sapei ± 500 kvdc - 1000 mw interconnection sardinia ... borgo sabotino sapei 24-01-14.pdf ·...
TRANSCRIPT
SAPEI± 500 kVdc - 1000 MW interconnection
Sardinia – Italian peninsula
HVDC links in Italy
SA.CO.I.Monopolar connection (triterminal)200 kV dc – 300 MW(Sardinia-Corsica-continental Italy)
SA.PE.I. (work in progress)Bipolar connection 500 kV dc – 1000 MW (Sardinia – Italian peninsula)(Sardinia – Italian peninsula)
ITALY- GREECE Monopolar connection 400 kV dc – 500 MW
(Italy-Greece)
Preliminary considerations
� To increase the security, the reliability and the quality of supply of
load in Sardinia
� To reduce the cost of reserve and guarantee a better utilization of
generation at peak load condition
� To promote the export of energy generated in Sardinia
SAPEI Feasibility study
� To guarantee the reduction of constrains to sardinian operators for
the participation to the electricity market
Long life span of SACOI
(submarine cable in service in 1967)
MAIN HYPOTHESES TO EVALUATE THE RATING OF THE HVDC LINK
Generation capacity and demand in SardiniaHydro plants:
� few plants with little capacity, one pumping plant with a great capacity (Taloro
200 MW)
� no new plants foreseen
SAPEI Feasibility study
Thermal plants
� 4 great carbon plants (tot. 1800 MW), of which more than half has the priority
Demand: 2000 MW in the first year with an yearly growth rate of 2,7%
Wind plants:
� a great number of plants planned
�Foreseen 700 MW in the first year, 900 MW in 2010 and 1200 MW in 2015
� 4 great carbon plants (tot. 1800 MW), of which more than half has the priority
of dispatch
� no new plants foreseen in the first year, 1 combined cycle of 400 MW in 2010
and 1 combined cycle of 400 MW in 2015
Definition of scenarios
Hypotheses:
� It is assumed that the generation in the continent is more expensive than in Sardinia, given the presence of carbon and wind plants.
� SACOI is supposed to be not in service
SAPEI Feasibility study
Main hypotheses to evaluate the rating of the HVDC link
� SACOI is supposed to be not in service
� Corsica is supplied by a AC link of 50 MW
� Time frame reference: year commissioning (2007), 2010, 2015
RESULTS
The results of the feasibility study has pointed out that:
� the link is substantially used to export power from Sardinia to continent
� the power that flows across the link substantially grows in the years, following
the increase of generation capacity in Sardinia
Studies of the power flow across the link and the costs foreseen gives:
SAPEI Feasibility study
Studies of the power flow across the link and the costs foreseen gives:
� the optimal rating of the link is 500 kVdc / 1000 MW;
� to optimize the flow across the link is given by the opportunity tocontract the link in two phases; with the SACOI in service during thefirst phase of SAPEI, the growth of capacity between Sardinia andthe continent to 700 MW, allows the maximization of the productionin Sardinia
Converter terminals : FIUME SANTO (Sardinia) – LATINA (Italian peninsula)
Power cable ±500 kVdc
• Length of submarine cable : 2x 420 km
• Maximum depth: 1620 m
SAPEI - main technical data
• Length of land cable : 2x1km (Sardinia) + 2x14 km (Latium)
Employment of existing upgrated anode SACOI linked to terminal with
submarine cable (32 km) and land cable (1 km)
New cathode at Latina linked to terminal with submarine cables (2x8 km)
and land cables (2x14 km)
Converter station
Fiume Santo substation
<0.5 km <1 km
Sea land joint 420 km
Latina substation and converter
station
14 km
Maximum depth 1640 m
SAPEI – Physical scheme
Sea land joint
Submarine cables
Tyrrenian sea
SARDINIA LATIUM
AC cables Dc cables Dc cables
** in air substation* GIS substation
*
Municipality involved: Sassari, Porto Torres, Castelsardo (anode punta Tramontana)
Municipality involved: Nettuno (Rm), Latina
**
SAPEI – single line diagram
SAPEI – Main aspects of substation design
Converter station design was carried out in the aim to substain the sardinianHV grid both in normal and emergency conditions.
SAPEI connection guarantee “black start” , starting in case of Sardinia blackout even thought with reduced performances, to participate at restarting of thegrid.
In case of pole fault, (converter station or cable), SAPEI can automaticallyswitch from bipolar to monopolar configuration , with ground or metallicswitch from bipolar to monopolar configuration , with ground or metallicreturn path , to guarantee at least 500 MW
Start/Stop sequences are provided to allow the maximum power range also inbipolar configuration (50 – 1000 MW).
The control system of SAPEI allows the full integration with existing SACOI linkin order to participate in frequency regulation of Sardinian HV grid
SAPEI – Operating mode
Operation in case of pole 1 converter fault
• Operation can be ensured at half nominal power (500 MW) without interruption of
the connection (current through pole 2 line and return through cable 1 after a
transient return through electrode in reverse direction)
Operation in case of pole 2 converter fault
• Operation can be ensured at half nominal power (500 MW) without
interruption of connection with current return through electrodes or
cable 2
SAPEI – Operating mode
Operation in case of cable 2 fault
• Operation can be ensured at half nominal power (500 MW) without
interruption of connection with current return through electrodes
SAPEI – Operating mode
Operation in case of cable 1 fault
• Operation can be assured at half nominal power (500 MW) after manual
reconfiguration of the circuits. Such reconfiguration requires a bipolar outservice that
can be planned after a temporary operation with electrodes in reverse mode.
SAPEI – Operating mode
SAPEI – Outline of the route
SAPEI - sea cable profile
Low-Medium depth L-M depthHigh depth
SAPEI - Cable design
Deep Water solution
Shallow Water solution
SAPEI – Land cables
Electrode cablecopper 1x1200 sqmm
Section of land cable trench Lazio side
1 Conduttore rotondo compatto a fili di rame, tamponato
2 Strato semiconduttivo interno
3 Isolante XLPE
4 Strato semiconduttivo esterno
5 Schermo a nastri di rame
6 Guaina di polietilene
7 Imbottitura in filato di polipropilene
8 Armatura a fili di acciaio zincato singolarmente isolati in politene
9 Fasciatura esterna in filato di polipropilene
500 kvdc pole cableCopper 1x1400 sqmm
1 Conduttore a conci di rame
2 Strato semiconduttivo
3Isolamento in strati di carta impregnato di miscela ad alta viscosità
4 Strato semiconduttivo
5 Guaina in lega di piombo
6 Guaina di polietilene
7 Rinforzo a nastri di acciaio zincato
8 Guaina anticorrosiva di polietilene
SAPEI – Fiume Santo land cables route
1 Conduttore a conci di rame
2 Strato semiconduttivo
3Isolamento in strati di carta impregnato di miscela ad alta viscosità
4 Strato semiconduttivo
5 Guaina in lega di piombo
6 Guaina di polietilene
7 Rinforzo a nastri di acciaio zincato
500 kvdc pole cableCopper 1x1400 sqmm
8 Guaina anticorrosiva di polietilene
SAPEI –Principle risks for submarine cables and Environmental aspects
• Fishing activities
• Maritime traffic and relevant anchorage
• Presence of protected vegetation as Posidonia prateries along the
route
• Cetacean mammal sanctuary areas
This require definition of final route on basis of a detailed marine survey,
special protection for submarine cable and modalities of installation .
SAPEI – Survey
A detailed survey has been carried out along the authorized route
SAPEI – Marine cable protection (1)
The cable will be buried utilizing jetting
machine and7or trenching machine
driven by divers or through a ROV down
to -400 m depth
The burial depth will depend on the soil
characteristics: target 1m with minimum
acceptance 30 cm
In poseidonia fields, the cable will be laid on the
sea bed and fixed by special anchoring devices
SAPEI – marine cable protection (2)
When the bottom is rocky or irregular, thecable cannot be buried. According to thepracticability of the operation, the cablecould be protected by means of concretemattresses or rock dumping
sea bed and fixed by special anchoring devices
In the shore crossing portion the cable will be
protected by means of pre-installed pipes. The
pipes will be installed with the HDD tecinique
SAPEI – Pole 1 cable laying
SAPEI – Pole 1 cable laying
SAPEI – Pole 1 cable laying
SAPEI – Pole 1 cable laying
SAPEI – Pole 1 cable laying
SAPEI – Anode - Punta Tramontana
Upgraded anode 2500 ASACOI + SAPEI
Pre-existing SACOI anode 1500A
SAPEI – Converter stations
Fiume Santo
LatinaLatina
Latina converter station layout
Control room
filters
transformers Valve Hall
DC Hall
Control room
380kV national grid substation
380 kV AC Yard