  • L127 094113/14

    21 July 2014

    Project No. 09-4113

    Britains Energy Coast

    Business Cluster

    Tender Opportunities

    Cumbria, UK

    REQUEST FOR PROPOSAL

    AGE DATING DRILLING SERVICES

    MOORSIDE SITE

    CUMBRIA, UNITED KINGDOM

    Dear Sir or Madam:

    RIZZO Associates (RIZZO) is undertaking a Site Suitability Study at the Moorside Site in

    Cumbria, United Kingdom, on behalf of Westinghouse Electric Company, LLC and

    NuGeneration Limited (NuGen). As part of this effort, Age Dating Drilling will be

    performed.

    You are hereby invited to submit a bid for consideration via this Request for Proposal (RFP).

    This RFP is comprised of this Letter and the following Attachments:

    Attachment A Technical Specification

    Attachment B Form of Contract and Insurance Requirements

    Please submit the following information in a complete bid package. Incomplete bids will not

    be considered.

    1. Response to Technical Specifications (Attachment A), including pricing. Confirm understanding of the Scope of Work and provide a plan to accomplish the desired

    scope. Confirm understanding and conformance to the Quality Assurance

    requirements.

    2. Acknowledgement of receipt and understanding of the Form of Contract and Insurance Requirements (Attachment B). Confirm agreement with the Form of

    Contract and insurance requirements or explain any points of disagreement. These

    will be negotiated following award of the Contract.

    3. Valid Certificates of Insurance (Attachment B).

    4. List of affiliations with contractor registrars, e.g., Achilles, CHAS, etc.

    5. Company Statement of Qualifications (SOQ); discussion on experience, knowledge, and qualifications.

    6. Schedule earliest date available to start.

  • Britains Energy Coast 2 21 July 2014

    L127 094113/14

    Proposal evaluation will consider qualifications, schedule readiness, quality assurance

    experience, and responsiveness in addition to price. RIZZO is not bound to select the lowest

    bid or any responding bidder.

    Bids are due by Noon, London time on 8 August 2014. Bids are to be submitted

    electronically to [email protected].

    A separate, larger Scope of Work (Site Characterisation) is also expected to be let in the next

    two to three weeks. Provide your contact information in order to be included in the

    distribution of that RFP.

    A combined site visit for both the Age Dating Drilling and Site Characterisation scopes are

    tentatively planned for 30 July 2014. If you intend to attend the site visit, please provide the

    following information to [email protected] no later than 23 July 2014:

    Names of staff attending

    Make, model, color, and registration number of vehicle(s) to be used

    We are anticipating providing notification of award for the Age Dating Drilling Scope in late

    August with mobilisation expected in late September 2014.

    If you have any questions, provide them in writing to [email protected] by 1 August

    2014. All responses will be provided in writing to all bidders.

    Sincerely,

    RIZZO Associates

    Anand K. Boscha, P.E.

    Senior Engineer

    AKB/sdr

    Attachments

    mailto:[email protected]:[email protected]:[email protected]

  • L127 094113/14

    ATTACHMENT A

    TECHNICAL SPECIFICATIONS

  • AGE DATING DRILLING TECHNICAL SPECIFICATION

    MOORSIDE SITE CUMBRIA, UNITED KINGDOM

    09-4113

    18 JULY 2014

    SUBMITTED TO:

    WESTINGHOUSE ELECTRIC COMPANY LLC and NuGENERATION LIMITED

    Corporate Headquarters 500 Penn Center Boulevard, Pittsburgh, PA 15235 USA

    Telephone: 412.856.9700 | Fax: 412.856.9749

  • Age Dating Drilling Page 2 of 22 Technical Specification 094113/14 Rev. 1 (18 July 2014)

    AGE DATING DRILLING TECHNICAL SPECIFICATION

    MOORSIDE SITE

    CUMBRIA, UNITED KINGDOM

  • Age Dating Drilling Page 3 of 22 Technical Specification 094113/14 Rev. 1 (18 July 2014)

    TABLE OF CONTENTS

    PAGE LIST OF TABLES AND FIGURES....................................................................................5

    1.0 INTRODUCTION ...................................................................................................6

    2.0 SCOPE OF WORK ..................................................................................................7

    2.1 INCLINED BORINGS .......................................................................................7

    2.2 LIGHT-SENSITIVE SAMPLING ........................................................................9

    2.3 VERTICAL DEVIATION SURVEY ...................................................................10

    2.4 ACOUSTIC TELEVIEWER TESTING ...............................................................10

    2.5 BACKFILLING OF BORINGS ..........................................................................11

    2.6 SCHEDULE, FACILITIES, AND SITE CONSTRAINTS ........................................11

    2.7 STAFFING ....................................................................................................12

    3.0 QUALITY, HEALTH, SAFETY, AND ENVIRONMENTAL REQUIREMENTS .................................................................................................14

    3.1 PERSONNEL QUALIFICATIONS .....................................................................15

    3.2 PROCEDURES ..............................................................................................15

    3.3 VERTICAL DEVIATION SURVEY ...................................................................16

    3.3.1 Boring Orientation .......................................................................16

    3.3.2 Boring Inclination ........................................................................16

    4.0 SUBMITTALS ......................................................................................................18

    4.1 PROPOSAL SUBMITTALS ..............................................................................18

    4.1.1 Logistics/Plan ..............................................................................18

    4.1.2 Health and Safety ........................................................................18

    4.1.3 Personnel Qualifications ..............................................................18

    4.1.4 Drilling Equipment, Procedures, and Materials ..........................18

    4.1.5 Vertical Deviation Survey and Acoustic Televiewer Testing .........................................................................................19

    4.1.6 Acoustic Televiewer Testing .......................................................19

    4.1.7 Duration .......................................................................................19

    4.1.8 Previous Experience ....................................................................19

    4.1.9 Subcontractors/Teaming ..............................................................20

    4.1.10 Bill of Quantities .........................................................................20

    4.2 IN-PROCESS SUBMITTALS ...........................................................................21

    4.2.1 Bi-Weekly Updates .....................................................................21

  • TABLE OF CONTENTS (CONTINUED)

    PAGE

    Age Dating Drilling Page 4 of 22 Technical Specification 094113/14 Rev. 1 (18 July 2014)

    4.3 FINAL SUBMITTALS .....................................................................................21

    4.3.1 Records ........................................................................................21

    4.3.2 Final Completion Report .............................................................21

    EXHIBIT 1 COMBINED SEISMIC SURVEY, REFLECTION AND REFRACTION PROFILES AND AGE-DATING BORINGS

  • Age Dating Drilling Page 5 of 22 Technical Specification 094113/14 Rev. 1 (18 July 2014)

    LIST OF TABLES

    TABLE NO. TITLE PAGE TABLE 2-1 PROPOSED BORING NUMBER AND DEPTH ...........................9

    TABLE 4-1 BILL OF QUANTITIES ................................................................20

    LIST OF FIGURES

    FIGURE NO. TITLE PAGE FIGURE 3-1 VERIFICATION OF VERTICAL DEVIATION

    SURVEY EQUIPMENT ...............................................................17

  • Age Dating Drilling Page 6 of 22 Technical Specification 094113/14 Rev. 1 (18 July 2014)

    AGE DATING DRILLING TECHNICAL SPECIFICATION

    MOORSIDE SITE

    CUMBRIA, UNITED KINGDOM

    1.0 INTRODUCTION The Moorside Site, which is the subject of this Technical Specification, is located adjacent to the Sellafield nuclear facility in Cumbria, UK. RIZZO Associates (RIZZO), acting as Principal Contractor, will subcontract a firm (the Subcontractor) to obtain samples of the fault materials and the glacial drift overlying the faults at the Site. Samples retrieved will be sent to specialized laboratories to determine the Date of Last Movement (DLM) of the faults. NuGen is developing a nuclear power plant at the Moorside Site. The Nuclear Decommissioning Authority (NDA) is the land owner. The Subcontractor will report to RIZZO technical and management leads. Interactions between NDA, Local Planning authority, and any other local authorities will be the responsibility of the NuGen Land Manager with input from RIZZO. The Site consists of unconsolidated glacial drift overburden abov