retrocommissioning lessons from the field by eveline killian

23
Retrocommissioning Lessons from the Field Eveline Killian, CEM Cx Associates, LLC

Upload: cx-associates

Post on 19-Aug-2014

176 views

Category:

Engineering


4 download

DESCRIPTION

Retrocommissioning has multi-faceted benefits – operating, maintenance and replacement cost reductions – but its value is still hard to market to building owners and energy utilities. This presentation details a number of successful retrocommissioning projects in Vermont with proven energy and maintenance savings. It also details an innovative consulting contract Cx Associates has structured to maintain the energy savings realized through retrocommissioning, as well as help control maintenance costs and identify further opportunities. Building owners and efficiency utilities are convinced by the facts of real savings – come listen to some examples! Success stories include a 70,000 square foot, 100-year old, 4-story brick building with office and retail spaces with a improvements made to its central heat pump system; a 42,000 square foot public library with BMS control upgrades, and a 2-story office building with a central hydronic heating system and rooftop unit cooling systems. Improvements range from simple maintenance items to VFD retrofits to BMS installations. We will detail the audit and analysis we performed to gain commitment from both the building owner and the energy utility, the design process, the actual construction trials and tribulations, and methods of proving the savings outcome. The projects have been in operation for a minimum of nine months and we will discuss their ongoing performance. Real-life examples of the system and human issues we encountered in these older buildings, and the collaboration it took to overcome them, will be described. In addition, we have entered an “Operational Performance” contract with one of our retrocommissioned buildings. This contract oversees the preventative maintenance program to ascertain its effectiveness, provides technical support for maintenance issues, monitors energy saving retention, ensures efficient operation of the HVAC systems, and identifies further opportunities. In this presentation we will discuss the process, successes and challenges of such an innovative program.

TRANSCRIPT

Page 1: Retrocommissioning Lessons From the Field by Eveline Killian

Retrocommissioning Lessons from the Field

Eveline Killian, CEMCx Associates, LLC

Page 2: Retrocommissioning Lessons From the Field by Eveline Killian

AIA Quality Assurance

The Building Commissioning Association is a Registered Provider with The American Institute of Architects Continuing Education Systems (AIA/CES). Credit(s) earned on completion of this program will be reported to AIA/CES for AIA members. Certificates of the Completion for both AIA members and non-AIA members are available upon request.

This program is registered with AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product.

Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.

2

Page 3: Retrocommissioning Lessons From the Field by Eveline Killian

3

At the end of this session participants will be able to:

See the benefits of: • Retrocommissioning small commercial buildings• Developing a collaborative team • Staying flexible with expectations• Choosing the measures carefully

And…be forewarned of some stumbling blocks

Learning Objectives

Page 4: Retrocommissioning Lessons From the Field by Eveline Killian

4

Presentation OverviewExample Projects

Lessons Learned

Page 5: Retrocommissioning Lessons From the Field by Eveline Killian

5

Howard Opera House

Page 6: Retrocommissioning Lessons From the Field by Eveline Killian

6

Problem Statement

• Constant speed pumps

• Manual diverter valve

• Failing controls

• Open ductwork to MEP

Page 7: Retrocommissioning Lessons From the Field by Eveline Killian

7

RCx Solutions

• VSDs on cooling tower and main pumps

• Removal of diverter valve

• Boiler circulating pump

• Central Plant controls

• Controlled OA dampers

Page 8: Retrocommissioning Lessons From the Field by Eveline Killian

8

Realized Savings

-

5,000

10,000

15,000

20,000

25,000

30,000

35,000

40,000A

pr-1

3

May

-13

Jun-

13

Jul-1

3

Aug

-13

Sep

-13

Oct

-13

Nov

-13

Dec

-13

Jan-

14

Feb-

14

Mar

-14

kWh

Pre- and Post-Installation Monthly kWh

Pre kWh Post kWh

Page 9: Retrocommissioning Lessons From the Field by Eveline Killian

9

Fletcher Free Library

Page 10: Retrocommissioning Lessons From the Field by Eveline Killian

10

Controls Upgrade Savings

Average annual utility bill savings of 18%.

Page 11: Retrocommissioning Lessons From the Field by Eveline Killian

11

Operational Performance Support Services Contract

• Monitor HVAC system operation & utility bills

• Maintenance program definition & oversight

• Assessment of unplanned maintenance items

• Further energy savings identification

• Long-term capital planning for HVAC system costs

Page 12: Retrocommissioning Lessons From the Field by Eveline Killian

12

Performance Monitoring Successes

• Chiller compressor failure Early cooling tower failure warning.

• HVAC-1 economizer/fan speed control.

• Exhaust fan failure discoveries.

• Resolution of draft issues at circulation desk.

• Freezestat failure discoveries.

Page 13: Retrocommissioning Lessons From the Field by Eveline Killian

13

Typical RCx Measures

• VSDs on pumps

• Controls

• Setpoint changes

• Pipe insulation

• Economizer

• System harmonizing

Page 14: Retrocommissioning Lessons From the Field by Eveline Killian

14

Stumbling Blocks• Scope increases during

project• Narrow our attention…

and then… refer to firstbullet

• Contractor schedule pushed out

• Plans were incomplete, took long to piece together

Page 15: Retrocommissioning Lessons From the Field by Eveline Killian

15

What Went Right

The people!• Quality

contractors

• Flexible team

• Collaborative team

• Good communication

Page 16: Retrocommissioning Lessons From the Field by Eveline Killian

16

Lessons Learned

Page 17: Retrocommissioning Lessons From the Field by Eveline Killian

17

Lesson #1: Gauge the OwnerDetermine:

• their version of the problem

• their openness to new efficiency ideas

• if there are others who could influence the project and involve them early

Hear and address their concerns immediately

Page 18: Retrocommissioning Lessons From the Field by Eveline Killian

18

Lesson #2: Good Contractors

Create a team you can trust and then listen to their ideas throughout the project

Page 19: Retrocommissioning Lessons From the Field by Eveline Killian

19

Lesson #3: Stay FlexibleIf it’s an old building, things WILL come up unexpectedly – stay flexible and creative, and convey this mindset to the owner.

HoweverDon’t necessarily promote this attitude to the contractors – you’ll be bombarded with suggestions and change orders!

Page 20: Retrocommissioning Lessons From the Field by Eveline Killian

20

Lesson #4: Choose Measures Wisely

• Present at least two tiers in the proposal:• Tier 1: conservative approach

that addresses their concerns • Tier 2: deeper cost-effective

opportunities• Tier 3: long term opportunities

• Don’t push – they’ll balk

• Don’t try to do it all – they’ll balk

Page 21: Retrocommissioning Lessons From the Field by Eveline Killian

21

Lesson #5: Choose Owners Wisely

If you can, pick owners that:• care about their

building, not just their bottom line

• have the support they need to make it happen

• will potentially lead to more projects

Page 22: Retrocommissioning Lessons From the Field by Eveline Killian

22

Why It’s Worth Doing

• Commercial Buildings consume nearly 20% of all energy used in the United States.

• We spend more than $200 billion each year to power our country's commercial buildings.

• “A typical commercial building could save 20% on its energy bills simply by commissioning existing systems so they operate as intended.”

Source: U.S. DOE - http://www4.eere.energy.gov/alliance/node/9

Page 23: Retrocommissioning Lessons From the Field by Eveline Killian

Company NameWebsiteEmail Address

Eveline Killian, CEMSenior Engineer

www. [email protected] ext. 15