safety plan program

85
Service Co. Ltd. Site Safety Plan (PP-8 SEC-COA) Project Name: Replacement MVU Container (13.8kV) of A2 at PP8 Location: Saudi Electricity Co.- Central Operating Area Riyadh, Saudi Arabia Contract No.: 11222054/00 Company/Owner: SITE SAFETY PLAN DOCUMENT NO. PAGE NO. REV, Replacement MVU Container (13.8kV) of A2 at PP8 EM-06916.001 1 OF 42 0

Upload: danielcabasa

Post on 06-Feb-2016

59 views

Category:

Documents


0 download

DESCRIPTION

SaFETY

TRANSCRIPT

Page 1: Safety Plan Program

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.0011OF420

Service Co. Ltd.Site Safety Plan (PP-8 SEC-COA)

Project Name:

Replacement MVU Container (13.8kV) of A2 at PP8

Location:

Saudi Electricity Co.- Central Operating Area Riyadh, Saudi Arabia

Contract No.:

11222054/00

Company/Owner:

S.No.DescriptionRev.DateApproved by01First Issue115.01.2013

Fadi Al-AbkariOHS Advisor ABB Service Co.

Page 2: Safety Plan Program

TABLE OF CONTENTSSECTION

NO.DESCRIPTIONPAGE NO.

iIntroduction and Project Summary3iiSafety Policy Statement4

1.0Assignment Of Project Personnel Safety Responsibilities52.0Rules And Regulations For Personnel And Equipment

Safety73.0Accident Reporting And Investigation84.0Safety Orientation and Meetings105.0Site Planning And Housekeeping106.0Personnel Protective Clothing and Equipment117.0Hand Tools And Power Tools128.0Working Places and Access Ladders129.0Material Handling And Storage13

10.0Lifting And Hoisting Equipment1411.0Work Permit1512.0Fire Prevention and Hazards1613.0First Aid1714.0Medical Health and Welfare1815.0Electrical Handling1816.0Attachments

AProject Organization Chart 25BOverall Construction Schedule & “S” Curve 26CInjury Accident Report 28DPreliminary Motor Vehicle Damage Report 30EMonthly Injury / Dammage Summary Report 32FList of Emergency Contact Numbers 34GSafety Reports 35HPermit to work/Limit of access/sanction to work (PTW/LOA/SOW)52ISite Location and Location of Fire Extinguishers53JBi-Weekly Site Safety Evaluation 55KSamples of Safety Signage as per SEC Safety Manual & ABB

Code of Safety Practice59LEmergency Evacuation Plan60MRisk Assessment Review61

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.0012OF420

Page 3: Safety Plan Program

i. INTRODUCTION AND PROJECT SUMMARY

The 13.8kV MVU container of ABB GT “A2” has been damaged due to fire

accident happened on said container. As a result of further study and

recommendations, it is necessary to restore back the damaged container by

providing a new state of the art design to accommodate the loads being supplied

from the 13.8kV MVU.

It is the scope of ABB Service Co. Ltd. to perform detailed engineering and

design, procurement, supply and deliver the materials at PP8 premises, including

installation, testing and commissioning, and put into service for a new 13.8kV MVU

container similar but state of the art design to be in line witrh the GT-A2 (ABB

11D5) gas turbine at SEC-COA’s PP8 premises.

To execute this tasks, careful study and safety planning has been conducted since

the tasks is highly prone to any incident may occur during site execution.

As a result, this Safety Plan has been established to served as a guide for the

safety and loss prevention of working personnel and company’s equipments.

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.0013OF420

Page 4: Safety Plan Program

ii. ABB SAFETY POLICY STATEMENT

1.0 ASSIGNMENT OF SAFETY RESPONSIBILITIES

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.0014OF420

Page 5: Safety Plan Program

Responsibilities of the personnel employed during the site execution with regards to the Safety Plan for Loss Prevention are defined as follows:

1.1 PROJECT MANAGER:

The Project Manager is the overall responsible for the project safety management assigned on this project. The Project Manager must ensure that:The health and safety plan drawn up during the proposal till site execution must strictly followed and that all significant health and safety risks are identified, eliminated or minimized according to the following safety plan;

Planning and scheduling of safety activities, identifies significant health and safety risks and eliminates or minimizes them.

Coordinate with SEC-COA Loss Prevention Division through their authorized representative.

Occupational health, safety performance of personnel, risks assessment, shall be implemented, monitored and reported to ABB OHS Department as well as SEC-COA Lossprevention Division (e.g. SOT’s, Tool Box Talks, Nearmiss, Injury Reports, etc.).

Insure that only competent Sub-Contractors are appointed and that their employees and any subcontractors (if necessary) are competent to execute the works.

Insure that competent Sub-contractors and any personnel involved in this project should undergone ABB’s Safety Training prior to any site deployment or start of site execution.

Insure that Sub-Contractors should conduct their own safety risk assessments and document their safe working methods before start of work.

Appoint a Site Manager who is competent to effectively perform health and safety duties set forth in the ABB’s Code of Practice for Site Manager’s Health and Safety Guide.

1.2 S ITE MANAGER:

The Site Manager is responsible in implementation of Site Safety Plan for the successful execution in Upgrading, Overhauling and Repairs of 380kV GIS Circuit Breakers and is defined under as;

Ensures that Work Permit Procedures are strictly followed. Is familiar with SEC-COA Work Permit Procedures and did undergone the

prequalification training as Authorized Permit Receiver in compliance to SEC-COA Safety Procedure.

Recommends ideas for safety improvement to the Project Manager and Safety Officer and shall act as an example in implementing site safety rules.

Ensures inspection of tools and equipments are done before using. Attends job progress meetings and safety evaluation in which safety problems

are reviewed. Ensure that all the employees/subcontractors working at site premises shall

have necessary and valid SEC-COA Authorization/Permission before commencement of any site work activitygtnb. All workers performing the specific task in this project such as dismantling, overhauling, erection/re-installation, wiring works, testing commissioning activities, etc., shall be well

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.0015OF420

Page 6: Safety Plan Program

qualified and must have a track record of similar experience in performing the tasks.

1.3 PROJECT ENGINEER :

The main responsibilities as project engineer in implementation of Site Safety Plan program for the execution of this project are as under;

Ensures that Work Permit has been issued and safety procedures are strictly followed.

Is familiar with SEC-COA Work Permit & Safety Procedures. Recommends ideas for Safety improvement to site manager and safety

officer and shall reinforce the rules and regulations of site safety procedures. Attends job progress meetings and safety evaluation in which safety

problems are reviewed.

1.4 SAFETY OFFICER

The safety officer reports directly to Project Manager. He is responsible for the establishment of an effective safey program which is based upon ABB and SEC-COA safety policy are properly implemented to meet ABB Service Co. Ltd’s contractural responsibilities. His principal responsibility relatd to the following functions;

Making regular safety inspections of job sites and taking the immediate necessary corrective action to eliminate unsafe acts and/or conditions. Record observations using the appropriate forms.

Providing appropriate safety advices on highlighted issues during the safety meetings.

Assisting in the accident investigation and reporting procedures. Implementing training programs for the supervisors, employees, subcontractors as

they apply to their specific responsibilities. Encouraging programs for recognition of individual employee safety efforts and

their contribution toward improved work methods. Providing advice regarding the necessary safety equipment, use of right tools, that is

required for the job at site. Complement of general and site based safety instructions Carry out in internal safety audits and feedback to include subcontractors.

1.5 TESTING COMMISSIONING ENGINEER

Be familiar with SEC-EOA Loss prevention requirements and company safety program applicable to work on which subordinate workers are engaged.

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.0016OF420

Page 7: Safety Plan Program

Conducts ten to fifteen minutes tool box meeting with men before daily work started.

Provides adequate Personal Protective Equipment to all of his team members.

Interacts with safety officer and ensures implementation of the safety aspects and instruction of safety officer from time to time.

Incorporates safety instructions in routine orders and see they are obeyed. Gives precise instructions on responsibilities for correct work methods. Corrects unsafe acts, such as horseplay or the taking of unnecessary risks. Ensures that newly arriving personnel at site are properly instructed in

precautions to be taken before they are allowed to start work. Ensures that verbal instructions are fully understood and check back to see

that they are carried out as intended. Reports unsafe conditions of tools and equipments to site manager and

recommends for replacement if necessary. Makes sure that all men know how to execute first aid and that proper care

is taken on all injuries, know how to call assistance in case of emergency and nominate others to act in absence.

1.6 TECHNICIANS & SITE ASSISTANTS

Uses the correct tools and equipment for the job and use the protective clothing and equipment provided.

Make inspection of their tools and equipment before use and shall report to his Testing/Commissioning Engineer if found tools is defective or not suitable to use.

Avoids any situation that may endanger himself or his workplace. Insure that proper safety procedures are strictly implemented and practiced

(e.g. lock-out tag-out procedure, 7 steps that saves life procedure, take 5 procedure, etc.)

Keep tools in good condition. Maintains his work area clean at all times. Avoid doing horseplay and abuse of safety devices, equipment, and welfare

facilities.

2.0 RULES AND REGULATIONS FOR PERSONNEL AND EQUIPMENT SAFETY

As an agreed principle and guideline, Contractor will follow all the general safety rules promulgated by SEC-COA for its employees laid down in their “ACCIDENT PREVENTION MANUAL.” As well as the ABB’s Code of Practice for Site Manager’s Health and Safety Guide.

Before start of the work, all involved workers will be made aware to;

a) Complete understanding of the work to be performed.b) Properly planned procedure of the work.

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.0017OF420

Page 8: Safety Plan Program

c) Possible hazards and danger points.d) Safety aspects as a continuing part of day-to-day work.

Before start of the work, every personnel present at the work site will make sure that:

a) Working conditions are safe and sound.b) No unsafe situation is expected to creep in.c) Prior arrangement for any unforeseen hazardous situation exists.d) First aid medication is available and accessible.

Every worker will take care of his personal safety in the first instance. Safety of his co-workers and of the equipment will be given equal importance. Below guidelines and procedures shall strictly be followed before attempting to execute any work as follows;

Work permit will be obtained from the authorized issuer from SEC-COA by any of authorized receiver from ABB Service Co. Ltd.

All working staff engaged near live overhead lines or underground cables will wear safety shoes, leather gloves, helmets and safety goggles. At areas of high noise levels, workers will use ear plug/ear muffs.

All the existing electrical circuits will be taken for granted as live circuits unless otherwise confirmed.

All de-energized electrical circuits will be properly grounded and tagged.

Adequate illumination will be made available while working at night.

Adequate signs, warning logos, identification marks will be used at work sites during the progress of work.

As far as possible, public access to work sites will not be allowed.

Wherever materials are stored, minimum 1.5 m space will be kept to avoid spread of fire and for inspection purpose.

In no case, smoking will be allowed at the work sites.

3.0 ACCIDENT REPORTING AND INVESTIGATION

Accident Classifications:

Fall from different level Fall on same level Struck by or against Caught by, in-between, or under Contact with electricity Contact with extreme temperature Contact with radiation, chemicals Vehicular

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.0018OF420

Page 9: Safety Plan Program

Other not list above

3.1 ACCIDENT REPORTING

In case of accident a report will be sent to SEC-COA Division Manager of proponent division and Contractor’s Project Manager.

Streamline system of accident reporting to be maintained in case of fatal injuries/Non fatal serious injuries, oral reports to be promptly followed by written report as per the accident report within 24 hours to SEC-COA Loss Prevention Division along with photographs if necessary.

In case of damage to plant equipment or machinery, a written report will be submitted immediately to SEC-COA using the attached standard forms. The Vendor/manufacturer will be furnished a copy of the report for any damage to new equipment.

All the important telephone numbers for the nearest fire brigade, police and hospital services will be posted near each fire extinguisher and near all exits.

ABB Project Manager - +966 54 158 2346ABB Site Safety - +966 50 216 4907ABB Site Manager - +966 Hazim KharwashABB Safety officer - +966 Fadi Al-Abkari Fire Brigade - 998Police - 999Red Crescent - 997Medical Clinic & Hospital - (As per attached hospital list)

3.2 TYPES OF REPORTS

Contractor personnel injury accident report.

Contractor preliminary motor vehicle damage report.

Monthly injury summary report.

Monthly damage summary report.

(Please refer to the attachments C, D and E

3.3 ACCIDENT INVESTIGATIONS

The Safety Office/Engineer and Site Engineer will immediately investigate all accidents or near miss incidents within his area of responsibility. He should complete a report and submit to the SEC – COA project manager within 24 hours.

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.0019OF420

Page 10: Safety Plan Program

Project Manager will review all accident investigation reports to ensure the corrective action is taken.

Accident investigator shall classify the accidents based on its type, like fall from high level, struck by or against, caught by/in between under, contact with electrical current, vehicular, etc.

4.0 SAFETY ORIENTATIONS AND MEETINGS

To ensure that workers fit into the company’s plans for accident prevention, safety orientations and meeting will be held as follows:

a) Every Saturday from the First week of every month, Safety officer will conduct a meeting, the meeting will be held to discuss and review any unsafe act resulting in an accident. The Site Manager, Site Engineers, and Field Commissioning Engineer will attend.

b) Safety orientation and instruction for newly arriving personnel in the job site will be conducted by Safety Engineer or Safety Officer before he will assigned for any work.

c) Commissioning Engineer & supervisors shall hold a 5 to 10 minutes tools box meeting on daily basis prior to commencement of work.

5.0 SITE PLANNING AND HOUSE KEEPING

5.1 SITE PLANNING

The ABB Existing site office or store yard shall be utilized so that working areas, roadways, access ways, stairways and scaffold platforms are kept free from unnecessary obstructions. Electrical cables and temporary utility cables, conduits and pipes shall be properly arranged so that, they do not become tripping hazards.

5.2 GOOD HOUSE-KEEPING

Good house keeping plays an important role in doing the work more efficiently and reducing man hours lost due to accidents. Stored materials shall be identified as to name, size, type and quantity. The materials shall be neatly stacked as per the identification codes mentioned above. Files/records shall be kept neatly in racks and indexed for easy access.

Adequate number of workers will be deputed for the housekeeping as and when required.

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00110OF420

Page 11: Safety Plan Program

Smoking will be controlled within plan premises and confirmed to safe designated places only.

Providing trash bin all around store and cleaning daily will help us to maintain good house keeping.

To maintain effective house keeping schedule in order to maintain safe working area, all unused and scrap materials shall be collected and disposed of in a timely manner to prevent formation of tripping hazards and fire hazards.

The safety signs, posters and banners are to be displayed at different work location for awareness of the workers.

Aplease refer sample pictures in Attachement J, Hazard as per SEC Safety Manuals.

6.0 PERSONNEL PROTECTIVE CLOTHING AND EQUIPMENT

All working personnel must have the following personnel protective equipment and clothing during the course of site work execution.

6.1 Head Protection - Safety helmets / hard hats

6.2 Eye and Face Protection - Safety glasses / goggles / Protective Shield for Welding.

6.3 Hand Protection - Hand gloves

6.4 Foot Protection - Safety shoes

6.5 Respiratory Protection - Respiratory Masks

6.6 Protection During Climbing - Full body Harness, harness and Lifelines

6.7 Hearing Protection - Ear plugs

7.0 HAND TOOLS AND POWER TOOLS

Handling and use of Hand tools and Power tools in proper manner is vital for reducing the risks involved.

7.1 HAND TOOLS

The tools shall be of high quality. Appropriate tools shall be used for specified works. Defective tools shall not be used.

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00111OF420

Page 12: Safety Plan Program

When work is being carried out at the elevated position, the tools That are not in use shall be secured or placed in holders.

Throwing Tools or materials from one location to another, from one worker to another, dropping them to lower levels shall be prohibited.

The Tools and tackles shall be protected against corrosion and maintained to be free of defects.

All tools shall never be altered and shall be kept in proper work conditions.

7.2 POWER TOOLS

The Tools shall be inspected regularly. Only trained persons shall be allowed to handle the tools. Necessary Guards shall be provided. Use of cracked or damaged grinding wheels shall be prohibited. The electric tools shall be provided with equipment grounding

connections. The Tools shall be checked before use and used with extreme care &

precaution. Check correct operating voltages and connect the power tools. Always draw power supply from a switch board, which is easily

accessible.

8.0 WORKING PLACES AND ACCESS LADDER

8.1 WORKING PLACES

Work place shall be safe to perform the job. Key personnel shall monitor working conditions on a daily basis.

Construction sites shall be clean, safe and enclosed (if necessary) with temporary fencing. There shall be adequate lighting, ventilation and sanitary systems.

Warning, safety and traffic directional signs shall be placed at appropriate places.

Portable fire extinguishers shall be provided during welding work, transformer installation work etc.

Project site offices shall have adequate parking facility. The access roads shall be free from obstruction and shall have adequate lighting.

8.2 LADDERS

Ladders shall be of appropriate length. Ladders with metal reinforced side rails shall not be used near electrical equipment with exposed conductors.

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00112OF420

Page 13: Safety Plan Program

Ladders shall be inspected periodically for any damage, deterioration, wear and tear, corrosion and structural failure.

8.2.1 POSITIONING OF LADDERS

Ladders shall not be positioned against insecure structures. They shall be placed firmly on solid ground and the area at the base of the ladders shall be kept clear. A–type ladders or scaffolding platforms shall be used on slippery grounds.

8.2.2 USAGE OF LADDERS

The user shall face the ladder when ascending and descending. The user shall not carry tools and material in his hands while using ladders.

The user shall maintain a secure hand hold or use a full body harness when both hands are engaged in work.

If the ladder is erected closed to the doorway, the door shall be either locked shut or be secured in the open position with a man on guard.

When an extension ladder is used fully extended, the minimum overlap of sections shall be four rungs.

Where a ladder is carried by one man, the front end shall be kept high enough to clear men’s heads and special care shall be taken at corners and blind spots.

Special care shall be taken while carrying ladders inside the live substation areas.

9.0 MATERIAL HANDLING AND STORAGE

9.1 MANUAL HANDLING OF MATERIALS:

Proper attention should be paid while handling material. Ascertain whether it can be done manually or it needs mechanical equipment. The following conditions and procedures as below:

a) Ascertain the weight of the object.b) Remove any sharp objects present.c) Wear appropriate protective equipment.d) Decide where to place the object.e) Survey the area around the object and proposed route of travel. f) Remove any obstruction present.g) Get sufficient help to lift and transport safely.h) Lift within your physical capacity. Keep feet close to object. Crouch close

to the load with knees bent. Position or keep backbone straight. Lift the object using legs and arm muscles.

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00113OF420

Page 14: Safety Plan Program

i) While two or more persons are transporting one extra man should give the signals while others march with the load.

The workmen shall be trained for lifting loads manually with demonstration during their training sessions.

9.2 STORAGE AREAS

Available site storage area as defined by the client will be used by ABB to store materials at site.

Adequate area shall be provided for safe handling and storage of materials.

Store materials shall be identified by Name, Size, Type, Quantity.

Flammable materials such as paints, fuels, lubricants, chemicals and thinner shall be separated from combustible materials.

Applicable/appropriate warning signs shall be displayed inside warehouse.

Fire extinguishers shall be provided in storage area.

Non compatible material shall be segregated in storage.

10.0 LIFTING AND HOISTING EQUIPMENT

The site has an available lifting equipment provided for this overhauling and maintenance purposes. Lifting operations shall be performed by SEC-COA site representative only or can be operated by a trained personnel capable to operated the overhead crane after proving his track record of experience in performing the lifting works and following the below lifting requirements;

Hoist operators must inspect equipment daily before use.

Do not operate a crane or hoist if limit switches, steel ropes, chains or other components are worn or in disrepair.

Replace nylon or web slings immediately if excessively worn.

Associates in the direction of travel should be warned to move and remain clear of a lifted load at all times.

Loads should not be suspended over personnel below.

Under no circumstances may anyone ride the hook or load.

Directional movement should be made smoothly and deliberately. Avoid rapid movements in any direction.

Do not exceed the rated loadcapacity of the crane, hoist, chain, cable, slings, or other component.

Slings, load chains and other lifting devices must be fully and securely seated in the hook before moving a load. Remove slack from the sling, chain, or cable before lifting a load.

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00114OF420

Page 15: Safety Plan Program

Use the following practices to avoid swinging loads:

> Locate the hoist directly above the lifting point of the load before lifting.

> Lower loads directly below the hoist.

> Keep hoisting ropes vertical. Do not pull or push the load.

> Maintain two full wraps of cable on the hoisting drum.

When lifting loads at or near capacity, test the hoist brakes by returning the master switch or push button to the “OFF” position after raising the load a few inches off the floor. If the brakes do not hold, lower the load to the floor slowly and do not operate the crane. Report the situation immediately and DO NOT USE until repaired

Ensure that all loads are lifted high enough to clear obstructions before moving the bridge or trolley. Whenever possible, maintain a minimum clearance of one foot above loads and to the sides. Raise the load only to the height necessary to clear lower objects.

Never pull a hoist by the pendant cable.

Never leave the controls unattended while a load is suspended. If it becomes necessary to leave the controls, lower the load to the floor.

Familiarize yourself with the location of the disconnect switch.

If loss of electrical power occurs, place controls in the “OFF” position to prevent unexpected startup upon restoration of power.

Disconnect power to a hoist that is unsafe or in need of repair. Arrange to have the disconnect switch locked and the control panel tagged with and “Out of Order” or “Do Not Operate” tag. Never operate a hoist that has been tagged with an “Out of Order” or “Do Not Operate” tag, or is your opinion, UNSAFE TO OPERATE.

11.0 WORK PERMIT

Work permit is an authorization to do or perform certain work on an energized equipment or part of the energized system in a restricted area. It is issued by an authorized employee of the concerned proponent organization. The receiver will also be an authorized person, who will be delegated the authority of receiving the work permit issued by SEC-COA Authorized issuer. Before issuance of the work permit both the issuer and receiver will ensure the safe working conditions of personnel and equipment.

Before issuing and receipting of work permit, the equipment or the circuit involved will be switched off by the on-duty switch man of the proponent organization. Appropriate lock and tags will be placed on the equipmentunder work permit as long as the permit is valid.

After completion of the work, the work permit will be closed-out by the authorized issuer and receiver after observing all closing-out requirements.

The tag will be then removed by the authorized person.

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00115OF420

Page 16: Safety Plan Program

Every care will be taken while restoring the electric supply. No job is more urgent or no service is more important than the safety of the workers. Therefore, safety of personnel must be ensured in a safe location before energizing the involved electrical equipment or system.

In case the receiver of the work permit needs to leave the work site (for genuine reason), he will inform the issuer and designate other authorized receiver of work permit to look after the work in his behalf.

The work permit will be displayed at the job site.

Receiver of the work permit will stay in the work place for the complete duration of work permit.

Issuer/receiver of the work permit shall stop the work if the facility is found unsafe.

Work permit shall be taken before execution of the work.

The Work Permits shall be handled carefully while on the job. They shall be in the safe custody of the personnel for whom the work permit has been issued. For details, client guidelines G.I. # 65.111 shall be referred.

12.0 FIRE PREVENTION AND HAZARDS

12.1 FIRE PREVENTION

To avoid the risk of fire and to minimize the losses due to fire a well organized fire prevention program will be established at site on each stages to achieve the objectives that;

1. Fire may not occur.2. If occurs, may not be spread.3. If spread, the losses shall be minimum.

The fire prevention program will be contained as under;

a. No exposed wiring and lose connection will be allowed; only conduit wiring will be permitted.

b. Distribution boards and other supply will be inspected regularly.

c. No chemicals and liquids will be permitted in the warehouse.

d. Sites will be kept clean and free of high inflammable/combustable liquids or materials, stray wooden logs, waste paper, catrons, rubber, trash etc. for fire prevention.

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00116OF420

Page 17: Safety Plan Program

e. Smoking is strickly prohibited.

f. Office equipments electic apparatus including A/C units, fixtures, and fans shall be switched off before leaving the work sites.

g. During unloading of fuel, trucks engines must be stopped and trucks and other unloading equipments should be well earthed to prevent static electric charge.

h. Observe material segregation and spacing according to class and type in storage area/warehouse.

12.2 KNOWING THE LOCATION OF FIRE EXTINGUISHERS

The substation is fully equipped with fire fighting equipment and it is the rights and duty of every personnel involved in site work execution to know the locations of existing fire extinguishers in the area. Every worker must investigate the integrity of fire extinguishers by checking the pressure gauges to make sure that the fire extinguishers are in proper working capability in eliminating the fire.

All working personnel including Project Manager, Site Manager, Testing Commissioning Engineer shall include in the tool box discussion the locations and integrity of each extinguishers and condition their minds where to approach to the nearest extinguisher whenever fire may happen.

13.0 FIRST AID:a) A first aid kit equipped with all the necessary medicines, dressing, bandages etc.

will be placed at work site. Every worker will be made familiar with the location and use of this kit.

b) If any worker gets injured or develops some ailment during working hours, first aid treatment will be administrated on him immediately. If necessary, he will be taken to the nearest hospital or medical clinic.

c) Chemical burns will be washed with sufficient water before applying first aid treatment.

d) In case of electric shock, the source of electric supply shall be disconnected immediately. The victim will be detached from the live circuit using some dry log, rope or safety gloves. The rescure should ensure his own safety at every cost. Artificial respiration should immeidately be applied to the victim.

e) In case of sun stroke, the victim will be shifted to a cool area and taken to hospital. His head will be wrapped with a cool and moist cloth.

f) In case a person becomes unconscious due to any serious accident or shock then he should be checked whether he is breathing or not. If he is not breathing then artificial respiration should be immediately applied to him.

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00117OF420

Page 18: Safety Plan Program

g) Important telephone/contact numbers of hospitals for emergency and treatments are available in attachmen F.

14.0 MEDICAL HEALTH AND WELFARE

Botlled drinking water supply shall be provided at site.

Site toilets can be utilized for workers personal necessity

Dining can be done at nearby restaurant facility since no available dining hall in substation site.

Transporation of employees is provided by Company for conveyance of to and from the Site. These vehicles are fully maintained properly.

Working hours is restricted to the regular eight hours per day with one – hour lunch Break. This may vary due to workload schedules. Friday, which is normal rest day, shall be utilized if need arises.

15.0 ELECTRICAL HANDLING

15.1 General Rules Electrical Safety

a) All Electrical Equipment shall be treated as live unless made safe and released for work as described in section 15.2 below.

b) Electrical equipment is subject to Electrical Safety Rules when it is capable of being energized from a power system through operation of switchgear, or by the replacement of fuses or links.

c) Electrical Safety Rules must, at all times, be applied in such a manner as to prevent danger to persons switching, working, on, or in the vicinity of live apparatus.

d) Each person within the Work Party must have the Competence to undertake the scope of work planned for them.

e) Normally the customer shall undertake all actions to safely disconnect and earth Electrical Equipment to be worked on.

f) Normally ABB Service personnel shall not work on live equipment. g) Work packages which require work on or very near live equipment must

follow relevant additional rules in Section 15.3.h) Personnel on Site must at all times wear appropriate personal protection

equipment (PPE). Flame resistant clothing must be worn. NFPA standard 70E will be used in the absence of local standards.

i) Other PPE may be used according to local regulations and risk assessment controls.

j) There must be safe and proper means of escape in the event of failure of any live apparatus.

k) The Nominated Person must establish prior to starting work relevant telephone numbers for emergency services.

l) Service technicians may not walk on top of live indoor switchgear panels.

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00118OF420

Page 19: Safety Plan Program

m) Appropriate safety precautions shall be taken when working on high equipment to avoid injury through falling.

n) No un-authorized person may enter the work area.

15.2 Rules for Working on Dead Electrical Equipment

safe working area must be created and maintained in accordance with the following principles. All 7 principles must be applied on every occasion.

Step 1 : Clearly Identify the work locationa) Sufficient labels, schematics and plans must be available to clearly identify

the location and the Electrical Equipment to be worked on.b) Where Electrical Equipment is not easily identifiable, such as cables,

suitable identification arrangements must be made by the Nominated Person.

c) Nearby live Electrical Equipment must be identified as dangerous by the application of highly visible temporary warning labels.

d) There must be clear and continuous identification of the safe working area. It must be possible to easily distinguish between safe and dangerous areas throughout the course of planned work.

Step 2 : Disconnect Completely, Secure against re-connectiona) Verify that the Electrical Equipment has been safely disconnected and

earthed.b) A suitable electrical gap (see Section 15.7.2 & 15.7.3 appendices 2 & 3)

must be made across all points at which the apparatus may be made live including potential in-feeds from low voltage apparatus.

c) The gap must be physically secured from inadvertent or willful re-connection, by the application of barriers or locks; or removal of fuses to a safe place; or removal of apparatus from its normal service position; or disconnecting/blocking stored mechanical energy devices.

d) It shall not be possible for remote protection or control to reconnect the circuit under work through electrically closing a switching device.

e) A prominent warning notice must be fixed to each point of disconnection.f) All keys must be kept in a secure place.

Step 3 : Provide protection against live partsa) All live apparatus in the vicinity of the work place must be locked off, clearly

identified and made inaccessible by barriers or other means.b) A risk assessment must be carried out to ensure that dangerous voltages

cannot be directly or indirectly created on any of the electrical circuits connected to the point of work from nearby live circuits (see appendix 2) including the re-arrangement of earth connections.

c) Special attention must be paid when the scope of work requires phased outages of different circuits. The sequence of circuits to be made dead must be clearly understood by all members of the work party. With each change of circuit from live to dead, or vice versa:

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00119OF420

Page 20: Safety Plan Program

Access control and warning labels must be changed to suit Each member of the work party must fully understand which new circuits are now live

d) Work on Electrical Equipment connected to overhead lines must cease in the event of a lightning storm.

e) On wood pole lines with one or more circuits live, precautions must be taken against steelwork being or becoming live.

f) On certain high voltage cable systems it may be necessary to take precautions against large induced voltages, for example by fully insulated working.

g) Precautions must be taken to prevent danger from low voltage conductors at the point of work.

Step 4 : Take special precautions when close to bare conductorsa) Special precautions must be agreed with the Nominated Person when the

minimum clearances (Appendix 1) cannot be made to unearthed conductors during preparation of the safe working area, which typically occurs when entering switchgear cells, applying screens, testing and applying portable earths.

b) The minimum safety precautions in the above circumstances are: Wear suitable insulated gloves Ensure access is suitable to avoid inadvertent slips. Be accompanied by a second person who can render assistance.

Step 5 : Verify the installation is deada) Where the design of the Electrical Equipment allows, it must be confirmed

dead by a suitable tester at all points of work and points of application of portable earths.

b) The tester shall be of a proper design, and proved before and after each test.

c) Where the design of the Electrical Equipment precludes this, other suitable arrangements shall be agreed with the Nominated Person. Typically: firing a spike through underground cables, using proximity testers on insulated conductors, operation of switches to earth or tracing cables or conductors back to a visible earth point.

Step 6 : Verify earthing and short circuiting a) The Electrical Equipment to be worked on must be connected to earth by

connections and conductors capable of carrying the full short circuit current at that point.

b) Where possible the Electrical Equipment shall be earthed by a fully rated switch.

c) Earths must be applied between the point of work and all possible sources of HV supply, and they shall remain in position for the full duration of work.

d) Portable earths shall be applied to all phases and in such a manner as to prevent danger from residual charge or induced voltages.

e) Separate earths at the point of work shall be connected to create an equi-potential zone for all persons at the point of work. They may be moved during the course of the work.

f) Precautions shall be taken to prevent danger from voltages developed across earth conductors connected to earth at different points.

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00120OF420

Page 21: Safety Plan Program

Step 7 : Issue a permit to worka) Note: The permit to work is about control of the workplace and people. It is

a summary of the previous protective measures and hazards. It is also a clear statement of responsibility from the Nominated Person for these protective measures.

b) The Electrical Equipment to be worked on must be released for work through the issue of an electrical Permit to Work at the point of work. The Nominated Person issuing this is responsible for creating and maintaining the safe working area in accordance with 7 steps principles.

c) The permit to work shall contain clear, legible details of: The location of the work, and the precautions that have been taken to establish the safe working area. The scope of the work Hazards in the immediate area Completion of site risk assessment Completion of Safety Check sheet Signature of the Nominated Person in charge of the work party, times and

dates of issue and cancellation. Signatures of work party members

d) The Nominated Person in charge of the work party shall be responsible for the safety of his work area and all other persons in his work party regardless of seniority.

e) Warning signs and demarcation equipment is not to be removed until after cancellation or the issue of further safety documents.

f) The Nominated Person in charge of the work party shall be responsible for ensuring all persons and tools are withdrawn on completion of work, and hand over of the Electrical Equipment in proper condition according to the work undertaken.

g) Where the boundary of the safe working area changes during the course of the work, further permits to work must be issued.

15.3 Rules for working on or very near live Electrical Equipment

a) All work packages that require work on or very near live Electrical Equipment must have prior written approval from the local Service Unit manager, who must be satisfied that personnel have the appropriate skills to undertake the required task.

b) The rules in Sections 11.1 – 11.2 shall be followed where relevant.c) The risk assessment shall specifically evaluate whether the work can be

done dead or in some other way, and what additional special safety measures must be undertaken.

15.4 Switching

a) Note that switching includes insertion or withdrawal of a switching device.b) ABB service personnel may only undertake Switching operations with

specific written approval from the local Service Unit manager.

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00121OF420

Page 22: Safety Plan Program

c) Any person carrying out switching must have sufficient information and competence to understand the effect of that switching on the system, and potential danger to himself or others.

d) Switching must only be carried out by a person properly trained and authorised in writing, and who is familiar with the function and operation of the switchgear concerned.

e) Switching must be carried out in conjunction with the person in control of the system.

f) Appropriate personal protection equipment must be worn by personnel undertaking switching operation. At minimum flame retardant overalls, gloves and a safety visor must be worn.

g) Where possible remote switching shall be undertaken.

15.5 Work on, or very near, live conductors

a) Any work which cannot be done beyond the safe working clearances in Appendix 1 must be the subject of a special written procedure, and carried out by specially trained and authorised persons.

b) Work is considered ‘Live work’ when it comes within the Live zone distances in appendix 1, or if the work requires the removal of covers, doors or barriers to expose live conductors.

c) Work must only be carried out by a person properly trained and authorised in writing, and who is familiar with the function and operation of the Electrical Equipment concerned.

d) Appropriate personal protection equipment must be worn by personnel undertaking the work. At minimum flame retardant overalls, gloves and a safety visor must be worn.

15.6 Testing and Commissioning

a) Where it is necessary to carry out electrical tests on Electrical Equipment, the safe working area must be established by following steps 1 – 6 as described in Section 15.2, before being released for tests by a safety document, and earths removed.

b) The test area must be under the control of a suitably competent person and precautions taken to avoid electric shock as in step 4 in Section 15.2.

c) Additional warning signs and barriers must be used to protect other persons nearby from test voltages.

d) Work on Electrical Equipment shall only be done, or supervised, by a person competent to recognize danger and apply controls from: Live low voltage wires ac and dc Voltages arising from current transformers, protection, pilot cables and earths Primary power conductors at high or low voltage Interference with fully operational power systems Test equipment

15.7 APPENDICES

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00122OF420

Page 23: Safety Plan Program

NOTES ON USE OF APPENDICES

The following tables are for guidance only. They should be used as part of a thorough risk assessment.The tables have been derived from documents which contain much more detail.Where possible consult local standards, which may have different figures and methods of application.

15.7.1 APPENDIX 1

Minimum working clearance

The minimum working clearance is the minimum distance, in air, between a live exposed conductor, and any part of a person’s body, tool, conductor or apparatus that a person may be touching. The clearance must take into account the nature of the work and relative positions of the live conductor and the working area.Where work infringes this clearance then addition control measures should be implemented to maintain safety.

Where work infringes the live working zone then it shall be considered to be live work.

SystemVoltage

kV.

MinimumWorking

Clearancemm.

LiveWorking

Zonemm.

<1 700 20010 1350 35020 1400 40036 1580 58070 1900 900

132 3100 1100275 3800 1800480 5200 3200

(Source: EN 50110-1 NB. ‘Minimum working clearance’ is Dv; ‘Outer limit of vicinity zone’ and’ live working zone’ is ‘Minimum working distance Dc in this standard.)

15.7.2 APPENDIX 2

Minimum design clearances where power lines cross or are in close proximity.

These provide a useful guide when assessing the degree of risk from nearby power circuits. They do not take into account the additional risks of failure created by extreme weather conditions or poor condition of the equipment.

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00123OF420

Page 24: Safety Plan Program

The clearances are calculated for the upper conductor operating at its maximum likely temperature and the lower conductor at 25deg.C less. They must also allow for a maximum wind loading swing of 45deg.

* extrapolated

(Source: derived from UK spec. EATS 43-8)

15.7.3 APPENDIX 3

Minimum separation across point of disconnection in air

These are between open isolator blades, or disconnection between fixed points. Where separation is not fixed, such as overhead line spans, greater clearances will be required (see appendix 15.7.1 & 15.7.2). Consideration should also be given to other conditions which may bridge or degrade the insulation gap.

SystemVoltage

kV

Electrical clearance(Phase to earth)

mm.12 22924* 33036 43266 786

132 1473

----- Please Proceed to Next Page for Attachments References ----

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00124OF420

SystemVoltage

kV.

Minimum DesignClearance between

circuitsmm.

<1 100010 180024* 190036 200070 2300

132 2700275 3700480 4400

ATTACHMENT - A

Project Organization Chart

Page 25: Safety Plan Program

ATTACHMENT – B

Overall Project Schedule & S-Curve

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00125OF420

Page 26: Safety Plan Program

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00126OF420

ATTACHMENT – C

Injury Accident Report Forms

Page 27: Safety Plan Program

PERSONNEL INJURY / ACCIDENT REPORTReport No.:Date:

Name & Address of Contractor

: Job Site

Job No. / Contract No.

:

:

Name of the injured : RTE No. / Age :

Part of body injured : Nature of Injury :

Date / Time of accident : Place of accident :

Classification ofaccident

: Source of Injury :

First Aid treatment : Yes / No. Clinic or Hospital :

Safety Incharge Approval

: Customer Representative :

Immediate cause (S)Of Accident

:

Corrective actions taken :

Recommendations : Safety InchargeSignature

Site-in-chargeSignature

:

:

Contractor Name: ABB Service Co. Ltd.

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00127OF420

Page 28: Safety Plan Program

ATTACHMENT – DPreliminary Motor Vehicle Damage

Report Form

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00128OF420

Page 29: Safety Plan Program

CONTRACTOR’s PRELIMINARY MOTOR VEHICLE DAMAGE REPORT

DATE:

JOB NO. /CONTRACT NO:JOB TITLE

NAME OF CONTRACTOR / BUSINESS ADDRESS:

NAME OF DRIVERBADGE NO.

SAG DRIVING LICENSE NO. DATE / TIME & PLACE

ESTIMATED COST OF REPAIRINDICATE BY DIAGRAM WHAT HAPPENDED:

DESCRIPTION OF WHAT HAPPENED

CORRECTIVE ACTION TAKEN:

CONTRACT0R’S REPRESENTATIVE

__________________________ SIGNATURE:

LOSS PREVENTION’s RECOMMENDATIONS

SEC – 15235 (03/06)

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00129OF420

Page 30: Safety Plan Program

ATTACHMENT – EMonthly Injury / Damage Summary

Report Form

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00130OF420

Page 31: Safety Plan Program

MONTHLY INJURY / DAMAGE SUMMARY REPORT Date:

Name of Contractor

Job No./Contract No.

:

:

Month

Location / Site

:

:

Date/Time/Place of Accident

Details of Damage / Injury Immediate Causes of Damage / Accident

Estimated Cost of Damage

Corrective action

CONTRACTOR REPRESENTATIVE : Name Signature Date

Safety Incharge

Site-in-charge

:

:

Contractor Name: ABB Service Co. Ltd.

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00131OF420

Page 32: Safety Plan Program

ATTACHMENT - FEMERGENCY CONTACT NUMBERS FOR HOSPITALS, GOVERNMENT AGENCIES, & RENTED UTILITY

VEHICLE SERVICE

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00132OF420

Page 33: Safety Plan Program

Emergency Contact Numbers:

General

Traffic Accident 993Ambulance 997Fire Service 998Police 999Highway Special Security Force 996Mobile Phone Service 902Electricity: 933

Hospitals

Al Jazeera Hospital Hassan Bin Thabet Street, Naseem Dist 01 2313303

Al Faiha Medical Center - Riyadh Imam Ahmed Ibn Hanbal Street 012329513

Al Majd Medical Center Riyadh Hamza Bin Abdulmottaleb St. 014289631

Al Mashfa Medical Center Riyadh Arrawdah - 12 exit 012088585

Olaya International Clinic Riyadh Olaya Main Road 014641158

Salamatak Medical Center Riyadh Khureis Road 0504143702

Al Shomooly Clinic Riyadh Exit 5 014543232

Khalid Medical Clinic Riyadh Al Naseem Area 012365000

ABB

ABB Service Co. Ltd ABB Head Office, Riyadh 01 476 2644Project Manager Motasem Al-Khalayleh 054 158 2346Site Manager Hazhem Kharwash ###########

Safety Officer Fadi Al-Abkari 054 8876685

Project Engineer Daniel Cabasa 0502164907

Rent A-Car Services

Budget Rent A-Car Riyadh Branch +966(1)4054631

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00133OF420

Page 34: Safety Plan Program

ATTACHMENT – G

Safety Reports

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00134OF420

Page 35: Safety Plan Program

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00135OF420

Page 36: Safety Plan Program

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00136OF420

Page 37: Safety Plan Program

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00137OF420

Page 38: Safety Plan Program

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00138OF420

Page 39: Safety Plan Program

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00139OF420

Page 40: Safety Plan Program

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00140OF420

Page 41: Safety Plan Program

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00141OF420

Page 42: Safety Plan Program

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00142OF420

Page 43: Safety Plan Program

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00143OF420

Page 44: Safety Plan Program

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00144OF420

Page 45: Safety Plan Program

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00145OF420

Page 46: Safety Plan Program

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00146OF420

Page 47: Safety Plan Program

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00147OF420

Page 48: Safety Plan Program

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00148OF420

Page 49: Safety Plan Program

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00149OF420

Page 50: Safety Plan Program

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00150OF420

Page 51: Safety Plan Program

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00151OF420

Page 52: Safety Plan Program

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00152OF420

Page 53: Safety Plan Program

ATTACHMENT - H

PERMIT TO WORK/LIMIT OF ACCESS/SANCTION TO WORK (PTW/LOA/SOW)

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00153OF420

Page 54: Safety Plan Program

ATTACHMENT - I

Site Location Plan and Location of Fire Extinguishers

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00154OF420

Page 55: Safety Plan Program

ATTACHMENT - JBi-Weekly Site Safety Evaluation

Report Form

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00155OF420

Page 56: Safety Plan Program

BIWEEKLY SITE SAFETY EVALUATION REPORT

NAME OF CONTRACTOR: CONTRACT NO.:

NAME OF PROJECT SITE:

Report # For The Period From:

To:

INSPECTION CONDUCTED BY: RATING:

CONSTRUCTION SAFETY INSPECTION CHECKLIST

1 WORK SITE GENERAL: BIWEEKLY1 2

a) Safety posters / warning signs displayed *b) Weekly tool box meetings heldc) Safety training givend) Medical / First Aid facilitiese) Emergency Tel. Nos. postedf) Site work injury records being keptg) Sanitary/washing facilities adequate and cleanh) Drinking water suppliedi) Daily Tool Box meeting held

**

2 HOUSE KEEPING: BIWEEKLY1 2

a) Work area clean and tidyb) Waste containers provided and usedc) Regular disposal of wasted) Passage and walkways clear of obstructionse) Adequate lightingf) Projecting nails removed from timber

3 FIRE PREVENTION: BIWEEKLY1 2

a) Fire instructions posted / known by personnelb) Fire extinguishers permanently positioned / regularly checkedc) Good Housekeepingd) "NO SMOKING" sign posted and enforced where needed

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00156OF420

Page 57: Safety Plan Program

e) Adequate Fire extinguishersf) Proper typeg) Location

4 ELECTRICAL INSTALLATION (PERMANENT & TEMPORARY)

BIWEEKLY

1 2a) Adequate wiring, well insulated without tapped joints, bare wiresb) Fuses of circuit breakers providedc) Electrical danger signs postedd) Suitable fire extinguishers provided (Dry powder / CO2)e) Wiring / extension cords not creating tripping hazardsf) Wiring / extension cords correctly terminated with suitable outlets

5 POWER TOOLS: BIWEEKLY1 2

a) Good housekeeping where tools are usedb) Tools and cords in good condition and plugs fittedc) Mechanical safeguards in used) Correct tool being used for the job in hande) Personal protection equipment being worn

6 PERCUSSION CARTRIDGE FIXING TOOLS (Nail guns): BIWEEKLY1 2

a) Operator trained and qualifiedb) Tools checked and maintained in good working orderc) Tools being used of recommended materials onlyd) Tool being used at a safe distance from other persons

7 HAND TOOLS: BIWEEKLY1 2

a) Tool being used for its intended purposeb) Damaged tools repaired / replaced promptlyc) Regular inspection of conditiond) No site modification / fabrication of toolse) Proper storage safe carrying

8 LADDERS BIWEEKLY1 2

a) In good condition and inspected regularlyb) Set at correct angle and secured to prevent movementc) Extending to at least one meter above landing leveld) Fitted with anti-slip feete) Metal ladders not being used near electrical hazardsf) Step ladders fully open and locked out when in useg) Site-made ladders properly constructed from sound materials

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00157OF420

Page 58: Safety Plan Program

h) Condition of Laddres / staging i) Working platform of the staging are in good condition & inspectedj) Full body harness safety belt is used for all works at height

9 EXCAVATION: (N/A) BIWEEKLY1 2

a) Shoringb) Slopingc) Barriersd) Warning Signs / Warning Tapese) Lightsf) Egressg) Ingress

10 PERSONAL PROTECTIVE EQUIPMENT BIWEEKLY1 2

a) Adequate use of Safety shoesb) Adequate use of Safety Helmetsc) Adequate use of Glovesd) Adequate use of Eye protection tools (goggles, full face shield)e) Adequate use of Personal safety equipment

11 COMPRESSED GAS (N/A) BIWEEKLY1 2

a) Proper Storageb) Handlingc) Color Codingd) Condition of

cylinderse) Indentification

12 MATERIAL STORAGE YARD BIWEEKLY1 2

a) Proper Storageb) Hazard Indentification / warning signs.c) Adequate protection

13 CRANES/BUCKET TRUCKS/HEAVY EQUIPMENT/LIFTING DEVICES BIWEEKLY1 2

a) Safety Stickersb) SAG operators licensec) Overall condition

14 SITE SAFETY ADMINISTRATION BIWEEKLY1 2

a) Accident Reportingb) Safety Engineerc) Safety Meetingsd) Loss Prevention Program Implementation

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00158OF420

Page 59: Safety Plan Program

e) Work Permit implementationf) Safety Reports and Logs

OVERALL PERFORMANCE: Define the category (Average of the ratings) ***

A: EXCELLENT (90 - 100)B: GOOD (70 - 90)C: SATISFACTORY (50 - 70)D: UNSATISFACTORY (0 - 40)

RECOMMENDATIONS

Evaluated By: Agreed By:

Name NameGTSD Site Engineer ABB Safety EngineerDate: Date:

Note: Contractor to submit the Signed Bi-weekly Site Safety Evaluation reports alongwith the bi-weekly project progress reports

* Individual category in each group will be given a category in terms of A to D.** Average of each category will be given a appropriate rating for each group.*** Overall rating will be Total sum of each category./ 14

Recommendations from site engineer to be recorded for all unsatisfactory ratings.

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00159OF420

ATTACHMENT - KSamples of Safety Signage, as per SEC Safety Manual & ABB Code of

Practice

Page 60: Safety Plan Program

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00160OF420

ATTACHMENT - L

EMERGENCY EVACUATION PLAN

Page 61: Safety Plan Program

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00161OF420

ATTACHMENT - M

RISKS ASSESSMENT REVIEW

Page 62: Safety Plan Program

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00162OF420

Page 63: Safety Plan Program

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00163OF420

Page 64: Safety Plan Program

SITE SAFETY PLANDOCUMENT NO.PAGE NO.REV,

Replacement MVU Container (13.8kV) of A2 at PP8

EM-06916.00164OF420