Project Name: Multidisciplinary Research Building 1 Project Number: 950528 Contract Number: 950528-PSA-2016-131 UCR Rev 2012-09-14 RFQ Advertisement University of California, Riverside Multidisciplinary Research Building 1 Request for Qualifications For Commissioning Consultant (University’s Commissioning Authority/Auditor) Project Number: 950528 Contract Number: 950528-PSA-2016-131 June 17, 2016 Advertisement Date: June 17, 2016 – July 06, 2016 Document Issue Date: Friday, June 17, 2016 Notice of Intent to Submit Due: Tuesday, June 28, 2016, 1:00 PM Last day for Questions: Friday, July 1, 2016, 1:00 PM RFQ Submittal Due by: Friday, July 8, 2016 1:00 PM

Upload: vodat

Post on 12-Jul-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: Multidisciplinary Research Building 1 Project Number: 950528

Contract Number: 950528-PSA-2016-131

UCR Rev 2012-09-14 RFQ Advertisement

University of California, Riverside Multidisciplinary Research Building 1

Request for Qualifications

For Commissioning Consultant

(University’s Commissioning Authority/Auditor)

Project Number: 950528 Contract Number: 950528-PSA-2016-131

June 17, 2016

Advertisement Date: June 17, 2016 – July 06, 2016 Document Issue Date: Friday, June 17, 2016 Notice of Intent to Submit Due: Tuesday, June 28, 2016, 1:00 PM Last day for Questions: Friday, July 1, 2016, 1:00 PM RFQ Submittal Due by: Friday, July 8, 2016 1:00 PM

Page 2: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: Multidisciplinary Research Building 1 Project Number: 950528

Contract Number: 950528-PSA-2016-131

UCR Rev 2012-09-14 RFQ Advertisement

TABLE OF CONTENTS I. ADVERTISEMENT FOR UNIVERSITY’S COMMISSIONING AUTHORITY / AUDITOR II. PROJECT INFORMATION, SCOPE OF WORK AND REQUIREMENTS

A. BACKGROUND B. PROJECT DESCRIPTION C. SCOPE OF WORK D. SCHEDULE OF WORK E. QUALIFICATIONS F. REGULATORY REQUIREMENTS G. JOINT VENTURES H. CONTRACT REQUIREMENTS

III. RFQ SUBMITTAL PROCESS

A. RFQ SCHEDULE FOR SCREENING AND SELECTION OF CONSULTANTS B. RFQ SELECTION PROCESS C. NEGOTIATION AND AWARD OF CONTRACT

ATTACHMENTS (Appropriate attachments may be recopied as necessary for submittal)

Attachment A RFQ QUESTIONNAIRE & SUBMITTAL FORM Attachment B SAMPLE PSA AGREEMENT

Attachment C SPECIFICATION SECTION 01-9113 – GENERAL COMMISSIONING REQUIREMENTS SPECIFICATION SECTION 23-0800 – HVAC COMMISSIONING REQUIREMENTS SPECIFICATION SECTION 26-0800 – ELECTRICAL COMMISSIONING REQUIREMENTS SUPPLEMENTAL COMMISSIONING CRITERIA

Page 3: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: Multidisciplinary Research Building 1 Project Number: 950528

Contract Number: 950528-PSA-2016-131

UCR Rev 2012-09-14 RFQ Advertisement

I. ADVERTISEMENT FOR UNIVERSITY’S COMMISSIONING AUTHORITY / AUDITOR The University of California, Riverside (UCR) Office of Architects & Engineers invites the submission of Qualification documents from experienced consultants to provide professional enhanced commissioning audit services for the Multidisciplinary Research Building 1 (MRB 1). The selected entity must be able to start work immediately. The complete RFQ packet will be available (in electronic format only) on Friday, June 17, 2016, at 1:00 PM. To receive a copy of the RFQ Documents, email the RFQ Administrator listed below: Chantell Mesha UCR Contracts Administration Email: [email protected] Or download directly from: http://pdc.ucr.edu/business/consultants.html It would be highly appreciated, but it is not mandatory, that interested firms contact the RFQ Administrator via email with their intent to submit Qualification Documents for this project by 1:00 PM Tuesday, June 28, 2016. Having this information will facilitate the University’s effort in disseminating changes in the RFQ to those interested firms if the need arises. Every effort will be made to ensure that all persons, regardless of race, religion, sex, color, ethnicity and national origin have equal access to contracts and other business opportunities with the University. Each candidate firm will be required to show evidence of its equal employment opportunity policy. The University reserves the right to reject any or all responses to this RFQ and to waive non-material irregularities in any response received. All information submitted for evaluation will be considered official information acquired in confidence, and the University will maintain its confidentiality to the extent permitted by law. Originally Published: 06/17/2016 – 07/06/2016

Page 4: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: Multidisciplinary Research Building 1 Project Number: 950528

Contract Number: 950528-PSA-2016-131

UCR Rev 2012-09-14 RFQ Advertisement

II. PROJECT INFORMATION, SCOPE OF WORK AND REQUIREMENTS

A. BACKGROUND The 1,127-acre UCR campus is located three miles east of downtown Riverside and is bisected by the I-215/SR-60 freeway. The 616 acres east of the freeway include the undergraduate academic core and most of the existing campus facilities; the 511 acres west of the freeway includes the agriculture research fields and support facilities, a large parking lot, administrative facilities, and University Extension. UCR present enrollment is approximately 21,000 students.

B. PROJECT DESCRIPTION In support of the University of California, Riverside (UCR) Strategic Plan, UCR 2020: The Path to Preeminence, the proposed Multidisciplinary Research Building 1 (MRB 1) is a 123,000 ASF, 186,000 GSF multi-story facility comprised of research laboratories and research support spaces [‘L’ occupancy with ’H’ chemical storage], faculty offices, office support, and building support spaces [‘B’ occupancy]. The building will be located north of the Materials Sciences and Engineering building on North Campus Drive, east of the soccer field, west of Aberdeen Drive, and south of the Student Recreation Center. The delivery method for this project is Design-Build. The University seeks firms with experience in the following types of projects:

• Wet [designed to Biosafety Level 2], damp and dry laboratories of various fume hood densities.

• Flexible, multi-purpose laboratory support spaces.

• Vivarium with centralized cage wash and a dedicated loading dock.

• Shell space for the future fit-out of vivarium, centralized and distributed core laboratories.

• Offices, scholarly activity and meeting spaces. • Free-standing coffee with pre-packaged food

retail café.

The planning process will develop facility requirements based upon best practices in order to create flexible research spaces that support biology and chemistry as noted above. Assignment of specific researchers and programs will be guided by research cluster proposals.

C. SCOPE OF WORK The University’s Commissioning Authority/Auditor (CxA) will provide commissioning review and verification on behalf of the University. The CxA will administer the overall commissioning process and will provide independent review of the Design Builder’s design and installation, as well as verification of the functional performance testing, documentation, and training by the Contractor’s Commissioning Agent (CCx). The CxA will coordinate and review the Commissioning Plan and will provide the final Commissioning Report. The CxA will be a part of the commissioning team and will report directly to the

MRB1 (red): Gateway to UCR’s academic research core

MRB1: Southeast perspective facing Aberdeen Drive

Page 5: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: Multidisciplinary Research Building 1 Project Number: 950528

Contract Number: 950528-PSA-2016-131

UCR Rev 2012-09-14 RFQ Advertisement

University. The CxA will work in collaboratively with the University’s MEP peer review team. University shall provide to the CxA:

1. Owner’s Project Requirements (OPR) documentation for use in developing the Commissioning Plan Outline; systems manual; operations and maintenance training plan; and testing plans and checklists.

2. Basis of Design (BoD), and 3. Contract Documents

This project is intended to achieve LEED Platinum Certification. Commissioning will be performed in accordance with the requirements of LEED EA Credit 3 – Enhanced Commissioning. For additional detailed description of the commissioning roles and responsibilities, please refer to attachments that includes:

A. Specifications Section 01-9113 General Commissioning Requirements; and B. Specifications Section 23-0800 HVAC Commissioning Requirements; and C. Specifications Section 26-0800 Electrical Commissioning Requirements; and D. Supplemental Commissioning Criteria

A principal means of interaction, exchange of ideas, collaboration and decision making on this project will be the collaborative Shoulder-to-Shoulder review process. The Shoulder-to-Shoulder review process shall be implemented in an effort to enhance and accelerate the review and approval process of submittal documents required through the duration of the project. The Shoulder-to-Shoulder review process consists of multiple (and frequent) live and active workshops involving all decision makers (Design Builder, Design Professionals, Architect and Engineers of Record, Subcontractors, Specialty Contractors, Specialty Consultants, University Representatives, and University Representative’s agency-employed Consultants, where real-time decisions and approvals are accomplished. Throughout the process, trust, respect and guidelines for open communication and agreement are established to achieve a productive integrated team, positive outcomes, cost savings, reduction in overall design and construction schedule, and shifts in risk with the potential to reduce or even eliminate claims. The Work of this contract shall be accomplished by task, with deliverables for each task as defined in this document. Task 1.

Task Description 1.1 Develop the Commissioning Plan in concert with the design build team 1.2 Administer the overall commissioning process. Review the reports prepared by the

Cx and submitted by the CCx. 1.3 Coordinate the review of the various commissioning plans into a Master

Commissioning Plan. 1.4 Provide the Final Commissioning Report

Task 1 Deliverables:

1.1 The Commissioning Plan 1.2 Technically-based written reports and communications 1.3 The Master Commissioning Plan and various written reports and communications

Page 6: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: Multidisciplinary Research Building 1 Project Number: 950528

Contract Number: 950528-PSA-2016-131

UCR Rev 2012-09-14 RFQ Advertisement

1.4 The Final Commissioning Report Task 2.

Task Description 2.1 Independent review of the Design Builder design and installation. 2.2 Independent verification of the functional performance testing, documentation,

and training by the Contractor Commissioning Agent (CCx). Task 2 Deliverables:

2.1 Technically-based written reports and communications 2.2 Technically-based written reports and communications

D. SCHEDULE OF WORK

Scope duration is anticipated and approximated as follows: Procurement: RFQ Due – July 8, 2016 Shortlist: July 15, 2016 Interview: July 25, 2016 Construction Documents: August 1, 2016 – October, 2016 Construction: August, 2016 – October, 2018

E. QUALIFICATIONS • The Consultant must possess one or more of the following professional certifications:

o CCP Certified Commissioning Professional conferred by Building Commissioning Association (BCxA) o CxA Certified Commissioning Authority conferred by AABC Commissioning Group o QCxP or QCP Accredited Qualified Commissioning Process Provides conferred by University of

Wisconsin-Madison • Fifteen (15) years of multi-phased, fast-track experience demonstrating the ability to conceive and

anticipate future and past packages as they are assembled; knowledge of schematic design, design development, construction documents, bidding and negotiations in a design-build environment.

• Must be familiar with Life Science facility mechanical systems that utilize an Airquity Management system.

• Individual(s) must be licensed professional(s) available to make a 28-month project commitment. (Immediately thru Oct 2018).

• Deliverables shall be in MS Excel or MS Word, 2010 (or newer) electronic file format. Quantitative deliverables shall be in in MS Excel, 2010 (or newer) electronic file format, unless instructed otherwise by University Representative in writing.

• CxA consulting firm shall be provided access to all appropriate project data to fulfill the duties described herein.

• Must use latest version of AutoCAD, when required to review electronic files generated by the Design-Builder.

• Must have the technical capabilities and personnel know-how to access and review Design-Builder’s BIM model, when directed by University’s Representative.

• Must be willing to provide both hard and soft copies of work. • Must be able to provide deliverables within specified time periods.

F. REGULATORY REQUIREMENTS

The design and construction of University building projects are required to conform to all applicable Federal, State and Local regulations including, but not limited to, the California Code of Regulations and the Americans with Disabilities Act.

Page 7: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: Multidisciplinary Research Building 1 Project Number: 950528

Contract Number: 950528-PSA-2016-131

UCR Rev 2012-09-14 RFQ Advertisement

G. JOINT VENTURES The University will not accept Joint Ventures for this project.

H. CONTRACT REQUIREMENTS 1. All consulting services to be provided by the consultant shall be in accordance with the issued

University Contract Documents. University Standard Form of Professional Services Agreement (PSA).

a. Note any exceptions to the attached Professional Services Agreement (“PSA”) that would prevent your firm from executing the Agreement in your response. We cannot accept any request to include language to limit liability with regards to insurance and/or modify the indemnification clauses.

2. University requires evidence of insurance coverage: general liability, automobile liability, and worker’s compensation. If consultant does not currently have coverage in accordance with University requirements, listed below, documentation shall be submitted indicating that such coverage will be in place prior to execution of the Consultant Agreement.

Commercial Form General Liability Insurance* - Limits of Liability Minimum Requirement Each Occurrence - Combined Single Limit for Bodily Injury and Property Damage $1,000,000 Products - Completed Operations Aggregate $2,000,000 Personal and Advertising Injury $1,000,000 General Aggregate $2,000,000 Business Automobile Liability Insurance* - Limits of Liability Minimum Requirement Each Accident - Combined Single Limit for Bodily Injury and Property Damage

$1,000,000

Workers’ Compensation and Employer’s Liability**

Minimum Requirement

Workers’ Compensation: (as required by Federal and State of California law)

Employer’s Liability: Each Employee Each Accident Each Policy

$1,000,000 $1,000,000 $1,000,000

Professional Liability Insurance* – Limits of Liability Minimum Requirement Each Occurrence General Aggregate

$1,000,000 $2,000,000

*This insurance must be (i) issued by companies with a Best rating of A- or better, and a financial classification of VIII or better (or an equivalent rating by Standard & Poor or Moody's) or (ii) guaranteed, under terms consented to by the University (such consent to not be unreasonably withheld), by companies with a Best rating of A- or better, and a financial classification of VIII or better (or an equivalent rating by Standard & Poor or Moody's). Further, the deductible, or retained limit, for each coverage shall not be more than $100,000. **This insurance must be issued by companies (i) that have a Best rating of B+ or better, and a financial classification of VIII or better (or an equivalent rating by Standard & Poor or Moody's); or (ii) that are acceptable to the University. 3. Selected firm shall provide evidence of an Equal Employment Opportunity policy, and its compliance

with applicable federal law pertaining to Equal Employment Opportunity.

Page 8: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: Multidisciplinary Research Building 1 Project Number: 950528

Contract Number: 950528-PSA-2016-131

UCR Rev 2012-09-14 RFQ Advertisement

III. RFQ SUBMITTAL PROCESS

A. SCHEDULE FOR SCREENING AND SELECTION OF CONSULTANTS In accordance with established University procedures, UC Riverside will review all submittals in response to the RFQ and will select the most qualified firm for the listed project. 1. The complete request for qualifications (RFQ) packet will be available

at http://pdc.ucr.edu/business/consultants.html on Friday, June 17, 2016 at 1:00 PM. 2. RFQ Qualification Submittals must be received on or before 1:00 PM, on Friday, July 8, 2016.

Provide (1) original, (1) copy, and one (1) electronic copy (flash drive) of the submittal to:

University of California, Riverside Architects & Engineers; Contracts Administration 1223 University Avenue, Suite 240 Riverside, CA 92507 Attention: Chantell Mesha Please note: Email submissions will not be accepted.

3. Questions may be addressed by email to Chantell Mesha at [email protected]. The last

day questions will be received will be Friday, July 1, 2016, 1:00 PM. LATE SUBMISSIONS, FOR ANY REASON, WILL NOT BE ACCEPTED.

B. RFQ SELECTION PROCESS The selection process will proceed as follows:

1. The University Screening Committee will evaluate each RFQ Submittal and will rank the

prospective firms on the criteria provided in the RFQ Questionnaire & Submittal Form (Attachment A).

2. The highest ranked firms will be recommended to the Selection Committee. The Selection

Committee will review the finalists and make a recommended selection to the Associate Vice Chancellor / Campus Architect for review and approval.

3. After review of the submittals the University may, or may not, schedule interviews.

4. If the University receives submissions from fewer than three qualified firms, the University may

select from the available qualified firms.

C. NEGOTIATION AND AWARD OF CONTRACT

1. The University will negotiate a contract with the best ranked qualified firm for services at compensation that the University determines as fair and reasonable.

2. Negotiations shall begin no later than 14 days after the successful firm has been notified of its

selection.

Page 9: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: Multidisciplinary Research Building 1 Project Number: 950528

Contract Number: 950528-PSA-2016-131

UCR Rev 2012-09-14 RFQ Advertisement

3. The University and firm shall work together to ensure the successful delivery of the requested services in a timely fashion.

4. In the event an impasse is reached in negotiations, the University may terminate negotiations and

enter into negotiations with the next qualified firm, in the same manner as prescribed below. a. Should the University be unable to negotiate a satisfactory contract with the firm

considered to be the most qualified, at a price the University determines to be fair and reasonable, negotiations with that firm shall be formally terminated in writing by the University.

b. The University shall then undertake negotiations with the second most qualified firm. Failing accord with the second most qualified firm, the University shall terminate negotiations in writing. The University shall then undertake negotiations with the third most qualified firm.

c. Should the University be unable to negotiate a satisfactory contract with any of the selected firms, the University shall select additional firms in order of their competence and qualification and continue negotiations in accordance with these Instructions until an agreement is reached.

d. Upon the completion of negotiations, the University and the firm shall proceed to execute a contract. The University shall provide the firm the contract within 45 days after the conclusion of negotiations, unless the University notifies the firm that additional time is necessary to complete the contract.

e. If the selected firm fails to execute the contract within 14 days of receipt, the University may formally terminate the negotiations with that firm in writing and undertake negotiations with the second most qualified firm and so on as previously described above.

Page 10: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: Multidisciplinary Research Building 1 Project Number: 950528

Contract Number: 950528-PSA-2016-131

UCR Rev 2012-09-14 RFQ Advertisement

ATTACHMENT A: RFQ QUESTIONNAIRE & SUBMITTAL FORM PLEASE FIND THE QUESTIONNAIRE AND FORMS ON THE SUBSEQUENT PAGES. WHERE NECESSARY, COPY THE FORMS IN THIS PACKAGE. USE ONLY THESE FORMS. Oral, telephonic, facsimile, telegraphic or emailed Submittals are invalid and will not be accepted.

SUBMIT RESPONSE TO THE UNIVERSITY NO LATER THAN THE RFQ DEADLINE.

Page 11: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: Multidisciplinary Research Building 1 Project Number: 950528

Contract Number: 950528-PSA-2016-131

UCR Rev 2012-09-14 RFQ Advertisement

ATTACHMENT A: RFQ QUESTIONNAIRE & SUBMITTAL FORM For

Commissioning Consultant (University’s Commissioning Authority/Auditor)

for the Multidisciplinary Research Building 1

PROJECT NO. 950528

CONTRACT NO. 950528-PSA-2016-131 UNIVERSITY OF CALIFORNIA, RIVERSIDE

(06/17/2016)

SUBMITTED BY: (Company Name. If a Joint Venture, state name of JV Entity)

Type of Organization: Sole Proprietor/Individual Partnership Corporation (State of Incorporation)

(Contact Name & Title)

(Street Address)

(City, State, Zip Code)

(Telephone Number) (Facsimile Number)

(E-mail)

Each prospective firm must answer all of the following questions and provide all requested information. All information submitted for prequalification evaluation in response to Section 2, if applicable, and marked as “confidential” will be considered official information acquired in confidence, and the University of California will maintain its confidentiality unless (1) the University determines that it is required to release the information to a third party pursuant to the requirements of the California Public Records Act or (2) the University is required by court order to release the information to a third party pursuant to the requirements of the California Public Records Act. In the event that the University receives a request pursuant to the California Public Records Act and the University determines that it is required to disclose information marked “confidential” by the provisions of the California Public Records Act, the University will notify the prospective firm of the pending disclosure at least 72 hours prior to such disclosure so that the prospective firm may seek a restraining order in advance of such disclosure. The University shall err on the side of transparency and will generally treat information provided by the prospective firm that is not marked “confidential” as subject to disclosure pursuant to the California Public Records Act. Likewise, any decision by the University that any document is subject to disclosure pursuant to the California Public Records Act shall not prevent the University from making a subsequent determination that any document is not subject to disclosure pursuant to the California Public Records Act. All other information submitted for evaluation will be considered official information acquired in confidence, and the University will maintain its confidentiality to the extent permitted by law. SUBMIT (1) ORIGINAL, (1) COPY, AND ONE (1) ELECTRONIC COPY (FLASH DRIVE) OF THE SUBMITTAL NO LATER THAN THE RFQ DEADLINE.

Page 12: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: Multidisciplinary Research Building 1 Project Number: 950528

Contract Number: 950528-PSA-2016-131

UCR Rev 2012-09-14 RFQ Advertisement

1. SURVEY (Information Only) How did you hear about this RFQ? UCR Website Other:

2. INSURER (Pass/Fail Section) Failure to provide the required information or check boxes marked as “Pass”

will result in the rejection of submitting entity from this Qualification. Prospective firm shall obtain and submit the Insurance Declaration in the form shown below, or submit a sample certificate of insurance form from its insurer, or submit a letter that declares the same as the Insurance Declaration, signed by an authorized representative of its insurer on the representative’s or insurer’s letterhead. (If more than one insurer or insurance representative, submit a completed form or sample certificate of insurance form or letter for each). 2.1 Is the firm able to obtain insurance in the following limits for the required coverages?

YES (PASS) NO (FAIL)

Commercial Form General Liability Insurance* - Limits of Liability Minimum Requirement Each Occurrence - Combined Single Limit for Bodily Injury and Property Damage $1,000,000 Products - Completed Operations Aggregate $1,000,000 Personal and Advertising Injury $1,000,000 General Aggregate $2,000,000 Business Automobile Liability Insurance* - Limits of Liability Minimum Requirement Each Accident - Combined Single Limit for Bodily Injury and Property Damage $1,000,000

Workers’ Compensation and Employer’s Liability** Minimum Requirement

Workers’ Compensation: (as required by Federal and State of California law)

Employer’s Liability: Each Employee Each Accident Each Policy

$1,000,000 $1,000,000 $1,000,000

Professional Liability Insurance* – Limits of Liability Minimum Requirement Each Occurrence General Aggregate

$1,000,000 $2,000,000

*This insurance must be (i) issued by companies with a Best rating of A- or better, and a financial classification of VIII or better (or an equivalent rating by Standard & Poor or Moody's) or (ii) guaranteed, under terms consented to by the University (such consent to not be unreasonably withheld), by companies with a Best rating of A- or better, and a financial classification of VIII or better (or an equivalent rating by Standard & Poor or Moody's). Further, the deductible, or retained limit, for each coverage shall not be more than $100,000.

**This insurance must be issued by companies (i) that have a Best rating of B+ or better, and a financial classification of VIII or better (or an equivalent rating by Standard & Poor or Moody's); or (ii) that are acceptable to the University.

Page 13: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: Multidisciplinary Research Building 1 Project Number: 950528

Contract Number: 950528-PSA-2016-131

UCR Rev 2012-09-14 RFQ Advertisement

2.2 Insurance Declaration:

PROVIDE THIS DECLARATION TO YOUR INSURANCE CARRIER FOR COMPLETION AND HAVE YOUR CARRIER RETURN THE COMPLETED DECLARATION TO YOU. THE PROSPECTIVE FIRM MUST SUBMIT THIS DECLARATION TO UNIVERSITY. DO NOT HAVE YOUR CARRIER SUBMIT THIS DECLARATION DIRECTLY TO THE UNIVERSITY The undersigned declares under penalty of perjury that the below named insurer is currently willing to provide the insurance listed above in Section 2 of this RFQ/RFP Qualification submittal (Name of Prospective Firm)

and that this Declaration was executed in

, in the State of , (Name of City if within a City, otherwise Name of County) (State)

on . (Date)

(Signature)

(Name &Title)

(Insurer Name)

(Street Address)

(City, State & Zip Code)

(Telephone Number) (Facsimile Number)

(Mobile Number) (Email)

Page 14: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: Multidisciplinary Research Building 1 Project Number: 950528

Contract Number: 950528-PSA-2016-131

4. UNIVERSITY OF CALIFORNIA CONSULTANT EXPERIENCE FORM Complete this form if your firm has worked on a UC Campus in the last 5 years, or check this box to confirm that this is not applicable. Have not worked at a UC Campus in the last 5 years.

Firm's Role e.g. Architect,

Geotechnical Consultant, etc.

Active UC projects ‐ campus/project (list all for your firm)

Cla

ims*

or

litig

atio

n

(Yes

** o

r N

o)

All UC projects within last 5 years ‐ campus/project (list all for each firm)

Cla

ims*

or

Liti

gati

on

? (Y

es**

o

r N

o)

All other projects with any claims* ‐ active & past 5 years (list all for each firm)

The information provided on this experience form was prepared by the office of the prime consultant listed above, who verifies under penalty of perjury that all information set forth on this form, to the best of my knowledge, is complete and accurate as of the date of

submission of the Statement of Qualifications.

Attach additional pages if necessary for any category

Signature

* Claims includes all Claims includes all pending, unresolved claims of professional negligence or breach of

contract for professional services against your firm or any owner or principal of your firm. Name

Title Date

** If yes, explain

Page 15: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: Multidisciplinary Research Building 1 Project Number: 950528

Contract Number: 950528-PSA-2016-131

UCR Rev 2012-09-14 RFQ Advertisement

3. EXPERIENCE SUBMITTAL (100 points possible.)

A. Prospective firm shall submit the following information in the specified order:

Section 1: Cover Letter (10 points possible).

The Cover Letter should introduce the team and provide a brief history of the firm, including: 1) Number of years in business. 2) Number of employees. 3) Person(s) who will be the principal-in-charge and responsible for oversight for duration of the

work. 4) Office that will be assigned.

Section 2: Project Team and Qualifications (30 points possible).

1) Team Organization Chart. 2) Explain the role of each individual and explain how the individual’s past experience applies to

his/her role and services for this Project as described in the RFQ Advertisement. 3) Resumes for each team member. Resumes should show experience applicable to this Project.

Provide licenses, certifications, and registrations.

Section 3: Describe relevant project experience (30 points possible). 1) Provide client information, including contact information for reference checks. 2) Project description. 3) Work scope, including services and deliverables. 4) Key personnel. 5) Contract sum. 6) Start and completion dates.

Section 4: Project Understanding (30 points possible).

1) Understanding of scope: services and deliverables. 2) Proposed approach.

a. NOTE THAT PROJECT REFERENCES WILL BE CONTACTED FOR VERIFICATION OF THE INFORMATION REPORTED. IN CASE OF CONFLICT BETWEEN THE INFORMATION REPORTED BY THE PROSPECTIVE FIRM AND THE INFORMATION PROVIDED BY THE REFERENCE, THE INFORMATION PROVIDED BY REFERENCE SHALL TAKE PRECEDENCE AND AMBIGUITIES SHALL BE RESOLVED AGAINST THE PROSPECTIVE FIRM.

b. An entity wishing to use a predecessor business to satisfy experience requirements must demonstrate

with written information submitted with this RFQ/RFP Qualification Submittal that it is substantially the same organization (in terms of who is managing the firm) as the predecessor business.

c. By signing the Declaration of this Qualification Submittal, you agree that each individual Team member

named your Team Organization Chart is subject to the University’s approval, and may be replaced at University’s request at any time. Any individual approved by the University cannot be replaced later without University’s prior written consent.

Page 16: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: Multidisciplinary Research Building 1 Project Number: 950528

Contract Number: 950528-PSA-2016-131

UCR Rev 2012-09-14 RFQ Advertisement

5. DECLARATION

I, , hereby declare that I am the (Printed Name)

of (Title) (Name of Company)

submitting this Qualification Submittal; that I am duly authorized to sign this Qualification Submittal on behalf of

the above named company; and that all information set forth in this Qualification Submittal and all attachments

hereto are, to the best of my knowledge, true, accurate, and complete as of its submission date.

I declare, under penalty of perjury, that the foregoing is true and correct and that this Declaration was

executed in:

, in the State of , (Name of City if within a City, otherwise Name of County) (State)

on . (Date)

(Signature)

Page 17: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: Multidisciplinary Research Building 1 Project Number: 950528

Contract Number: 950528-PSA-2016-131

UCR Rev 2012-09-14 RFQ Advertisement

ATTACHMENT B: SAMPLE PSA AGREEMENT

Page 18: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: _ Project Number: #

Contract Number: #

UC Revision June 30, 2015 Professional Services Agreement

UCR Revision 2015-09-30 PSA-1

PROFESSIONAL SERVICES AGREEMENT

between

THE REGENTS OF THE UNIVERSITY OF CALIFORNIA

and

{CONSULTANT or LABORATORY NAME}

This Agreement is made on between The Regents of the University of California, a

California corporation, hereinafter called “University,” and

,

an individual/sole proprietor a partnership a joint venture a corporation,

(State of Incorporation)

holder of all necessary and applicable licenses required for the performance of the services described in this Agreement,

hereinafter called “Consultant,” to furnish certain services upon the following terms and conditions:

I. CONSULTANT SERVICES AND RESPONSIBILITIES

A. The Consultant shall furnish the following services:

1. Act as a consultant to the University of California, Riverside, to perform

{BRIEF DESCRIPTION OF SERVICES} as required and authorized by the University. Under this

Agreement, the consultant may perform pre-design services but in no event does this Agreement

authorize the preparation of any design documents, including Schematic Design.

The University will authorize the Consultant to perform specific services by the issuance of a Written

Authorization(s) on the form contained in the Exhibits. Each Written Authorization will state the

specific services to be performed, the schedule for their completion, and the method of

compensation in accordance with paragraph IV.

2. Furnish drawings, documents, reports, surveys, renderings, exhibits, models, prints, and

photographs, and other materials as required and as authorized by the University.

{OPTIONAL: INSERT THE FOLLOWING LANGUAGE IN PSA IF CONSULTANT HAS BEEN SELECTED

TO ACT AS DESIGN PROFESSIONAL INCLUDING, IF NECESSARY, ADVERTISEMENT AND

INTERVIEWS/DISCUSSIONS}

B. Consultant hereby represents to the University that:

1. Consultant acknowledges that it has been selected to perform services for the Project including

services as Design Professional under the Executive Design Professional Agreement (EDPA) in the

Exhibits;

2. Consultant acknowledges that University have deferred negotiations on a fee for Basic Services and

rate schedule for Additional Services described in the EDPA; and

3. Consultant has read and understood the EDPA in Exhibits and agrees to all of its terms and

provisions.

C. If University requires the Consultant's services as Design Professional for the Project, Consultant agrees

to the following:

1. Consultant will not request any modifications to those terms and provisions to the EDPA and will

execute the EDPA in the form in the Exhibits; and

2. Consultant will negotiate in good faith both a fee to perform the Basic Services and a rate schedule

Page 19: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: _ Project Number: #

Contract Number: #

UC Revision June 30, 2015 Professional Services Agreement

UCR Revision 2015-09-30 PSA-2

to perform Additional Services based on its then current rate structure consistent with its normal

practice and consistent with University guidelines for fees and rates for similar projects.

II. TERM

A. Order Period. The period of time for issuance of written Authorizations to Perform Services (hereinafter

“Order Period”) shall be from to .

B. Period of Performance. The period of performance under the Agreement shall be as specified in any

written Authorizations to Perform Services, or subsequent revisions thereto, issued during the Order

Period. However, the period of performance shall not commence prior to the date of execution of any

such written Authorization.

C. University- initiated Termination

1. If the University determines that the Consultant has failed to perform in accordance with the terms

and conditions of this Agreement, the University may terminate all or part of the Agreement for cause. This

termination shall become effective if the Consultant does not cure its failure to perform within 10 days (or

more, if authorized in writing by the University) after receipt of a notice of intention to terminate from the

University specifying the failure in performance. If a termination for cause does occur, the University shall

have the right to withhold monies otherwise payable to the Consultant until the services under this

Agreement are completed. If the University incurs additional costs, expenses, or other damages due to

the failure of the Consultant to properly perform pursuant to the Agreement, these costs, expenses, or

other damages shall be deducted from the amounts withheld. Should the amounts withheld exceed the

amounts deducted, the balance will be paid to the Consultant upon completion of the services to be

provided under this Agreement. If the costs, expenses, or other damages incurred by the University

exceed the amounts withheld, the Consultant shall be liable to the University for the difference.

2. University may terminate this Agreement for convenience at any time upon written notice to

Consultant, in which case University will pay Consultant for all services performed and all expenses

incurred under this Agreement up to and including the effective date of termination less any costs,

expenses or other damages due to the failure of the Consultant to properly perform pursuant to the

Agreement. In ascertaining the services actually rendered up to the date of termination, consideration

will be given to both completed Work and Work in progress, whether delivered to University or in the

possession of Consultant, and to authorized Reimbursable Expenses. No other compensation will be

payable for anticipated profit on unperformed services.

D. Consultant - initiated Termination

Consultant may terminate this Agreement for cause if the University fails to cure a material default in

performance within a period of 30 days, or such longer period as the Consultant may allow, after receipt

from the Consultant of a written termination notice specifying the default in performance. In the event of

termination for cause by the Consultant, the University will pay the Consultant in accordance with

paragraph II.C.2.

III. GENERAL PROVISIONS

A. Independent Contractor. The Consultant shall perform the services hereunder as an independent

contractor and not as an agent or employee of the University.

B. Consultant Hiring. The Consultant shall not hire any officer or employee of the University to perform any

service covered by this Agreement. If the service is to be performed in connection with a federal contract

or grant, the Consultant shall not hire any employee of the United States government to perform any

Page 20: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: _ Project Number: #

Contract Number: #

UC Revision June 30, 2015 Professional Services Agreement

UCR Revision 2015-09-30 PSA-3

service covered by this Agreement.

C. Subconsultants. The Consultant shall cooperate with other professionals employed by the University in

the production of other work related to its services. Subject to approval by the University, the Consultant

shall contract for or employ, at its expense, such professional subconsultants, as the Consultant deems

necessary for the completion of the services. The Consultant may hire the services of subconsultants with

University approval in place of or in addition to those employed or retained by the Consultant. The

Consultant is as responsible for the performance of its subconsultants as it would be if it had rendered

these services itself. Nothing in the foregoing procedure shall create any contractual relationship between

the University and the professionals employed by the Consultant under the terms and conditions of this

Agreement. The Consultant is solely responsible for payment of any subconsultants.

D. Legal and Regulatory Compliance. The Consultant shall perform all services and prepare documents in

compliance with the applicable requirements of laws, codes, rules, regulations, ordinances, and standards.

E. Copyright, Ownership and Use of Materials. Consultant hereby assigns to the University all right, title, and

interest, including, but not limited to, copyright and all copyright rights, in all Materials created by

Consultant in its performance under this Agreement and/or delivered to the University hereunder and shall

execute any documents necessary to effectuate such assignment, with the exception that Consultant

hereby grants to the University an irrevocable, fully-paid up, royalty-free license to use any document

provided to the University including without limitation any document known as a " detail." Consultant

warrants that it has the lawful right to grant the forgoing license to the University. . In the event Consultant

uses any individual who is not a full-time employee of Consultant or entity to perform any work required of

it pursuant to this Agreement, Consultant shall require said individual or entity to sign an agreement

containing identical wording as the foregoing with the exception that word “Consultant” is to be replaced

with the individual’s or entity’s name. Materials constitute all written and other tangible expressions,

including, but not limited to, drawings, documents, reports, surveys, renderings, exhibits, models, prints,

photographs, etc. All Materials furnished by the Consultant hereunder shall be and shall remain the

property of the University. In the event of Agreement termination by either party for any reason, as

provided under this Agreement, the University will have the right to receive, and the Consultant shall

promptly provide to the University, all drawings, documents, reports, surveys, renderings, exhibits, models,

prints, photographs, and other materials prepared by the Consultant for the services under this Agreement.

In the event of termination, and any dispute regarding the amount to be paid under this Agreement not

withstanding, the University retains the right to receive and use any such documents or materials any

dispute regarding the amount to be paid under this Agreement notwithstanding. The foregoing provisions

shall survive the term and termination of this Agreement.

F. Consultant's Accounting Records. All books and records relating to this Agreement shall be maintained

in accordance with Generally Accepted Accounting Principles (GAAP) or International Financial Reporting

Standards (IFRS). University or University's authorized representative shall have access to and the right

to audit and the right to copy all of Consultant's books and records. Consultant records shall include but

not be limited to accounting records (hard copy, as well as computer readable data if it can be made

available); contracts; payroll records; subconsultant agreements; vendor agreements; purchase orders;

leases; original estimates; estimating work sheets; correspondence; receipts; memoranda; and any other

supporting evidence deemed necessary to substantiate charges under this agreement. All such books

and records shall be preserved for a period of at least 3 years from the date of Final Payment under this

Agreement.

G. Conflict of Interest. The Consultant affirms that to the best of its knowledge there exists no actual or

potential conflict between the Consultant's family, business, or financial interests (including services

provided to another client) and the services provided under this Agreement, and that in the event of a

change in either the private interests or services under this Agreement, any questions regarding a possible

conflict of interest that may arise as a result of this change shall be disclosed in writing to the University.

Page 21: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: _ Project Number: #

Contract Number: #

UC Revision June 30, 2015 Professional Services Agreement

UCR Revision 2015-09-30 PSA-4

The Consultant shall not be in a reporting relationship to a University employee who is a near relative,

nor shall the near relative be in a decision-making position with respect to the Consultant.

H. Successors and Assigns. If the Consultant transacts business as an individual, upon the Consultant's

death or incapacitation, the University will automatically terminate this Agreement as of the date of such

event. If so terminated, neither the Consultant nor the Consultant's estate shall have any further right to

perform hereunder, and University shall pay the Consultant, or the Consultant’s estate, the prorated unpaid

compensation due under Article IV for any services rendered prior to this termination.

If there is more than one Consultant, and any one of them dies or becomes incapacitated, and the others

continue to render the consulting services covered herein, the University will make payments to those

continuing as though there had been no death or incapacitation; the University will not be obliged to take

any account of the person who died or became incapacitated or to make any payment to this person or

this person's estate. These provisions shall apply in the event of progressive or simultaneous occasions

of death or incapacitation among any group of persons named as Consultant herein; if death or

incapacitation befalls the last member of this group before the services of this Agreement are fully

performed, then the rights shall be as if there had been only one Consultant.

This Agreement shall be binding upon the University and the Consultant and their respective successors

and assigns. Neither the performance of this Agreement nor any part thereof, nor any monies due or to

become due hereunder, may be assigned by the Consultant without the prior written consent and approval

of the University.

I. Information Furnished by University. If required for the performance of the Consultant's services, the

University will furnish information, surveys, reports, as-builts, and other materials at the University's

expense.

J. Statistical Reporting. At the commencement of performance, Consultant shall complete and submit, and

require each Subconsultant who performs services under this Agreement to complete and submit, a Self-

Certification on the form contained in the Exhibits. At the completion of work and prior to final payment,

Consultant shall complete and submit a Final Distribution of Contract Dollars under this Agreement on the

form contained in the Exhibits.

K. Confidentiality. The Consultant shall use his or her best efforts to keep confidential a) any information

produced or created by Consultant under this Agreement including but not limited to test results,

sampling results, data, plans and reports; b) any information provided by the University and marked

"Confidential Information"; or c) any oral information conveyed to the Consultant by the University and

followed by a written communication within thirty (30) days that said information shall be considered

Confidential Information. In the event that Consultant determines that it has a legal obligation to disclose

such Confidential Information pursuant to a third party demand, Consultant shall notify the University in

writing of its receipt of such demand and of Consultant’s determination that it has a legal obligation to

disclose Confidential Information. Consultant shall not disclose any such Confidential Information until

at least ten (10) days from the date of receipt by University of Consultant’s written notice. This

nondisclosure provision shall not apply to any of the following:

1. Information which the Consultant can demonstrate by written records was known to him or her

prior to the effective date of this Agreement; 2. Information that is currently in, or in the future enters, the public domain other than through a

breach of this Agreement or through other acts or omissions of Consultant; or

3. Information that is obtained lawfully from a third party

L. Survival. The provisions of this Agreement which by their nature survive expiration or termination of the

Agreement or Final Completion of any related Project or the performance of services under this

Agreement, including any and all warranties, confidentialities, indemnities, payment obligations, and

Page 22: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: _ Project Number: #

Contract Number: #

UC Revision June 30, 2015 Professional Services Agreement

UCR Revision 2015-09-30 PSA-5

University’s right to audit Consultant’s books and records, shall remain in full force and effect after any

expiration or termination of the Agreement or Final Completion of any related Project or the

performance of services under this Agreement.

IV. COMPENSATION

A. Compensation payable by University under this Agreement shall not exceed $ .

B. The University will have the right to withhold payment from Consultant for any unsatisfactory service until

such time service is performed satisfactorily.

C. The University will compensate the Consultant for the scope of services provided in accordance with this

Agreement, computed as follows:

1. For each written authorization, a maximum payment shall be established that shall not be exceeded

without the prior written approval of the University.

2. All fees shall be in accordance with the Consultant Rate Schedule contained in the Exhibits. Unless

otherwise provided in the Consultant Rate Schedule, rates shall not be changed except in

accordance with paragraph VIIIA. Alternatively, a lump-sum fee may be negotiated.

3. Payments to the Consultant shall be made monthly, subsequent to the University’s receipt of an

invoice itemizing the fees and reimbursable expenses for each written authorization for the month

invoiced.

a. Invoicing for Services Performed on a Labor Hour / Time-and-Materials Basis. Consultant must submit an itemized invoice for services rendered for each Work Authorization. The itemized invoice must include (i) fees and authorized reimbursable expenses for the month invoiced, (ii) the Contract Number of this Agreement, (iii) the Work Authorization number, (iv) the project name and number if applicable, (v) the date of services, (vi) a summary of the tasks performed with associated hours and billing rates and (vii) supporting timesheets. Payment will be subject to verification by University’s Representative. Overtime premiums will not be allowed for exempt service professionals. Authorized overtime will be compensated at straight-time rates unless specifically provided otherwise in the Rate Schedule.

b. Invoicing for Services Performed for an Established Lump-Sum Fee. Consultant will invoice University for authorized services performed for an established Lump-Sum Fee. A lump-sum invoice may be submitted upon completion of the authorized work. If monthly billings are requested, Consultant shall submit a proposed monthly billing schedule for University’s approval. Proposed monthly billings must relate to the percentage of work performed each month in proportion to the total Work Authorization amount. Payments will not be made that exceed the value of work performed during the billing period. Each invoice must include (1) the fee for the month invoiced, (ii) the Contract Number of this Agreement, (iii) the Work Authorization number, (iv) the project name and number if applicable, (v) the dates of services or a copy of the approved billing schedule, and (vi) a summary of the tasks performed. The amount invoiced will be subject to verification by University’s Authorized Representative. All overtime premiums, reimbursable expenses except as mutually agreed per IV.C.4., and project related overhead or administrative expenses are Consultant’s responsibility and are considered included in the lump-sum fee.

c. Invoices shall be sent to the following address:

UCR Architects & Engineers; Capital Finance 1223 University Avenue, Suite 240 Riverside, CA 92521

Page 23: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: _ Project Number: #

Contract Number: #

UC Revision June 30, 2015 Professional Services Agreement

UCR Revision 2015-09-30 PSA-6

4. When provided in a written Work Authorization as mutually agreed between Consultant and

University, reimbursable expenses will be paid in addition to the fees for Services under this

Agreement; otherwise, Consultant is responsible for all other operating expenses, overhead and

administrative costs that are considered included in the rates in the Consultant’s Rate Schedule

contained in the Exhibits. Reimbursable expenses are actual expenditures made by the Consultant

and the Consultant's employees and subconsultants in accordance with the “Reimbursement

Schedule” contained in the Exhibits. All expenses must be itemized, justified, and supported with

receipts to University’s reasonable satisfaction. All expenses must fall within the established

applicable not-to-exceed Work Authorization amount.

5. Payment Terms. Properly submitted invoices will be paid on a net-30 day basis. Invoices that do

not conform to the requirements of this Agreement will be returned to Consultant for revision and/or

supporting documents. Properly revised invoices will be paid net-30 days.

a. Payments will not be made for services performed in advance of the Work Authorization effective

date unless such advanced services are specifically authorized in the applicable Work Authorization.

For each Work Authorization, the maximum payment shall not exceed the established Work

Authorization amount without University’s prior signed written approval.

b. If University fails to pay undisputed amounts within 45 days of invoice receipt, Consultant may submit

a written payment demand. If University fails to cure the requested payment demand within 7

calendar days from receipt, Consultant may suspend work under this Agreement until such

undisputed payments are made. Any payment issues must be brought to the immediate attention

of University’s Director of Contracts Administration for resolution.

6. Consultant must complete and sign an IRS Form W-9, and send it to the above address for invoices.

V. INDEMNIFICATION AND INSURANCE

A. INDEMNIFICATION

1. Consultant shall indemnify, defend, and hold harmless University and its Regents, officers,

employees, agents, and representatives (collectively, “Indemnitee”), against all liability, demands,

claims, costs, damages, injury including death, settlements, and expenses (including without

limitation, interest and penalties) incurred by Indemnitee (“Losses”) arising out of the performance

of services or Consultants other obligations under this Agreement, but only in proportion to and to

the extent such Losses are caused by or result from (1) the negligent acts or omissions of

Consultant, its officers, agents, employees, subcontractors, subconsultants, or any person or entity

for whom Consultant is responsible (collectively, “Indemnitor”); (2) the breach by Indemnitor of any

of the provisions of this Agreement; or (3) willful misconduct by Indemnitor.

2. The indemnification obligations under this Article V shall not be limited by any assertion or finding

that (1) the person or entity indemnified is liable by reason of non-delegable duty, or (2) the Losses

were caused in part by the negligence of, breach of contract by, or violation of law by Indemnitee.

The obligation to defend shall arise regardless of any claim or assertion that Indemnitee caused or

contributed to the Losses. Indemnitor’s reasonable defense costs (including attorney and expert

fees) incurred in providing a defense for Indemnitees shall be reimbursed by University except to

the extent such defense costs arise, under principles of comparative fault, from Indemnitor’s (a)

negligent acts or omissions; (b) breach of any of the provisions of this Agreement; or (c) willful

misconduct.

3. Consultant shall indemnify, defend, and save harmless Indemnitee from and against all loss, cost,

expense, royalties, claims for damages or liability, in law or in equity, including, without limitation,

Page 24: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: _ Project Number: #

Contract Number: #

UC Revision June 30, 2015 Professional Services Agreement

UCR Revision 2015-09-30 PSA-7

attorney fees, court costs, and other litigation expenses that may at any time arise or be set up for

any infringement (or alleged infringement) of any patent, copyright, trade secret, trade name,

trademark or any other proprietary right of any person or entity in consequence of the use by

Indemnitee of any documents (including any method, process, product, concept specified or

depicted) supplied by Indemnitor in the performance of this Agreement.

4. Nothing in this Agreement, including the provisions of this Article V, shall constitute a waiver or

limitation of any rights which Indemnitee may have under applicable law, including without limitation,

the right to implied indemnity.

B. INSURANCE

1. Insurance Requirements. Consultant, at Consultant's sole cost and expense, shall insure its

activities in connection with this Agreement, and shall obtain, keep in force, and maintain insurance

as listed below. The coverages required under paragraph V.B. shall not in any way limit the liability

of the Consultant.

a. Commercial Form General Liability Insurance with coverage and minimum limits as follows:

i. Each occurrence $1,000,000

ii. Products Completed; Operations Aggregate $1,000,000

iii. Personal and Advertising Injury $1,000,000

iv. General Aggregate $2,000,000

b. Business Automobile Liability Insurance for owned, scheduled, non-owned, and hired auto-

mobiles, with a combined single limit of no less than $1,000,000 per accident.

c. Professional Liability Insurance, with minimum limits of $1,000,000 per claim and $2,000,000

in the aggregate.

d. If the above insurance (subparagraphs V.B.1.a – V.B.1.c) is written on a claims-made basis,

it shall be maintained continuously for a period of no less than 3 years after the date of Final

Completion of the services authorized pursuant to each Written Authorization executed. The

insurance shall have a retroactive date of placement prior to, or coinciding with, the date

services are first provided that are governed by the terms of this Agreement and shall include,

without limitation, coverage for professional services as called for in this Agreement.

Insurance required by subparagraphs V.B.1.a-V.B.1.c shall be (i) issued by companies that

have a Best rating of A- or better, and a financial classification of VIII or better (or an equivalent

rating by Standard & Poor or Moody’s) or (ii) guaranteed, under terms consented to by the

University (such consent to not be unreasonably withheld), by companies with a Best rating

of A- or better, and a financial classification of VIII or better (or an equivalent rating by

Standard & Poor or Moody’s).

e. Workers' Compensation and Employer’s Liability Insurance as follows: i. Worker’s Compensation: as required by Federal and State of California law. ii. Employer’s Liability: Each Employee $1,000,000 Each Accident $1,000,000 Policy Limit $1,000,000 iii. Insurance required by this subparagraph V.B.1.e shall be issued by companies (i) that

Page 25: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: _ Project Number: #

Contract Number: #

UC Revision June 30, 2015 Professional Services Agreement

UCR Revision 2015-09-30 PSA-8

have a Best rating of B+ or better, and a financial classification of VIII or better (or an equivalent rating by Standard & Poor or Moody’s) or (ii) that are acceptable to the University.

f. Consultant, upon the execution of this Agreement, shall furnish University with Certificate of

Insurance evidencing compliance with this Article V., including the following requirements:

i. Consultant shall have the insurance company complete University's Certificate of

Insurance on the form contained in the Exhibits. If Consultant’s insurance company

refuses to use the University's Certificate of Insurance form, it must provide a Certificate

of Insurance (and endorsements, if needed) evidencing compliance with Paragraph V.B.

and Special Provisions 1 through 3 on the Certificate of Insurance Exhibit. It alone

constitutes evidence of insurance.

ii. If insurance policies are canceled for non-payment, University reserves the right to

maintain policies in effect by continuing to make the policy payments and assessing the

cost of so maintaining the policies against Consultant.

iii. University, University’s officers, agents, employees, consultants, University's

Representative, and University's Representative's consultants, regardless of whether or

not identified in the Contract Documents or to Consultant in writing, will be included as

additional insureds on Consultant’s general liability policy for and relating to the Work to

be performed by Consultant and Subcontractors. Consultant’s general liability insurance

policy shall name University as an additional insured pursuant to additional insured

endorsement CG2010 (11/85) or a combination of both CG 2010 (10/01 or 07/04) and

CG 2037 (10/01 or 07/04). The General Liability coverage shall contain a Severability of

Interest provision and shall be primary insurance as respects The Regents of the

University of California, its officers, agents and employees. Any insurance or self-

insurance maintained by The Regents of the University of California shall be excess of

and non-contributory with this insurance. This requirement shall not apply to Worker’s

Compensation and Employer’s Liability Insurance. The Professional Liability insurance

policy shall include Contractual Liability Coverage or endorsements to the insurance

policies for Contractual Liability Coverage for liability that would exist in the absence of

the contract.

iv. The General Liability and the Professional Liability insurance policies shall apply to the

negligent acts, or omissions of Consultant, its officers, agents, employees, and for

Consultant's legal responsibility for the negligent acts or omissions of its subconsultants

and anyone directly or indirectly under the control, supervision, or employ of Consultant

or Consultant's subconsultants.

VI. STATUTORY AND OTHER REQUIREMENTS

A. NONDISCRIMINATION

1. In connection with the performance of the Consultant pursuant to this Agreement, the Consultant

shall provide equal treatment to, and shall not willfully discriminate against or allow harassment of

any employee or applicant for employment on the basis of: race; color; religion; sex; age; ancestry;

national origin; sexual orientation; physical or mental disability; veteran's status; medical condition

(as defined in Section 12926 of the State of California Government Code and including cancer-

related medical conditions and or genetic characteristics); genetic information (as defined in the

Genetic Information Nondiscrimination Act of 2008 and including family medical history); marital

status; gender identity, pregnancy, or citizenship (within the limits imposed by law or University's

policy) or service in the uniformed services (as defined by the Uniformed Services Employment and

Page 26: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: _ Project Number: #

Contract Number: #

UC Revision June 30, 2015 Professional Services Agreement

UCR Revision 2015-09-30 PSA-9

Reemployment Rights Act of 1994). Contractor will also take affirmative action to ensure that any

such employee or applicant for employment is not discriminated against on any of the bases

identified above. Such equal treatment shall apply, but not be limited to the following: employment;

upgrade; demotion or transfer; recruitment or recruitment advertising; layoff or termination; rates of

pay or other forms of compensation; and selection for training, including apprenticeship. The

Consultant also agrees to post in conspicuous places, available to employees and applicants for

employment, notices setting forth the provisions of this nondiscrimination clause. The Consultant

will, in all solicitations or advertisements for employees placed by or on behalf of the Consultant,

state that qualified applicants will receive consideration for employment without regard to: race;

color; religion; sex; age; ancestry; national origin; sexual orientation; physical or mental disability;

veteran's status; medical condition (as defined in Section 12926 of the State of California

Government Code and including cancer-related medical conditions and or genetic characteristics);

genetic information (as defined in the Genetic Information Nondiscrimination Act of 2008 and

including family medical history); marital status; gender identity, pregnancy, or citizenship (within the

limits imposed by law or University's policy) or service in the uniformed services (as defined by the

Uniformed Services Employment and Reemployment Rights Act of 1994). For purposes of this

provision: (1) "Pregnancy" includes pregnancy, childbirth, and medical conditions related to

pregnancy and childbirth; and (2) "Service in the uniformed services" includes membership,

application for membership, performance of service, application for service, or obligation for service

in the uniformed services.

B. PREVAILING WAGE RATES

1. For purposes of this Article, the term subcontractor or subconsultant shall not include suppliers,

manufacturers, or distributors.

2. Consultant shall comply and shall ensure that all Subcontractors comply with prevailing wage law

pursuant to the State of California Labor Code, including but not limited to Sections 1770, 1771,

1771.1, 1772, 1773, 1773.1, 1774, 1775, 1776, 1777.5, and 1777.6 of the State of California Labor

Code. Compliance with these sections is required by this Contract. The Work under this Contract

is subject to compliance monitoring and enforcement by the State of California Department of

Industrial Relations.References to Covered Services hereinafter shall mean services performed

pursuant to this Agreement that are covered by the aforementioned provisions as implemented by

the State of California Department of Industrial Relations.

3. The State of California Department of Industrial Relations has ascertained the general prevailing per

diem wage rates in the locality, if any, listed in the written authorization for the performance of

construction, alteration, demolition or repair work as defined in Section 1720 of the State of California

Labor Code for each craft, classification, or type of worker required to perform the Covered Services

hereunder. A schedule of the general prevailing per diem wage rates will be on file at University's

principal facility office and will be made available to any interested party upon request. By this

reference, such schedule is made part of this Agreement. Consultant shall pay not less than the

prevailing wage rates, as specified in the schedule and any amendments thereto, to all workers

employed by Consultant in the execution of the Covered Services hereunder. Consultant shall cause

all subcontracts or subconsultant agreements to include the provision that all subcontractors or

subconsultants shall pay not less than the prevailing wage rates to all workers employed by such

subcontractor or subconsultants in the execution of the Covered Services hereunder. Consultant

shall forfeit to University, as a penalty, not more than $200 for each calendar day, or portion thereof,

for each worker that is paid less than the prevailing wage rates as determined by the Director of

Industrial Relations for the work or craft in which the worker is employed for any portion of the Covered

Services hereunder performed by Consultant or any subcontractor or subconsultant. The amount of

this penalty shall be determined by the Labor Commissioner pursuant to applicable law. Such

forfeiture amounts may be deducted from the Consultant fee. Consultant shall also pay to any worker

who was paid less than the prevailing wage rate for the work or craft for which the worker was

Page 27: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: _ Project Number: #

Contract Number: #

UC Revision June 30, 2015 Professional Services Agreement

UCR Revision 2015-09-30 PSA-10

employed for any portion of the Covered Services hereunder, for each day, or portion thereof, for

which the worker was paid less than the specified prevailing per diem wage rate, an amount equal to

the difference between the specified prevailing per diem wage rate and the amount which was paid

to the worker.

C. PAYROLL RECORDS

1. Consultant and all subcontractors or subconsultants shall keep an accurate payroll record, showing

the name, address, social security number, job classification, straight time and overtime hours worked

each day and week, and the actual per diem wages paid to each journeyperson, apprentice, or other

employee employed in connection with the Covered Services hereunder. All payroll records shall be

certified as being true and correct by Consultant or subcontractors or subconsultants keeping such

records; and the payroll records shall be available for inspection at all reasonable hours at the

principal office of Consultant on the following basis:

a. A certified copy of an employee's payroll record shall be made available for inspection or

furnished to such employee or the employee's authorized representative on request.

b. A certified copy of all payroll records shall be made available for inspection upon request to

University, the State of California Division of Labor Standards Enforcement, and the Division

of Apprenticeship Standards of the State of California Division of Industrial Relations.

c. A certified copy of all payroll records shall be made available upon request by the public for

inspection or copies thereof made; provided, however, that the request by the public shall be

made to either University, the Division of Apprenticeship Standards, or the Division of Labor

Standards Enforcement. The public shall not be given access to such records at the principal

offices of Consultant or subcontractors or subconsultants. Any copy of the records made

available for inspection as copies and furnished upon request to the public or any public agency

by University shall be marked or obliterated in such a manner as to prevent disclosure of an

individual's name, address, and social security number. The name and address of Consultant

awarded the Agreement or performing the Agreement shall not be marked or obliterated.

2. Consultant shall file a certified copy of the payroll records with the entity that requested the records

within 10 days after receipt of a written request. Consultant shall inform University of the location of

such payroll records for the written authorization, including the street address, city, and county; and

Consultant shall, within 5 working days, provide notice of change of location of such records. In the

event of noncompliance with the requirements of this Paragraph or with the State of California Labor

Code Section 1776, Consultant shall have 10 days in which to comply following receipt of notice

specifying in what respects Consultant must comply. Should noncompliance still be evident after the

10-day period, Consultant shall forfeit to University, as a penalty, $100 for each day, or portion thereof,

for each worker, until strict compliance is accomplished. Such forfeiture amounts may be deducted

from the Consultant fee.

D. APPRENTICES

1. Only apprentices, as defined in the State of California Labor Code Section 3077, who are in training

under apprenticeship standards and written apprentice agreements under Chapter 4, Division 3, of

the State of California Labor Code, are eligible to be employed by Consultant and subcontractors or

subconsultants as apprentices for the Covered Services hereunder. The employment and training of

each apprentice shall be in accordance with the provisions of the apprenticeship standards and

written apprentice agreements under which the apprentice is training and in accordance with

Page 28: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: _ Project Number: #

Contract Number: #

UC Revision June 30, 2015 Professional Services Agreement

UCR Revision 2015-09-30 PSA-11

prevailing wage law pursuant to the Labor Code, including but not limited to Section 1777.5. The

Consultant bears responsibility for compliance with this section for all apprenticeable occupations.

2. Every apprentice shall be paid the standard wage to apprentices, under the regulations of the craft or

trade at which the apprentice is employed, and shall be employed only for the Covered Services

hereunder in the craft or trade to which the apprentice is indentured.

3. When Consultant or subcontractors or subconsultants employ workers in any apprenticeship craft or

trade for the Covered Services hereunder, Consultant or subcontractors or subconsultants shall apply

to the joint apprenticeship committee, which administers the apprenticeship standards of the craft or

trade in the locality, if any, listed in the written authorization for the performance of construction,

alteration, demolition or repair work as defined in Section 1720 of the State of California Labor Code,

for a certificate approving Consultant or subcontractors or subconsultants under the apprenticeship

standards for the employment and training of apprentices in the locality so identified. The committee

will issue a certificate fixing the number of apprentices or the ratio of apprentices to journeypersons

who shall be employed in the craft or trade on the Covered Services hereunder. The ratio will not

exceed that stipulated in the apprenticeship standards under which the joint apprenticeship

committee operates; but in no case shall the ratio be less than 1 hour of apprentice work for every 5

hours of journeyperson work, except as permitted by law. Consultant or subcontractors or

subconsultants shall, upon the issuance of the approval certificate in each such craft or trade, employ

the number of apprentices or the ratio of apprentices to journeypersons fixed in the certificate issued

by the joint apprenticeship committee or present an exemption certificate issued by the Division of

Apprenticeship Standards.

4. “Apprenticeship craft or trade,” as used in this Paragraph, shall mean a craft or trade determined as

an apprenticeship occupation in accordance with rules and regulations prescribed by the

Apprenticeship Council.

5. If Consultant or subcontractors or subconsultants employ journeypersons or apprentices in any

apprenticeship craft or trade in the locality, if any, listed in the written authorization for the performance

of construction, alteration, demolition or repair work as defined in Section 1720 of the State of

California Labor Code, and there exists a fund for assisting to allay the cost of the apprenticeship

program in the trade or craft, to which fund or funds other contractors in the locality so identified are

contributing, Consultant and subcontractors or subconsultants shall contribute to the fund or funds in

each craft or trade in which they employ journeypersons or apprentices on the Covered Services

hereunder in the same amount or upon the same basis and in the same manner done by the other

contractors. Consultant may include the amount of such contributions in computing its compensation

under the Agreement; but if Consultant fails to do so, it shall not be entitled to any additional

compensation therefore from University.

6. In the event Consultant willfully fails to comply with this Paragraph VI.D, it will be considered in

violation of the requirements of the Agreement.

7. Nothing contained herein shall be considered or interpreted as prohibiting or preventing the hiring by

Consultant or subcontractors or subconsultants of journeyperson trainees who may receive on-the-

job training to enable them to achieve journeyperson status in any craft or trade under standards

other than those set forth for apprentices.

E. WORK DAY

1. Consultant shall not permit any worker providing Covered Services to labor more than 8 hours during

any 1 day or more than 40 hours during any 1 calendar week, except as permitted by law and in such

cases only upon such conditions as are provided by law. Consultant shall forfeit to University, as a

penalty, $25 for each worker employed in the execution of this Agreement by Consultant, or any

Page 29: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: _ Project Number: #

Contract Number: #

UC Revision June 30, 2015 Professional Services Agreement

UCR Revision 2015-09-30 PSA-12

subcontractors or subconsultant, for each day during which such worker is required or permitted to

work providing Covered Services more than 8 hours in any 1 day and 40 hours in any 1 calendar week

in violation of the terms of this Paragraph or in violation of the provisions of any law of the State of

California. Such forfeiture amounts may be deducted from the compensation otherwise due under

this Agreement. Consultant and each subcontractor or subconsultant shall keep, or cause to be kept,

an accurate record showing the actual hours worked each day and each calendar week by each

worker employed under this Agreement, which record shall be kept open at all reasonable hours to

the inspection of University, its officers and agents, and to the inspection of the appropriate

enforcement agency of the State of California.

F. PATIENT HEALTH INFORMATION

1. Consultant acknowledges that its employees, agents, subcontractors, consultants and others acting

on its behalf may come into contact with Patient Health Information ("PHI") while performing work

at the Project Site. This contact is most likely rare and brief (e.g. walking through a clinic where

patient files may be visible, overhearing conversations between physicians while working or touring

a hospital, noticing a relative or acquaintance receiving treatment in a University facility, etc.).

Consultant shall immediately notify University Representative of any such contact. Any and all forms

of PHI should not be examined closer, copied, photographed, recorded in any manner, distributed

or shared. Consultant will adopt procedures to ensure that its employees, agents and

subcontractors refrain from such activity. If Consultant, its employees, agents or subcontractors do

further examine, copy, photograph, record in any manner, distribute or share this information,

Consultant will report such actions immediately to the University Representative. Consultant will

immediately take all steps necessary to stop any such actions and will ensure that no further

violations of this contractual responsibility will occur. Consultant will report to University

Representative within five (5) days after Consultant gives University Representative notice of the

event/action of the steps taken to prevent future occurrences.

VII. NOTICES

A. University. Any notice may be served upon the University by delivering it, in writing, to the University at

the address set forth on the last page of this Agreement, by depositing it in a United States Postal Service

deposit box with the postage fully prepaid and with the notice addressed to the University at the

aforementioned address, or by sending a facsimile of it to the University facsimile number set forth on the

last page of this Agreement.

B. Consultant. Any notice may be served upon the Consultant by delivering it, in writing, to the Consultant at

the address set forth on the last page of this Agreement, by depositing it in a United States Postal Service

deposit box with the postage fully prepaid and with the notice addressed to the Consultant at this address,

or by sending a facsimile of it to the Consultant facsimile number set forth on the last page of this

Agreement.

VIII. AUTHORITY OF AGREEMENT

A. This Agreement represents the entire and integrated agreement between the University and the Consultant and supersedes all prior negotiations, representations, or agreements, either written or oral. This Agreement may be modified only by a written instrument signed by both the University and the Consultant and the written instrument shall be an Amendment on the form contained in the Exhibits.

B. This Agreement includes the following Exhibits attached herewith:

Page 30: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: _ Project Number: #

Contract Number: #

UC Revision June 30, 2015 Professional Services Agreement

UCR Revision 2015-09-30 PSA-13

Amendment Certificate of Insurance Final Distribution of Contract Dollars Rate Schedule Reimbursement Schedule Self-Certification Work Authorization Reference RFQ/RFP Documents

Executive Design Professional Agreement

Page 31: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: _ Project Number: #

Contract Number: #

UC Revision June 30, 2015 Professional Services Agreement

UCR Revision 2015-09-30 PSA-14

IN WITNESS WHEREOF, the UNIVERSITY and the CONSULTANT have executed this Agreement on the {DAY} day of

{MONTH} , {YEAR}

CONSULTANT:

(Name of Company)

By:

(Signature & Date)

(License Number, if applicable)

(Print Name & Title)

(Employer ID Number)

Address: Telephone Number(s):

Facsimile Number:

Recommended: Funds Sufficient:

By: University’s Representative By: Financial Administrative Officer

(Signature & Date)

(Signature & Date)

Name Title

Architects & Engineers

Sabrina Schuster Interim Assistant Director of Finance

Architects & Engineers

(Print Name & Title)

(Print Name & Title)

UNIVERSITY: By: The Regents of the University of California University of California, Riverside

(Signature & Date)

Rob Gayle, AIA Associate Vice Chancellor/Campus Architect

Architects & Engineers

(Print Name & Title)

Address: UCR Capital Programs Telephone Number: 951.827.4724

Architects & Engineers, Attn: Contracts Facsimile Number: 951.827.4556

1223 University Avenue, Suite 240

Riverside, CA 92521

Page 32: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

Project Name: Multidisciplinary Research Building 1 Project Number: 950528

Contract Number: 950528-PSA-2016-131

UCR Rev 2012-09-14 RFQ Advertisement

ATTACHMENT C: COMMISSIONING SPECIFICATIONS

Page 33: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

University of California, Riverside Multidisciplinary Research Building 1 Project No. 950528

SECTION 01 9113 - GENERAL COMMISSIONING REQUIREMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes general requirements that apply to implementation of commissioning without regard to systems, subsystems, and equipment being commissioned.

B. OPR documentation prepared by University contains requirements that apply to this Section.

C. Related Sections include the following:

1. Division 23 Section "HVAC Commissioning Requirements" for specific requirements for commissioning HVAC systems.

2. Division 26 Section “Electrical Commissioning” for specific requirements for commissioning Electrical systems.

1.2 DEFINITIONS

A. BoD: Basis of Design.

B. CxA: Commissioning Authority.

C. OPR: Owner's (University) Project Requirements.

D. Systems, Subsystems, and Equipment: Where these terms are used together or separately, they shall mean "as-built" systems, subsystems, and equipment.

E. TAB: Testing, Adjusting, and Balancing.

1.3 COMMISSIONING TEAM

A. Members Appointed by the Design Builder and approved by the University’s Representative: Individuals, each having authority to act on behalf of the entity he or she represents, explicitly organized to implement the commissioning process through coordinated actions. The commissioning team shall consist of, but not be limited to, representatives of Design Builder, including Project superintendent, architect and engineering design professionals and subcontractors, installers, suppliers, and specialists deemed appropriate by the CxA.

B. Members Appointed by University:

1. Representatives of the facility user and operation and maintenance personnel. 2. Architect and engineering design professionals that are not the AE designers of record.

1.4 UNIVERSITY’S RESPONSIBILITIES

A. Coordinate University’s operation and maintenance personnel and engineering staff, schedule them to participate in commissioning team activities including, but not limited to, the following:

1

Page 34: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

University of California, Riverside Multidisciplinary Research Building 1 Project No. 950528

1. Coordination meetings. 2. Training in operation and maintenance of systems, subsystems, and equipment. 3. Testing meetings. 4. Demonstration of operation of systems, subsystems, and equipment. 5. Review and approve final commissioning documentation.

B. Provide the OPR documentation to the CxA for use in developing the commissioning plan; systems manual; operation and maintenance training plan; and testing plans and checklists.

C. Observe and inspect construction and report progress and deficiencies. In addition to compliance with the OPR, BoD, and Contract Documents, inspect systems and equipment installation for adequate accessibility for maintenance and component replacement or repair.

1.5 DESIGN BUILDER'S RESPONSIBILITIES

A. Provide utility services required for the commissioning process.

B. Design Builder shall assign representatives with expertise and authority to act on behalf of the Design Builder and schedule them to participate in and perform commissioning team activities including, but not limited to, the following:

1. Participate in design-and construction-phase coordination meetings. 2. Participate in maintenance orientation and inspection. 3. Participate in operation and maintenance training sessions. 4. Participate in final review at acceptance meeting. 5. Certify that Work is complete and systems are operational according to the Contract Documents,

including calibration of instrumentation and controls. 6. Evaluate performance deficiencies identified in test reports and, in collaboration with entity

responsible for system and equipment installation, recommend corrective action.

C. Subcontractors shall assign representatives with expertise and authority to act on behalf of subcontractors and schedule them to participate in and perform commissioning team activities including, but not limited to, the following:

1. Participate in design- and construction-phase coordination meetings. 2. Participate in maintenance orientation and inspection. 3. Participate in procedures meeting for testing. 4. Participate in final review at acceptance meeting. 5. Provide schedule for operation and maintenance data submittals, equipment startup, and testing

to CxA for incorporation into the commissioning plan. Update schedule on a weekly basis throughout the construction period.

6. Provide information to the CxA for developing construction-phase commissioning plan. 7. Participate in training sessions for the University’s operation and maintenance personnel. 8. Provide updated Project Record Documents to the CxA. 9. Gather and submit operation and maintenance data for systems, subsystems, and equipment to the

CxA, as specified in Division 01 Section "Operation and Maintenance Data." 10. Provide technicians who are familiar with the construction and operation of installed systems and

who shall develop specific test procedures and participate in testing of installed systems, subsystems, and equipment.

D. Provide the BoD documents to the CxA and the University for use in developing the commissioning plan, systems manual, and operation and maintenance training plan.

2

Page 35: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

University of California, Riverside Multidisciplinary Research Building 1 Project No. 950528

E. Assemble the final commissioning documentation, including the commissioning report and Project Record Documents.

1.6 COMMISSIONING AUTHORITY QUALIFICATIONS

A. The Commissioning Authority (CxA) shall satisfy the following requirements:

1. Have extensive experience in startup and troubleshooting HVAC, refrigeration, hot water heating, chilled water, steam, plumbing, electrical, emergency power, fire alarm, life safety, laboratory and medical services systems of similar complexity to those contained in these documents;

2. Have excellent working knowledge of complex environmental, fire alarm, and electric power control and facility management systems; be capable of understanding control vendors’ operating system and control code; be capable of trouble-shooting control code and recommending necessary modifications;

3. Be competent in system design and intent; 4. Be knowledgeable in test and balance of both air and hydronic system; 5. Have excellent communication and writing skills, be highly organized, and be able to work well

with both management and trades contractors. 6. A Bachelors degree in Mechanical Engineering and P.E. certification, with extensive practical

field experience, is preferred; however, other technical training and experience with extensive practical field experience will be considered.

B. The CxA cannot be financially associated with any of the Division 01 through 33 contractors or vendors prior to engaging in this Contract, to avoid potential conflicts of interest.

C. The University’s Representative reserves the right to personally interview the CxA candidate prior to accepting placement in the position. Final approval of the Commissioning Agent will be by the University’s Representative.

1.7 CxA'S RESPONSIBILITIES

A. Organize and lead the commissioning team.

B. Prepare a construction-phase commissioning plan. Collaborate with Design Builder and with subcontractors to develop test and inspection procedures. Include design changes and scheduled commissioning activities coordinated with overall Project schedule. Identify commissioning team member responsibilities, by name, firm, and trade specialty, for performance of each commissioning task.

C. Review and comment on submittals from Design Builder for compliance with the OPR, BoD, Contract Documents, and construction-phase commissioning plan. Review and comment on performance expectations of systems and equipment and interfaces between systems relating to the OPR and BoD.

D. Convene commissioning team meetings for the purpose of coordination, communication, and conflict resolution; discuss progress of the commissioning processes. Responsibilities include arranging for facilities, preparing agenda and attendance lists, and notifying participants. The CxA shall prepare and distribute minutes to commissioning team members and attendees within three workdays of the commissioning meeting.

E. At the beginning of the construction phase, conduct an initial construction-phase coordination meeting for the purpose of reviewing the commissioning activities and establishing tentative schedules for

3

Page 36: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

University of California, Riverside Multidisciplinary Research Building 1 Project No. 950528

operation and maintenance submittals; operation and maintenance training sessions; TAB Work; and Project completion.

F. Prepare Project-specific test procedures and checklists.

G. Schedule, direct, witness, and document tests, and systems startup.

H. Compile test data, and certificates and include them in the systems manual and commissioning report.

I. Certify date of acceptance and startup for each item of equipment for start of warranty periods.

J. Review Project Record Documents for accuracy. Request revisions from Design Builder to achieve accuracy. Project Record Documents requirements are specified in Division 01 Section "Project Record Documents."

K. Review and comment on operation and maintenance documentation and systems manual outline for compliance with the OPR, BoD, and Contract Documents. Operation and maintenance documentation requirements are specified in Division 01 Section "Operation and Maintenance Data."

L. Coordinate operation and maintenance training program with the Design Builder to provide qualified instructors to conduct operation and maintenance training. Operation and maintenance training is specified in Division 01 Section "Demonstration and Training."

M. Video and edit training sessions.

N. Prepare commissioning reports.

1.8 COMMISSIONING DOCUMENTATION

A. Index of Commissioning Documents: CxA shall prepare an index to include storage location of each document.

B. OPR: A written document, prepared by University’s Representative that details the functional requirements of Project and expectations of how it will be used and operated. This document includes Project and design goals, measurable performance criteria, budgets, schedules, success criteria, and supporting information.

C. BoD Document: A document, prepared by Design Builder, that records concepts, calculations, decisions, and product selections used to meet the OPR and to satisfy applicable regulatory requirements, standards, and guidelines. The document includes both narrative descriptions and lists of individual items that support the design process.

D. Commissioning Plan: A document, prepared by CxA, that outlines the schedule, allocation of resources, and documentation requirements of the commissioning process, and shall include, but is not limited to the following:

1. Plan for delivery and review of submittals, systems manuals, and other documents and reports. Identification of the relationship of these documents to other functions and a detailed description of submittals that are required to support the commissioning processes. Submittal dates shall include the latest date approved submittals must be received without adversely affecting commissioning plan.

4

Page 37: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

University of California, Riverside Multidisciplinary Research Building 1 Project No. 950528

2. Description of the organization, layout, and content of commissioning documentation (including systems manual) and a detailed description of documents to be provided along with identification of responsible parties.

3. Identification of systems and equipment to be commissioned. 4. Description of schedules for testing procedures along with identification of parties involved in

performing and verifying tests. 5. Identification of items that must be completed before the next operation can proceed. 6. Description of responsibilities of commissioning team members. 7. Description of observations to be made. 8. Description of requirements for operation and maintenance training, including required training

materials. 9. Description of expected performance for systems, subsystems, equipment, and controls. 10. Schedule for commissioning activities with specific dates coordinated with overall construction

schedule. 11. Identification of installed systems, subsystems, and equipment, including design changes that

occurred during the construction phase. 12. Process and schedule for documenting changes on a continuous basis to appear in Project Record

Documents. 13. Process and schedule for completing prestart and startup checklists for systems, subsystems, and

equipment to be verified and tested. 14. Step-by-step procedures for testing systems, subsystems, and equipment with descriptions for

methods of verifying relevant data, recording the results obtained, and listing parties involved in performing and verifying tests.

E. Test Checklists: CxA, with assistance of Design Builder, shall develop test checklists for each system, subsystem, or equipment including interfaces and interlocks, and include a separate entry, with space for comments, for each item to be tested. Prepare separate checklists for each mode of operation and provide space to indicate whether the mode under test responded as required. Provide space for testing personnel to sign off on each checklist. Specific checklist content requirements are specified in Division 23 Section "HVAC Commissioning Requirements." Each checklist, regardless of system, subsystem, or equipment being tested, shall include, but not be limited to, the following:

1. Name and identification code of tested item. 2. Test number. 3. Time and date of test. 4. Indication of whether the record is for a first test or retest following correction of a problem or

issue. 5. Dated signatures of the person performing test and of the witness, if applicable. 6. Individuals present for test. 7. Deficiencies. 8. Issue number, if any, generated as the result of test.

F. Certificate of Readiness: Certificate of Readiness shall be signed by Design Builder, Subcontractor(s), Installer(s), and CxA certifying that systems, subsystems, equipment, and associated controls are ready for testing. Completed test checklists signed by the responsible parties shall accompany this certificate.

G. Test and Inspection Reports: CxA shall record test data, observations, and measurements on test checklists. Photographs, forms, and other means appropriate for the application shall be included with data. CxA shall compile test and inspection reports and test and inspection certificates and include them in systems manual and commissioning report.

H. Corrective Action Documents: CxA shall document corrective action taken for systems and equipment that fail tests. Include required modifications to systems and equipment and revisions to test procedures, if any. Retest systems and equipment requiring corrective action and document retest results.

5

Page 38: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

University of California, Riverside Multidisciplinary Research Building 1 Project No. 950528

I. Issues Log: CxA shall prepare and maintain an issues log that describes design, installation, and performance issues that are at variance with the OPR, BoD, and Contract Documents. Identify and track issues as they are encountered, documenting the status of unresolved and resolved issues.

1. Creating an Issues Log Entry:

a. Identify the issue with unique numeric or alphanumeric identifier by which the issue may be tracked.

b. Assign a descriptive title of the issue. c. Identify date and time of the issue. d. Identify test number of test being performed at the time of the observation, if applicable,

for cross-reference. e. Identify system, subsystem, and equipment to which the issue applies. f. Identify location of system, subsystem, and equipment. g. Include information that may be helpful in diagnosing or evaluating the issue. h. Note recommended corrective action. i. Identify commissioning team member responsible for corrective action. j. Identify expected date of correction. k. Identify person documenting the issue.

2. Documenting Issue Resolution:

a. Log date correction is completed or the issue is resolved. b. Describe corrective action or resolution taken. Include description of diagnostic steps

taken to determine root cause of the issue, if any. c. Identify changes to the OPR, BoD, or Contract Documents that may require action. d. State that correction was completed and system, subsystem, and equipment is ready for

retest, if applicable. e. Identify person(s) who corrected or resolved the issue. f. Identify person(s) documenting the issue resolution.

3. Issues Log Report: On a periodic basis, but not less than for each commissioning team meeting, CxA shall prepare a written narrative for review of outstanding issues and a status update of the issues log. As a minimum, CxA shall include the following information in the issues log and expand it in the narrative:

a. Issue number and title. b. Date of the identification of the issue. c. Name of the commissioning team member assigned responsibility for resolution. d. Expected date of correction.

J. Commissioning Report: CxA shall document results of the commissioning process including unresolved issues and performance of systems, subsystems, and equipment. The commissioning report shall indicate whether systems, subsystems, and equipment have been completed and are performing according to the OPR, BoD, and Contract Documents. The commissioning report shall include, but is not limited to, the following:

1. Lists and explanations of substitutions; compromises; variances in the OPR, BoD, and Contract Documents; record of conditions; and, if appropriate, recommendations for resolution. This report shall be used to evaluate systems, subsystems, and equipment and shall serve as a future reference document during University’s occupancy and operation. It shall describe components and performance that exceed requirements of the OPR, BoD, and Contract Documents and those that do not meet requirements of the OPR, BoD, and Contract Documents. It may also include a recommendation for accepting or rejecting systems, subsystems, and equipment.

6

Page 39: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

University of California, Riverside Multidisciplinary Research Building 1 Project No. 950528

2. OPR and BoD documentation. 3. Commissioning plan. 4. Testing plans and reports. 5. Corrective modification documentation. 6. Issues log. 7. Completed test checklists. 8. Listing of off-season test(s) not performed and a schedule for their completion.

K. Systems Manual: CxA shall gather required information and compile systems manual. Systems manual shall include, but is not limited to, the following:

1. OPR and BoD, including system narratives, schematics, and changes made throughout the Project.

2. Project Record Documents as specified in Division 01 Section "Project Record Documents." 3. Final commissioning plan. 4. Commissioning report. 5. Operation and maintenance data as specified in Division 01 Section "Operation and Maintenance

Data."

1.9 SUBMITTALS

A. CxA Qualifications Submittal: Submit the Commissioning Authority’s resume and sample documents in a timely fashion to the University’s Representative for approval; which shall include the following:

1. Education and technical training. 2. Present employment:

a. Company name and address b. Present title and job description c. History of employment (include dates and positions held)

3. Relevant work experience:

a. Job name b. Position held c. Work history (include dates and positions held)

4. Example of prior building commissioning project performed by the proposed CxA

a. Submitted project shall be similar in commissioning scope and complexity. b. Include construction/commissioning schedule developed by proposed CxA c. Include test procedures developed by proposed CxA d. Include final report prepared by proposed CxA

B. Commissioning Plan Prefinal Submittal: CxA shall submit hard copies of prefinal commissioning plan to the Design Builder for review by the Design Builder and their Design Professional. Design Builder shall submit five copies to the University’s Representative. Present submittal in sufficient detail to evaluate data collection and arrangement process. One copy, with review comments, will be returned to the CxA for preparation of the final construction-phase commissioning plan.

C. Commissioning Plan Final Submittal: CxA shall submit hard copies and electronically formatted information of final commissioning plan to the Design Builder. Design Builder shall submit two hard copies and one disc to the University. The final submittal must address previous review comments. The

7

Page 40: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

University of California, Riverside Multidisciplinary Research Building 1 Project No. 950528

final submittal shall include a copy of the prefinal submittal review comments along with a response to each item.

D. Test Checklists and Report Forms: CxA shall submit sample checklists and forms to Design Builder quality-control manager and subcontractors for review and comment. Submit three copies of each checklist and report form.

E. Corrective Action Documents: CxA shall submit corrective action documents pertaining to installation and start up of systems. CxA shall also submit recommendations to better operation and maintenance of the systems, if applicable.

F. Prefinal Commissioning Report Submittal: CxA shall submit five hard copies of the prefinal commissioning report CxA shall deliver three copies to the University, and one copy to the Design Builder. One copy, with review comments, will be returned to the CxA for preparation of final submittal.

G. Final Commissioning Report Submittal: CxA shall submit hard copies and electronically formatted information of the final commissioning report. Design Builder shall deliver four hard copies and two set of discs to the University. The final submittal must address previous review comments and shall include a copy of the prefinal submittal review comments along with a response to each item.

1.10 QUALITY ASSURANCE

A. Training Instructor Qualifications: Factory-authorized service representatives, experienced in training, operation, and maintenance procedures for installed systems, subsystems, and equipment.

B. Test Equipment Calibration: Comply with test equipment manufacturer's calibration procedures and intervals. Recalibrate test instruments immediately whenever instruments have been repaired following damage or dropping. Affix calibration tags to test instruments. Instruments shall have been calibrated within six months prior to use.

1.11 COORDINATION

A. Coordinating Meetings: CxA shall conduct monthly coordination meetings of the commissioning team to review progress on the commissioning plan, to discuss scheduling conflicts, and to discuss upcoming commissioning process activities. Coordination meetings shall start at least 8 months prior to project completion.

B. Pretesting Meetings: CxA shall conduct pretest meetings of the commissioning team to review startup procedures, biweekly testing procedures, testing personnel and instrumentation requirements, and manufacturers' authorized service representative services for each system, subsystem, equipment, and component to be tested. Pretest meetings shall start at least 4 months prior to project completions

C. Testing Coordination: CxA shall coordinate sequence of testing activities weekly to accommodate required quality-assurance and -control services with a minimum of delay and to avoid necessity of removing and replacing construction to accommodate testing and inspecting.

1. Schedule times for tests, inspections, obtaining samples, and similar activities.

D. Manufacturers' Field Services: CxA shall coordinate services of manufacturers' field services.

8

Page 41: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

University of California, Riverside Multidisciplinary Research Building 1 Project No. 950528 PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 OPERATION AND MAINTENANCE TRAINING REQUIREMENTS

A. Training Preparation Conference: Before operation and maintenance training, CxA shall convene a training preparation conference to include the University’s operation and maintenance personnel, Design Builder, and subcontractors. In addition to requirements specified in Division 01 Section "Demonstration and Training," perform the following:

1. Review the OPR and BoD. 2. Review installed systems, subsystems, and equipment. 3. Review instructor qualifications. 4. Review instructional methods and procedures. 5. Review training module outlines and contents. 6. Review course materials (including operation and maintenance manuals). 7. Inspect and discuss locations and other facilities required for instruction. 8. Review and finalize training schedule and verify availability of educational materials, instructors,

audiovisual equipment, and facilities needed to avoid delays. 9. For instruction that must occur outside, review weather and forecasted weather conditions and

procedures to follow if conditions are unfavorable.

B. Training Modules: Develop an instruction program that includes individual training modules for each system, subsystem, and equipment as specified in Division 01 Section "Demonstration and Training.

END OF SECTION 01 9113

9

Page 42: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

University of California, Riverside Multidisciplinary Research Building 1 Project No. 950528

SECTION 23 0800 - COMMISSIONING OF HVAC

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes commissioning process requirements for HVAC&R systems, assemblies, and equipment.

B. Related Sections:

1. Division 01 Section "General Commissioning Requirements" for general commissioning process requirements.

2. OPR documentation prepared by the University contains requirements that apply to this Section.

1.2 DEFINITIONS

A. Design Builder: Includes Design Builder, Architect, and Engineer design professionals responsible for design of HVAC, electrical, controls for HVAC systems, and other related systems identified in the Contract for Construction with the University.

B. Commissioning Plan: A document that outlines the organization, schedule, allocation of resources, and documentation requirements of the commissioning process.

C. BoD: Basis of Design.

D. BoD-HVAC: HVAC systems basis of design.

E. CxA: Commissioning Authority.

F. OPR: Owner's (University) Project Requirements.

G. Systems, Subsystems, and Equipment: Where these terms are used together or separately, they shall mean "as-built" systems, subsystems, and equipment.

H. TAB: Testing, Adjusting, and Balancing.

1.3 DESIGN BUILDER'S RESPONSIBILITIES

A. The following responsibilities are in addition to those specified in Division 01 Section "General Commissioning Requirements."

10

Page 43: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

University of California, Riverside Multidisciplinary Research Building 1 Project No. 950528

B. Design Builder:

1. Attend procedures meeting for TAB Work. 2. Certify that TAB Work is complete.

C. Mechanical Subcontractor:

1. Attend TAB verification testing. 2. Provide measuring instruments and logging devices to record test data, and data acquisition

equipment to record data for the complete range of testing for the required test period.

D. HVAC Instrumentation and Control Subcontractor: With the CxA, review control designs for compliance with the OPR and BoD, controllability with respect to actual equipment to be installed, and recommend adjustments to control designs and sequence of operation descriptions.

E. TAB Subcontractor:

1. Contract Documents Review: With the CxA, review the Contract Documents before developing TAB procedures.

a. Verify the following:

1) Accessibility of equipment and components required for TAB Work. 2) Adequate number and placement of duct balancing dampers to allow proper

balancing while minimizing sound levels in occupied spaces. 3) Adequate number and placement of balancing valves to allow proper balancing and

recording of water flow. 4) Adequate number and placement of test ports and test instrumentation to allow

reading and compilation of system and equipment performance data needed to conduct both TAB and commissioning testing.

5) Air and water flow rates have been specified and compared to central equipment output capacities.

6) Building’s pressurization requirements.

b. Identify discontinuities and omissions in the Contract Documents. c. This review of the Contract Documents by the TAB Subcontractor satisfies

requirements for a design review report as specified in Division 23 Section "Testing, Adjusting, and Balancing for HVAC."

2. Additional Responsibilities: Participate in tests specified in Division 23 Sections "Instrumentation and Controls" and Sequence of Operation.

F. Electrical Subcontractor:

1. With the Mechanical Subcontractor, coordinate installations and connections between and among electrical and HVAC systems, subsystems, and equipment.

1.4 CxA'S RESPONSIBILITIES

A. Provide Project-specific construction checklists and commissioning process test procedures for actual HVAC&R systems, assemblies, equipment, and components to be furnished and installed as part of the construction contract.

B. Direct commissioning testing.

11

Page 44: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

University of California, Riverside Multidisciplinary Research Building 1 Project No. 950528

C. Verify testing, adjusting, and balancing of Work are complete.

D. Provide test data, inspection reports, and certificates in Systems Manual.

1.5 COMMISSIONING DOCUMENTATION

A. The following are in addition to documentation specified in Division 01 Section "General Commissioning Requirements."

B. BoD HVAC: University will provide BoD-HVAC documents, to the CxA for use in developing the commissioning plan, systems manual, and operation and maintenance training plan.

C. Test Checklists: CxA with assistance of University’s Representative shall develop test checklists for HVAC systems, subsystems, and equipment, including interfaces and interlocks with other systems. CxA shall prepare separate checklists for each mode of operation and provide space to indicate whether the mode under test responded as required. In addition to the requirements specified in Division 01 Section "General Commissioning Requirements," checklists shall include, but not be limited to, the following:

1. Calibration of sensors and sensor function. 2. Testing conditions under which test was conducted, including (as applicable) ambient conditions,

set points, override conditions, and status and operating conditions that impact the results of test. 3. Control sequences for HVAC systems. 4. Strength of control signal for each set point at specified conditions. 5. Responses to control signals at specified conditions. 6. Sequence of response(s) to control signals at specified conditions. 7. Electrical demand or power input at specified conditions. 8. Power quality and related measurements. 9. Expected performance of systems, subsystems, and equipment at each step of test. 10. Narrative description of observed performance of systems, subsystems, and equipment. Notation

to indicate whether the observed performance at each step meets the expected results. 11. Interaction of auxiliary equipment.

12. Issues log.

1.6 SUBMITTALS

A. The following submittals are in addition to those specified in Division 01 Section "General Commissioning Requirements."

B. Testing Procedures: CxA shall submit detailed testing plan, procedures, and checklists for each series of tests. Submittals shall include samples of data reporting sheets that will be part of the reports.

C. Certificate of Readiness: CxA shall compile certificates of readiness from Design Builder certifying that systems, subsystems, equipment, and associated controls are ready for testing.

D. Certificate of Completion of Installation, Prestart, and Startup: CxA shall certify that installation, prestart, and startup activities have been completed. Certification shall include completed checklists provided by TAB Subcontractor as specified in Division 23 Section "Testing, Adjusting, and Balancing for HVAC."

E. Certified Pipe Cleaning and Flushing Report: CxA shall certify that pipe cleaning, flushing, hydrostatic testing, and chemical treating have been completed.

12

Page 45: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

University of California, Riverside Multidisciplinary Research Building 1 Project No. 950528

F. Test and Inspection Reports: CxA shall compile and submit test and inspection reports and certificates,

and shall include them in systems manual and commissioning report.

G. Corrective Action Documents: CxA shall submit corrective action documents.

H. Certified TAB Reports: CxA shall submit verified, certified TAB reports.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION

3.1 TESTING PREPARATION

A. Prerequisites for Testing:

1. Certify that HVAC systems, subsystems, and equipment have been completed, calibrated, and started; are operating according to the OPR, BoD, and Contract Documents; and that Certificates of Readiness are signed and submitted.

2. Certify that HVAC instrumentation and control systems have been completed and calibrated; are operating according to the OPR, BoD, and Contract Documents; and that pretest set points have been recorded.

3. Certify that TAB procedures have been completed, and that TAB reports have been submitted, discrepancies corrected, and corrective work approved.

4. Test systems and intersystem performance after approval of test checklists for systems, subsystems, and equipment.

5. Set systems, subsystems, and equipment into operating mode to be tested (e.g., normal shut down, normal auto position, normal manual position, unoccupied cycle, emergency power, and alarm conditions).

6. Verify each operating cycle after it has been running for a specified period and is operating in a steady-state condition.

7. Inspect and verify the position of each device and interlock identified on checklists. Sign off each item as acceptable, or failed. Repeat this test for each operating cycle that applies to system being tested.

8. Check safety cutouts, alarms, and interlocks with smoke control and life-safety systems during each mode of operation.

9. Annotate checklist or data sheet when a deficiency is observed. 10. Verify equipment interface with monitoring and control system and TAB criteria; include the

following:

a. Supply and return flow rates for VAV and constant volume systems in each operational mode.

b. Operation of terminal units in both heating and cooling cycles. c. Minimum outdoor-air intake in each operational mode and at minimum and maximum

airflows. d. Building pressurization. e. Total exhaust airflow and total outdoor-air intake. f. Operation of indoor-air-quality monitoring systems.

11. Verify proper responses of monitoring and control system controllers and sensors to include the following:

13

Page 46: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

University of California, Riverside Multidisciplinary Research Building 1 Project No. 950528

a. For each controller or sensor, record the indicated monitoring and control system reading and the test instrument reading. If initial test indicates that the test reading is outside of the control range of the installed device, check calibration of the installed device and adjust as required. Retest malfunctioning devices and record results on checklist or data sheet.

b. Report deficiencies and prepare an issues log entry.

12. Verify that HVAC equipment field quality-control testing has been completed and approved. CxA shall direct, witness, and document field quality-control tests, inspections, and startup specified in individual Division 23 Sections.

B. Testing Instrumentation: Install measuring instruments and logging devices to record test data for the required test period. Instrumentation shall monitor and record full range of operating conditions and shall allow for calculation of total capacity of system for each mode of operation. Operational modes include the following:

1. Occupied and unoccupied. 2. Warm up and cool down. 3. Economizer cycle. 4. Emergency power supply. 5. Life-safety and safety systems. 6. Smoke control. 7. Fire safety. 8. Stair pressurization system. 9. Temporary upset of system operation. 10. Partial occupancy conditions. 11. Special cycles.

3.2 TAB VERIFICATION A. TAB Subcontractor shall coordinate with CxA for work required in Division 23 Section "Testing,

Adjusting, and Balancing for HVAC." TAB Subcontractor shall copy CxA with required reports, sample forms, checklists, and certificates.

B. Design Builder, HVAC Subcontractor, and CxA shall witness TAB Work.

C. TAB Preparation:

1. TAB Subcontractor shall provide CxA with data required for "Pre-Field TAB Engineering Reports" specified in Division 23 Section "Testing, Adjusting, and Balancing for HVAC."

a. CxA shall use this data to certify that prestart and startup activities have been completed for systems, subsystems, and equipment installation.

D. Ductwork Air Leakage Testing:

1. All portions of the mechanical room ducts, riser ducts and main trunk duct systems shall have ductwork air leakage testing. Only branch ducts downstream of terminal units and ductwork within the conditioned space shall not be tested. Ductwork air leakage testing shall be performed according to Division 23 Section "Metal Ducts," and shall be witnessed by the CxA.

2. On approval of preliminary ductwork air leakage testing report, the CxA shall coordinate verification testing of ductwork air leakage testing. Verification testing shall include random retests of portions of duct section tests, reported in preliminary ductwork air leakage testing report.

14

Page 47: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

University of California, Riverside Multidisciplinary Research Building 1 Project No. 950528

The HVAC Subcontractor shall perform tests using the same instrumentation (by model and serial number) as for original testing; the CxA shall witness verification testing.

E. Verification of Final TAB Report:

1. CxA shall select, at random, 10 percent of report for field verification. 2. CxA shall notify TAB Subcontractor 10 days in advance of the date of field verification; however,

notice shall not include data points to be verified. The TAB Subcontractor shall use the same instruments (by model and serial number) that were used when original data were collected.

3. Failure of an item is defined as follows:

a. For all readings other than sound, a deviation of more than 10 percent. b. For sound pressure readings, a deviation of 3 dB. (Note: Variations in background noise

must be considered.)

4. Failure of more than 10 percent of selected items shall result in rejection of final TAB report.

F. If deficiencies are identified during verification testing, CxA shall notify the HVAC Subcontractor and University’s Representative, and shall take action to remedy the deficiency. Design Builder and University’s Representative shall review final tabulated checklists and data sheets to determine if verification is complete and that system is operating according to the Contract Documents.

G. CxA shall certify that TAB Work has been successfully completed.

3.3 TESTING

A. Test systems and intersystem performance after test checklists for systems, subsystems, and equipment have been approved.

B. Perform tests using design conditions whenever possible.

1. Simulate conditions by imposing an artificial load when it is not practical to test under design conditions and when written approval for simulated conditions is received from CxA. Before simulating conditions, calibrate testing instruments. Set and document simulated conditions and methods of simulation. After tests, return settings to normal operating conditions.

2. Alter set points when simulating conditions is not practical and when written approval is received from CxA.

3. Alter sensor values with a signal generator when design or simulating conditions and altering set points are not practical. Do not use sensor to act as signal generator to simulate conditions or override values.

C. Scope of HVAC Subcontractor Testing:

1. Testing scope shall include entire HVAC installation for the project, from point of connection for high temperature water and for chilled water generation through distribution systems to each conditioned space. It shall include measuring capacities and effectiveness of operational and control functions.

2. Test all operating modes, interlocks, control responses, responses to abnormal or emergency conditions, and verify proper response of building automation system controllers and sensors.

15

Page 48: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

University of California, Riverside Multidisciplinary Research Building 1 Project No. 950528

D. Detailed Testing Procedures: CxA, with HVAC Subcontractor, TAB Subcontractor, and HVAC Instrumentation and Control Subcontractor, shall prepare detailed testing plans, procedures, and checklists for HVAC systems, subsystems, and equipment.

E. Boiler Testing and Acceptance Procedures (if applicable): Testing requirements are specified in Division 23 boiler Sections. CxA shall review and comment on submittals, test data, inspector record, and boiler certification and shall compile information for inclusion in systems manual. F. HVAC Instrumentation and Control System Testing:

1. Field testing plans and testing requirements are specified in Division 23 Sections "Instrumentation and Controls" and Sequence of Operation. The CxA, HVAC Subcontractor, and the HVAC Instrumentation and Control Subcontractor shall collaborate to prepare testing plans.

2. CxA shall convene a meeting of appropriate entities to review test report of HVAC instrumentation and control systems.

G. Pipe cleaning, flushing, hydrostatic tests, and chemical treatment requirements are specified in Division 23 Sections. HVAC Subcontractor shall prepare pipe system cleaning, flushing, and hydrostatic testing. CxA shall review and comment on plan and final reports. CxA shall certify that pipe cleaning, flushing, hydrostatic tests, and chemical treatment have been completed. Plan shall include the following:

1. Sequence of testing and testing procedures for each section of pipe to be tested, identified by pipe zone or sector identification marker. Markers shall be keyed Drawings for each pipe sector showing the physical location of each designated pipe test section. Drawings keyed to pipe zones or sectors shall be formatted to allow each section of piping to be physically located and identified when referred to in pipe system cleaning, flushing, hydrostatic testing, and chemical treatment plan.

2. Description of equipment for flushing operations. 3. Minimum flushing water velocity. 4. Tracking checklist for managing and ensuring that all pipe sections have been cleaned, flushed,

hydrostatically tested, and chemically treated.

H. Energy Supply System Testing (if applicable): HVAC Subcontractor shall prepare a testing plan to verify performance of hot-water systems and equipment. Plan shall include the following:

1. Sequence of testing and testing procedures for each equipment item and pipe section to be tested, identified by pipe zone or sector identification marker. Markers shall be keyed to Drawings for each pipe sector showing the physical location of each designated pipe test section. Drawings keyed to pipe zones or sectors shall be formatted to allow each section of piping to be physically located and identified when referred to in system testing plan.

2. Tracking checklist for managing and ensuring that all pipe sections have been tested.

I. Heat-Generation System Testing (if applicable): HVAC Subcontractor shall prepare a testing plan to verify performance of boilers, feedwater equipment, furnaces, and auxiliary equipment. Plan shall include the following:

1. Sequence of testing and testing procedures for each item of equipment and section of pipe to be tested, identified by identification marker. Markers shall be keyed to Drawings for each pipe sector showing the physical location of each item of equipment and pipe test section. Drawings shall be formatted to allow each item of equipment and section of piping to be physically located and identified when referred to in the system testing plan.

2. Tracking checklist for managing and ensuring that all pipe sections have been tested.

16

Page 49: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

University of California, Riverside Multidisciplinary Research Building 1 Project No. 950528

J. Refrigeration System Testing (if applicable): HVAC Subcontractor shall prepare a testing plan to verify performance of, refrigerant compressors and condensers, and other refrigeration systems. Plan shall include the following:

1. Sequence of testing and testing procedures for each item of equipment and section of pipe to be tested, identified by identification marker. Markers shall be keyed to Drawings showing the physical location of each item of equipment and pipe test section. Drawings shall be formatted to allow each item of equipment and section of piping to be physically located and identified when referred to in the system testing plan.

2. Tracking checklist for managing and ensuring that all pipe sections have been tested.

K. HVAC Distribution System Testing: HVAC Subcontractor shall prepare a testing plan to verify performance of air, steam, and hydronic distribution systems; special exhaust; and other distribution systems. Include HVAC terminal equipment and unitary equipment. Plan shall include the following:

1. Sequence of testing and testing procedures for each item of equipment and section of pipe to be tested, identified by identification marker. Markers shall be keyed to Drawings showing the physical location of each item of equipment and pipe test section. Drawings shall be formatted to allow each item of equipment and section of piping to be physically located and identified when referred to in the system testing plan.

2. Tracking checklist for managing and ensuring that all pipe sections have been tested.

L. Vibration and Sound Tests: HVAC Subcontractor shall prepare testing plans to verify performance of vibration isolation and seismic controls. CxA shall witness and certify tests and inspections.

M. Deferred Testing:

1. If tests cannot be completed because of a deficiency outside the scope of the HVAC system, the deficiency shall be documented and reported to University’s Representative. Deficiencies shall be resolved and corrected by appropriate parties and test rescheduled.

N. Testing Reports:

1. Reports shall include measured data, data sheets, and a comprehensive summary describing the operation of systems at the time of testing.

2. Include data sheets for each controller to verify proper operation of the control system, the system it serves, the service it provides, and its location. For each controller, provide space for recording its readout, the reading at the controller's sensor(s), plus comments. Provide space for testing personnel to sign off on each data sheet.

3. Prepare a preliminary test report. Deficiencies will be evaluated by University’s Representative to determine corrective action. Deficiencies shall be corrected and test repeated.

4. If it is determined that the system is constructed according to the Contract Documents, University’s Representative will decide whether modifications required to bring the performance of the system to the OPR and BoD documents shall be implemented or if tests will be accepted as submitted. If corrective Work is performed, University’s Representative will decide if tests shall be repeated and a revised report submitted.

END OF SECTION 23 0800

17

Page 50: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

University of California, Riverside Multidisciplinary Research Building 1 Project No. 950528

SECTION 26 0800 - ELECTRICAL COMMISSIONING

PART 1 - GENERAL

1.1 SUMMARY

A. This Section describes the requirements for start-up and commissioning for Division 26 installed work, including but not limited to:

1. Medium voltage distribution system 2. Low voltage distribution system. 3. Emergency power system. 4. Fire alarm system. 5. Lighting system. 6. Lighting control system. Daylight control system. 7. Grounding Equipment and Building Grounding System 8. Lighting Dimming System. 9. Security system. 10. Audio/Visual system.

1.2 REFERENCES

A. National Electrical Testing Association (NETA). B. American National Standard Institute (ANSI). C. Institute of Electrical and Electronic Engineers (IEEE). D. National Electrical Code (NEC). E. California Electric Code (CEC).

1.3 SUBMITTALS

A. Provide a complete commissioning and training plan submittal for the electrical work.

B. Perform the additional field tests and inspections and prepare test reports not mentioned in this section but required by each section under “Field Quality Control” of Divisions 26, 27 and 28.

1.4 QUALITY ASSURANCE

A. Provide testing equipment and accessories that are free of defects and are certified for use.

B. Provide testing equipment with current calibration labels.

C. Comply with commissioning procedures to ANSI and IEEE guidelines. Incorporate manufacturer's recommend commission procedures for equipment.

1.5 COORDINATION

A. Coordinate commissioning work with the requirements of Section 01 9113 – General Commissioning Requirements.

B. Coordinate commissioning requirements noted in other Division 26 Sections.

PART 2 - PRODUCTS - Not Used

18

Page 51: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

University of California, Riverside Multidisciplinary Research Building 1 Project No. 950528

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that equipment testing work is complete before starting functional performance of power equipment.

B. Verify that operational manuals are complete and been approved by the University’s Representative before starting functional performance testing.

C. Inspect equipment and confirm that it is clean and ready for operation. All shipping tags removed, nameplates installed and equipment manuals in place.

3.2 PREPARATION

A. Provide at least one journeyman electrician with tools and equipment necessary to perform functional testing.

B. Provide equipment factory representative for this work when needed.

C. Provide certified testing agency personnel for this work when needed.

D. Provide any necessary temporary power provisions, diesel fuel, equipment and sundries to complete this work.

3.3 POWER COMMISSIONING

A. Perform commissioning work after equipment is installed and system ready for operation.

B. Perform commissioning work in accordance with Power Check Lists and equipment manufacturer's standard procedures and check lists, including but not limited to:

1. Verify test readings, such as:

a. Ground fault protection. b. Ground resistance. c. Frequency. d. Transformer heating. e. Circuit breaker tripping.

2. Verify calibration of meters:

a. Kwhr meters. b. Voltmeters. c. Ammeters. d. Frequency meters. e. Circuit Breakers f. Fuses.

3. Verify operation of electronic power monitors.

19

Page 52: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

University of California, Riverside Multidisciplinary Research Building 1 Project No. 950528

4. Verify readings of remote data systems, such as:

a. Generator alarm.

5. Verify operation of emergency generator system during power loss and in specific:

a. Engine generator start b. Automatic transfer of power and bypass. c. Load demand. d. Engine cooling. e. Exhaust f. Generator rated capacity (full load test).

6. Verify that total power system is performing time delays outlined in the design intent under part and full load conditions.

3.4 FIRE ALARM SYSTEM COMMISSIONING

A. Perform commissioning work after alarm equipment is installed and system ready for operation.

B. Perform commissioning work in accordance to the manufacturer's standard procedures and check lists, including but not limited to:

1. Verify tests such as:

a. Alarm db. b. Detectors initiating signal. c. Trouble lights.

2. Verify settings of:

a. Smoke detectors. b. Heat detectors. c. Duct detectors.

3. Verify readings of remote data, such as annunciator panel.

4. Verify operation of system modes:

a. Elevator control. b. Sprinkler supervisory alarm. c. Kitchen hood extinguishing system. d. Kitchen gas solenoid valves. e. Door hold open/release.

5. Verify that total alarm system is performing to provide conditions as outlined in the design intent.

3.5 CHECKLIST - NORMAL POWER DISTRIBUTION

A. Prior to Functional Performance Test:

20

Page 53: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

University of California, Riverside Multidisciplinary Research Building 1 Project No. 950528

1. System in place, including all components indicated, and tested. 2. Connected to campus power system on a permanent basis. 3. Meter wired correctly. 4. Wiring installed in conduits or other raceways. 5. System checked for unwanted grounds, short circuits or open circuits. 6. Ground installed as indicated, including transformers. 7. Equipment connections properly torqued. 8. Equipment, where indicated, on housekeeping pads. 9. Equipment cleaned and shipping blocks removed. 10. Equipment labeled. 11. Boxes and nameplates meet color coding requirements.

B. Personnel to be present or assist as required to Perform Functional Performance Test:

1. Electrical Contractor, sub-contractors and specialty contractors as required. 2. University’s Representative's Project Manager/Representative and/or Inspector of Record (I.O.R.).

3. University’s maintenance staff, as desired. 4. Design Engineer.

C. Functional Performance Test: Demonstrate operation of normal power distribution system per specifications including the following:

1. Activate system by connection to utility power. 2. Demonstrate draw out operation of circuit breakers. 3. Verify voltages and amperes at meters on switchgear. 4. Verify voltages and amperes at switchgear, substations, switchboards, motor control centers, panelboards, and transformers, both primary and secondary. 5. Verify voltages and amperes at mechanical motors and other major pieces of equipment. 6. Verify meter accuracy and connection to the Campus energy system reads correctly.

D. Results:

1. If specified equipment performance is not verified, the Design Builder shall have corrections made and reschedule Functional performance Test as soon as possible after corrective work is completed.

3.6 CHECKLIST - EMERGENCY POWER DISTRIBUTION

A. Prior to Functional Performance Test:

1. System in place, including all components indicated, and tested. 2. Facility shall be connected to utility company power system on a permanent basis before emergency checklist is addressed. 3. Wiring installed in conduits or other raceways. 4. System check for unwanted grounds, short circuits or open circuits. 5. Grounds installed as indicated, including transformers. 6. Ground fault settings made. 7. Equipment connections properly torqued. 8. Equipment, where indicated, on housekeeping pads.

21

Page 54: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

University of California, Riverside Multidisciplinary Research Building 1 Project No. 950528

9. Equipment cleaned and shipping blocks removed. 10. Proper ventilation of electrical rooms. 11. Electrical rooms free of foreign pipes and ducts. 12. Fuel oil in fuel storage tank. 13. Intake and exhaust air, exhaust gas pipe and muffler, fuel oil piping installed. 14. Equipment labeled. 15. Boxes and nameplates meet color coding requirements. 16. Proper phase rotation coordinated between emergency and normal sources.

B. Personnel to be present or assist as required to perform Functional Performance Test:

1. General Contractor, Mechanical Contractor, Control Contractor, and Electrical Contractor, sub-contractors and specialty contractors as required. 2. University’s Representative's Project Manager Representative and/or Inspector of Record (IOR). 3. University’s maintenance staff, as desired. 4. Design Engineer(s).

C. Functional Performance Test: Demonstrate operation of emergency power distribution system per specifications including the following:

1. Activate system by manual transfer from utility power. 2. Demonstrate automatic transfer of power. 3. Verify voltages and amperes at meters on paralleling gear. 4. Verify voltages and amperes at paralleling gear switchboards. 5. Demonstrate synchronization and paralleling automatic and manual. 6. Demonstrate load shedding and load demand. 7. Verify generator performance (KW rating).

D. Results:

1. If specified equipment performance is not verified, the Design Builder shall have corrections made and reschedule Functional Performance Test as soon as possible after corrective work is completed.

3.7 CHECKLIST - FIRE ALARM SYSTEM

A. Prior to Functional Performance Test:

1. System in place, including all components indicated, and tested. 2. Connected to emergency power system. 3. Wiring is plenum rated where required. 4. Exposed Areas: Wiring installed in conduit. 5. System checked for grounds or breaks. 6. System connected to elevator control system, sprinkler alarm system and air handling systems. 7. Wiring installed in cable tray, or J-hooks, or bridal spring clips. 8. Cables have color coded identification tags. 9. Boxes and nameplates meet color coding requirements. 10. Verify system has been inspected and given approval by jurisdictional authority.

B. Personnel to be present or assist as required to perform Functional Performance Test:

22

Page 55: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

University of California, Riverside Multidisciplinary Research Building 1 Project No. 950528

1. General Contract, Mechanical Contractor, Control Contractor, Fire Alarm Manufacturer's Representative, and Electrical Contractor, sub-contractors and specialty contractors as required. 2. University’s Representative's Project Manager/Representative and/or Inspector of Record (I.O.R.). 3. University’s maintenance staff, as desired. 4. Design Engineer(s).

C. Functional Performance Test: Demonstrate operation of fire alarm system per specifications including the following:

1. Alarm initiating devices including pull stations, ceiling smoke detectors, duct smoke detectors, heat detectors, and sprinkler alarm switches. 2. Air handling unit redirect upon alarm. 3. Verify tie-in and proper system operation with any off-site system monitoring. 4. Fire alarm system annunciator panel. 5. Alarm devices, visual and audible. 6. Central processing unit alphanumeric display and printer. 7. Verify system function upon loss of power.

D. Results:

1. If specified equipment performance is not verified, the Design Builder shall have corrections made and reschedule Functional Performance Test as soon as possible after corrective work is completed.

3.8 GROUNDING/BUILDING GROUNDING SYSTEM

A. Starting Procedures: Follow the manufacturer's written procedures and the following as a minimum:

1. Conduct fall of potential ground resistance tests per IEEE Standard 81at each test well and at service equipment. 2. Conduct insulation resistance, short circuit, and ground tests of each motor.

3.9 TRAINING

A. At job completion, allow a period of not less than 24 hours for instruction of building operating and maintenance personnel in the use of all systems. Include high voltage safety training where medium voltage equipment is installed. This instruction time (24 hours) is in addition to any instruction time called out in other Division 26 Sections. B. Instruct all personnel at the same time. Design Builder shall be responsible for coordinating factory representative arrangements. C. Design Builder shall be responsible for training expenses incurred.

END OF SECTION 26 0800

23

Page 56: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

University of California, Riverside Multidisciplinary Research Building 1 Project No. 950528 S 18.0 COMMISSIONING CRITERIA

S 18.1 SUMMARY – Goals, Concepts & Quality Parameters

Commissioning is the process of ensuring that systems are designed, installed, functionally tested and capable of being operated and maintained to perform in conformity with the owner’s project requirements and the design intent.

S 18.2 COMMISSIONING – Qualifications & Responsibilities

The Design-Build team is responsible for the design, installation, testing, commissioning and functional performance of the facility in accordance with the owner’s project requirements identified in the Request for Proposal (RFP) documents, Design-Build team Basis of Design, the design documents, and related codes and standards. The Design-Build team shall certify that the facility is designed, built, and is functionally performing in accordance with the requirement of the RFP and related codes, standards, and contract documents. The Design-Build team shall provide contractor commissioning agents (CCx) qualified in each area of construction specialty. The CCx shall review, track, verify and document that their specific systems are designed, installed, tested, and are functionally performing in accordance with the Owner’s RFP requirements, and related codes and standards. The CCx shall perform functional performance tests for each specific discipline. The CCx shall certify and submit documentation confirming the systems are complete and functionally performing as required. The CCx shall be a part of the Design-Build team Quality Control (QC) team as 1st tier subcontractors and shall communicate directly with the Owner’s Commissioning Authority on all CCx commissioning issues, activities, and communications. The contractor commissioning agents shall be present for all startups and functional performance verification activities. The CCx shall setup training programs for each particular area of specialty. The contractor is responsible for maintaining a Cx schedule and Cx issues tracking including issues related to all programs. The Owner’s Commissioning Authority (CxA) will provide independent commissioning review and verification on behalf of the Owner. The Commissioning Authority will administer the overall commissioning process and will provide independent review of the Design-Build team design and installation, as well as verification of the functional performance testing, documentation, and training by the CCx. The Commissioning Authority will verify the functional performance tests performed by the CCx. The Commissioning Authority will coordinate and review the Commissioning Plan and will provide the final Commissioning Report. The Commissioning Authority will be a part of the commissioning team and will report directly to the Owner. The contractor commissioning agents (CCx) shall report to the owner’s third party commissioning authority (CxA). The contractor commissioning agents shall submit startup forms and functional performance verification forms for each system and piece of equipment. The owner’s third party commissioning authority (CxA) shall develop the Cx plan and incorporate functional performance verification into the overall Cx plan. The CCx shall submit Cx reports to the CxA to meet the submittal and reporting requirements of the LEED Ea Requirements for Enhanced Commissioning. All of the contractors Cx activities are subject to review by the owner’s third party cx authority

24

Page 57: Request for Qualifications For Commissioning Consultant ...ae.ucr.edu/business/950528_mrb11_rfq_commissioning_authority.pdf · Last day for Questions: Friday, July 1, ... • Free-standing

University of California, Riverside Multidisciplinary Research Building 1 Project No. 950528 S 18.4 COMMISSIONING – Program

• Pre-startup Verification • Functional Performance Testing • Point to Point Verification

S 18.5 COMMISSIONING – Systems

• Renewable Energy Systems

S 18.7 COMMISSIONING – Sustainable Design Criteria

Provide Commissioning in accordance with the requirements of LEED EA Credit 3 – Enhanced Commissioning. The CCx contractor commissioning agents shall submit completed Cx reports and documentation to the Commissioning Authority CxA for review, compilation, and upload to the USGBC LEED review system.

END OF COMMISSIONING CRITERIA

END OF QUALIFICATION SUBMITTAL