resource adequacy and cross-border capacity remuneration
TRANSCRIPT
Resource adequacy
and cross-border capacity remuneration schemes
Konrad Purchała, Director for European Integration Policy
Budapest, 30 May 2017
22
Key Figures of the Polish power system
■ Installed capacity
● ~40 GW
● incl ~7 GW renewable
● incl 1.4 GW pumped storage
■ Peak demand
● Peak winter: ~26 GW in Feb 17’
● Peak summer: ~23 GW in June 16’
■ Electricity production / consumption
● Production : ~160 TWh
● Consumption : ~162 TWh
■ Export/Import (real flows)
● Physical import: ~ 14 TWh
● Physical export: ~ 12 TWh
47.0% 46.6%
22.6%30.2%
3.7%
4.4%3.1%
4.5%
3.7%
0,3%15.0%
7.9%2.4%
4.7%2.6% 1.4%
NGC Generation
Net Generating Capacity (NGC) vs. net energy generation mix (2016)
Renewable hydro
Biomass & biogas
Onshore wind
Pump storage
Other non-renewable
Gas
Lignite
Hard Coal
3
Location of generation units in Poland
Opole - 4 units total capacity1532 MW
El. Bełchatów - 13 units total capacity 5420 MW
Kozienice - 10 units total capacity 2935 MW
Połaniec - 7 units hard
coal, 1 unit biomastotal capacity 1872 MW
Dolna Odra - 6 units total capacity 1362 MW
Rybnik – 8 units total capacity 1780 MW
Pątnów - 7 units total capacity 1708 MW
Adamów - 5 units total capacity 600 MW
Łaziska - 6 units total capacity 1155 MW
Ostrołęka - 3 unitstotal capacity 681 MW
Łagisza - 3 unitstotal capacity 700 MW
Siersza - 4 units total capacity 557 MW
Skawina - 3 unitstotal capacity 330 MW
Turów - 6 unitstotal capacity - 1488 MW
Żarnowiec - 4 units total capacity716 MW
hydro (mainly pumped storage)
lignite
hard coal
Stalowa Wola - 2 unitstotal capacity 250 MW
Jaworzno - 6 units total capacity 1345 MW
Porąbka-Żar - 4 unitstotal capacity 540 MW
Status on
January 1, 2016
4
Cross-border interconnections
Synchronous profile
Germany:
• line 400kV Krajnik – Vierraden (temporary
on the voltage 220 kV)
• line 400kV Mikułowa – Hagenwerder
Czech Republic:
• line 400kV Dobrzeń - Albrechtice
• line 400kV Wielopole – Nosovice
• line 220kV Kopanina/Bujaków – Liskovec
Slovakia:
line 400 kV Krosno Iskrzynia – Lemesany
Asynchronous interconnections
Ukraine:
• line 220 kV Zamość – Dobrotwór
• line 750 kV Rzeszów – Chmielnicka
(currently out of operation)
Bielarus:
• line 220 kV: Białystok – Roś
(currently out of operation)
Lithuania:
• line 400 kV: Ełk Bis – Alytus (with B2B
located in Alytus)
Sweden:
• 450 kV DC cable Słupsk Wierzbięcino –
Stärno
Krajnik
Słupsk
Białystok
DobrzeńWielopole
Krosno
Iskrzynia
Kopanina
Bujaków
AlbrechticeNosovice
Lemešany
Chmielnicka
Dobrotwor
Roś
Stärno
Vierraden
Hagenwerder
Liskovec
Mikułowa
Rzeszów
Zamość
POLANDGermany
Czech
Republic
Slovakia
Ukraine
Belarus
LithuaniaRussia
X
Boguszów
Porici Ustroń /
Mnisztno
BrześćWólka
Dobrzyńska
X
Pogwizdów
Darkov
110 kV
220 kV
400 kV
450 kV DC cable
400 KV temporary on the
voltage 220 kV
X Out of operation
Kudowa -Zdrój
Náchod
Hirschfelde
Trzyniec
750 kV
Alytus
Ełk BisX
(Radial
operation)
(Temporarily diconnected,
(until PST in Vieraden is installed
Back-to-back DC converter
5
■ Factors determining the security of energy supply
▪ Appropriate network infrastructure (network adequacy) development through
regulatory mechanisms
▪ Required amount of generation capacity (generation adequacy) development
through market mechanisms
■ Requirements regarding generation adequacy
▪ Volume of generation capacity must be higher than system peak demand, to cover:
• Losses in generation capacity resulting from limits/outages in the generation resources
• Losses in generation capacity resulting from limits/outages in the network infrastructure
• Contribution from foreign power systems to be also duly considered (although with care)
▪ Important attributes of the generation adequacy
• Volume – building new generation resources and decommissioning the old ones
• Location – coordination with network development
• Technology – adequate for the shape of demand curve (system needs)
Security of energy supply
6
■Will the Energy-only market be able to deliver long-term adequacy?
▪ Some say that generation investments will be triggered by scarcity pricing
▪ Missing generation investments to be tackled by „dedicated strategic generation
reserves” and Demand Response
▪ Reality:
• No dedicated capacity market but all kinds of reserves putting generation capacity out
of the market: network reserve, emergency reserve, balancing reserve, coal reserve, etc…
• Virtually no new investments in conventional generation technologies (only subsidized RES)
• When risks to adequacy identified (trigger for scarcity prices), special measures considered!
■Will it be enough?
▪ Generation investments are very risky: lumpy with long pay-back times (technology
and regulatory risks)
▪ Possibility for a high price every now and then might be insufficient to freeze
billions of EUR for 30 years pay-back
▪ This approach results in volatile and unpredictable electricity prices for final consumers
▪ How do you distinguish scarcity pricing from market power?
How to ensure long-term adequacy?
77
Polish power balance Scenario „BAT modernization”
-22000
-21000
-20000
-19000
-18000
-17000
-16000
-15000
-14000
-13000
-12000
-11000
-10000
-9000
-8000
-7000
-6000
-5000
-4000
-3000
-2000
-1000
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
I IV VII X I IV VII X I IV VII X I IV VII X I IV VII X I IV VII X I IV VII X I IV VII X I IV VII X I IV VII X I IV VII X I IV VII X I IV VII X I IV VII X I IV VII X I IV VII X I IV VII X I IV VII X I IV VII X I IV VII X
2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035
Excess of required power surplus Deficit of required power surplus Power surplus required by TSO Power surplus available to TSO
MW
8
Recourses adequacy in PolandRelation between unscheduled power flows and generation adequacy
Illustration based on critical generation adequacy issues
experienced on August 10th to 12th 2015 in Poland (insufficient generation to cover domestic demand for energy and reserves)
9
Combination of unscheduled flows issue together with
scarcity situation led to load reduction in PL last August:
August 10th, 2015, 3:30 pm
(day ahead market schedules vs related physical flows)
HU
3519
262
58
9
1810
14
66
329
2010
I
Import
2433
54,99€
0
1160
185
1000
NL – B
Import 5954
NL 51,42€
BE 47,47€
I
1349
D
Export 7435
31,40€
PL
Import 0
76,06€
CR
Export 1626
32,13€
HU
Import
2722
60,05€
SK
Import 430
32,13€
250
FR
Export 8189
37,04€ AU
Import 3176
31,40€CH
Import 1928
35,06€
schedules of day ahead market (DA)
DK West/East
72,09€ / 72,09€
S
10,59€
calculated flows DA;first run of DACF
25
3
Schedule in line with price difference
Schedule not in line with price difference
913
10
Situation on the DE-PL border on 10.08.15 (1)
10
500 MW
2000 MW
3000 MW
(3) MRA limited due toexhaustion of power reservesfor MRA at AT, CH i SL
500 MW
0 MW
(2) CZ, HU, HR, SK:no possibility to increasegeneration for MRA
(1) 6 pm on Aug 9th:XBR not possible at alldue to power reserves in PLat the minimum DA level
500 MW
(4) Relieving DE/PL from Congestions due to Unscheduled flowscompleted only at 3 amon Aug 10th
11
11
500 MW
2000 MW
3000 MW
500 MW
0 MW
max 3.4 GW
500 MW
(1) 9pm on Aug 9th:power deficit of 1.2 GWin Poland
600 MW(2) 1.2 GW import fromthe only available direction(Germany) would have increased flow on congestedDE/PL border by 600 MW
(3) to relieve the flow by 600 MWincrease of 6 GW of generation in Western Germany (where available only) would be necessary (only 3.4 GW available), moreover no more time to agree it (only 4h left)
4) 6 am on Aug 10th: power deficyt in PolandIncreases by another 1 GW
Situation on the DE-PL border on 10.08.15 (2)What should be done to allow for 1.2 GW import
13
■Complement the energy market with adequacy-related commodity
▪ Liberalized energy market is a multi-commodity market
▪ Capacity market is a market-based means to correctly remunerate the service
rendered by stable generation for the overall security of supply
■ Planned Capacity Market in Poland - structural market
improvement by implementation of the missing market segment
▪ Market based mechanism ensuring competition between
• all generation technologies
• cross-border resources
• demand side
▪ Reduces the investment risks for utilities, not eliminating it!
▪ Tool for authorities to set adequate levels of security of supply
▪ However, required clearance from EU competition authorities
• Capacity market is considered by EC as state aid
Solution to generation long-term adequacy:
dedicated generation capacity market
14
■Capacity market is a mechanism to facilitate generation adequacy
▪ Domestic resources are under jurisdiction of relevant authorities: easier to execute
delivery of energy, less prone to political twists (i.e. unexpected nuclear phase-out)
▪ However, EU law requires equal treatment of all resources
■ According to EC, procurement of generation resources outside
of the country cannot be unduly limited (free movement of goods
and services)
▪ One need to account for the available cross-zonal transfer capacity
▪ However, no guarantees for delivery to the concerned Member State can be required
• According to the EC, it is up to the market to ensure that the energy will be directed
to the Member State with energy deficit.
■ Talks between EC and Poland on the capacity market are ongoing
▪ Main issues: details of cross-border participation, distinction new/modernized
Cross-border participation in capacity
mechanism