Page 1: SANER TANJU ATIS_MMS

1

INDUSTRIAL PROJECTS......

STRATEGIC APPROACHES TO MATERIAL MANAGEMENT SYSTEM AT SITE

CONFIDENTIAL – Saner Tanju ATIS

Page 2: SANER TANJU ATIS_MMS

2

  1 -What is the Strategic Material Management

System at Site? 2 -Why is it important? 3 -Strategic MMS analysis at Site 4 -Principles of Warehouse design 5 -Essentials Symbols for handling and storage 6 -Receipt and Incoming Stages Inspection Flow Inspection of Incoming Process- IIP What constitute a material deviation ? 7 -Objectives of the MTC – Material Test

Certificates 8 -Storage – a Pillar of Category Process 9 -In-Warehouse Preservation – Improving the

work Methods 10-Proven Issue methods – LBID Cycle 11-Question /ClosingCONFIDENTIAL – Saner Tanju ATIS

AGENDA

Page 3: SANER TANJU ATIS_MMS

3

What is the Strategic Material Management System at Site?

Scientific technique, Concerned with planing, Organizing & Control of flow of ..

... Good Overview, Comprehensive view of Inventory

...A well- organized design on effective stores layout

...Enhance performance to support operations......

...To consolidate and efficiently handling process...

...Safety, Knowledge and Data transfer...

...Quality control is integral to the continuing of operation..

Ability to anticipate needs, forecast

conditions, set goals and standarts, plan and schedule work and measure results.

 

CONFIDENTIAL – Saner Tanju ATIS

Page 4: SANER TANJU ATIS_MMS

4

Why is MMS important at site?

Support us organisation’s strategic and complimantary planing at site

Increase ability of workforce to utilize operations bases

Creates and enable a learning , sharing and focus an practical application

Quality and technical skills improvement.

Improved internal teamwork and communication

Streamlined our work for better time and business process

Focuses on making changes to simplify and become more efficiency

CONFIDENTIAL – Saner Tanju ATIS

Page 5: SANER TANJU ATIS_MMS

5

STRATEGIC MMS ANALYSIS at Site

Transportation

- Review

- Needs

-Time Period

- Knowledge Transfers

Observed Shipment Data

Selection Criteria

- Detect lists

- Classify

- Internal & Exter.

Communications

Observed Packing

Analysis

Handling Plan

- Indivudual materials group

- Storage objective

- Storage strategies

Planning

Management Plan

- Procedures

- Instructions

- Training

Planning

Organ.Chart

- People/ Positions

- Seperate disciplines

- Workforce Planing

Observed Data Analysis

Action Plan

- Analysis Prioritize

- Review plan

- Execution planPlaning

Strategic Action View

Strategic Look-ahead View

SUCCESS

CONFIDENTIAL – Saner Tanju ATIS

Page 6: SANER TANJU ATIS_MMS

6

Principles Of Warehouse design

Scope of Work ; Storage instructions based on materials

specifications and manufacturers instruction .......Take over facilities for warehouse and

site store ......... Type, condition,number of

facilities Temporary site facilities arrangement

..... location of quarantine store, clear separation

Technical specification for warehousing .... .Materials handling

details,organizing principals ........Organize storage areas in

compliance with storage instructions ...........Designation of storage areas by

categories(open air, covered,with air-conditioning, etc)

Install computer hardware and software

CONFIDENTIAL – Saner Tanju ATIS

Page 7: SANER TANJU ATIS_MMS

7

The factors elements

The Factors affecting

warehouseOrganisation

Safety Measures

Order Volume

Material Specificati

onsData

Tracking System

The scope of items supplied

Equipments

CONFIDENTIAL – Saner Tanju ATIS

Page 8: SANER TANJU ATIS_MMS

8

- Type Of Storage (TOS)=A + B + C + D- A=The Scope of items Supplied- Piping, Electrical, Equipments, Steel Structures- B=Material Specifications- Instructions Specified by Manufacturers- C=Order Volume- Project Material Orders (Acc.. BOQ)- D=Safety Measures- Detrimental Conditions (by moisture,rain, snow,sandstorm,insects),dirt(by

bird droppings,dust,tar), static and dynamics load.- Closed Area TOS

Open Area With Fence,

Without Fence,Roofed

CONFIDENTIAL – Saner Tanju ATIS

Lockable, Air condioned,

Dry

Page 9: SANER TANJU ATIS_MMS

9

Features of Database System for Material Handling

Material cataloque and part list of ısometrics

Filter functions Import record of order data Scheduling in advance Storage areas and material Certificate Material receving on site Storage list Material reservation (Piping) and

material issuing

CONFIDENTIAL – Saner Tanju ATIS

Page 10: SANER TANJU ATIS_MMS

10

Material handling process

CONFIDENTIAL – Saner Tanju ATIS

HEAD OFFICE

Page 11: SANER TANJU ATIS_MMS

11

Material Work Flow

WAREHOUSE

CONFIDENTIAL – Saner Tanju ATIS

Page 12: SANER TANJU ATIS_MMS

12

Essentials Symbols for handling and storage

The Symbols for handling storage marked on the packages and equipment items in accordance with EN ISO 780 should be observed. Symbols for the handling of equipment

• 1 = This is up• 2 = Fragile, handle with care• 3 = Keep dry • 4 = Keep away from heat 1 2 3 4

5• 5 = Use no hooks• 6 = Centre of gravity• 7 = Sling here • 8 = No hand truck here • 9 = Clamp here 6 7 8 9

10• 10 = Do not use fork lift truck here • 11 = Roofed storage• 12 =Storage in closed rooms• 13 =Storage at ambient temperature of >0 • 14 =Storage in air condition 11 12 13 14

CONFIDENTIAL – Saner Tanju ATIS

Page 13: SANER TANJU ATIS_MMS

13

Lifting and Slinging gear

ROPES

SHACKLES

CROSS BEAMS

CHAINS

CONFIDENTIAL – Saner Tanju ATIS

Page 14: SANER TANJU ATIS_MMS

14

Receipt and Incoming Stages•

Tasks Content Result Inspect incoming materials,

check for damage, completeness and compliance with delivery documents and speciation’s as well as data transferred

Mark any damaged materials, transfer to quarantine store

Prompt and coordinate corrective action, e.g. inspections by transport insurance company, repair work

Implement storage instructions correctly

Prompt any additional preservation or special measures and document in accordance with regulations (e.g. continuous inerting, turning of shafts, etc.)

Any damage, incomplete delivery, variance from delivery specification

Type of damage, planned measures if any

Detailed description of damage, detailed description of planned repair work, etc.

Specification of storage location and characteristics, measures in case of emergency (failure of HVAC)

What measures when and how often – times, duration, tests

Notification of receipt of material, damage report, NCR, certificate filing

Quarantine store status

Inspection log, repair procedure, repeat order

Database stroge list, special instructions

Preservation and special measures log

CONFIDENTIAL – Saner Tanju ATIS

Page 15: SANER TANJU ATIS_MMS

15

Port

Transport Agent

Loaded On Truck

LOT

Receipt Of

PackageUnpacked Reports

Checking the packing for damage during the Ship Checking the outside packing for damage during transport to site

Checking the packing lists against the number of packages received, Checking the outside packing for damage, Checking the inside packing (e.g. welded plastic sheets) for damage, Checking damaged packages for completeness and damage to the contents, Checking any protective inert-gas fillings.

Essential Reports

(MRR,etc..)

Checking the contents for completeness,

Checking the outer condition of the

indivudual components.

(e.g. corrosion protection, preservation),

Checking the technical details

Project site

Inspection Flow

CONFIDENTIAL – Saner Tanju ATIS

Page 16: SANER TANJU ATIS_MMS

16

Inspection of Incoming Process IIP – Specific Projects Materials

• checking for damage in transit, • checking the accessories (gaskets, bolts, etc.) supplied for completeness and correctness

• checking the material for completeness, • checking the material for being undamaged (damage in transit), • visual inspection for compliance with the technical specification (e.g. sealing faces, supporting surfaces of bolts, welding edges, etc.), • checking for correct stamping, coding, batch number and compliance with certificate, • checking the marking of valves, • dimensional checking (mating dimensions, wall thickness, weld edge preparation, thickness of flanges, bolt holes, roundness),

• checking the name plate data for compliance with the purchase order specification, • comparing the characteristic data of the material supplied with the data sheets, • checking the material for being undamaged (damage in transit), • checking for completeness, especially the accessories.

• Sensitive Materials• checking the package properly

Equipment & Steel

Structures

Piping Materials

Electrical & Instrumentat

ion

Fragile, Others

IIP

CONFIDENTIAL – Saner Tanju ATIS

Page 17: SANER TANJU ATIS_MMS

17

What Constitutes a material Deviation ?

Deviations

Overage Damage Hold Rejection

Shortage

Deficiency Report Dimensional Technical Specification Elimination of Defects Faulty Assembly CONFIDENTIAL – Saner Tanju ATIS

Page 18: SANER TANJU ATIS_MMS

18

Objectives of the Material Test Certificates

Tasks Content Result Create filing system for

certificate management

Check incoming certificates for correctness and completeness and completeness, and enter in Database

Initiate and expedite corrective measures

Put material with no or incorrect / incomplete certificates in quarantine store

Classification, structure

Checklist based on check criteria

Type of corrective action, critical deadlines

Reason why certificates are not O.K., name of material

Certificate management in Database

Updates incoming materials log

Correspondence

Quarantine store status

Correspondence

CONFIDENTIAL – Saner Tanju ATIS

Page 19: SANER TANJU ATIS_MMS

19

A control necessary to meet the control objectives is available or...

Identified material and Match with Test Certificates to ensure..

Material Safety Data Sheet (MSDS),Chemical and Hazardous Materials

.... Work place safety .... Physical and chemical datas ..... Storage and handling informations

Item Code (Part No)

ASTM Standart

DimensionHeat Number

90 Degree Elbow CONFIDENTIAL – Saner Tanju ATIS

Face the Fact

Page 20: SANER TANJU ATIS_MMS

20CONFIDENTIAL – Saner Tanju ATIS

Page 21: SANER TANJU ATIS_MMS

21

Storage – a Pillar of Category Process

...............Technical SpecificationThe individual groups of components must be characterized by boards, marked with

part number, dimensionand material.Technical International Standarts.Stored in accordance with the technical specification...................Implement Instruction (Vendor)In accordance with the manufacturer’s instructions either outdoors,indoors, in cooled or

in dry rooms.Material Data Sheet instruction to be followed.......................Safety and Security RegulationsSafety regulations for chemicals and dangerous materials should be applied.The products which would be damaged through exposure from sunlight should be

protected by adequate covers or stored indoors.Adequately protected and guarded against theft, pilferage,fire.........................Segregation (Storage Profiles and Layouts)External and internal storage areas (aisles,bin,section,yard plots etc.) should be clearly

defined and identified with appropriatestorage location sign as per material storage plan.Designated Area in the basis of Unit Process.............................TraceabilityIdentify Locations data transfer to material Tracking system.Completeness of the information for every step in a process.Refers to the capability to gain materials in the timely manner.Monitor and issued “first come-first go” basis..

CONFIDENTIAL – Saner Tanju ATIS

Page 22: SANER TANJU ATIS_MMS

22

Storage – Creating a Plan to achieve your goals !

Anticipation to deliveries schedule for priority plan

Make a adequate reserve place of estimated capacity for materials

Knowledge sharing with team,information, Skills, or expertise

Build and Organize , motive your team to get to do deliveries and storage conditions

CONFIDENTIAL – Saner Tanju ATIS

Page 23: SANER TANJU ATIS_MMS

23

Open area (Laydown)

CONFIDENTIAL – Saner Tanju ATIS

Page 24: SANER TANJU ATIS_MMS

24

Piping componentsPipes, spools, fittings, elbows, flanges and valves.

stored outdoors on timber baulks of approx. 150 mm thickness or on timber pallets.

Flange faces shall not be damaged.Pipes may be stacked to a height of approx. 1.5 m if properly secured.In the case of pipes . DN 500, only two pipes should be stacked one

upon the other.

Equipment & Vessels, Steel StructuresdcsSteel structures, vessels, machinery, and the like should be stored outdoors on

timber baulks of approx. 150 mmthickness. Placing the equipment on unprotected, bare, or machined surfaces as

well as on flanges is notpermitted. Care shall be taken not to damage nozzles, shaft ends, or other

protruding parts.

Electrical & InstrumentationTransformers for outdoor service, cable supports, cable drums and

sectional steel for fixtures may be stored outdoors.Other electrical, measuring and control equipment should be stored in dry

and well ventilated rooms on timber pallets or on shelves.Instruments shall be stored on shelves. The original packing shall only be

removed at the place of installation.

CONFIDENTIAL – Saner Tanju ATIS

Storage – Individual Stock

Page 25: SANER TANJU ATIS_MMS

25

. Rubber-lined equipment and plastic equipment

shall be stored with special care.The temperature within rubber-lined equipment should

not drop below -10oC if the hardness of therubber lining is > 75 Shore D and not below -20oC if the hardness of the rubber lining is < 75 Shore D Coating materials shall be stored at temperatures between 5 C and 30 C in dry and well ventilated rooms.

Bricks (for refractory linings), Polyester resins

Solvents, fuels, lubricants, and corrosive chemicals

Oils and insulating fluids

CONFIDENTIAL – Saner Tanju ATIS

Storage – Individual Stock

Page 26: SANER TANJU ATIS_MMS

26

Matrix for Storing Facilities and Locations

SN ItemInside the warehouse

Out Side the warehouseAir Condition No Air Condition

1 Steel Plates, Shapes, Fittings, etc < 4” Fitting > 4”

2 Materials with Machined Parts <4” Remaining

3 Valves <4” >5”4 Gaskets, O-rings, bolts and nuts ü 

5 Welding Wires and Electrodes ü 

6 Paints and adhesives As per MSDS NA7 Insulation and Refractory

ü 

8 Machinery and Equipments ü 

9

Civil Materials sands, Mortars, Cement Aggregating

As per MSDS

10 Architectural Material ü  ü 

11 Anchor Bolts ü 

12 Electrical and InstrumentationAs per instruction Measuring Equipment,Switch

Board,Distrubution board,Contol Panel,Instrument Tubes

Transformer, cable,Supports,Cable Drum and steel structure

CONFIDENTIAL – Saner Tanju ATIS

Page 27: SANER TANJU ATIS_MMS

27

In-Warehouse Preservation – Improving the work Methods

Create a preservation communication and

application plan Make an Assessment, Classified group of

materials, safety regulations Establish priorities, Designated Storage

areas,Preservation team for tasks.. Identified needed resources, vendor specific

documents,Manufacturers Instructions Identify short and long term activities, storage and

maintenance duration Develop a strategy to increase preservation,

enhance performance result of implementation Application of preservation agents instructions ( e.g.

Table.1..),recommendations Tracibility of Preservation Matrix, Requirements,

Interval, Referance documents,Storage areas Execution at site, Labeling – Job Card and

RecordingCONFIDENTIAL – Saner Tanju ATIS

Page 28: SANER TANJU ATIS_MMS

28CONFIDENTIAL – Saner Tanju ATIS

In-Warehouse Preservation – Preservation Recommendation

Page 29: SANER TANJU ATIS_MMS

29CONFIDENTIAL – Saner Tanju ATIS

In-Warehouse Preservation – Regular Checking Period

Page 30: SANER TANJU ATIS_MMS

30

After BeforeCONFIDENTIAL – Saner Tanju ATIS

KEEPME

CLEAN

Page 31: SANER TANJU ATIS_MMS

31

Proven issue Methods

Issue starts and an ongoing with engaged the project time schedule

Compliance of essential circumstances to issue

Indivudal groups materials

Return, Take back to Store

LBID Cycle – Journey to Movement........ From our initial engagement with all

movements to the end of Material journey to adhere to the stipulated time for Individual Projects.

CONFIDENTIAL – Saner Tanju ATIS

Page 32: SANER TANJU ATIS_MMS

32

Proven issue Methods - LBID CYCLE

Delivery + Order

Piping – Prefabrication

Piping - Erection

Isometric -Reservation

Pipes, Fittings....

Isometric -Reservation

Valves, Bolts,Gaskets...

MTC- MSDS

Availablity

Inspection

AUTHENTICATED

REALIZE

ASSURE

Equipment

Electrical

Equipment, Others

E + IE + I

Equipment, Others

Breakthrough

Incremental

Lean

Decisive

Piping - Erection

Commissioning

Recycling

CONFIDENTIAL – Saner Tanju ATIS

Page 33: SANER TANJU ATIS_MMS

33CONFIDENTIAL – Saner Tanju ATIS

% 55 Piping > % 20 Eqp. + % 15 Elec.

% 55 Eqp > % 30 Piping + % 20 E+I

% 65 E+I > % 25 Eqp. + % 15 Piping

1

23

% 58 E+I > Eqp % 40 Eqp > Piping

% 75 E+I > Piping

Proven issue Methods – Variable Rates

Page 34: SANER TANJU ATIS_MMS

34CONFIDENTIAL – Saner Tanju ATIS

55

30

50

25 20 15

65

%

.

.

.

.

. .

. .

Zone 1 3 2

.

End Line Initial Line

Eqp. P

E+I

Proven issue Methods - Progress Zone Coordinates

Z1

Z2

Z1 > Z2

Page 35: SANER TANJU ATIS_MMS

35CONFIDENTIAL – Saner Tanju ATIS

Required Ordered Delivered Issued0

2000000

4000000

6000000

8000000

10000000

12000000

14000000

16000000

18000000

PipingEquipmentE+IOthers

Required Ordered Delivered Issued

Piping 2800000 2950000 1416707 1042755

Equipment 15000000 15500000 10500000 6570000

E+I 10500000 7560000 5470000 3260000

Others 1500000 1650000 1100000 950000

Kg

Sample - Cycle of Project Materials

Kg

Page 36: SANER TANJU ATIS_MMS

36CONFIDENTIAL – Saner Tanju ATIS

MIF- Material Issue Form

Page 37: SANER TANJU ATIS_MMS

37

MMS – Closing

......Facilitate having good inventory improve the efficiency organization

.........Organizational goal settings

.............Additional strategic planning initiatives

.................Evaluation of correct performance indicators

Development of additional internal and external performance measures for the Organization

Building an integrated Warehousing system It is an integrated process that demands integrated

processes and databases to become truly effective. The need for sharing processes and databases

throughout the entire organization Additional education and employee empowerment

lead to increased job satisfaction and personal performance

CONFIDENTIAL – Saner Tanju ATIS

Page 38: SANER TANJU ATIS_MMS

38

MMS – Closing

Open Discussion

Questions

Saner Tanju

ATIS

[email protected] – Saner Tanju ATIS