SAUDI ARAMCO ID/PID - MAY-15-05 - REV 0 (Standards Cutoff - June 2008) REV 3 30-Jun-08
SAUDI ARAMCO INSPECTION CHECKLIST SAIC NUMBER DATE APPROVED QR NUMBER
Duct System Handling, Storage and Preservation SAIC-K-4011 15-Dec-09 HVACPROJECT TITLE WBS / BI / JO NUMBER CONTRACTOR / SUBCONTRACTOR
EQUIPMENT ID NUMBER(S) EQUIPMENT DESCRIPTION EQPT CODE SYSTEM ID. PLANT NO.
LAYOUT DRAWING NUMBER REV. NO. PURCHASE ORDER NUMBER EC / PMCC / MCC NO.
SCHEDULED INSPECTION DATE & TIME ACTUAL INSPECTION DATE & TIME QUANTITY INSP. MH's SPENT TRAVEL TIMESAUDI ARAMCO USE ONLY
SAUDI ARAMCO TIP NUMBER SAUDI ARAMCO ACTIVITY NUMBER WORK PERMIT REQUIRED?
SAUDI ARAMCO INSPECTION LEVEL CONTRACTOR INSPECTION LEVEL
ACCEPTANCE CRITERIA REFERENCE PASS FAIL N/A RE-INSP DATE
A1
REFERENCE DOCUMENTS:
1-Schedule "Q" Saudi Aramco Quality Requirements
Contractor / Third-Party Saudi Aramco
Name, Initials and Date:Work is Complete and Ready for Inspection:
Name, Initials and Date:T&I Witnessed QC Record Reviewed Work Verified
QC Inspector PID Representative
Name, Initials and Date:Performed Inspection Work / Rework May Proceed
Name, Initials and Date:T&I Witnessed QC Record Reviewed Work Verified
QC Supervisor Proponent and Others
Name, Sign and Date: Quality Record Approved: T&I Witnessed QC Record Reviewed Work Verified
*Person Responsible for Completion of Quality Work / Test Y = YES N = NO F = FAILED
ITEM No.
Verify that approved procedures for handling, storage and preservation lists all the required inspection schedules for maintaining the quality of the followings:
a) Metal Ducts
b) Duct Hangers and Supports
c) Duct Insulation
d) Air Terminal Devices
e) Fire Dampers
f) Duct Accessories( Duct Heaters, Volume Dampers, etc)
Schedule " Q"Section 5, ATT. IV