replacement pedestrian bridge design using pultruded fiber … · frp bridge design design load = 5...

14
Replacement Pedestrian Bridge Design using Pultruded Fiber Reinforced Polymer (FRP) Dr. Amit Sagar, Bridge Engineer pitt&sherry

Upload: others

Post on 02-Apr-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Replacement Pedestrian Bridge Design using Pultruded Fiber … · FRP Bridge Design Design Load = 5 Kpa (AS5100.2-2017) Codes –Australian Standards : AS5100-2017 –Pre-Standard

Replacement Pedestrian Bridge Design using Pultruded Fiber Reinforced Polymer (FRP)

Dr. Amit Sagar, Bridge Engineer

pitt&sherry

Page 2: Replacement Pedestrian Bridge Design using Pultruded Fiber … · FRP Bridge Design Design Load = 5 Kpa (AS5100.2-2017) Codes –Australian Standards : AS5100-2017 –Pre-Standard

Presentation Pathway

Page 2

• Background

• Client Requirements

• New Bridge Design

• Construction Photos

• Conclusion

• Questions

Page 3: Replacement Pedestrian Bridge Design using Pultruded Fiber … · FRP Bridge Design Design Load = 5 Kpa (AS5100.2-2017) Codes –Australian Standards : AS5100-2017 –Pre-Standard

Background: Original Bridge

Page 3

Bridge Type Simply Supported

Usage Pedestrian and Cyclists

Material Superstructure Timber

Footing Concrete Strip Footing

Construction Date 1988

Total Length of Bridge 30.36 m

Width of Bridge 2.4 m

No of Spans 12

Crossing Blind Creek

Owner City of Knox

Page 4: Replacement Pedestrian Bridge Design using Pultruded Fiber … · FRP Bridge Design Design Load = 5 Kpa (AS5100.2-2017) Codes –Australian Standards : AS5100-2017 –Pre-Standard

Location of Bridge

Page 4

Bridge Location

Page 5: Replacement Pedestrian Bridge Design using Pultruded Fiber … · FRP Bridge Design Design Load = 5 Kpa (AS5100.2-2017) Codes –Australian Standards : AS5100-2017 –Pre-Standard

Fire Damage

Page 5

Page 6: Replacement Pedestrian Bridge Design using Pultruded Fiber … · FRP Bridge Design Design Load = 5 Kpa (AS5100.2-2017) Codes –Australian Standards : AS5100-2017 –Pre-Standard

Client Requirements

New Construction Material: FRP

Use Existing Concrete Strip Footing

New Bridge Configuration to Match Old Bridge

Page 6

Page 7: Replacement Pedestrian Bridge Design using Pultruded Fiber … · FRP Bridge Design Design Load = 5 Kpa (AS5100.2-2017) Codes –Australian Standards : AS5100-2017 –Pre-Standard

FRP Bridge Design

Why FRP Bridge ?

Extended Service Life

More Durable

Less Maintenance Cost than Timber

Fire Resistant

Page 7

Page 8: Replacement Pedestrian Bridge Design using Pultruded Fiber … · FRP Bridge Design Design Load = 5 Kpa (AS5100.2-2017) Codes –Australian Standards : AS5100-2017 –Pre-Standard

FRP Bridge Design

Design Load = 5 Kpa (AS5100.2-2017)

Codes – Australian Standards : AS5100-2017– Pre-Standard for Load & Resistance Factor Design (LRFD) of Pultruded Fiber Reinforced Polymer

(FRP) Structures developed by American Society of Civil Engineers

FRP Material Properties– FRP Composites are Anisotropic – Properties are established by Direction of Fibres

• Characteristic longitudinal modulus of flange is different to the web • Characteristic transverse modulus of the web is different to the flange

Challenge– Current gap in knowledge of Material Behaviour and Design Guidelines

Page 8

Page 9: Replacement Pedestrian Bridge Design using Pultruded Fiber … · FRP Bridge Design Design Load = 5 Kpa (AS5100.2-2017) Codes –Australian Standards : AS5100-2017 –Pre-Standard

New Bridge Configuration

Page 9

Total Length of Bridge 30.36 m

Width of Bridge 2.40 m

No of Spans 12

Span Length 2.53 m

New bridge design has approximately same lengthand width as original bridge.

Number of spans are same, i.e. 12.

Page 10: Replacement Pedestrian Bridge Design using Pultruded Fiber … · FRP Bridge Design Design Load = 5 Kpa (AS5100.2-2017) Codes –Australian Standards : AS5100-2017 –Pre-Standard

Construction

Page 10

• Project Awarded in Late 2018

• Construction Commenced Jan 2019

• Bridge Completed Feb 2019

• Two Weeks Prior to Scheduled Opening Date

Page 11: Replacement Pedestrian Bridge Design using Pultruded Fiber … · FRP Bridge Design Design Load = 5 Kpa (AS5100.2-2017) Codes –Australian Standards : AS5100-2017 –Pre-Standard

CONCLUSION

Page 11

• Existing timber bridges are decaying and in need of replacement, anopportunity to use FRP as primary design material

• Durable and Less Maintenance Costs for Asset Owners

• Common place for asset owners to use FRP for re-decking existing timberstructures

• Australian Standards provide Limited Guidance

Page 12: Replacement Pedestrian Bridge Design using Pultruded Fiber … · FRP Bridge Design Design Load = 5 Kpa (AS5100.2-2017) Codes –Australian Standards : AS5100-2017 –Pre-Standard

Acknowledgements

City of Knox

David Chow

Mr Nathan Hadfield

Pitt&Sherry

Mr Chris Morton

Dr Andrew Sonnenberg

Page 12

Page 13: Replacement Pedestrian Bridge Design using Pultruded Fiber … · FRP Bridge Design Design Load = 5 Kpa (AS5100.2-2017) Codes –Australian Standards : AS5100-2017 –Pre-Standard

QUESTIONS

Page 13

Natural Bridge, Queensland

Its name is taken from a rock arch in Springbrook National

Park. A waterfall along Cave Creek, a tributary of the Nerang

River flows through the arch

Picture Taken By: Amit Sagar

Page 14: Replacement Pedestrian Bridge Design using Pultruded Fiber … · FRP Bridge Design Design Load = 5 Kpa (AS5100.2-2017) Codes –Australian Standards : AS5100-2017 –Pre-Standard

Fire Resistant Supporting Information

C1.10 refers to Clause A2.4 Fire Hazard Properties which requires the material to be tested to AS/NZS 1530.3 for flame spread index and smoke developed index

The mean critical radiant flux rating for our material as tested in the attached certification has a result of 10.9kW/m2 and 0 smoke developed index. This is well above the highest rating for a Fire-isolated exit and fire control rooms requirement of minimum 4.5kW/m2 according to Table 2 of C1.10

Page 14