S., McMahon, C (2004). Remanufacturing: a key strategy for sustainable development. in Proceedings of the 3rd International Conference on Design and Manufacture for Sustainable Development. Pp.712-719.

• J. R. San Cristóbal Mateo., 2012 Multi-Criteria Analysis in the Renewable Energy Industry, 7

• Johnston, P. Et al., 2007. Reclaiming the definition of sustainability. Environmental science and pollution research international, 14(1), pp.60–61.

• King, A., Burgess, S., Ijomah, W. and McMahon, C. (2006). Reducing waste: repair, recondition, remanufacture or recycle?. Sustainable Development, 14(4), pp.257-267.

• Living Planet Report 2016. (2017). [ebook] Global Footprint Network, p.3. Available at: http://wwf.panda.org/about_our_earth/all_publications/ecological_footprint2/[Accessed 21 Nov. 2017].

Page 58: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

• Martínez, E., Jiménez, E., Blanco, J. and Sanz, F. (2010). LCA sensitivity analysis of a multi-megawatt wind turbine. Applied Energy, 87(7), pp.2293-2303.

• Mcdonough, W., Braungart, M. (2002). Cradle to cradle: remaking the way we make things. New York, North Point Press.

• NREL, (2004). An Analysis of the Technical and Economic Potential for Mid-Scale Distributed Wind,. National Renewable Energy Laboratory, Farifax, Virginia.

• Nrel.gov. (2015). Cite a Website - Cite This For Me. [online] Available at: https://www.nrel.gov/docs/fy17osti/66861.pdf [Accessed 26 Nov. 2017].

• Ortegon K., Nies L.F., Sutherland J.W. (2012) Remanufacturing: An Alternative for End of Use of Wind Turbines. In: Dornfeld D., Linke B. (eds) Leveraging Technology for a Sustainable World. Springer, Berlin, Heidelberg pp.156-160.

• Ortegon, K., Nies, L. and Sutherland, J. (2014). The Impact of Maintenance and Technology Change on Remanufacturing as a Recovery Alternative for Used Wind Turbines. Procedia CIRP, 15, pp.182-188.

• Parker, D., Walton, S. (2008). The Potential for Remanufacturing of Wind Turbines. Centre for Remanufacture and Reuse.

• PES Wind, (2017). [ebook] Turbine transformation – a new lease of life for ageing wind turbines., p.109. Available at: new.abb.com/.../wind-power.../turbine-transformation---a-new-lease-of-life-for-ageing-wind-turbines [Accessed 25 Nov. 2017].

• PLATE. (2017). Routes for extending the lifetime of wind turbines - PLATE. [online] Available at: http://www.plateconference.org/routes-extending-lifetime-wind-turbines/ [Accessed 25 Nov. 2017].

• Princen, T. (1999). Consumption and environment: some conceptual issues. Ecological Economics, 31(3), pp.347-363.

• Rees, W. and Wackernagel, M. (1996). Urban ecological footprints: Why cities cannot be sustainable—And why they are a key to sustainability. Environmental Impact Assessment Review, 16(4-6), pp.223-248.

• Renewableuk.com. (2017). Statistics Explained - RenewableUK. [online] Available at: http://www.renewableuk.com/page/UKWEDExplained [Accessed 26 Nov. 2017].

• Repoweringsolutions.com. (2017). refurbished wind turbine | Overhaul second hand wind turbines | Growing with the wind turbine. [online] Available at: http://www.repoweringsolutions.com/english/products/refurbished_wind_turbine/index.htm [Accessed 25 Nov. 2017].

• Repoweringsolutions.com. (2017). refurbished wind turbine | Overhaul second hand wind turbines | Growing with the wind turbine. [online] Available at: http://www.repoweringsolutions.com/english/products/refurbished_wind_turbine/index.htm [Accessed 26 Nov. 2017].

• Smith, V. and Keoleian, G. (2008). The Value of Remanufactured Engines: Life-Cycle Environmental and Economic Perspectives. Journal of Industrial Ecology, 8(1-2), pp.193-221.

• Souza, G.C., Ketzenberg, M.E., Guide Jr, V.D.R. (2002). Capacitated remanufacturing with service level constraints. Production and Operations Management 11 (2), 231–248.

• Stahel, W. (1998), “From products to services: selling performance instead of goods”, The IPTS Report, Institute for Prospective Technological Studies, Seville

• Statham, S. (2006). Remanufacturing Towards a More Sustainable Future, Electronics-enabled Products Knowledge-transfer Network.

Page 59: REMANUFACTURING IN WIND POWER: A MULTI ...1463409/...wind turbine manufacturing; Figure 1 is a representation of the current top 10 onshore wind turbine manufacturers. Figure 1 is

• Sutherland, J., Adler, D., Haapala, K. and Kumar, V. (2008). A comparison of manufacturing and remanufacturing energy intensities with application to diesel engine production. CIRP Annals, 57(1), pp.5-8.

• Topham, E. and McMillan, D. (2017). Sustainable decommissioning of an offshore wind farm. Renewable Energy, 102, pp.470-480.

• Vargas, A., Zenón, E., Oswald, U., Islas, J., Güereca, L. and Manzini, F. (2015). Life cycle assessment: A case study of two wind turbines used in Mexico. Applied Thermal Engineering, 75, pp.1210-1216.

• Vestas, (2011). Life Cycle Assessment of Electricity Production from a V90-2.0 MW Gridstreamer Wind Plant.

• Vindkraftverk och efterbehandling av platsen. Stockholm: Energimyndigheten. P.17. • Walton, S, Parker, D, 2008. The potential for Remanufacturing of Wind Turbines. Centre

for Remanufacturing & Refuse Product Group Study, p5 • Wang, J., Jing, Y., Zhang, C. & Zhao, J., 2009. Review on multi-criteria decision analysis

aid in sustainable energy decision-making. Renewable and Sustainable Energy Reviews, 13(9), pp. 2263-2278.

• Wątróbski, J.; Sałabun, W., (2016) The characteristic objects method: a new intelligent decision support tool for sustainable manufacturing. In Sustainable Design and Manufacturing; Springer: Berlin, Germany; pp. 349–359.

• WCED, 1987. Our Common Future. World Commission on Environment and Development. Oxford University Press, Oxford. P.41.

• Welstead, J., Hirst, R., Keogh, D., Robb G. And Bainsfair, R. 2013. Research and guidance on restoration and decommissioning of onshore wind farms. Scottish Natural Heritage Commissioned Report No. 591.

• Wind in Power - 2016 European Statistics. (2017). [ebook] Wind Europe, p.7. Available at: https://windeurope.org/wp-content/uploads/files/about-wind/statistics/windeurope-Annual-Statistics-2016.pdf [Accessed 21 Nov. 2017].

• Windpowermonthly.com. (2017). Vestas signs remanufacturing deal with Caterpillar. [online] Available at: https://www.windpowermonthly.com/article/1102756/vestas-signs-remanufacturing-deal-caterpillar [Accessed 25 Nov. 2017].

• Scottish Government, 2008. legislation.gov.uk. [Online] Available at: http://www.legislation.gov.uk/ukpga/2008/32/pdfs/ukpga_20080032_en.pdf[Accessed 24 09 2017].

• Scottish Government, 2008. legislation.gov.uk. [Online] Available at: http://www.legislation.gov.uk/uksi/2008/314/pdfs/uksi_20080314_en.pdf [Accessed 03 10 2017].

• Scottish Government, 2010. Scotland's Zero Waste Plan. [Online] Available at: http://www.gov.scot/Resource/0045/00458945.pdf [Accessed 15 10 2017].