rider levett bucknall ketchikan berth i ii expansion
TRANSCRIPT
Ketchikan Berth I & II Expansion Schematic Design Estimate
Project Details
Description
Basis of Estimate
Rider Levett Bucknall
This estimate has been prepared at the request of Barmello, Ajamil & Partners and is to develop a 35% Sumbittal Document estimate for the Ketchikan Berth I & II Expansion project for the City of Ketchikan. The project is located in Ketchikan , AK.
The estimate is based upon measured quantities and built-up rates prepared from the drawings by Moffitt & Nichol dated 6/11/2018.
Where information was insufficient, assumptions and allowances were made based wherever possible on discussions with the architect and engineers. We have utilized our experience with similar projects, our cost data information from suppliers and subcontractors, taking into consideration the local construction market for the type and size of similar projects.
Unit pricing is based on May 2019 costs.
Project Schedule:
1) Berth I should be figured to start on Oct 1st, 2021 and must be complete by April 15, 2022.
2) Berth II would go the year after- October 1st, 2022 and complete on April15, 2023.
3) Duration: 6 months each phase.
A reasonable allowance of estimating contingency has been included to account for the level of the design and the complexity of the project.
It is assumed that the contractor will have free access to the work areas.
The costs used in this estimate are based on the assumption that competitive bids for all trades will be received, unless noted otherwise, and that the contractor will be required to pay state prevailing wages for the areas including travel and associated fringe benefits.
COMMENTARY ON THE ESTIMATE DETA ILS:
Items are represented by standard units of measure. Example; LF, SY, CY, Item, Each, etc
Unless otherwise noted in the cost report, quantities are measures as fixed in position. There is no allowance for waste in the quantity.
UNIT RATES INCLUDE:
SEA21177-10 Printed 7 May 2019 2:01PM Page 1 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate
Project Details
Description
II Rider Levett Bucknall
Materials, goods, and all costs in connection therewith including material required for lapping, jointing and the like and all connections therewith such as conveyance, delivery, unloading, storing, returning, packings, handling, hoisting and lowering, square and raking straight cutting , circular cutting and splay cutting, waste of materials, protection, progressive and final cleaning , samples, guarantees and warranties, labor and all costs in connection therewith, shop fabrication work, shop drawings, as-built drawings, manuals, testing, establishment costs, overhead costs and profit, plant and equipment, and site allowances.
Items Specifically Included
Mark-ups included:
1.50% Travel/Subsistence/Lodging
10.00% - Estimating Contingency
5.00% - Insurance and Bonds
7.00% General Conditions/Requirements
5.00% Overhead and Profit
7.79% Escalation - Berth I to start of construction Oct. 2021
10.79% - Escalation- Berth II to start of construction Oct. 2022
Excluded - Sales Tax
Allowances and Clarifications:
1) Assumes Berth I & II can each be completed in one off season each.
2) Straight piles are figured at 150' -0" deep
3) Batter piles are figured at 200'-0" deep.
4) Assume piling driven to bedrock.
5) Light blasting
6) Over drilling
7) Travel & Subsistence for workers
8) Coating steel pipes
9) Galvanizing rails and steel
1 0) Environmental Monitoring
11 ) Sea Mammal Monitoring
12) Cathodic Protection
Items Specifically Excluded
Sales Tax
Pinnacle removal and existing B1 & B2 CP costs
Hazardous Materials
Utility tap fees and charges
Owner's Insurances
SEA21177-10 Printed 7 May 2019 2:01 PM Page 2 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate
Project Details
Description
Special testing & inspections
Permit & plan review fees
Work outside the site boundaries unless noted otherwise
Work to existing buildings unless otherwise noted
Land and legal costs
Architectural, Engineering and other professional fees
Geotechnical, traffic and other studies
Construction Contingency
Owners Contingency
Allowance for shutdowns
Documents
See Basis of Estimate
SEA21177-10 Printed 7 May 2019 2:01PM
Ill Rider Levett Bucknall
Page 3 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate
Estimate Summary
II Rider Levett Bucknall
Rates Current At May 2019
Location Total Cost
BERTH I
11 Pontoons 7,793,750 12 Access Platform 517,475 13 Access Ramp Platform 1,296,085 14 Drive Down Ramp 1,809,255 15 Gangway Berth 1,072,874 16 Mooring Dolphin 2,646,360 17 Breasting Dolphin 3,268,772 18 Reaction Dolphin 3,878,130 19 Catwalks 308,478 110 Power/Lighting 444,100 111 Water & Fire Protection 278,500 112 Mob/Demob/Barge/Rig 10,996,000 113 Selective Demolition 378,420 114 Misc. 900,000
1- BERTH I $35,588,199
II BERTH II
111 Pontoons 7,793,750 112 Access Platform 517,505 113 Access Ramp Platform 1,296,145 114 Drive Down Ramp 1,809,255 115 Gangway Berth 1,072,876 116 Mooring Dolphin (N/A)
117 Breasting Dolphin 3,268,891 118 Reaction Dolphin 3,878,430 119 Catwalks 165,082 11 10 Power/Lighting 259,900 1111 Water & Fire Protection 286,000 11 12 Mob/Demob/Barge/Rig 8,290,000 11 13 Selective Demolition 333,735 1114 Misc. 900,000
II- BERTH II $29,871,569
ESTIMATED NET COST $65,459,768
MARGINS & ADJUSTMENTS
Travel/Subsistence/Lodging 1.5 % $981 ,897 Estimating Contingency 10.0 % $6,644,167
SEA21 177-1 0 Printed 7 May 2019 2:01 PM Page 4 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate
Estimate Summary
Rider Levett Bucknall
Rates Current At May 2019
Location Total Cost
MARGINS & ADJUSTMENTS (continued)
Insurance and Bonds
General Conditions/Requirements
Overhead and Profit
Escalation (Berth I)- start Oct. 2021
Escalation (Berth II) - start Oct. 2022
Sales Tax
SEA21177-1 0 Printed 7 May 2019 2:01 PM
ESTIMATED TOTAL COST
5.0% $3,654,292
7.0% $5,371,809
5.0% $4,105,597
4.2% $3,651,444
4.7% $4,245,224
Excl.
$94,114,198
Page 5 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate
Elemental Summary
Rider Levett Bucknall
Rates Current At May 2019
Description % Total Cost
A1030 Slab on Grade 0.4% $371,000
81010 Floor Construction 2.8% $2,654,465
81020 Roof Construction 0.4 % $413,025
82010 Exterior Walls 4.0 % $3,796,710
83010 Roof Coverings 0.5% $508,800
C1030 Fittings 0.0% $3,200
D4020 Standpipes 0.0 % $18,000
D4030 Fire Protection Specialties 0.0 % $12,000
D5010 Electrical Service & Distribution 0.3 % $300,000
F1010 Special Structures 16.0 % $15,050,000
F1030 Special Construction Systems 18.9% $17,786,000
G1020 Site Demolition and Relocations 0.8 % $712,155
G1030 Site Earthwork 20.8 % $19,558,950
G2010 Roadways 0.0 % $15,000
G2040 Site Development 2.8% $2,627,963
G3010 Water Supply 0.6 % $528,500
G4010 Electrical Distribution 0.3 % $255,700
G4020 Site Lighting 0.2 % $148,300
GC General Conditions 7.5 % $7,053,706
IN Insurances and Bonds 3.9 % $3,654,292
OH Overhead and Profit 4.4% $4,105,597
EC Estimating Contingency 7.1 % $6,644,167
TX State Sales Tax Excl.
EL Escalation 8.4 % $7,896,668
ESTIMATED TOTAL COST $94,114,198
SEA21177·10 Printed 7 May 2019 2:01 PM Page 6 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate Estimate Details
I BERTH I 11 Pontoons
II Rider Levett Bucknall
Rates Current At May 2019
Description Unit Qty Rate Total
82010 Exterior Walls
05 Metals
8 Removable railing LF 1,075.00 250.00 268,750
Metals $268,750
Exterior Walls $268,750
F1010 Special Structures
35 Waterway and Marine Construction
7 Foam filled floating fender EA 8.00 50,000.00 400,000
9 Concrete pontoon SF 23,750.00 300.00 7,125,000
Waterway and Marine Construction $7,525,000
Special Structures $7,525,000
PONTOONS $7,793,750
SEA21177-10 Printed 7 May 2019 2:01 PM Page 7 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate Estimate Details
I BERTH I 12 Access Platform
Description
A1030 Slab on Grade
03 Concrete
4 1' Thick reinforced concrete slab
8 1010 Floor Construction
05 Metals
1 Access platform structural steel
82010 Exterior Walls
05 Metals
5 Steel railing
G1030 Site Earthwork
31 Earthwork
2 36" Pipe piling
3 Reinforced concrete in pipe piling
Concrete
Slab on Grade
Metals
Floor Construction
Metals
Exterior Walls
Earthwork
Site Earthwork
ACCESS PLATFORM
SEA21177-10 Printed 7 May 2019 2:01 PM
Unit Qty
CY 11 .52
T 4.1612
LF 45.00
LF 600.00
CY 76.68
Rider Levett Bucknall
Rates Current At May 2019
Rate Total
3,500.00 40,320
$40,320
$40,320
8,000.00 33,290
$33,290
$33,290
85.00 3,825
$3,825
$3,825
350.00 210,000
3,000.00 230,040
$440,040
$440,040
$517,475
Page 6 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate Estimate Details
I BERTH I 13 Access Ramp Platform
Description
A1030 Slab on Grade
03 Concrete
4 1' Thick reinforced concrete slab
81010 Floor Construction
05 Metals
1 Access platform structural steel
6 Metal decking
82010 Exterior Walls
05 Metals
5 Steel railing
G1030 Site Earthwork
31 Earthwork
2 36" Pipe piling
3 Reinforced concrete in pipe piling
Concrete
Slab on Grade
Metals
Floor Construction
Metals
Exterior Walls
Earthwork
Site Earthwork
ACCESS RAMP PLATFORM
SEA21177-10 Printed 7 May 2019 2:01PM
Unit Qty
CY 41 .48
T 32.2488
SF 1,110.00
LF 40.00
LF 1,200.00
CY 153.36
II Rider Levett Bucknall
Rates Current At May 2019
Rate Total
3,500.00 145,180
$145,180
$145,180
8,000.00 257,990
8.50 9,435
$267,425
$267,425
85.00 3,400
$3,400
$3,400
350.00 420,000
3,000.00 460,080
$880,080
$880,080
$1,296,085
Page 9 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate Estimate Details
I BERTH I 14 Drive Down Ramp
Description
81010 Floor Construction
05 Metals
10 9/16" Steel deck at drive down ramp
11 Removable lifting lugs at drive down ramps
Metals
Floor Construction
82010 Exterior Walls
05 Metals
14 Wire mesh railings at drive down ramps
15 Structural steel at drive down ramp
Metals
08 Openings
16 Glazing
Openings
Exterior Walls
83010 Roof Coverings
07 Thermal and Moisture Protection
13 Standing seam metal roofing (including flashings, sealants and trims)
Thermal and Moisture Protection
Roof Coverings
G2010 Roadways
05 Metals
12 Steel drive apron w/piano hinge
Metals
Roadways
DRIVE DOWN RAMP
SEA21177-10 Printed 7 May 2019 2:01PM
Unit Qty
SF 2,640.00
EA 4.00
SF 640.00
T 124.4650
SF 1,300.00
SF 3,000.00
SF 60.00
Rider Levett Bucknall
Rates Current At May 2019
Rate Total
75.00 198,000
750.00 3,000
$201,000
$201,000
550.00 352,000
7,000.00 871 ,255
$1,223,255
175.00 227,500
$227,500
$1,450,755
50.00 150,000
$150,000
$150,000
125.00 7,500
$7,500
$7,500
$1,809,255
Page 10 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate Estimate Details
I BERTH I 15 Gangway Berth
Description
81010 Floor Construction
05 Metals
54 Unistrut below floor beam
56 Structural steel at gangway f loor
06 Wood, Plastics, and Composites
53 1" Fiberglass anti-skid grat ing
Metals
Wood, Plastics, and Composites
Floor Construction
81020 Roof Construction
05 Metals
55 Structural steel at gangway roof
Metals
Roof Construction
82010 Exterior Walls
05 Metals
58 Railing system at gangway
Metals
Exterior Walls
83010 Roof Coverings
05 Metals
57 Aluminum roof skirt
Metals
07 Thermal and Moisture Protection
59 Metal roofing system at gangway including flashings, trims, sealants
Thermal and Moisture Protection
Roof Coverings
C1030 Fittings
10 Specialt ies
52 Signage at gangway
Specialties
Fittings
GANGWAY BERTH
SEA21177-10 Printed 7 May 2019 2:01PM
Unit Qty
LF 270.00
T 32.0750
SF 1,420.00
T 27.5350
LF 280.00
SF 450.00
SF 1,800.00
EA 2.00
Rider Levett Bucknall
Rates Current At May 2019
Rate Total
40.00 10,800
7,500.00 240,562
$251,362
250.00 355,000
$355,000
$606,362
7,500.00 206,512
$206,512
$206,512
550.00 154,000
$154,000
$154,000
40.00 18,000
$18,000
48.00 86,400
$86,400
$104,400
800.00 1,600
$1,600
$1,600
$1,072,874
Page 11 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate Estimate Details
I BERTH I 16 Mooring Dolphin
II Rider Levett Bucknall
Rates Current At May 2019
Description Unit Qty Rate Total
G1030 Site Earthwork
31 Earthwork
3 Reinforced concrete in pipe piling
40 60" Batter pipe piling
48 1/2" Steel pipe cap plate
G2040 Site Development
35 Waterway and Marine Construction
49 Structural steel at mooring dolphin
50 Steel floor grate at mooring dolphin
51 Ladder at mooring dolphin
Earthwork Site Earthwork
Waterway and Marine Construction
CY
LF
T
T
SF
LF
340.77 3,000.00 1,022,310
1,600.00 600.00 960 ,000
2.3000 6,500.00 14,950
$1,997,260
$1,997,260
59.4400 8,750.00 520,100
800.00 150.00 120,000
30.00 300.00 9,000
$649,100 Site Development--------------,..-::--:c:,......,....,~ $649,100
MOORING DOLPHIN $2,646,360
SEA21177-10 Printed 7 May 2019 2:01PM Page 12 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate Estimate Details
I BERTH I 17 Breasting Dolphin
Ill Rider Levett Bucknall
Rates Current At May 2019
Description Unit Qty Rate Total
G1030 Site Earthwork
31 Earthwork
3 Reinforced concrete in pipe piling CY 340.78 3,000.00 1,022,340
39 60" Pipe piling LF 600.00 500.00 300,000
40 60" Batter pipe piling LF 1,600.00 600.00 960,000
Earthwork $2,282,340
Site Earthwork $2,282,340
G2040 Site Development
35 Waterway and Marine Construction
41 Structural steel at breasting dolphin T 83.3750 8,750.00 729,532
42 Metal grating at breasting dolphin SF 800.00 150.00 120,000
43 Fender assembly EA 2.00 50,000.00 100,000
44 Railing at breasting dolphin LF 80.00 350.00 28,000
45 1/2" steel support plate at breasting dolphin SF 32.00 75.00 2,400
46 1 00 MT ballard EA 1.00 1,500.00 1,500
47 1/2" Steel at catwalk landing EA 2.00 2,500.00 5,000
Waterway and Marine Construction $986,432
Site Development $986,432
BREASTING DOLPHIN $3,268,772
SEA21177-10 Printed 7 May 2019 2:01 PM Page 13of33
Ketchikan Berth I & II Expansion Schematic Design Estimate Estimate Details
I BERTH I 18 Reaction Dolphin
Rider Levett Bucknall
Rates Current At May 2019
Description Unit Qty Rate Total
G1030 Site Earthwork
31 Earthwork
3 Reinforced concrete in pipe piling
39 60" Pipe piling
SEA21 177-10 Printed 7 May 2019 2:01 PM
Earthwork
Site Earthwork
REACTION DOLPHIN
CY 725.21
LF 3,405.00
3,000.00 2,175,630
500.00 1,702,500
$3,878,130
$3,878,130
$3,878,130
Page 14 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate Est imate Details
I BERTH I 19 Catwalks
Rider Levett Bucknall
Rates Current At May 2019
Description Unit Qty Rate Total
81010 Floor Construction
05 Metals
36 1" Galvanized, serrated bar grating SF 930.00 225.00 209,250
37 Structural steel at catwalks T 10.8540 7,000.00 75,978
Metals $285,228
Floor Construction $285,228
82010 Exterior Walls
05 Metals
38 Handrail at catwalk LF 310.00 75.00 23,250
Metals $23,250
Exterior Walls $23,250
CATWALKS $308,478
SEA21177-10 Printed 7 May 2019 2:01 PM Page 15 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate Estimate Details
I BERTH I 11 0 Power/Lighting
Description
D5010 Electrical Service & Distribution
26 Electrical
73 Allowance for new breakers and tie into panels
Electrical
Electrical Service & Distribution
G4010 Electrical Distribution
26 Electrical
24 3" Conduit
25 4 #1 & 1#6 ground
26 2.5" Conduit
27 4 #4/0 & 1#4 ground
28 NEMA 4x enclosures
29 Panels 1&11
31 3 #10 & 1#6 ground
Electrical
Electrical Distribution
G4020 Site Lighting
26 Electrical
32 20' High walkway lights
33 Catwalk light fixtures
34 Full lights for access ramp & gangway
35 Half lights at access way
Electrical
Site Lighting
POWER/LIGHTING
SEA21177-10 Printed 7 May 2019 2:01PM
Unit Qty
LS 1.00
LF 2,600.00
LF 1,300.00
LF 400.00
LF 400.00
EA 2.00
EA 2.00
LF 1,300.00
EA 9.00
EA 8.00
EA 13.00
EA 5.00
Rider Levett Bucknall
Rates Current At May 2019
Rate Total
150,000.00 150,000
$150,000
$150,000
50.00 130,000
20.00 26,000
45.00 18,000
20.00 8,000
3,250.00 6,500
4,200.00 8,400
16.00 20,800
$217,700
$217,700
4 ,000.00 36,000
1,500.00 12,000
1,800.00 23,400
1,000.00 5,000
$76,400
$76,400
$444,100
Page 16 of33
Ketchikan Berth I & II Expansion Schematic Design Estimate Est imate Details
I BERTH I 111 Water & Fire Protection
Description
04020 Standpipes
22 Plumbing
19 Fire hydrant standpipe
Plumbing
Standpipes
04030 Fire Protection Specialties
22 Plumbing
18 Hose cabinet
Plumbing
Fire Protection Specialties
G2040 Site Development
11 Equipment
23 Life ring cabinet
Equipment
Site Development
G3010 Water Supply
33 Utilities
17 6" HOPE fire line
20 4" HOPE waterline
21 Portable water vault
22 Flexible hose connector
Utilities
Water Supply
WATER & FIRE PROTECTION
SEA21 177-10 Printed 7 May 2019 2:01PM
Unit Qty
EA 2.00
EA 2.00
EA 2.00
LF 600.00
LF 450.00
EA 1.00
LF 200.00
II Rider Levett Bucknall
Rates Current At May 2019
Rate Total
4,500.00 9,000
$9,000
$9,000
3,000.00 6,000
$6,000
$6,000
1,500.00 3,000
$3,000
$3,000
225.00 135,000
200.00 90,000
7,500.00 7,500
140.00 28,000
$260,500
$260,500
$278,500
Page 17 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate Estimate Details
I BERTH I 112 Mob/Demob/Barge/Rig
Rider Levett Bucknall
Rates Current At May 2019
Description Unit Qty Rate Total
F1 030 Special Construction Systems
35 Waterway and Marine Construction
60 Derrick crane
61 ABS Barge
62 Tow Boat
63 Tender boat
G1 030 Site Earthwork
Waterway and Marine Construction
Special Construction Systems
35 Waterway and Marine Construction
Day
Mth
Hr
Day
360.00 15,000.00 5,400,000
12.00 80,000.00 960,000
1,440.00 900.00 1,296,000
360.00 6,500.00 2,340,000
$9,996,000
$9,996,000
64 Mobilzation/Demob LS 2.00 500,000.00 1,000,000 Waterway and Marine Construction ------------$;;;:-1:;-, 0;;;:-0~0~,0~0~0
Site Earthwork $1,000,000 MOB/DEMOBIBARGE/R/G -------------;;$~170,-=99;;;:-6:-,0=-:0:-::-0
SEA21177-10 Printed 7 May 2019 2:01 PM Page 18 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate Estimate Details
I BERTH I 113 Selective Demolition
II Rider Levett Bucknall
Rates Current At May 2019
Description Unit Qty Rate Total
G1 020 Site Demolition and Relocations
02 Existing Conditions
74 Bullrail removal
75 Fender panel removal
76 Mooring dolphin pile removal
77 Misc. demo allowance
78 Misc. dockface modifications - Berth I
Existing Conditions
LF
EA
EA
LS
LS
76.00
2.00
4.00
1.00
1.00
45.00 3,420
10,000.00 20,000
50,000.00 200,000
30,000.00 30,000
125,000.00 125,000
$378,420 Site Demolition and Relocations ------------~=:--:-::-:-$378,420
SELECTIVE DEMOLITION $378,420
SEA21177-10 Printed 7 May 2019 2:01 PM Page 19 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate Estimate Details
I BERTH I 114 Misc.
Description
G1030 Site Earthwork
05 Metals
68 Galvanizing of steel
07 Thermal and Moisture Protection
67 Coating of pipes
Metals
Thermal and Moisture Protection
31 Earthwork
71 Light blasting of rock
72 Allowance for rock drilling
Earthwork
Site Earthwork
GC General Conditions
35 Waterway and Marine Construction
65 Enviromental monitoring and controls
66 Sea mammal monitoring
69 Cathodic protection
70 Allowance for divers
Waterway and Marine Construction
General Conditions
MISC.
SEA21177-10 Printed 7 May 2019 2:01 PM
Unit Qty
LS 1.00
LS 1.00
LS 1.00
LS 1.00
LS 1.00
LS 1.00
LS 1.00
LS 1.00
Rider Levett Bucknall
Rates Current At May 2019
Rate Total
250,000.00 250,000
$250,000
100,000.00 100,000
$100,000
100,000.00 100,000
100,000.00 100,000
$200,000
$550,000
125,000.00 125,000
50,000.00 50,000
125,000.00 125,000
50,000.00 50,000
$350,000
$350,000
$900,000
Page 20 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate Estimate Details
II BERTH II 111 Pontoons
Rider Levett Bucknall
Rates Current At May 2019
Description Unit Qty Rate Total
82010 Exterior Walls
05 Metals
8 Removable rail ing LF 1,075.00 250.00 268,750
Metals $268,750
Exterior Walls $268,750
F1010 Special Structures
35 Waterway and Marine Construction
7 Foam filled floating fender EA 8.00 50,000.00 400,000
9 Concrete pontoon SF 23,750.00 300.00 7,125,000
Waterway and Marine Construction $7,525,000
Special Structures $7,525,000
PONTOONS $7,793,750
SEA21177-10 Printed7May20192:01 PM Page 21 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate Estimate Details
II BERTH II 112 Access Platform
Description
A1030 Slab on Grade
03 Concrete
4 1' Thick reinforced concrete slab
81010 Floor Construction
05 Metals
1 Access platform structural steel
82010 Exterior Walls
05 Metals
5 Steel railing
G1030 Site Earthwork
31 Earthwork
2 36" Pipe piling
3 Reinforced concrete in pipe piling
Concrete
Slab on Grade
Metals
Floor Construction
Metals
Exterior Walls
Earthwork
Site Earthwork
ACCESS PLATFORM
SEA21177-1 0 Printed 7 May 2019 2:01 PM
Unit Qty
CY 11 .52
T 4.1612
LF 45.00
LF 600.00
CY 76.69
II Rider Levett Bucknall
Rates Current At May 2019
Rate Total
3,500.00 40,320
$40,320
$40,320
8,000.00 33,290
$33,290
$33,290
85.00 3,825
$3,825
$3,825
350.00 210,000
3,000.00 230,070
$440,070
$440,070
$517,505
Page 22 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate Estimate Details
II BERTH II 113 Access Ramp Platform
Description
A1030 Slab on Grade
03 Concrete
4 1' Thick reinforced concrete slab
81010 Floor Construction
05 Metals
1 Access platform structural steel
6 Metal decking
82010 Exterior Walls
05 Metals
5 Steel rai ling
G1030 Site Earthwork
31 Earthwork
2 36" Pipe piling
3 Reinforced concrete in pipe piling
Concrete
Slab on Grade
Metals
Floor Construction
Metals
Exterior Walls
Earthwork
Site Earthwork
ACCESS RAMP PLATFORM
SEA21177-10 Printed 7 May 2019 2:01 PM
Unit Qty
CY 41 .48
T 32.2488
SF 1,11 0.00
LF 40.00
LF 1,200.00
CY 153.38
Rider Levett Bucknall
Rates Current At May 201 9
Rate Total
3,500.00 145,180
$145,180
$145,180
8,000.00 257,990
8.50 9,435
$267,425
$267,425
85.00 3,400
$3,400
$3,400
350.00 420,000
3,000.00 460,140
$880,140
$880,140
$1,296,145
Page 23 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate Estimate Details
II BERTH II 114 Drive Down Ramp
Description
81010 Floor Construction
05 Metals
10 9/16" Steel deck at drive down ramp
11 Removable lifting lugs at drive down ramps
Metals
Floor Construction
82010 Exterior Walls
05 Metals
14 Wire mesh railings at drive down ramps
15 Structural steel at drive down ramp
Metals
08 Openings
16 Glazing
Openings
Exterior Walls
83010 Roof Coverings
07 Thermal and Moisture Protection
13 Standing seam metal roofing (including flashings, sealants and trims)
Thermal and Moisture Protection
Roof Coverings
G2010 Roadways
05 Metals
12 Steel drive apron w/piano hinge
Metals
Roadways
DRIVE DOWN RAMP
SEA21177-10 Printed 7 May 2019 2:01PM
Unit Qty
SF 2,640.00
EA 4.00
SF 640.00
T 124.4650
SF 1,300.00
SF 3,000.00
SF 60.00
II Rider Levett Bucknall
Rates Current At May 2019
Rate Total
75.00 198,000
750.00 3,000
$201,000
$201,000
550.00 352,000
7,000.00 871 ,255
$1,223,255
175.00 227,500
$227,500
$1,450,755
50.00 150,000
$150,000
$150,000
125.00 7,500
$7,500
$7,500
$1,809,255
Page 24 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate Estimate Details
II BERTH II 115 Gangway Berth
Description
81010 Floor Construction
05 Metals
54 Unistrut below floor beam
56 Structural steel at gangway floor
06 Wood, Plastics, and Composites
53 1" Fiberglass anti-skid grating
Metals
Wood, Plastics, and Composites
Floor Construction
81020 Roof Construction
05 Metals
55 Structural steel at gangway roof
Metals
Roof Construction
82010 Exterior Walls
05 Metals
58 Railing system at gangway
Metals
Exterior Walls
83010 Roof Coverings
05 Metals
57 Aluminum roof skirt
Metals
07 Thermal and Moisture Protection
59 Metal roofing system at gangway including flashings, trims, sealants
Thermal and Moisture Protection
Roof Coverings
C1030 Fittings
10 Specialties
52 Signage at gangway
Specialties
Fittings
GANGWAY BERTH
SEA21177·10 Printed 7 May 2019 2:01 PM
Unit Qty
LF 270.00
T 32.0750
SF 1,420.00
T 27.5350
LF 280.00
SF 450.00
SF 1,800.00
EA 2.00
Rider Levett Bucknall
Rates Current At May 2019
Rate Total
40.00 10,800
7,500.00 240,563
$251,363
250.00 355,000
$355,000
$606,363
7,500.00 206,513
$206,513
$206,513
550.00 154,000
$154,000
$154,000
40.00 18,000
$18,000
48.00 86,400
$86,400
$104,400
800.00 1,600
$1,600
$1,600
$1,072,876
Page 25 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate Estimate Details
II BERTH II 117 Breasting Dolphin
II Rider Levett Bucknall
Rates Current At May 2019
Description Unit Qty Rate Total
G1030 Site Earthwork
31 Earthwork
3 Reinforced concrete in pipe piling CY 340.82 3,000.00 1,022,460
39 60" Pipe piling LF 600.00 500.00 300,000
40 60" Batter pipe piling LF 1,600.00 600.00 960,000
Earthwork $2,282,460
Site Earthwork $2,282,460
G2040 Site Development
35 Waterway and Marine Construction
41 Structural steel at breasting dolphin T 83.3750 8,750.00 729,531
42 Metal grating at breasting dolphin SF 800.00 150.00 120,000
43 Fender assembly EA 2.00 50,000.00 100,000
44 Railing at breasting dolphin LF 80.00 350.00 28,000
45 1/2" steel support plate at breasting dolphin SF 32.00 75.00 2,400
46 1 00 MT bollard EA 1.00 1,500.00 1,500
47 1/2" Steel at catwalk landing EA 2.00 2,500.00 5,000
Waterway and Marine Construction $986,431
Site Development $986,431
BREASTING DOLPHIN $3,268,891
SEA21177-10 Printed 7 May 2019 2:01PM Page 26 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate Estimate Details
II BERTH II 118 Reaction Dolphin
II Rider Levett Bucknall
Rates Current At May 2019
Description Unit Qty Rate Total
G1 030 Site Earthwork
31 Earthwork
3 Reinforced concrete in pipe piling
39 60" Pipe piling
SEA21177-10 Printed 7 May 2019 2:01 PM
CY 725.31 3,000.00 2,175,930
LF 3,405.00 500.00 1,702,500
Earthwork $3,878,430
Site Earthwork $3,878,430 REACTION DOLPHIN -----------....,.$-3,-8=78-,4- 3-0
Page 27 of33
Ketchikan Berth I & II Expansion Schematic Design Estimate Estimate Details
II BERTH II 119 Catwalks
II Rider Levett Bucknall
Rates Current At May 2019
Description Unit Qty Rate Total
81010 Floor Construction
05 Metals
36 1" Galvanized, serrated bar grating SF 510.00 225.00 114,750
37 Structural steel at catwalks T 5.4760 7,000.00 38,332
Metals $153,082
Floor Construction $153,082
82010 Exterior Walls
05 Metals
38 Handrail at catwalk LF 160.00 75.00 12,000
Metals $12,000
Exterior Walls $12,000
CATWALKS $165,082
SEA21177-10 Printed 7 May 2019 2:01 PM Page 26 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate Estimate Details
II BERTH II 1110 Power/Lighting
Description
D5010 Electrical Service & Distribution
26 Electrical
73 Allowance for new breakers and tie into panels
Electrical
Electrical Service & Distribution
G4010 Electrical Distribution
26 Electrical
26 2.5" Conduit
27 4 #4/0 & 1#4 ground
30 1" Conduit
31 3 #10 & 1#6 ground
Electrical
Electrical Distribution
G4020 Site Lighting
26 Electrical
32 20' High walkway lights
33 Catwalk light fixtures
34 Full lights for access ramp & gangway
35 Half lights at access way
Electrical
Site Lighting
POWER/LIGHTING
SEA21177-10 Printed7May 20192:01 PM
Unit Qty
LS 1.00
LF 200.00
LF 200.00
LF 500.00
LF 500.00
EA 9.00
EA 5.00
EA 13.00
EA 5.00
II Rider Levett Bucknall
Rates Current At May 2019
Rate Total
150,000.00 150,000
$150,000
$150,000
45.00 9,000
20.00 4,000
34.00 17,000
16.00 8,000
$38,000
$38,000
4,000.00 36,000
1,500.00 7,500
1,800.00 23,400
1,000.00 5,000
$71,900
$71,900
$259,900
Page 29 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate Estimate Details
II BERTH II 1111 Water & Fire Protection
Description
D4020 Standpipes
22 Plumbing
19 Fire hydrant standpipe
Plumbing
Standpipes
D4030 Fire Protection Specialties
22 Plumbing
18 Hose cabinet
Plumbing
Fire Protection Specialties
G2040 Site Development
11 Equipment
23 Life ring cabinet
Equipment
Site Development
G3010 Water Supply
33 Utilities
17 6" HOPE fire line
20 4" HOPE waterline
21 Portable water vault
22 Flexible hose connector
Utilities
Water Supply
WATER & FIRE PROTECTION
SEA21177-10 Printed 7 May 2019 2:01PM
Unit Qty
EA 2.00
EA 2.00
EA 2.00
LF 600.00
LF 450.00
EA 2.00
LF 200.00
Rider Levett Bucknall
Rates Current At May 2019
Rate Total
4,500.00 9,000
$9,000
$9,000
3,000.00 6,000
$6,000
$6,000
1,500.00 3,000
$3,000
$3,000
225.00 135,000
200.00 90,000
7,500.00 15,000
140.00 28,000
$268,000
$268,000
$286,000
Page 30 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate Estimate Details
II BERTH II 11 12 Mob/Demob/Barge/Rig
Rider Levett Bucknall
Rates Current At May 2019
Description Unit Qty Rate Total
F1 030 Special Construction Systems
35 Waterway and Marine Construction
60 Derrick crane
61 ABS Barge
62 Tow Boat
63 Tender boat
G1 030 Site Earthwork
Waterway and Marine Construction
Special Construction Systems
35 Waterway and Marine Construction
64 Mobilzation/Demob
Day
Mth
Hr
Day
LS
300.00 15,000.00 4,500,000
10.00 80,000.00 800,000
600.00 900.00 540,000
300.00 6,500.00 1,950,000
$7,790,000
$7,790,000
1.00 500,000.00 500,000
Waterway and Marine Construction $500,000 Site Earthwork ---------------:;:$-=so=-:o=-,o=-:o=-=-o
MOB/DEMOB/BARGE/R/G $8,290,000
SEA21177-10 Printed 7 May 2019 2:01 PM Page 31 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate Estimate Details
II BERTH II 1113 Selective Demolition
II Rider Levett Bucknall
Rates Current At May 2019
Description Unit Qty Rate Total
G1020 Site Demolition and Relocations
02 Existing Conditions
7 4 Bullrail removal
75 Fender panel removal
77 Misc. demo allowance
79 Misc. dockface modifications - Berth I
Existing Conditions
LF
EA
LS
LS
83.00
5.00
1.00
1.00
45.00 3,735
10,000.00 50,000
30,000.00 30,000
250,000.00 250,000
$333,735 Site Demolition and Relocations---------------,-,...,....,~,..,... $333,735
SELECTIVE DEMOLITION $333,735
SEA21177-10 Printed 7 May 2019 2:01PM Page 32 of 33
Ketchikan Berth I & II Expansion Schematic Design Estimate Estimate Details
II BERTH II 1114 Misc.
Description
G1030 Site Earthwork
05 Metals
68 Galvanizing of steel
07 Thermal and Moisture Protection
67 Coating of pipes
Metals
Thermal and Moisture Protection
31 Earthwork
71 Light blasting of rock
72 Allowance for rock drilling
Earthwork
Site Earthwork
GC General Conditions
35 Waterway and Marine Construction
65 Enviromental monitoring and controls
66 Sea mammal monitoring
69 Cathodic protection
70 Allowance for divers
Waterway and Marine Construction
General Conditions
MISC.
SEA21177-10 Printed 7 May 2019 2:01 PM
Unit Qty
LS 1.00
LS 1.00
LS 1.00
LS 1.00
LS 1.00
LS 1.00
LS 1.00
LS 1.00
Ill Rider Levett Bucknall
Rates Current At May 2019
Rate Total
250,000.00 250,000
$250,000
100,000.00 100,000
$100,000
100,000.00 100,000
100,000.00 100,000
$200,000
$550,000
125,000.00 125,000
50,000.00 50,000
125,000.00 125,000
50,000.00 50,000
$350,000
$350,000
$900,000
Page 33 of 33