sap releasewechsel auf erp 6.0 unter komplexen bedingungen matthias gramm-schwarze / continental ag
TRANSCRIPT
SAP Releasewechsel auf ERP 6.0 unter komplexen Bedingungen
Matthias Gramm-Schwarze / Continental AG
MySAP ERP Upgrade – Matthias Gramm-Schwarze 2
MY SAP ERP Upgrade 22.01.2009Agenda
1. Project Scope
2. Involved SAP system environment
I. WAMOS (WArehouse Management and Optimization System)
II. TEMPO (Tire Enterprise Migration and Process Optimization)
III. PP (Production planning system)
3. Realization
4. Challenges & Highlights
5. Questions & Answers
MySAP ERP Upgrade – Matthias Gramm-Schwarze 3
MY SAP ERP UpgradeRequirements 1/2
Parallel projects has to be accomplished
Parallel projects has to be realized before and right after the going live dates.
Synchronization of development activities, based on different releases and (non-)unicode platforms.
Synchronize IT teams to one global team
Some local requirements had been done by local teams
Country / Company code specific testing has to be covered.
Reduce overall downtime to a minimum
All downtime relevant upgrade and unicode conversion activities has to be reduce to a minimum.
Realization of combined upgrade and unicode conversion (CUUC) for two SAP system environments
Start release SAP ERP 4.6C, without Unicode (UC), based on MDMP implementation
Target release ECC 6.0 with UC (technical upgrade!)
MySAP ERP Upgrade – Matthias Gramm-Schwarze 4
MY SAP ERP UpgradeRequirements 2/2
Going Live has to be accomplished with negative impacts to business process
Specially the following month / year end activities
Cross-system processes / Interface management
Project must be in time and in budget
In time realization was absolutely necessary due to dependencies to following project go live dates, specially at 1rd of January 2009.
MySAP ERP Upgrade – Matthias Gramm-Schwarze 5
Global Footprint: System WAMOS (SAP R/3)
Europe, part I
Herstal / RF/RDCAachen / PWHKorbach / RDC/PWHAskim RDCJarqlund / RDCEspoo / RDCGislaved / RDCWarschau / RDCIsernhagen / RFStöcken / SLSOtrokovice / RF/PWHTraiskirchen / RDCTimisoara / PWHStraubing / RF/EDCSacalacz / RDCUlm / RF/RDCRome / RDCSomaglia / RDCGrans / RDCMadrid / RDC----------------Total 20
Russia
Moskau / RDC
NAFTA
Gainsville / DCColumbus / DCCharlotte / PWHTexcoco / DCSan Louis Potosi / PWHMonterey / DCOntario / DCMt. Vernon (RF) / PWH-----------Total 8
Texas / DC (scheduled)Canada / DC (scheduled)
Brazil
Jundai / DCCamacari / PWH---------------------Total 2
Asia Shanghai / RDCAlo Setar / RDCMY-East / RDCMY-North / RDCMY-KO / RDCMY-KC / RDCMY-South / RDCMY-PJ / PWHMY-Central / RDCAS-Exessive / PWH---------------------------Total 10
South Africa
Johannesburg / DCCape Town / RDCDurban / RDCPort Elizabeth / PWH/RDC---------------------Total 4
Europe, part II
Lisboa / RDCLousado / PWHNeuendorf / RDCMer / RDCSarreguimine / RDCClairoix / RDC-----------------------Total 6
MySAP ERP Upgrade – Matthias Gramm-Schwarze 6
Upgrade WAMOSBasics
D054.6C
Q064.6C
Q054.6C
P064.6C
P054.6C
0 weeks 29 weeks-16 weeks
EU / Africa
NAFTA / Asia
Codepages (MDMP): 7( 1100 / 1401 / 1500 / 1610 / 8000 / 8300 / 8400 )Installed languages: 21( DE, EN, ES, FR, NL, SV, FI, PT, DA, NO / PL, CZ, SK, RO, HU / RU / TR / JA / ZH / ZF )
MySAP ERP Upgrade – Matthias Gramm-Schwarze 7
Upgrade WAMOSProject landscape
D056.0
Q066.0
Q056.0
P064.6C
P054.6C
Temp. Transport
Temp. Transport
0 weeks 29 weeks-16 weeks
X054.6C
Y054.6C
Y064.6C
Z066.0
Z056.0
EU / Africa
NAFTA / Asia
S056.0
MySAP ERP Upgrade – Matthias Gramm-Schwarze 8
Global Footprint: System TEMPO (SAP R/3)
Europe Sales Companies
GermanyBelgiumFranceItalySpainPolandHungaryPortugalAustriaSwitzerlandCzech RepublicFinlandSwedenNorwayDenmarkUnited KingdomRumaniaRussia----------------Total 20
Europe Plants
Slovakia 1Germany 3France 2Portugal 1Austria 1Czech Republic 1Romania 1------------------------------------------Total 10
Europe: 4500 UserAmerica: 1300 UserAsia: 300 UserAfrica: 200 User----------------------Total ~ 6300 User
NAFTA
SalesUSCANMexico------------Total 3
PlantsUS Charlotte
Mount VernonAldora
Mexico SLP ----------Total 4
Brazil Sales JundaiPlant Camarcari Total 2
Asia Sales China
TaiwanMalaysia
Plant Petaling Jaya
Malaysia Alor SetarAlor Gajah
Technology Centre Total 7
South Africa
Sales PEPlant PE 2
MySAP ERP Upgrade – Matthias Gramm-Schwarze 9
Upgrade TEMPOBasics
0 weeks 29 weeks-16 weeks
Codepages (MDMP): 7( 1100 / 1401 / 1500 / 1610 / 8000 / 8300 / 8400 )Installed languages: 21( DE, EN, ES, FR, NL, SV, FI, PT, DA, NO / PL, CZ, SK, RO, HU / RU / TR / JA / ZH / ZF )
D504.6C
Q504.6C
Q514.6C
Q524.6C
P504.6C
P514.6C
P524.6C
Temp. Transport
Temp. Transport
Asia
Europe / Africa
NAFTA
MySAP ERP Upgrade – Matthias Gramm-Schwarze 10
Upgrade TEMPOProject landscape
D506.0
Q506.0
Q516.0
Q526.0
P504.6C
P514.6C
P524.6C
X504.6C
Y514.6C
Temp. Transport
Y524.6C
Temp. Transport
Y504.6C
Z516.0
Temp. Transport
Z506.0
Z526.0
0 weeks 29 weeks-16 weeks
Asia
Europe / Africa
NAFTA
S506.0
MySAP ERP Upgrade – Matthias Gramm-Schwarze 11
MY SAP ERP UpgradeTiming
1. Preparation Phase
2. PP upgrade
3. Upgrade/Unicode
• D50 / D05
• Q51 / Q52 / Q06
• Q50 / Q05
4. BAT 1 Test IT /CKU
5. BAT 2 Central (US / Europe / Asia)
6. BAT 3 Local (US / Europe / Asia)
7. Go Live US / AS
8. Go Live Europe
Project milestones 01/08 01/0905/08 06/08 07/08 08/08 09/08 10/08 11/08 12/08
“Thanks Giving”
Hard
Frozen
Zone
“P20 upgrade”
“Christmas”
“Week 42 + 43”
“Week 35”
“Week 31 + 32”
Q-Systems available
Going Live dates
MySAP ERP Upgrade – Matthias Gramm-Schwarze 12
Upgrade TEMPO Phase 0: Upgrade / Unicode Preparation
D504.6C
Q504.6C
Q514.6C
Q524.6C
P504.6C
P514.6C
P524.6C
Transport
S504.6C
PREPAREUpgrade to 6.0SPDD/SPAUUC-Tools availableUC-Preparation
Z-Programs
0 weeks 29 weeks
System Copy
MySAP ERP Upgrade – Matthias Gramm-Schwarze 13
Upgrade TEMPO Phase 1: Implementation X50 & Upgrade D50
D506.0
Q504.6C
Q514.6C
Q524.6C
P504.6C
P514.6C
P524.6C
X504.6C
PREPAREUpgrade to 6.0SPDD/SPAUUC-Tools availableUC-PreparationZ-ProgramsUC-Migration∆ - Customizing
S506.0
Temp. Transport
-16 weeks 0 weeks 8 weeks 29 weeks
System copy
MySAP ERP Upgrade – Matthias Gramm-Schwarze 14
Phase 1: Upgrade D50Activities regarding temporary D-system
Soft Frozen ZoneMay 17th until Nov 9th Select ‘X50_TRANPORT’ from the attribute value list:
MySAP ERP Upgrade – Matthias Gramm-Schwarze 15
Phase 1: Upgrade D50Activities regarding temporary D-system
Soft Frozen ZoneMay 17th until Nov 9th Then add the X50 transport request number to the value field:
If multiple transport requests have been created in X50 for the same object, they can be combined into one new transport in D50 with the latest status. To have a complete overview in D50 you should add all related X50 transport numbers to the D50 transport ( each transport request number as a separate entry in the attributes ! )
Don’t forget to save the entries you made
All ‘doubled’ X50 transport requests in D50 have to be released and will be transported to Q5x and P5x once the new ECC 6.0 systems are available ( even though the original X50 transport has already been sent to the ‘old’ P50 ! ) in order to have all systems in sync.
MySAP ERP Upgrade – Matthias Gramm-Schwarze 16
Upgrade TEMPO Phase 2c: Upgrade Q-Systems
D506.0
Q506.0
Q516.0
Q526.0
P504.6C
P514.6C
P524.6C
X504.6C
Y514.6C
Temp. Transport
Y524.6C
Temp. Transport
Y504.6C
PREPAREUpgrade to 6.0SPDD/SPAUUC-Tools availableUC-PreparationZ-ProgramsUC-Migration∆ - Customizing
-16 weeks 0 weeks 26 weeks 29 weeks
S506.0
MySAP ERP Upgrade – Matthias Gramm-Schwarze 17
Upgrade TEMPO Phase 2c: Upgrade BATs (Business Acceptance Test 3)
D506.0
Q506.0
Q516.0
Q526.0
P504.6C
P514.6C
P524.6C
X504.6C
Y514.6C
Temp. Transport
Y524.6C
Temp. Transport
Y504.6C
TESTING:
- Participants: ~ 430 people (Business-Keyuser + IT)
- Locations: Charlotte (NC), Vienna (A), Hanover (D), Lousado (PT), Kuala Lumpur (MY), Jundai (BR), SLP (MEX)
- Tool: SAP Solution Manager
- Test cases: ~ 100.000 (nearly 2000 cases x 50 companies)
-Result: Business sign off !!!
-16 weeks 0 weeks 26 weeks 29 weeks
Begin hard frozen zone, right after sign-off.
MySAP ERP Upgrade – Matthias Gramm-Schwarze 18
Upgrade TEMPO Phase 3b: Performance Tuning, e.g. P52
D506.0
Q506.0
Q516.0
Q526.0
P504.6C
P514.6C
P524.6C
X504.6C
Y514.6C
Temp. Transport
Y524.6C
Temp. Transport
Y504.6C
Z516.0
Temp. Transport
Z506.0
Z526.0
PREPAREUpgrade to 6.0SPDD/SPAUUC-Tools availableUC-PreparationZ-ProgramsUC-Migration∆ - Customizing
UC runtime optimization
Temp. Transport
0 weeks 23 weeks 29 weeks-16 weeks
MySAP ERP Upgrade – Matthias Gramm-Schwarze 19
Upgrade TEMPO Phase 4b: Upgrade NAFTA / ASIA
D506.0
Q506.0
Q516.0
Q526.0
P504.6C
P516.0
P526.0
X504.6C
Y514.6C
Y524.6C
Y504.6C
PREPAREUpgrade to 6.0SPDD/SPAUUC-Tools availableUC-PreparationUC-DecisionsUC-Migration∆ - Customizing
Temp. Transport
0 weeks 26 weeks 29 weeks-16 weeks
PREPAREUpgrade to 6.0SPDD/SPAUUC-Tools availableUC-PreparationUC-DecisionsUC-Migration∆ - Customizing
MySAP ERP Upgrade – Matthias Gramm-Schwarze 20
Upgrade TEMPO Phase 4c: Upgrade Europe
D506.0
Q506.0
Q516.0
Q526.0
P506.0
P516.0
P526.0
X504.6C
Y514.6C
Y524.6C
Y504.6C
PREPAREUpgrade to 6.0SPDD/SPAUUC-Tools availableUC-PreparationUC-DecisionsUC-Migration∆ - Customizing
29 weeks-16 weeks 0 weeks
MySAP ERP Upgrade – Matthias Gramm-Schwarze 21
2
14
MY SAP ERP UpgradeGoing Live Timing: Asia and Americas
Friday, 28th of Nov 2008 Sunday, 30th of Nov 2008 Monday, 1st of Dec 2008
22 UTC !!!
M1
P1
15 18
P2
M2
24 3
P3 P4
14
P7P6
4
P5
9
P8
M3 M4
22 UTC !!!
P1
15 18
P2
20 22
P3 P4
5
P7P6
13
P5
24
P8
22 UTC !!!
M1
P1
15 18
P2
M2
23 1
P3 P4
8
P7P6
22
P5
3
P8
M3 M4
M1 M2 M3 M4
Begin of downtime for ALL systems
P06
P51
P52
System unavailability
18
Restore/Recovery duration to 4.6C
Saturday, 29th of Nov 2008
Offline Phases - Px:P1 - Conti specific upgrade preparationP2 - ECC 6.0 upgradeP3 - UC - preparationP4 - UC - exportP5 – UC - Schema implementationP6 – UC – importP7 - Post UC activitiesP8 - Conti specific post upgrade activities, incl. BAT4
MySAP ERP Upgrade – Matthias Gramm-Schwarze 22
IT team: coming together H - HQ
23
24
MY SAP ERP UpgradeGoing Live Timing: Europe
Wednesday, 24th of Dec 2008
Thursday, 25th of Dec 2008
Friday, 26th of Dec 2008
12 UTC !!!
M1
P1
Release of ECC 6.0Begin of downtime
Saturday, 27th of Dec 2008
10 13
P2
M2
18 20
P3 P4
5
P7P6
13
P5 P8
M3 M4
14
Sunday, 28th of Dec 2008
13
M5
15
P9
812 UTC !!!
M1
P1
5 8
P2
M2
19 1
P3 P4
13
P7P6
3
P5 P8
M3 M4
14 13
M5
15
P9
P05
P50
3
System unavailability Restore/Recovery duration to 4.6C
Buffer
Buffer
8
8
Offline Phases - Px:P1 - Conti specific upgrade preparationP2 - ECC 6.0 upgradeP3 - UC - preparationP4 - UC - exportP5 – UC - Schema implementationP6 – UC – importP7 - Post UC activitiesP8 - Conti specific post upgrade activities, incl. BAT4
MySAP ERP Upgrade – Matthias Gramm-Schwarze 23
MY SAP ERP UpgradeChallenges & Highlights 1/2 (related to this project)
Communication is all !!!
In case of outsourcing: Integrate your outsourcing partner as soon as possible.
“Distribute presentation and pick up the phone.”
Start archiving and reorganization as soon as possible
Expand the retention periods for archiving objects (Business alignment !!!)
Use “SAP Data Management Guide” for large tables.
Always use newest Unicode Tools
Newest SPUM4 and SPUMG transaction updates provides necessary features, specially for large database/tables.
Only use proven UC tools! SAP quality assurance has not take place in this area.
Become familiar with the UC tools.
Check out default settings for specific tables (default code page!)
MySAP ERP Upgrade – Matthias Gramm-Schwarze 24
MY SAP ERP UpgradeChallenges & Highlights 2/2 (related to this project)
Use native speaker for unicode conversion
Train them in using SPUMG & SPUM4 transactions
Specially for large systems with many different languages, use native speaker.
Use “SAP upgrade coach”
Specially during UC conversion tests
Focus on UC conversion (within this project!)
Use appropriate testing tool
Usage of SAP Solution Manager was the right decision.
Interface handling easier than expected
By usage of central message hub (SAP XI)
MySAP ERP Upgrade – Matthias Gramm-Schwarze 26
Questions?
otherwise
Thanks for your attention!
MY SAP ERP Upgrade