Retrofit Doors to Open Vertical Cases Provisional UES Proposal Presentation to the Regional Technical Forum August 30, 2011 1

Upload: paul-peters

Post on 20-Jan-2016

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Retrofit Doors to Open Vertical Cases Provisional UES Proposal Presentation to the Regional Technical Forum August 30, 2011 1

Retrofit Doors to Open Vertical Cases

Provisional UES Proposal Presentation to the Regional Technical Forum

August 30, 2011

1

Page 2: Retrofit Doors to Open Vertical Cases Provisional UES Proposal Presentation to the Regional Technical Forum August 30, 2011 1

Measure Summary

• Retrofitting insulated glass doors to existing medium temperature open multi-deck cases

• Provisional savings estimates ~440-kWh/lin ft and 52-therms/lin ft

• Based on a calibrated DOE2.2r simulation

• Requesting Provisional UES Status

2

Page 3: Retrofit Doors to Open Vertical Cases Provisional UES Proposal Presentation to the Regional Technical Forum August 30, 2011 1

3

UES Analysis Summary

Page 4: Retrofit Doors to Open Vertical Cases Provisional UES Proposal Presentation to the Regional Technical Forum August 30, 2011 1

Appendix A: Provisional UES Checklist

4

Page 5: Retrofit Doors to Open Vertical Cases Provisional UES Proposal Presentation to the Regional Technical Forum August 30, 2011 1

5

Appendix B: UES Measure Summary

Page 6: Retrofit Doors to Open Vertical Cases Provisional UES Proposal Presentation to the Regional Technical Forum August 30, 2011 1

6

Page 7: Retrofit Doors to Open Vertical Cases Provisional UES Proposal Presentation to the Regional Technical Forum August 30, 2011 1

7

Page 8: Retrofit Doors to Open Vertical Cases Provisional UES Proposal Presentation to the Regional Technical Forum August 30, 2011 1

8

Page 9: Retrofit Doors to Open Vertical Cases Provisional UES Proposal Presentation to the Regional Technical Forum August 30, 2011 1

9

Page 10: Retrofit Doors to Open Vertical Cases Provisional UES Proposal Presentation to the Regional Technical Forum August 30, 2011 1

Implementation and Product Standards

10

• No anti-sweat heat in door glass, frames or mounting equipment

• Total lighting power may not be increased as a part of the retrofit

Page 11: Retrofit Doors to Open Vertical Cases Provisional UES Proposal Presentation to the Regional Technical Forum August 30, 2011 1

Estimation Procedure

11

• Modeled using DOE 2.2R to capture interactive effects

• “Typical” store was built using GrocerSmart Audit Data

• Multiplex Baseline assumes Floating Head Pressure, T8 lamps, and EC motors are in place.

• Stand-alone system baseline assumes T8 lamps and EC motors.

• Infiltration, conduction, and radiation load based on manufacturer data, the ASHRAE Refrigeration Handbook, and SCE lab test reports

Page 12: Retrofit Doors to Open Vertical Cases Provisional UES Proposal Presentation to the Regional Technical Forum August 30, 2011 1

Model Calibration: Whole Building

12

Page 13: Retrofit Doors to Open Vertical Cases Provisional UES Proposal Presentation to the Regional Technical Forum August 30, 2011 1

Model Calibration:Compressor Energy Use

13

Page 14: Retrofit Doors to Open Vertical Cases Provisional UES Proposal Presentation to the Regional Technical Forum August 30, 2011 1

Model Calibration- Baseline:Case Refrigeration Load

14

Total case load based on ANSI/ASHRAE 72 testing = 1600 btu/hr-ft

ASHRAE data used to disaggregate load components

Page 15: Retrofit Doors to Open Vertical Cases Provisional UES Proposal Presentation to the Regional Technical Forum August 30, 2011 1

Model Calibration – Efficient-Case: Fixture Refrigeration Load

15

Page 16: Retrofit Doors to Open Vertical Cases Provisional UES Proposal Presentation to the Regional Technical Forum August 30, 2011 1

16

Costs Estimated

• All measure variants: $566/ft

• Average of 4 bids from 2 vendors

• Includes additional costs from minor system upgrades required to compensate for reduced load (replace expansion valves, etc.)

Page 17: Retrofit Doors to Open Vertical Cases Provisional UES Proposal Presentation to the Regional Technical Forum August 30, 2011 1

17

Measure Effective Useful Life

• EUL: 12 years

• Source: CALMAC

• Assumes display cases have a 16 year EUL and have expended 25% of EUL

Page 18: Retrofit Doors to Open Vertical Cases Provisional UES Proposal Presentation to the Regional Technical Forum August 30, 2011 1

18

Reliable Efficient Case Data

Page 19: Retrofit Doors to Open Vertical Cases Provisional UES Proposal Presentation to the Regional Technical Forum August 30, 2011 1

Calibration Plan• Collect Metered Data

– Rack: Volts, Amps, PF– Condenser: Volts, Amps, PF– Defrost: 1-time Voltage reading, Amps– HVAC Unit: 1-time Voltage reading, Amps– Hourly Natural Gas via Utility Interval Meter– Hourly Outside Air Temperature

• Minimum 3 weeks baseline • Minimum 3-weeks post

– This is a direct load measure. We expect less seasonal interaction than system measures like floating head pressure.

19

Page 20: Retrofit Doors to Open Vertical Cases Provisional UES Proposal Presentation to the Regional Technical Forum August 30, 2011 1

Calibration Plan• Develop regressions for daily or hourly

refrigeration use correlated to ambient temperature

• Annualize using TMY data– Pre, Post and Savings (Pre minus Post)

20

Page 21: Retrofit Doors to Open Vertical Cases Provisional UES Proposal Presentation to the Regional Technical Forum August 30, 2011 1

Calibration Plan

• Collect DOE2.2r inputs per data collection specifications• Use inputs to run DOE2.2r for Baseline & Post estimates

of total refrigeration energy• Compare estimates of Baseline, Post & Savings

estimates of refrigeration energy to best-practice estimates

• Modify DOE2.2r models and iterate tests until both baseline energy use, post energy use and energy savings at all sites are reasonable and there is no significant bias.

21

Page 22: Retrofit Doors to Open Vertical Cases Provisional UES Proposal Presentation to the Regional Technical Forum August 30, 2011 1

Proposed Provisional UES Values

Measure

Site Savings (kWh/ft)

Site Savings

(therms/ft)Measure

LifeCapital

Cost ($/ft)TRC B/C

Ratio

Door Retrofit- No night covers in Baseline/Multiplex Compressor- Seattle, WA 457.2 57.4 12 $566 2.2

Door Retrofit- Night covers in Baseline/Multiplex Compressor- Seattle, WA 415.2 51.9 12 $566 2.0

Door Retrofit- No night covers in Baseline/Stand-alone Compressor- Seattle, WA 477.4 57.4 12 $566 2.2

Door Retrofit- Night covers in Baseline/Stand-alone Compressor- Seattle, WA 432.7 51.9 12 $566 2.0

Door Retrofit- No night covers in Baseline/Multiplex Compressor- Spokane, WA 419.1 51.7 12 $566 2.0

Door Retrofit- Night covers in Baseline/Multiplex Compressor- Spokane, WA 377.5 46.5 12 $566 1.8

Door Retrofit- No night covers in Baseline/Stand-alone Compressor- Spokane, WA 436.7 51.7 12 $566 2.0

Door Retrofit- Night covers in Baseline/Stand-alone Compressor- Spokane, WA 392.7 46.5 12 $566 1.8

Door Retrofit- No night covers in Baseline/Multiplex Compressor- Billings, MT 417.3 48.0 12 $566 1.9

Door Retrofit- Night covers in Baseline/Multiplex Compressor- Billings, MT 371.6 43.1 12 $566 1.7

Door Retrofit- No night covers in Baseline/Stand-alone Compressor- Billings, MT 433.9 48.0 12 $566 2.0

Door Retrofit- Night covers in Baseline/Stand-alone Compressor- Billings, MT 386.1 43.1 12 $566 1.8

Page 23: Retrofit Doors to Open Vertical Cases Provisional UES Proposal Presentation to the Regional Technical Forum August 30, 2011 1

RTF Proposed Motion:

“I _________ move that the RTF approve the UES for Adding Doors to Medium Temperature Open Vertical Refrigerated Display Cases under provisional status with a sunset date of August 31st, 2013.