rion-antirion bridge, greece

11
Rion-Antirion Bridge, Greece. Presented by James Mitchell, Dan Bundy and Hung Nguyen

Upload: todd

Post on 08-Feb-2016

127 views

Category:

Documents


2 download

DESCRIPTION

Rion-Antirion Bridge, Greece. Presented by James Mitchell, Dan Bundy and Hung Nguyen. 1. Introduction. 1. SITE DESCRIPTION. Spans 2880m across Gulf of Corinth Links town of Rion to mainland Greece Previous crossings by boat took 45 minutes, reduced to 5 - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Rion-Antirion Bridge, Greece

Rion-Antirion Bridge, Greece.

Presented by James Mitchell, Dan Bundy and Hung Nguyen

Page 2: Rion-Antirion Bridge, Greece

• Spans 2880m across Gulf of Corinth• Links town of Rion to mainland

Greece• Previous crossings by boat took 45

minutes, reduced to 5• Completed August 2004, 4 months

ahead of schedule• Second longest cable stayed deck in

the world• Cost €630 million

1. SITE DESCRIPTION1. Introduction

Rio

Antirrio

Page 3: Rion-Antirion Bridge, Greece

2. Geology Geological conditions

1. Subsoil Steep slopes on each side

and long plateau seabed 65m below water surface.

Site investigations found no bedrock at depths of 100m

The weak alluvial deposits of interbeded granular and cohesive layers continue down to a predicted 1000m.

Interspersed with liquefiable sand pockets

Page 4: Rion-Antirion Bridge, Greece

2. Geology Geological conditions

2. Tectonic movement

The Corinth Rift is caused by a geological feature known as a ‘Graben’

The rift is relatively young at 2-5 million years old

North and south sides separating due to tectonic forces by up to ~15 millimetres per year

Uplifting of its southern shore approximately 1mm per year.

Page 5: Rion-Antirion Bridge, Greece

2. Geology Geological conditions

3. Seismic activity This area is one of the most seismic

regions in Europe. Seismicity lies between antithetic

faults, the Alepohori fault dipping north and the Kaparelli fault dipping south

The circle symbols on the map represent historical earthquakes with a magnitude greater than 5.5 Richter.

Page 6: Rion-Antirion Bridge, Greece

An exceptional combination of geological conditions present many challenges in the engineering of The Rion Antirion Bridge: Creating stable foundations on porous granular soils in deep seabed

Reduced effective strength Tectonic movement

Possible seismic activity Isolation of bridge deck to seismic energy- reduce sway Reduce dynamic response under wind loading Liquefaction of soil Movement of foundations

Expansion of rift Elongation of bridge deck

3. The challenges

Page 7: Rion-Antirion Bridge, Greece

Possible Solutions• Could not tunnel due to seismic activity• Bridge only option• Minimum number of seabed supports

desired• Two choices:

• Suspension• Cable Stayed

• Antirion side of gulf possessed slope stability problem

• Could not install large ground anchors needed for suspension bridge

• Cable stayed bridge only option

4. Engineering solutions

Page 8: Rion-Antirion Bridge, Greece

• Soil strengthened with steel inclusions• 200 Hollow steel tubes 2m in diameter, 25-

30m long driven into soil beneath each pier

• Covered by 3m thick gravel layer to reduce shear force transfer to substructure

• 90m diameter footings rest on top• No connection between footings and gravel • Pylons are able to lift or slide up to 2m in

an earthquake

Foundation4. Engineering solutions

Page 9: Rion-Antirion Bridge, Greece

• Bridge deck is fully suspended by the cables• Isolated as much as possible from piers to

reduce seismic impacts• Longitudinally, expansion joints allow

adjustment to thermal and seismic movements

• Deck can withstand movements of 2m between each set of piers

• Fuse restraints installed on pylons, as gulf expands load cell monitors identify change in load and dampers can be extended

• Allow for 2-5m expansion over 125 years

Bridge deck

4. Engineering solutions

Page 10: Rion-Antirion Bridge, Greece

• 4 Dampers and a fuse restraint at each pylon isolate bridge deck in transverse direction

• 10500kN fuse restraint keeps deck rigid during high winds

• Fails under seismic events allowing bridge to swing with 3500kN dampers

• This is the only connection between pylons and bridge deck

• Deck designed to move 2m in all directions

Bridge deck

4. Engineering solutions

Page 11: Rion-Antirion Bridge, Greece

5. Construction methods Construction of the foundation footings in

a dry dock. In parallel, driving steel inclusions is

carried out to strengthen soil. Towing and mooring of these footings to a

wet dock site. Immersion of the foundations at final

position. Erection of the prefabricated bridge deck

 using the balanced free-cantilever technique