    Roadbeds underlie highway pavementstructures and the ballast and track on whichtrains move.

    Unless there is a bridge, tunnel, or otherspecial structures, this roadbed is constructedof in-situ soils or on earth embankments.

  • 8/12/2019 Roadbed Construction

    3/28

    CONTRACTUAL, MANAGEMENT, AND

    QUALITY ASPECTS OF CONSTRUCTION Organizing to Carry Out Construction

    Competitive bids

    Payments to contractor usually is on a unitprice basis.

    Construction contracts are directed and carriedout by the management staff and workers ofcontractors or by subcontractors employed bythem.

  • 8/12/2019 Roadbed Construction

    4/28

    Quality Assurance in Construction

    Construction plans and specificationsstipulate many requirements that are tobe met by materials or construction

    procedures.Two approaches for obtaining them:

    a) Manner and method spell out in detail thematerials to be supplied or the procedures

    to be followed.b) Result or End result stipulates the desired

    end product and leaves manner and methodto the contractor.

  • 8/12/2019 Roadbed Construction

    5/28

    Weather Effects on Construction Precipitation as rain snow, high winds, and

    extremely hot or very cold temperatures canslow or halt certain construction operations.

  • 8/12/2019 Roadbed Construction

    6/28

    CLEARING THE SITES

    Site clearing in rural areas

    Site clearing in urban areas

  • 8/12/2019 Roadbed Construction

    7/28

    GRADING OPERATIONS Grading an inclusive term to describe

    construction operations between site clearingand paving.

    Detours are carefully planned, signed, andoperated so that traffic flows freely.

  • 8/12/2019 Roadbed Construction

    8/28

    Excavation Excavation the process of loosening and

    removing earth or rock from its originalposition in a cut and transporting it to a fill orto a waste deposit.

    Selection of equipment depends on the natureof the material, how far it is to be moved(hauled), and the method of disposal.

    Materials are usually described as rock,

    loose rock, or common with commonsignifying all materials not otherwiseclassified.

  • 8/12/2019 Roadbed Construction

    9/28

    Where material is moved less than about

    200ft of steeply downhill, drifting with a trackor wheel type bulldozer.

    For moderate and longer hauls, self loadingscrapers pulled by rubber-tired hauling units

    and push-loaded by tractors offer low costs. For hauls of considerable length over the

    public highways where axle loads are limited,rear- or bottom-dump trucks loaded by front-

    end loaders, power shovels, or belt conveyorsmay be cheapest.

  • 8/12/2019 Roadbed Construction

    10/28

    bulldozer

  • 8/12/2019 Roadbed Construction

    11/28Pull-type scraper

  • 8/12/2019 Roadbed Construction

    12/28

    rear- or bottom-dump trucks

  • 8/12/2019 Roadbed Construction

    13/28

    Payment for excavation commonly is made at

    a bid price per cubic yard measured inplace in the space originally occupied.

    This unit price includes payment forloosening and loading the material,

    transporting it any distance less than thefree haul limit, and spreading andcompacting it in the fill.

    Payment for light clearing and grubbing andfor trimming cut and fill slopes is also includedin the unit price for excavation.

  • 8/12/2019 Roadbed Construction

    14/28

    Slides and Slipouts The side slopes of all cuts are steeper than

    the original ground surface and those of highfills commonly are relatively steep in order toreduce the amount of embankment.

    Payment for slides on cuts commonly is madeunder the excavation item for the project.

  • 8/12/2019 Roadbed Construction

    15/28

    Overbreak Presplitting Overbreak occurs in rock cuts when material

    outside the staked backslopes becomesloosened and falls or is removed along withthe intended excavation.

    Presplitting is a drilling and blasting procedurethat may be employed or even specified tocontrol overbreak and give a uniform face tothe backslope of rock cuts.

  • 8/12/2019 Roadbed Construction

    16/28

    EMBANKMENT Embankment describes the fill added above

    the low points along the roadway to raise thelevel to bottom of the pavement structure.

    Materials for embankment commonly comesfrom roadway cuts or designated borrowareas.

  • 8/12/2019 Roadbed Construction

    17/28

    Free Haul - Overhaul When the material is moved a distance

    greater than this free-haul distance, it is usualto pay for the added transportation under abid item called overhaul.

    Units for overhaul are commonly the station-yard or cubic yard-mile.

  • 8/12/2019 Roadbed Construction

    18/28

    CONSTRUCTION OF FILLS AND

    EMBANKMENTS Principles of Embankment Construction

    At one time, fills, weather of rock or earth,were constructed to full height by enddumping from the transporting vehicle.

    Today, engineers agree that properembankment construction requires that the soilbe spread in layers, moistened or dried to

    something near an optimum moisture content,and compacted.

  • 8/12/2019 Roadbed Construction

    19/28

    Control ofEmbankment Construction Two basically control procedures for assuring

    a specified embankment density.

    1. State the expected end result which is theminimum acceptable value for relativecompaction, and to make sure, by fielddensity tests, that the specified density isobtained.

    2. State the manner and method for constructingthe embankment.

  • 8/12/2019 Roadbed Construction

    20/28

    COMPACTION EQUIPMENT Tamping rollers

    Grid rollers

    Pneumatic-tired rollers Smooth-tired rollers

    Vibratory compactors

    Hauling and spreading equipment

  • 8/12/2019 Roadbed Construction

    21/28

    Tamping rollers

  • 8/12/2019 Roadbed Construction

    22/28

    Grid rollers

  • 8/12/2019 Roadbed Construction

    23/28

    Pneumatic-tired rollers

  • 8/12/2019 Roadbed Construction

    24/28

    Vibratory compactor

  • 8/12/2019 Roadbed Construction

    25/28

    Payment for Embankment

    Construction Methods of payment for embankment

    construction vary.

    Some agencies , specify that the price percubic yard of excavation or of borrow shallinclude all charges for compaction, forwater as needed, or for aerating the soil.

    Others, pay separately for water. Still others pay for rolling, either at a bid price

    per hour of rolling with an acceptable roller orat a bid price per cubic yard of material.

  • 8/12/2019 Roadbed Construction

    26/28

    FINISHING THE ROADBED Finishing describes a number of operations

    associated with shaping the roadbed and therest of the cross section.

    Surfaces that will underlie the traveled wayand shoulders are compacted and smoothedto close tolerance.

    Roadside and other ditches, backslopes in

    cuts, sideslopes in embankments, androadside areas will be dressed to therequirements set by the plans andspecifications.

  • 8/12/2019 Roadbed Construction

    27/28

    There is no specific pay item covering thesefinishing operations; rather the contractor isinstructed to include these costs in other bid

    items.

  • 8/12/2019 Roadbed Construction

    28/28

    THANK YOU!