rosie bolton skads workshop april 10th 2008 skads costing work: beyond the benchmark scenario rosie...

24
Rosie Bolton SKADS Workshop April 10th 2008 SKADS Costing work: beyond the benchmark scenario Rosie Bolton Paul Alexander, Andy Faulkner and SKADS Costing tool development with Aaron Chippendale, Tim Colegate, Dominic Ford, Peter Hall and CDIT and …

Upload: jessie-hines

Post on 03-Jan-2016

220 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: Rosie Bolton SKADS Workshop April 10th 2008 SKADS Costing work: beyond the benchmark scenario Rosie Bolton Paul Alexander, Andy Faulkner and SKADS Costing

Rosie BoltonSKADS Workshop April 10th 2008

SKADS Costing work: beyond the benchmark scenario

Rosie Bolton

Paul Alexander, Andy Faulkner and SKADS

Costing tool development with Aaron Chippendale, Tim Colegate, Dominic Ford, Peter Hall and CDIT and …

Page 2: Rosie Bolton SKADS Workshop April 10th 2008 SKADS Costing work: beyond the benchmark scenario Rosie Bolton Paul Alexander, Andy Faulkner and SKADS Costing

Rosie BoltonSKADS Workshop April 10th 2008

Overview

• SKADS costing work to date– Memo 93, Benchmark scenario

– “Second round” – Tiger Team Preliminary Specification for the SKA, costing of the SKADS “vision” for the SKA

• Current / Future work: The SKA design and costing tool

Page 3: Rosie Bolton SKADS Workshop April 10th 2008 SKADS Costing work: beyond the benchmark scenario Rosie Bolton Paul Alexander, Andy Faulkner and SKADS Costing

Rosie BoltonSKADS Workshop April 10th 2008

Previous SKADS costing work

• Benchmark scenario (old)– 12,800 6.1m dishes (ATA), in dish

stations

– 250 Aperture array stations, co-placed with dish stations

– Radius range out to 3,000km

– Low frequency array costed very roughly

– Reduction in data rate for longest distances (for AA),

– Comms very expensive: 300 M€, +500 M€ for full data rate

– Total cost ~1.9 Bn Euros (2011)

Page 4: Rosie Bolton SKADS Workshop April 10th 2008 SKADS Costing work: beyond the benchmark scenario Rosie Bolton Paul Alexander, Andy Faulkner and SKADS Costing

Rosie BoltonSKADS Workshop April 10th 2008

Outline Configuration: Tiger team doc

• Follow concentration based on the SKA Draft specification:

– Dish AA-hi AA-lo

– <1Km 20% 30% ~15%

– <5Km 50% 66% 50%

– <180Km 75% 100% 100%

– <3000Km 100%

• AAs only out to 180km, frequency bands 70MHz-450MHz and 300MHz-

1,000MHz. AA bandwidth up to full range – set by data transfer spec

• Dishes all correlated, not beam-formed in Stations. 800MHz-10GHz. B/W 4GHz

• 5 spiral arms, with

– 3 to 3,000km, 2 only to 180km (saves trenching cost but configuration studies must

verify / challenge this)

Station

Core ~5km dia

Central ProcessingFacility

Not to scale!

180km

Dishes AA-hi

AA-lo

Page 5: Rosie Bolton SKADS Workshop April 10th 2008 SKADS Costing work: beyond the benchmark scenario Rosie Bolton Paul Alexander, Andy Faulkner and SKADS Costing

Rosie BoltonSKADS Workshop April 10th 2008

System design overview

Dishes and feeds in core and in outer

array2400 dishes

Dishes and feeds in core and in outer

array2400 dishes

AA-lo array antennas

AA-lo array antennas

AA Station85 Stations, 1 AA-lo, 1 AA-hi

“array” in each

AA Station85 Stations, 1 AA-lo, 1 AA-hi

“array” in each

Digital Signal TransportDigital Signal Transport Central processing and correlator

Central processing and correlator

SKA SKA

First stage Analogue

beam-former

First stage Analogue

beam-former

First stage digital beam-

forming

First stage digital beam-

forming

Station beam-formerStation beam-former

Analogue data transport

Analogue data transport

Mechanical infrastructureMechanical infrastructure

AA-hi array antennas

AA-hi array antennas

AA-hi

Local digital data transportLocal digital

data transportMechanical

InfrastructureMechanical

InfrastructureAnalogue data

transportAnalogue data

transport

Digital data transport

Digital data transport

First stage digital beamforning

First stage digital beamforning

AA-lo

AA CollectorsAA Collectors

AA-hi core165 AA-hi “arrays”

AA-hi core165 AA-hi “arrays”

AA-lo core165 AA-lo “arrays”

AA-lo core165 AA-lo “arrays”

Processing boxesProcessing boxes

Infrastructure and Trenching

Infrastructure and Trenching

Page 6: Rosie Bolton SKADS Workshop April 10th 2008 SKADS Costing work: beyond the benchmark scenario Rosie Bolton Paul Alexander, Andy Faulkner and SKADS Costing

Rosie BoltonSKADS Workshop April 10th 2008

• Central Processing Facility– Correlator

– Back-end computing

– Some station beamforming for AA-lo core

Dishes and feeds in core and in outer

array2400 dishes

Dishes and feeds in core and in outer

array2400 dishes

Digital Signal Transport

Digital Signal Transport

SKA SKA

AA CollectorsAA CollectorsInfrastructure

and Trenching

Infrastructure and

Trenching

System design overview

Station

Core ~5km dia

Central ProcessingFacility

Comms links

Not to scale!

180km

Dishes spread along spiral arms

Dishes

AA-hi

AA-lo

Central processing and

correlator

Central processing and

correlator

Page 7: Rosie Bolton SKADS Workshop April 10th 2008 SKADS Costing work: beyond the benchmark scenario Rosie Bolton Paul Alexander, Andy Faulkner and SKADS Costing

Rosie BoltonSKADS Workshop April 10th 2008

• Digital Signal Transport– Detailed model for

Communications

– Technology choice dependent on link length and data rate

– Development work in progress within SKADS (Roshene McCool and others)

Dishes and feeds in core and in outer

array2400 dishes

Dishes and feeds in core and in outer

array2400 dishes

Central processing and

correlator

Central processing and

correlator

SKA SKA

AA CollectorsAA CollectorsInfrastructure

and Trenching

Infrastructure and

Trenching

System design overview

Station

Core ~5km dia

Central ProcessingFacility

Comms links

Not to scale!

180km

Dishes spread along spiral arms

Dishes

AA-hi

AA-lo

Digital Signal Transport

Digital Signal Transport

Page 8: Rosie Bolton SKADS Workshop April 10th 2008 SKADS Costing work: beyond the benchmark scenario Rosie Bolton Paul Alexander, Andy Faulkner and SKADS Costing

Rosie BoltonSKADS Workshop April 10th 2008

• Dishes– 15m (in line with Tiger Team

Spec)

– Costed from SKAcost

– Cost of dish and feed

– €200,000 NPV per dish

– 2,400 dishes

– Range

Digital Signal Transport

Digital Signal Transport

Central processing and

correlator

Central processing and

correlator

SKA SKA

AA CollectorsAA CollectorsInfrastructure

and Trenching

Infrastructure and

Trenching

System design overview

Station

Core ~5km dia

Central ProcessingFacility

Comms links

Not to scale!

180km

Dishes spread along spiral arms

Dishes

AA-hi

AA-lo

Dishes and feeds in core and in outer

array2400 dishes

Dishes and feeds in core and in outer

array2400 dishes

Page 9: Rosie Bolton SKADS Workshop April 10th 2008 SKADS Costing work: beyond the benchmark scenario Rosie Bolton Paul Alexander, Andy Faulkner and SKADS Costing

Rosie BoltonSKADS Workshop April 10th 2008

• AA collectors are SKADS focuses – especially the AA-hi (300-1,000MHz)

• AA collectors sit in central cores (AA-lo and AA-hi separately) and in outer stations (together)

Dishes and feeds in core and in outer

array2400 dishes

Dishes and feeds in core and in outer

array2400 dishes

Digital Signal Transport

Digital Signal Transport

Central processing and

correlator

Central processing and

correlator

SKA SKA

Infrastructure and

Trenching

Infrastructure and

Trenching

System design overview

Station

Core ~5km dia

Central ProcessingFacility

Comms links

Not to scale!

180km

Dishes spread along spiral arms

Dishes

AA-hi

AA-lo

AA CollectorsAA Collectors

Page 10: Rosie Bolton SKADS Workshop April 10th 2008 SKADS Costing work: beyond the benchmark scenario Rosie Bolton Paul Alexander, Andy Faulkner and SKADS Costing

Rosie BoltonSKADS Workshop April 10th 2008

Aperture array systems

AA-lo array antennas

AA-lo array antennas

AA Station85 Stations, 1 AA-lo,

1 AA-hi “array” in each

AA Station85 Stations, 1 AA-lo,

1 AA-hi “array” in each

First stage Analogue

beam-former

First stage Analogue

beam-former

First stage digital beam-

forming

First stage digital beam-

forming

Station beam-formerStation beam-former

Analogue data transport

Analogue data transport

Mechanical infrastructureMechanical infrastructure

AA-hi array antennas

AA-hi array antennas

AA-hi

Local digital data transportLocal digital

data transportMechanical

InfrastructureMechanical

InfrastructureAnalogue data

transportAnalogue data

transport

Digital data transport

Digital data transport

First stage digital

beamforming

First stage digital

beamforming

AA-lo

AA CollectorsAA Collectors

AA-hi core165 AA-hi “arrays”

AA-hi core165 AA-hi “arrays”

AA-lo core165 AA-lo “arrays”

AA-lo core165 AA-lo “arrays”

Processing boxes

Processing boxes

Each AA-lo array is ~180m diameter

Core may be fully-filled for improved temperature sensitivity (EoR signal)

LOFAR high-band

Log-Periodic dipole schematic

Each AA-hi station ~60m diameter

Page 11: Rosie Bolton SKADS Workshop April 10th 2008 SKADS Costing work: beyond the benchmark scenario Rosie Bolton Paul Alexander, Andy Faulkner and SKADS Costing

Rosie BoltonSKADS Workshop April 10th 2008

Costed Data Rates

• AA-hi Data rate equivalent to 250 square degrees across the whole band from 300 MHZ to 1,000 MHz. Including 8:10 encoding, 16.5 Tb/s per station

• AA-lo Data rate equivalent to 200 square degrees across the band from 70 MHz to 450 MHz, 12.5 Tb/s

• Complete flexibility in the beams that are sent back

Increase field of view (more beams on the sky)

Decrease the bandwidth

Page 12: Rosie Bolton SKADS Workshop April 10th 2008 SKADS Costing work: beyond the benchmark scenario Rosie Bolton Paul Alexander, Andy Faulkner and SKADS Costing

Rosie BoltonSKADS Workshop April 10th 2008

Aperture array sensitivity

A/T total, 250 stations

0

2000

4000

6000

8000

10000

12000

0 200 400 600 800 1000 1200

frequency (MHz)

A/T

sys

AA-lo, Trec 50K, 180m diameter, f(Nyq)=100MHz

AA-hi, Trec 30K, 56m diameter, f(Nyq) = 833MHz

Combined total

Sensitivity averaged over scan angles out to 30º

Page 13: Rosie Bolton SKADS Workshop April 10th 2008 SKADS Costing work: beyond the benchmark scenario Rosie Bolton Paul Alexander, Andy Faulkner and SKADS Costing

Rosie BoltonSKADS Workshop April 10th 2008

SKA cost breakdown

No: Infrastructure

Roads, buildings

No: Development costs

NREs, toolingNo: Software development

costsNo: Running costs

No: Project management

costsNo: Contingency(but we do have an uncertainty estimate)

Page 14: Rosie Bolton SKADS Workshop April 10th 2008 SKADS Costing work: beyond the benchmark scenario Rosie Bolton Paul Alexander, Andy Faulkner and SKADS Costing

Rosie BoltonSKADS Workshop April 10th 2008

SKA cost breakdown

€162 Million

€394 Million

€526 Million

€165 Million

€92 Million

€63 Million€34 Million

Special Offe

r: 1.52 Billio

n Euros NPV ± 31%

Page 15: Rosie Bolton SKADS Workshop April 10th 2008 SKADS Costing work: beyond the benchmark scenario Rosie Bolton Paul Alexander, Andy Faulkner and SKADS Costing

Rosie BoltonSKADS Workshop April 10th 2008

Scaling models: the way forward

Page 16: Rosie Bolton SKADS Workshop April 10th 2008 SKADS Costing work: beyond the benchmark scenario Rosie Bolton Paul Alexander, Andy Faulkner and SKADS Costing

Rosie BoltonSKADS Workshop April 10th 2008

Comms cost scaling - DishesComms cost per Dish (80 Gb/s)

0

5

10

15

20

25

30

35

40

45

0 20 40 60 80 100 120 140 160 180 200

Radial distance (km)

Co

mm

s co

st (

tho

usa

nd

eu

ros)

First, second and third amplifiers added

a b

c

a: Cheap VCSELs can be used out to 10km fibre length

RELATIVE COMMUNICATIONS COSTS BECOME MUCH MORE EXPENSIVE AFTER 50KM OF FIBRE DISTANCE

FURTHER BREAK POINT AT 480KM WHERE O-E-O REGEN IS REQUIRED

b: Uncooled, directly modulated lasers out to 50kmc: Cooled, externally modulated lasers > 50 km

Page 17: Rosie Bolton SKADS Workshop April 10th 2008 SKADS Costing work: beyond the benchmark scenario Rosie Bolton Paul Alexander, Andy Faulkner and SKADS Costing

Rosie BoltonSKADS Workshop April 10th 2008

Comms cost scaling - AA

AA comms costs with varying 95% radius

0

20

40

60

80

100

120

0 10 20 30 40 50 60 70 80 90

95% radius, km (within which 95% of the stations are)

AA

Co

mm

s c

ost

for

ou

ter

sta

tio

ns

(mil

lio

ns o

f E

uro

s,

2011)

Comms costs are sensitive to station placementConfig work and costing work must be linked

60 million!

Page 18: Rosie Bolton SKADS Workshop April 10th 2008 SKADS Costing work: beyond the benchmark scenario Rosie Bolton Paul Alexander, Andy Faulkner and SKADS Costing

Rosie BoltonSKADS Workshop April 10th 2008

Cost scaling: ACost scaling: Aeff eff for AAsfor AAsTotal SKA cost with reduced collecting area

€800,000,000

€900,000,000

€1,000,000,000

€1,100,000,000

€1,200,000,000

€1,300,000,000

€1,400,000,000

€1,500,000,000

€1,600,000,000

0.5 0.6 0.7 0.8 0.9 1

Fraction of spec collecting area

To

tal

SK

A c

ost

(E

uro

s, N

PV

)

Page 19: Rosie Bolton SKADS Workshop April 10th 2008 SKADS Costing work: beyond the benchmark scenario Rosie Bolton Paul Alexander, Andy Faulkner and SKADS Costing

Rosie BoltonSKADS Workshop April 10th 2008

Cost scaling: ACost scaling: Aeff eff for AAsfor AAs

010

2030

400 10 20 30 40

0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

0.9

1

Rel

ativ

e se

nsi

tivi

ty

Offset (x) degrees

Offset (y) degrees

0.9-1

0.8-0.9

0.7-0.8

0.6-0.7

0.5-0.6

0.4-0.5

0.3-0.4

0.2-0.3

0.1-0.2

0-0.1

Variation with scan angle due to:•Projected area•Element responseFixed <Aeff> ...

Amount of collecting area required is a strong function of scan angle requirement: change 30 deg to 45 deg, need 40% more collector: extra ~500 million Euros!

Collecting area requirements vs max angle

139%123%

110%100%

78% 81% 86% 92%

0

0.2

0.4

0.6

0.8

1

1.2

1.4

1.6

10 15 20 25 30 35 40 45

Max angle, degrees

Co

llec

tin

g a

rea

req

uir

emen

ts

Page 20: Rosie Bolton SKADS Workshop April 10th 2008 SKADS Costing work: beyond the benchmark scenario Rosie Bolton Paul Alexander, Andy Faulkner and SKADS Costing

Rosie BoltonSKADS Workshop April 10th 2008

Scaling: complex dependencies

Collector costs

Data transport

Correlator Back end computing

Trenching

AA Field of View

Sensitivity ()

Tsys ()

AA Station size ()

Dish size ()

Bandwidth

Layout

Interdependencies are too complex to do with a spreadsheet: we need a more sophisticated model

SKACost

Page 21: Rosie Bolton SKADS Workshop April 10th 2008 SKADS Costing work: beyond the benchmark scenario Rosie Bolton Paul Alexander, Andy Faulkner and SKADS Costing

Rosie BoltonSKADS Workshop April 10th 2008

Science Requirements

Engineering Design & Cost

The Job of PrepSKA

Readiness Assessments

Eng. Simulations

Prototypes

Pathfinders & DS

Technical R&D Fou

r Y

ears

Case Studies

SKACost

CourtesyPeter Dewdney

Page 22: Rosie Bolton SKADS Workshop April 10th 2008 SKADS Costing work: beyond the benchmark scenario Rosie Bolton Paul Alexander, Andy Faulkner and SKADS Costing

Rosie BoltonSKADS Workshop April 10th 2008

Future work:• SKADS AA model is already scalable on a broad level

– Collecting area requirements

– Bandwidth

– FoV

• Needs more work to make fine details scale:– Operating frequency / Antenna spacing requirements

– Station layout / Configuration

– AA-lo: further design work required for low-freq antennas

– Analogue beamforming / Digital beam-forming

• SKACost costing tool is essential for this– SKACost will be used by selection committee to further define the SKA

spec

– Important that all technologies are adequately represented in SKACost

– Need a shift in approach towards a “model”

Page 23: Rosie Bolton SKADS Workshop April 10th 2008 SKADS Costing work: beyond the benchmark scenario Rosie Bolton Paul Alexander, Andy Faulkner and SKADS Costing

Rosie BoltonSKADS Workshop April 10th 2008

Future work:• SKACost developments will include:

– Improved web-tool, with AA costing, in near-term future

– End-August distribution of GUI-based tool• Help required to test this tool - contact us! (Me, Tim Colegate,

Dominic Ford, Aaron Chippendale, Peter Hall, Paul Alexander)

• The better the tool is a describing the technology, the better the merits of that option will show up.

– Longer-term flexible GUI-based tool allowing design blocks and components to be created and an SKA designed from a shopping basket of sub-components

Page 24: Rosie Bolton SKADS Workshop April 10th 2008 SKADS Costing work: beyond the benchmark scenario Rosie Bolton Paul Alexander, Andy Faulkner and SKADS Costing

Rosie BoltonSKADS Workshop April 10th 2008

Web-tool plug:

http://www.atnf.csiro.au/projects/ska/cost/

…it’s not perfect but we are working on it, and are keen for feedback

Dominic Rosie Tim Paul