RIM MANUFACTURING PROCESS FLOW
Prepared by:-Atul Kaushal
-
8/3/2019 Rim Layout
2/25
Valve Hole Piercing& Coining
Butt Weld
Finishing
RIM MANUFACTURING PROCESS FLOW
De-coiler Leveler Cut To Length BatchMarking
Coiling Flattening ButtWelding
TrimmingRollingSlittingRe-RoundingBandCooling
Flaring
R F-2 RF -3
EdgeConditioning
Expander Air LeakTesting
InspectionR F -1
-
8/3/2019 Rim Layout
3/25
Coil Loader
Process:- Coil loading in the de-coiler
Process Objective:-To load the coil tofeed in CTL
Key points :-
1.Check the Telecopy defect in the coil
2.Check the Burr at the edge
3.Coil acceptance status, Batch code ,Heat no./
De-coiler:-
-
8/3/2019 Rim Layout
4/25
Process:- Straitening of the loaded
CoilProcess Objective:-In this leveler withhelp of the these all roller do straight thecoil.
Key points :-
1.Check the entry roller and exit rollerthickness as per requirement or not
2.Guide roller must be in center
3.Both guide roller(entry and exit) must bein parallel
Leveler:-
Leveler
-
8/3/2019 Rim Layout
5/25
Process:- Cut the coil as on strip
Process Objective:-In this operation withhelp of the cutter cut the coil as on strip.
Key points :-
1.Check the cutter plate angle is ok or not
2.Check the left side of the all guide rollermust be in center
CUT TO LENGTH :-
Cut to length(CTL)
-
8/3/2019 Rim Layout
6/25
Process:- Punch the batch marking on
stripProcess Objective:-In this operation withhelp of the marking insert we doing batchcode marking on strip.eg. AAA AMW 4.5JX13H2 RCC016 A92999A-Year code ,A-Month code ,A-1st heat codeA-Asia , M-Motor, W-Works4.5-Rim width in inch , J-Profile code13-Rim OD in inch, H2-Hump TwoR-Rim , C- Car, C-CodeA92999-TAC no.(Test Approval Certificate)
Key points :-
1.Check the marking as visual must be ok &free form insert mark.
BATCH MARKING :-
Batch marking
-
8/3/2019 Rim Layout
7/25
Process:- Converting strip in to coil
form
Process Objective:-In this operation withhelp of the rollers we coil the strip.
Key points :-
1.Butt joint both face must be in parallel.
2.Check the outer/inner both side coilermark .
coiling:-
coiling
-
8/3/2019 Rim Layout
8/25
Process:- Flattening on butt joint area
Process Objective:-To get good welding &good finishing in trimming operation.
Key points :-
1.Check the flattening must be proper andfree form tool mark .
FLATTENING :-
Flattening
-
8/3/2019 Rim Layout
9/25
Process:- Butt welding on butt joint area
Process Objective:- To joint the both coilend.
Key points :-
1.Check the Butt joint both side should beok and free form defect (Heeling, Fusing,overlap etc.)
BUTT WELDING :-
Butt welding
-
8/3/2019 Rim Layout
10/25
Process:-Trim on the butt joint .
Process Objective:-To remove theunwanted material which is available on thebutt weld.
Key points :-
1.Check the cutting must be proper and noany shallow flash cutting, deep flashcutting, overlap etc.
TRIMMING:-
Trimming
-
8/3/2019 Rim Layout
11/25
Process:-Rolling on the butt weld
Process Objective:-In this operation withhelp of the two roller(upper& bottom) dorolling on the butt weld.
Key points :-
1.Rolling platform must be clean by wirebrush
2.Both roller free form dent mark
3.Check the rolling mark, deep rolling markshould not be there
4.Check at the time of operation bothroller is rotating or not
rolling:-
Rolling
-
8/3/2019 Rim Layout
12/25
Process:-Trim the butt joint edge
Process Objective:-To trim the unwantedmaterial which is available on both sidebutt joint edge.
Key points :-
1.Check the surface must be free formburr & tool mark.
slitting:-
Slitting
-
8/3/2019 Rim Layout
13/25
Process:-Re-rounding the butt joint area
Process Objective:- To do the flaringoperation near butt joint area roundnessis required.
Key points :-
1.Check the surface must be free formtool mark.
Re-rounding:-
Re-rounding
-
8/3/2019 Rim Layout
14/25
Process:-Cooling of the band
Process Objective:-The band should be getcooled to the level of bare hand touchfeel.
Key points :-
1.Butt joint must be free form defect..(Heeling, Flash cutting, Overlap , Deepdent, Block mark, Necking etc)
Band cooling:-
Band cooling
-
8/3/2019 Rim Layout
15/25
Process:- remove the burr which is
available on the butt weld.Process Objective:-To increase the flaringtool life(Burr can damage the flaring tool).
Key points :-
1.Burr should be clean properly & check thetool rolling mark etc
Edge conditioning:-
Edge conditioning
-
8/3/2019 Rim Layout
16/25
Process:-Preforming operation of the rim
Process Objective:- Preforming operationas well as the butt welding testing.
Key points :-
1.Check the scoring mark & burr on bothside.
flaring:-
Flaring
-
8/3/2019 Rim Layout
17/25
Process:-First stage of rim profile
makingProcess Objective:-To support the 3rd rollformer to get thePrint dimension
Key points :-
1.Check the Scuffing, rolling mark & burron both side.
Roll former-1:-
R.F-1
-
8/3/2019 Rim Layout
18/25
Process:-Second stage of rim profile
makingProcess Objective:-To support the 3rd rollformer to get the Print dimension
Key points :-
1.Check the Scuffing, rolling mark & burron both side.
Roll forming-2:-
R.F-2
-
8/3/2019 Rim Layout
19/25
Process:-Third stage of rim profile
makingProcess Objective:- To support theexpander to get the Print dimension
Key points :-
1.Check the Scuffing, rolling mark & burron both side.
Roll forming-3:-
R.F-3
-
8/3/2019 Rim Layout
20/25
Process:-Last stage of rim profile making
Process Objective:-With help of expandertool, expand the complete rim profile asper print.
Key points :-
1.Check the rim must be free form burr &expander tool mark .
EXPANDER:-
EXPANDER
-
8/3/2019 Rim Layout
21/25
Process:-Valve hole for air filling in the
tyre.Process Objective:-For air filling in thetyre valve hole piercing is required & toremoved the burr from the valve holecoining operation required.
Key points :-
1.Check the valve hole dia ok or not.
2.Valve hole must be free form burr &toolmark .
VALVE HOLE PIERCING & COINING:-
VHP&VHC
-
8/3/2019 Rim Layout
22/25
Process:-Checking operation of the butt
weld.
Process Objective:-To check the butt weldany pin hole or hair line crack.
Key points :-
1.Check the air pressure as per controlPlan.
2.Check the machine is giving result ok or
not, for that check with air leak samplerim this must be show Rej.
3.Check the punch must be in center of thewell area.
Air leak test:-
Air leak testing m/c
-
8/3/2019 Rim Layout
23/25
Process:-Final finishing on the rim
Process Objective:-Cleaning the butt weldedge ,burr & mark.
Key points :-
1.Check the butt weld finishing ,mark &buffer mark.
BUTT WELD FINISHING:-
BUTT WELD FINISHING
-
8/3/2019 Rim Layout
24/25
Process:-Rim visual inspection
Process Objective:-Rim visual inspectionby Quality like dent mark ,butt welddefect, rolling mark, hair line crack etc.
Key points :-
1.Ensure the inspector having knowledgeabout rim defect & appearance inspectionstandard.
2.He must be aware about MARU-A, safety& critical characteristics of rim.
RIM INSPECTION:-
INSPECTION AREA
-
8/3/2019 Rim Layout
25/25