rtsp metrorail strategies: split yellow line, new blue lines, interline, enhanced surface transit,...

57
RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory Group October 21 st , 2010

Upload: shonda-mathews

Post on 29-Jan-2016

217 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

RTSP Metrorail Strategies:Split Yellow Line, New Blue Lines, Interline, Enhanced

Surface Transit, and Walkability

Presentation to the Technical Advisory Group

October 21st, 2010

Page 2: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 2

I. Welcome & IntroductionsII. Public EngagementIII. Update on Rail Interoperability StudyIV. Model Runs Completed and ProposedV. New Model ResultsVI. Next Steps

10/21/2010

Meeting Agenda

Page 3: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 3

• How will we engage the public?

– Jurisdictional Briefings/”Piggy-back” (Jan. – April)• TAG Member requests RTSP Briefing• Metro’s GOVR staff briefs jurisdictional representative• TAG Member & RTSP Staff schedule briefing/piggy-back

– Metro-hosted Regional Workshops (February-March)• 2 Workshops in each jurisdiction

• What will be discussed at the Workshops?

– Background– RTSP Purpose/People/Process/Product– Current Challenges– Transit Mode Characteristics– Strategies– Scenarios– How to Stay Involved

10/21/2010

Public Engagement Strategy

Page 4: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 410/21/2010

RTSP Website

WMATA
It may be nice to add a few examples of other content that will be available on the blog, i.e. Metro's long range planning history, description of current long range plan, strategies modeled to offer potential plans for the next 30+ years.
Page 5: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 5

Model Runs Completed & Proposed

• “Round 1” – Base Case (2), Yellow Line (2), Rosslyn Interline, Pedestrian Tunnel (2)

• “Round 2” – Yellow Line (3rd option), Blue Line (2), Interline (3 more), PCN Bus, Enhanced Walkability

• “Round 3” – To be discussed later on agenda

10/21/2010

Page 6: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 6

Overview of New Model Results• Review of Base Case (Max CLRP)

– Refer to Attachment 3 for Strategies presented in Round 1• Definition of Strategies and Impact on Ridership and Capacity

(Round 2)– Set 1:

• New Rail Lines Through The Core– New Split Yellow Line (2nd St SE/NE)– New East-West Blue Line M St and New Jersey Ave– New East-West Blue Line M St and Constitution Ave

– Set 2:• Rail Enhancements

– Four Interline Connections

– Set 3:• Enhanced Existing Surface Transit

– Priority Corridor Network

• Improved Walkability

• Preliminary Evaluation10/21/2010

Page 7: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 7

REVIEW OF BASE CASE (MAX CLRP)

10/21/2010

Page 8: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 8

Base Case (Max CLRP)• Address CLRP* issues related to capacity by:

– Increasing train frequencies to maximum supported by the infrastructure

– Reallocate Orange/Silver/Blue Line train frequencies to better balance demand

• Improve system understandability by eliminating multiple destinations for single color train– Extend Silver Line trains to Largo & route all Orange Line

trains to New Carrollton– Rename “Blue Line Split” via 14th Street Bridge to “Yellow

Line”• Basis for comparing various strategies

10/21/2010

(*MWCOG 2030 CLRP Modeled with 2040 Land Use)

Page 9: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 9

Core Capacity Analysis- 2040 Max CLRP

10/21/2010

Note: Metrorail capacity assumes 100 passengers per car

South SW NW North NE SE0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

40,000

Year 2008

2008 Capacity 2008 Demand

Demand ex-ceeds capacity by 7%

South SW NW North NE SE0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

40,000

Base Case (Max CLRP)

Max CLRP Capacity Max CLRP Demand

Demand exceeds capacity by 17%

Demand exceeds capacity by 22%

Screenline definition:South: Metrorail services from Virginia on Yellow line crossing PotomacSouthwest: Metrorail services from Virginia on Orange and Blue lines crossing PotomacNorthwest: Red Line approaching Dupont CircleNorth: Green/Yellow lines approaching Mt. Vernon Square and Red line approaching Union StationNortheast: Blue/Orange/[Silver] from Eastern Market to Capitol SouthSoutheast: Green line approaching L’Enfant Plaza

Page 10: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 10

Base Case (Max CLRP): 2040 Peak Hour Link Loads

10/21/2010

Note: The values posted on the plot are the passengers per car during peak hour. The width of the band represents peak hour volumes.

Page 11: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 11

Preliminary Evaluation (Round 1)

• Region continues to face critical issues about core capacity, auto VMT, and Metrorail parking.

• The Max CLRP and Interline Option provide some relief to the core capacity by better balancing the demand.

• Pedestrian tunnels provide some relief at congested rail stations.• New stations along 10th St SW/NW and re-location of Yellow line

resolves key core capacity restraint.• New stations along 2nd St SE/NE and re-location of Yellow line

increase crowding on Orange/Blue line at Rosslyn.

10/21/2010

Efficiency Auto Travel

Alternative

Sufficient Capacity to

Serve Demand

Reserve Capacity/

RedundancyStation

Capacity

Transit system

coverage

Service to Major Activity

Centers

Metrorail Parking

Sufficiency

Reduce Dependence

on Automobile to Access Metrorail

Region-wide Transit Share

Transit Access to

jobs

Passenger Miles Per

Route MileAuto VMT and Trips

Existing Conditions in 2008

2040 CLRP

2040 Max CLRP

2040 Interline Option 1

2040 New N-S Yellow Line 10th St SW/NW

2040 New N-S Yellow Line 2nd St SE/NE

Core Capacity Access Mobility

Page 12: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 12

DEFINITION OF STRATEGIESNEW RAIL LINES THROUGH THE CORE (ROUND 2)

10/21/2010

Page 13: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 13

Split N-S Yellow Line via 2nd St SE/NE• Relocate Yellow line trains from Huntington

to 2nd St SE/NE• Yellow line trains routing from Franconia

Springfield to Greenbelt are unchanged.• Headways:

• Pedestrian Tunnels:– Farragut West - Farragut North– Metro Center - Gallery Place– 3rd and Eye St SW - Waterfront– 2nd and D Street SE – Capitol South– Massachusetts Avenue and North Capitol

Street - Union Station

10/21/2010

Peak Off-Peak Peak Off-Peak

Red 2.5 6.0 2.5 6.0

Orange 6.0 12.0 6.0 12.0

Silver 6.0 12.0 6.0 12.0

Blue 10.0 12.0 10.0 12.0

Yellow 1 6.0 12.0 6.0 12.0

Yellow 2 12.0 ------- 6.0 12.0

Green 5.5 12.0 4.0 12.0

Yellow 1 (Base): Huntington-Mt Vernon Sq

Yellow 1 (Split Yellow): Huntington - 2nd St SE/NE

Yellow 2: Franconia Springfield - Greenbelt

Base (Max CLRP) Split Yellow

Page 14: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 14

East-West Blue Line (Via M Street and New Jersey Avenue, NW)

Pedestrian Tunnels:– Farragut West - Farragut

North– Metro Center - Gallery Place– Rosslyn I – Rosslyn II– Conn. Ave. – Farragut North– Convention Center I –

Convention Center II– Union Station I – Union

Station II

10/21/2010

• Metrorail service plan optimized to minimize the maximum peak hour load at key segments on all rail lines.

Initial Operating Plan Optimized Operating Plan

Peak Off-Peak Peak Off-Peak Peak Off-Peak Peak Off-Peak

Red 2.5 6.0 2.5 6.0 Red 2.5 6.0 2.5 6.0

Orange 6.0 12.0 5.0 12.0 Orange 6.0 12.0 4.0 12.0

Silver 6.0 12.0 5.0 12.0 Silver 6.0 12.0 6.0 12.0

Blue 10.0 12.0 5.0 12.0 Blue 10.0 12.0 4.0 12.0

Yellow 1 6.0 12.0 5.0 12.0 Yellow 1 6.0 12.0 5.5 12.0

Yellow 2 12.0 ------- ------ ------- Yellow 2 12.0 ------- ------ -------

Green 5.5 12.0 5.0 12.0 Green 5.5 12.0 4.0 12.0

Yellow 1: Huntington-Mt Vernon Sq Blue (Base): Franconia Springfield - Largo

Yellow 2: Franconia Springfield - Greenbelt Blue (New Blue M/NJ): Franconia Springfield - Largo via M St/NJ Ave

Base (Max CLRP) New Blue (M/NJ) Base (Max CLRP) New Blue (M/NJ)

Page 15: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 15

East-West Blue Line (Via M Street, Virginia Ave and Constitution Avenue, NW)

Pedestrian Tunnels:– Farragut West - Farragut North– Metro Center - Gallery Place– Rosslyn I – Rosslyn II– State Department – Foggy

Bottom– American History Museum –

Federal Triangle– National Gallery –

Archives/Navy Memorial– Union Station I – Union Station

II

10/21/2010

• Metrorail service plan optimized to minimize the maximum peak hour load at key segments on all rail lines.

Initial Operating Plan Optimized Operating Plan

Peak Off-Peak Peak Off-Peak Peak Off-Peak Peak Off-Peak

Red 2.5 6.0 2.5 6.0 Red 2.5 6.0 2.5 6.0

Orange 6.0 12.0 5.0 12.0 Orange 6.0 12.0 4.0 12.0

Silver 6.0 12.0 5.0 12.0 Silver 6.0 12.0 6.0 12.0

Blue 10.0 12.0 5.0 12.0 Blue 10.0 12.0 5.5 12.0

Yellow 1 6.0 12.0 5.0 12.0 Yellow 1 6.0 12.0 4.0 12.0

Yellow 2 12.0 ------- ------ ------- Yellow 2 12.0 ------- ------ -------

Green 5.5 12.0 5.0 12.0 Green 5.5 12.0 5.5 12.0

Yellow 1: Huntington-Mt Vernon Sq Blue (Base): Franconia Springfield - Largo

Yellow 2: Franconia Springfield - Greenbelt Blue (New Blue M/Const): Franconia Springfield - Largo via M St/Const Ave

Base (Max CLRP) New Blue (M/Const) Base (Max CLRP) New Blue (M/Const)

Page 16: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 16

IMPACT ON RIDERSHIP AND CAPACITYNEW RAIL LINES THROUGH THE CORE (ROUND 2)

10/21/2010

Page 17: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 17

Year 2040 Linked Transit Trips

10/21/2010

Round 1 Round 2

Summary of Weekday Transit Linked Trips by 4 Districts: 2040

Core (DC/Arl CBD) 754,000 762,000 758,000 764,000 779,000 772,000

Central Jurisdictions Outside Core 322,000 322,000 325,000 327,000 328,000 327,000

Inner Suburbs 277,000 277,000 277,000 277,000 278,000 277,000

Outer Suburbs 4,000 4,000 4,000 4,000 4,000 4,000

Region-wide 1,357,000 1,365,000 1,364,000 1,372,000 1,389,000 1,380,000

Percent growth vs. 2040 Max CLRP ----- 0.6% 0.5% 1.1% 2.4% 1.7%

Split Yellow N-S 2nd SE/NE

Att

ract

ion

L

oca

tio

n

New Blue (M St and NJ Ave., NW)

New Blue (M St and Const.

Ave., NW)

2040 Base (Max CLRP)

New Yellow N-S 10th SW/NW

New Yellow N-S 2nd SE/NE

Page 18: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 18

Year 2040 Transit Boardings

10/21/2010

Round 1 Round 2

2040 Base (Max CLRP)

New Yellow N-S 10th SW/NW

New Yellow N-S 2nd SE/NE

Split Yellow N-S 2nd SE/NE

New Blue (M St and NJ Ave., NW)

New Blue (M St and Const.

Ave., NW)Metrorail (Fare gate to fare gate) 1,055,000 1,072,000 1,074,000 1,082,000 1,109,000 1,094,000Commuter Rail 51,000 51,000 52,000 52,000 50,000 51,000Metrobus 555,000 552,000 552,000 550,000 534,000 537,000Other Bus 193,000 194,000 193,000 193,000 192,000 191,000Streetcar/LRT 65,000 65,000 65,000 65,000 65,000 65,000BRT/Rapid Bus 0 0 0 0 0 0Total Transit Boardings 1,919,000 1,934,000 1,936,000 1,942,000 1,950,000 1,938,000% Growth vs. 2040 Max CLRP 0.8% 0.9% 1.2% 1.6% 1.0%

2040 Transit Boardings

Page 19: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 19

New Metrorail Stations: 2040 Weekday Boardings

10/21/2010

Round 1 Round 2

New Metrorail Stations

East Potomac Park 2 630 90

Banneker Park 11,080 - -

Museum of Natural History 7,100 - -

City Center 10,180 - -

Thomas Circle 4,030 - -

3rd and Eye St SW - 3,210 2,380

S Capitol and Eye St - 8,680 6,270

2nd and D St SE - 5,420 3,160

2nd St and Const. Ave - 2,570 2,140

Mass Ave and N Capitol St - 12,080 9,210

New Yellow N-S 10th SW/NW

New Yellow N-S 2nd SE/NE

Split Yellow N-S 2nd SE/NE

New Metrorail Stations

Rosslyn II 7,020 6,230

Georgetown University 2,340 2,030

Georgetown (31st & M St, NW) 14,850 12,960

West End (23rd & M St NW) 11,230 -

Conn. & M Streets, NW 18,360 -

Thomas Cir (14 & M St NW) 7,740 -

Mt Vernon Square II 5,880 -

NoMa (NJ and L, NW) 1,280 -

State Dept (23 & E St NW) - 7,030

DAR/Corcoran - 2,710

American History Museum - 3,100

National Gallery of Art - 4,170

Union Station II 16,930 14,510

8th & H Streets, NE 1,640 1,360

Atlas Dist MD & Benn RdNE 4,080 3,610

Langston Dwellings 2,670 2,540

Benn Road & Minn Ave. NE 2,270 2,500

New Blue (M St and NJ Ave.,

NW)

New Blue (M St and

Const. Ave., NW)

Page 20: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 20

New N-S Yellow Line 10th St SW/NW: 2040 Peak Hour Link Loads and Daily Ridership on Key Facilities (Round 1)

10/21/2010

Note: The values posted on the plot are the passengers per car during peak hour. The width of the band represents peak hour volumes.

Daily VolumesRelocated Yellow Line Segment Ridership 129,100

Farragut North – Farragut West Ped Tunnel Flows 42,700

Metro Center - City Center - Gallery Pl Ped Tunnel Flows 82,900

Remaining New Yellow Line Ped Tunnels Flows 103,200

Page 21: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 21

New N-S Yellow Line 2nd St SE/NE:2040 Peak Hour Link Loads and Daily Ridership on Key Facilities (Round 1)

10/21/2010

Note: The values posted on the plot are the passengers per car during peak hour. The width of the band represents peak hour volumes.

Daily VolumesRelocated Yellow Line Segment Ridership 105,200

Farragut North – Farragut West Ped Tunnel Flows 49,600

Metro Center – Gallery Place Ped Tunnel Flows 15,400

New Yellow Line Ped Tunnels Flows 147,300

Page 22: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 22

Split N-S Yellow Line 2nd St SE/NE:2040 Peak Hour Link Loads and Daily Ridership on Key Facilities (Round 2)

10/21/2010

Note: The values posted on the plot are the passengers per car during peak hour. The width of the band represents peak hour volumes.

Daily VolumesRelocated Yellow Line Segment Ridership 49,900

Farragut North – Farragut West Ped Tunnel Flows 42,600

Metro Center – Gallery Place Ped Tunnel Flows 14,800

New Yellow Line Ped Tunnels Flows 89,100

Page 23: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 23

New E-W Blue Line via M St and New Jersey Ave NW:2040 Peak Hour Link Loads and Daily Ridership on Key Facilities (Round 2)

10/21/2010

Note: The values posted on the plot are the passengers per car during peak hour. The width of the band represents peak hour volumes.

Daily VolumesNew E-W Blue Line Segment Ridership 215,100

Farragut North – Farragut West Ped Tunnel Flows 37,800

Metro Center – Gallery Place Ped Tunnel Flows 10,400

New Blue Line Ped Tunnels Flows 187,600

Page 24: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 24

New E-W Blue Line via M St and Constitution Ave NW:2040 Peak Hour Link Loads and Daily Ridership on Key Facilities (Round 2)

10/21/2010

Note: The values posted on the plot are the passengers per car during peak hour. The width of the band represents peak hour volumes.

Daily VolumesNew E-W Blue Line Segment Ridership 153,800

Farragut North – Farragut West Ped Tunnel Flows 39,000

Metro Center – Gallery Place Ped Tunnel Flows 11,100

New Blue Line Ped Tunnels Flows 135,900

Page 25: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 25

DEFINITION OF STRATEGIESRAIL ENHANCEMENTS (ROUND 2)

10/21/2010

Page 26: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 26

Four Interline Connections

10/21/2010

1) Connect Orange and Blue at Rosslyn

2) Connect Yellow and Blue at Pentagon

3) Connect Yellow and Green near L’Enfant Plaza

4) Connect Orange and Silver near West Falls ChurchThree new rail services:

1. VA-772 to Mount Vernon Square using connectors 1 and 2 (Silver1)

2. Dulles to Branch Avenue using connectors 1, 2, and 3 (Green2)

3. Dulles to Vienna using connector 4 (Silver2)

Page 27: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 27

Four Interline Connections

10/21/2010

New stations at:• Pentagon II (Silver 1 and Green 2) with pedestrian connection

between Pentagon I and Pentagon II• West Falls Church II (Silver 2) with pedestrian connection

between WFC I and WFC II

Peak Off-Peak Peak Off-Peak

Red 2.5 6.0 2.5 6.0

Orange 6.0 12.0 5.0 12.0

Silver 6.0 12.0 ------- -------

Silver 1 ------- ------- 10.0 12.0

Silver 2 ------- ------- 10.0 12.0

Blue 10.0 12.0 5.0 12.0

Yellow 1 6.0 12.0 6.0 12.0

Yellow 2 12.0 ------- ------ -------

Green 1 5.5 12.0 6.0 12.0

Green 2 ------- ------- 10.0 12.0

Base (Max CLRP) Four Interline

Yellow 1: Huntington-Mt Vernon Sq

Yellow 2: Franconia Springfield - Greenbelt

Green 1: Greenbelt - Branch Ave

Green 2 (Interline): Dulles - Branch Ave

Silver 1 (Interline): VA 772 - Mt Vernon Sq

Silver 2 (Interline): Dulles - Vienna

Page 28: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 28

IMPACT ON RIDERSHIP AND CAPACITYRAIL ENHANCEMENTS (ROUND 2)

10/21/2010

Page 29: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 29

Year 2040 Linked Transit Trips

10/21/2010

Round 1 Round 2

Summary of Weekday Transit Linked Trips by 4 Districts: 2040

Core (DC/Arl CBD) 754,000 757,000 755,000

Central Jurisdictions Outside Core 322,000 324,000 326,000

Inner Suburbs 277,000 279,000 281,000

Outer Suburbs 4,000 4,000 4,000

Region-wide 1,357,000 1,364,000 1,366,000

Percent growth vs. 2040 Max CLRP ----- 0.5% 0.7%

2040 Base (Max CLRP)

Interline Rosslyn "Y"

Four Interline Connections

Att

ract

ion

L

oca

tio

n

Page 30: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 30

Year 2040 Transit Boardings

10/21/2010

Round 1 Round 2

2040 Base (Max CLRP)

Interline Rosslyn "Y"

Four Interline Connections

Metrorail (Fare gate to fare gate) 1,055,000 1,066,000 1,064,000Commuter Rail 51,000 51,000 51,000Metrobus 555,000 555,000 560,000Other Bus 193,000 193,000 194,000Streetcar/LRT 65,000 65,000 63,000BRT/Rapid Bus 0 0 0Total Transit Boardings 1,919,000 1,930,000 1,932,000% Growth vs. 2040 Max CLRP 0.6% 0.7%

2040 Transit Boardings

Page 31: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 31

Interline Rosslyn “Y”: 2040 Peak Hour Link Loads and Daily Ridership on Key Facilities (Round 1)

10/21/2010

Note: The values posted on the plot are the passengers per car during peak hour. The width of the band represents peak hour volumes.

Daily VolumesDulles Airport to National Airport Rail Line Ridership 37,500

Courthouse - Arlington Cemetery Rail Link Flows 19,700

Farragut North – Farragut West Ped Tunnel Flows 42,300

Metro Center – Gallery Place Ped Tunnel Flows 15,800

Page 32: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 32

Four Interline Connections:2040 Peak Hour Link Loads and Daily Ridership on Key Facilities (Round 2)

10/21/2010

Note: The values posted on the plot are the passengers per car during peak hour. The width of the band represents peak hour volumes.

Daily Weekday VolumesDulles Airport to Vienna Line Ridership 11,200

Dulles Airport to Branch Ave. Line Ridership 61,200

VA-772 to Mt. Vernon Sq Line Ridership 63,300

Tyson East - West Fall Church II Rail Link Flows 5,000

Courthouse - Arlington Cemetery Rail Link Flows 45,400

Pentagon II - Waterfront Rail Link Flows 17,600

Farragut North – Farragut West Ped Tunnel Flows 45,500

Metro Center – Gallery Place Ped Tunnel Flows 12,300

Page 33: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 33

DEFINITION OF STRATEGIESENHANCED EXISTING SURFACE TRANSIT, WALKABILITY

10/21/2010

Page 34: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 34

Enhanced Surface Transit Strategy – Priority Corridor Network

• Based on networks developed for Priority Corridor Network (PCN) study– New routes coded as a limited stop BRT mode– Improved running times for existing background bus

service as per PCN• PCN Routes operated at 10-minute peak and 15-

minute off-peak frequency• Average speed for PCN Routes improved by 2 MPH• Overlay the Metrorail operating plan from Max CLRP

alternative10/21/2010

Page 35: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 35

Enhanced Surface Transit Strategy – Priority Corridor Network Routes

10/21/2010

Page 36: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 36

Improved Walkability StrategyIdentify TAZs within 3/4th mile of a Metrorail station with the potential for development;

Categorize the TAZs into two groups:1. Group 1 = TAZs inside or near the Capital Beltway with PEF = 150

(comparable to Clarendon or Ballston Stations):a. High volume of walk access;b. Development oriented towards transit access.

2. Group 2 = TAZs outside the Capital Beltway with PEF = 100 (comparable to Silver Spring or Greenbelt Town Center):a. High volume of drive access;b. Low density development at transit stations.

10/21/2010

Page 37: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 3710/21/2010

PEF – Base Case

Improved Walkability Strategy

PEF – Improved Walkability

The transit service plan is kept same as Base (Max CLRP)

Page 38: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 38

IMPACT ON RIDERSHIP AND CAPACITYENHANCED EXISTING SURFACE TRANSIT, WALKABILITY

10/21/2010

Page 39: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 39

Year 2040 Linked Transit Trips

10/21/2010

Summary of Weekday Transit Linked Trips by 4 Districts: 2040

Core (DC/Arl CBD) 754,000 764,000 766,000

Central Jurisdictions Outside Core 322,000 335,000 361,000

Inner Suburbs 277,000 294,000 360,000

Outer Suburbs 4,000 4,000 4,000

Region-wide 1,357,000 1,397,000 1,491,000

Percent growth vs. 2040 Max CLRP ----- 2.9% 9.9%

2040 Base (Max CLRP)

Att

ract

ion

L

oca

tio

nEnhanced

Surface Transit - PCN

Improved Walkability

Round 2Round 1

Page 40: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 40

Year 2040 Transit Boardings

10/21/2010

2040 Base (Max CLRP)

Enhanced Surface

Transit - PCNImproved

WalkabilityMetrorail (Fare gate to fare gate) 1,055,000 1,039,000 1,120,000Commuter Rail 51,000 49,000 53,000Metrobus 555,000 450,000 642,000Other Bus 193,000 181,000 242,000Streetcar/LRT 65,000 54,000 72,000BRT/Rapid Bus 0 216,000 0Total Transit Boardings 1,919,000 1,989,000 2,129,000% Growth vs. 2040 Max CLRP 3.6% 10.9%

2040 Transit Boardings

Round 2Round 1

Page 41: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 41

Enhanced Surface Transit – Priority Corridor Network:2040 Peak Hour Link Loads and Key Statistics (Round 2)

10/21/2010

Note: The values posted on the plot are the passengers per car during peak hour. The width of the band represents peak hour volumes.

Daily VolumesTotal ridership on PCN Routes 216,000

Change in linked transit trips vs. Max CLRP 40,000

Change in Metrorail trips vs. Max CLRP -16,000

Change in transit boardings vs. Max CLRP 70,000

Page 42: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 42

Improved Walkability:2040 Peak Hour Link Loads and Key Statistics (Round 2)

10/21/2010

Daily Volumes

Change in linked transit trips vs. Max CLRP 134,000

Change in Metrorail trips vs. Max CLRP 65,000

Change in transit boardings vs. Max CLRP 210,000

Note: The values posted on the plot are the passengers per car during peak hour. The width of the band represents peak hour volumes.

Page 43: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 43

PRELIMINARY EVALUATION

10/21/2010

Page 44: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 44

Key Findings - 2040 North-South New Yellow Lines:

10/21/2010

Strategy Pros Cons

New Yellow N-S 10th St SW/NW

Continues direct service to high demand locations in core

Increased core capacity, reduces crowding on Green line and many core stations

Potential East Potomac Park station

Does not extend service to new core areas

Maintains much of transfer burden with little or no relief for Court House/Rosslyn link

New Yellow N-S 2nd St SE/NE

Provides broader Metrorail service to SE/NE

Increased core capacity

Potential East Potomac Park station

Discontinues direct service to high demand locations in core

Results in greater congestion on:

o Blue line through Rosslyno Green line via transfers at

Waterfront/SEU station

Offers little or no relief for Court House/Rosslyn link

Split Yellow N-S 2nd St SE/NE

Continues direct service to high demand locations in core

Provides broader Metrorail service to SE/NE

Increased core capacity, reduces crowding on Green line and many core stations

Offers little or no relief for Court House/Rosslyn link

New tunnel under utilized (10 trains per hour during peak)

East Potomac Park station is questionable

Page 45: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 4510/21/2010

Strategy Pros Cons

New E-W Blue via M St / New Jersey

Ave.

Increased core capacity, reduces crowding on Orange, Silver, and Green lines and many core stations

Increases Metrorail coverage and transit share to core areas with moderately-high levels of demand

New tunnel under utilized (15 trains per hour during peak)

Offers little or no relief for Yellow/Green lines at L’Enfant Plaza

New E-W Blue via M St / Constitution

Ave.

Increased core capacity, reduces crowding on Orange and Silver lines

Increases Metrorail coverage and transit share to core areas with moderately-low levels of demand

Crowding continues to be an issue on both Yellow and Green lines

Requires more rail-to-rail transfers

New tunnel under utilized (11 trains per hour during peak)

Key Findings - 2040 East-West New Blue Lines:

Page 46: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 4610/21/2010

Key Findings – Rail Interline Options:

Strategy Pros Cons

Interline options – Rosslyn “Y”

Better intra-Virginia service

Reduces transfer volumes at Rosslyn

Provided some flexibility in rail operations

Does not address core capacity

Loads on service using interline do not justify 8-car trains

Four Interline Connections

Better intra-Virginia service

Reduces transfer volumes at Rosslyn

Provides considerable flexibility in rail operations

Aggravates peak congestion problem at Rosslyn

Increases transfer volumes at more stations

Does not address core capacity

Loads on new rail lines do not justify 8-car trains

Page 47: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 4710/21/2010

Key Findings – Improved Walkability, Enhanced Surface Transit (PCN)

Strategy Pros Cons

Improved Walkability

Total transit trips increase by 9.9% vs. Max CLRP

Reduces parking overflow by reducing short drive access to rail trips

Increased utilization of reverse peak direction Metrorail capacity

Higher peak loads on Metrorail due to improved transit access/egress

Enhanced Surface Transit -

PCN

Total transit trips increase by 2.9% vs. Max CLRP

Limited relief of parking overflow

New PCN Routes carry 216,000 riders per weekday in 2040

Higher peak loads on Metrorail system due to:

o Better access via PCN

o PCN routes do not cross jurisdictions

Page 48: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 48

Preliminary Evaluation

10/21/2010

Efficiency Auto Travel

Alternative

Sufficient Capacity to

Serve Demand

Reserve Capacity/

RedundancyStation

Capacity

Transit system

coverage

Service to Major

Activity Centers

Metrorail Parking

Sufficiency

Reduce Dependence

on Automobile to Access Metrorail

Region-wide Transit Share

Transit Access to

jobs

Passenger Miles Per

Route MileAuto VMT and Trips

Existing Conditions in 2008

2040 CLRP 2040 Max CLRP 2040 New N-S Yellow Line 10th St SW/NW 2040 New N-S Yellow Line 2nd St SE/NE 2040 Split N-S Yellow Line 2nd St SE/NE 2040 New E-W Blue Line via M St and NJ Ave

2040 New E-W Blue Line via M St and Const Ave

2040 Interline Rosslyn "Y" 2040 Four Interline Connections 2040 Enhanced Surface Transit - PCN 2040 Improved Walkability

Measures of Effectiveness

Core Capacity Access Mobility

• Strategies developed so far address many of the issues (core capacity, parking capacity, mobility); however, some issues (transit coverage, service to activity centers, auto VMT) are not addressed by any of the strategies studied so far.

• No one strategy addresses all/most of the issues. Addressing most issues will require combining strategies into scenarios.

Page 49: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 49

UPCOMING MODEL RUNS

10/21/2010

Page 50: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 50

Parking Capacity Relief Strategy - 1• Add direct shuttle bus service between remote parking location and Metrorail

station.• Shuttle service at 15 minute peak and 30 minute off-peak frequency.• Shadow price oversubscribed Metrorail park-and-ride lots.

10/21/2010

Metrorail Segment# of Parking

Spaces

2040 Metrorail Parking

Utilization Location Shuttle ToRed Line - Shady Grove-Grosvenor 10,140 94% Urbana (South Lot) MD 80 & I-270 Shady Grove Metrorail

Red Line - Silver Spring - Glenmont 3,354 123%

Burtonsville and Calvert County Fairgrounds

US 29 & MD 198/Calvert County Fairground Glenmont Metrorail

Green Line - Waterfront-Congress Heights 808 102% Equestrian Center MD 4 & Water Street Branch Avenue Metrorail

Green Line - Southern Avenue - Branch Avenue 7,310 126%

St. Charles Towne Ctr @ JC Penney and Dick's Sporting Goods and behind JoAnn's

11110 Mall Circle and MD 301 & Smallwood Drive Branch Avenue Metrorail

Yellow/Blue Line - Fran-Springfield, Van Dorn & Huntington 8,520 121%

Fredericksburg (NEW) ; Prince William Pkwy Transit Center (PRTC) (NEW); Massaponax (NEW);

Fredericksburg ( Rte 17 & RT 1); Massaponax (I-95 & Spotsylvania Pkwy); Prince William Pkwy Transit Center (PRTC) (I-95 & Telegraph Road)

Franconia-Springfield Metrorail

Orange Line- Vienna/Fairfax - West Falls Church 9,258 87%

Stone Road-US 29; Stringfellow Road; Sully Station; Bull Run @ 234/Sudley Road; VA 234 Bypass @ US 29; and Haymarket @ US 15

VA Bypass & US 29;VA 234 Bypass/Cushing Road; VA 234 & Sudley Road; Stone Road-US 29; US 15 in Haymarket Vienna Metrorail Station

Blue Line - Benning Road-Largo Town Center 4,475 133% Harry S. Truman

Harry S. Truman & Riva Road

Largo Town Center Metrorail

Park-and-Ride Lot

Page 51: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 51

CLRP Aspirations Strategy• Households

– Moves 69,000 additional households into the region;– Relocates 205,000 households to activity centers and

transit station areas.

• Jobs– Moves 22,000 additional jobs into the region;– Shifts 240,000 jobs to activity centers and transit station

areas.

10/21/2010

Page 52: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 52

Potential In-fill Stations:• Eisenhower Avenue Valley between

King Street & Van Dorn Stations;

• St. Elizabeth’s Hospital (West Campus) between Anacostia and Congress Heights Stations;

• Kansas Avenue, NW between Fort Totten and Takoma Stations;

• Others?

10/21/2010

In-fill Station Strategy

Page 53: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 53

Enhanced Surface Transit – PCN+• Improve the PCN network strategy by

implementing the following:– Extend select premium buses to core to relieve

Metrorail peak load points– Interline existing PCN routes where possible– Identify PCN corridors with opportunity for:

• Express BRT• Off-Board Fare Collection

– Commuter Rail Enhancements:• MARC to Crystal City• Bi-directional service

10/21/2010

Page 54: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 5410/21/2010

Rail Extensions-Combo of up to 5

• Greenbelt to BWI-Marshall Airport

• Vienna to Centreville/Rte. 28

• New Carrollton to Bowie

• Springfield to Dale City

• Branch Avenue to Waldorf

NOTE: Extensions may impact core capacity

Page 55: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 55

Rail Extensions- additional ones• Shady Grove/Glenmont Closed Loop;

• Yellow Line relocated continuing north via North Capitol;

• St. Elizabeth’s Hospital to National Harbor;

• Richmond Highway;

• Leesburg;

• Brown Line:– Bethesda/Friendship Heights via Massachusetts

Avenue ;– Georgetown to Mt. Rainier or North Capitol Street

Corridor.

NOTE: Extensions may impact core capacity10/21/2010

Page 56: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 5610/21/2010

LRT/BRT Connections-First Run

• Purple Line in Md to Va Connections– Grosvenor to Dunn Loring;– New Carrollton to Eisenhower Avenue.

• Virginia to DC Connections– Fairfax City and Vienna via Chain Bridge Road to

DC;– Pentagon City to DC;– Rosslyn to Georgetown.

• Intra-Virginia Connections:– Dulles to Manassas;– Potomac Yard to Ballston via Glebe Road;– Tysons Corner to Alexandria via Route 7.

NOTE: Extensions may impact core capacity

Maryland

District of Columbia

Virginia

Page 57: RTSP Metrorail Strategies: Split Yellow Line, New Blue Lines, Interline, Enhanced Surface Transit, and Walkability Presentation to the Technical Advisory

Regional Transit System Plan 57

TAG Meetings 1 & 2 TAG Meetings 3 & 4 TAG Meetings 5 & 6 TAG Meetings 7 & 8 & Public Engagement

Goals & Strategy Development

Strategy Modeling & Evaluation

Scenario Modeling & Evaluation Findings

Winter-Spring 2010 Spring – Summer Fall– Winter Winter – Spring 2011

RTSP Project Schedule

10/21/2010

We are here!