scope mgmt
TRANSCRIPT
-
8/12/2019 Scope Mgmt
1/18
Project Scope Management
-
8/12/2019 Scope Mgmt
2/18
2
What is Project Scope Management?
Scoperefers to allthe work involved in creating theproducts of the project and the processes used to create
them.
A deliverableis a product produced as part of a
project, such as hardware or software, planning
documents, or meeting minutes.
Project scope management includes the processes
involved in defining and controlling what is or is not
included in a project.
-
8/12/2019 Scope Mgmt
3/18
3
Project Scope Management Processes
Scope planning:Deciding how the scope will be defined,verified, and controlled.
Scope definition: Reviewing the project charter and
preliminary scope statement and adding more information
as requirements are developed and change requests areapproved.
Creating the WBS: Subdividing the major project
deliverables into smaller, more manageable components.
Scope verification: Formalizing acceptance of the
project scope.
Scope control: Controlling changes to project scope.
-
8/12/2019 Scope Mgmt
4/18
4
Work Breakdown Structure (WBS)
A WBSis a deliverable-oriented grouping of the work
involved in a project that defines the total scope of the
project.
A WBS is a foundation document that provides the
basis for planning and managing project schedules,
costs, resources, and changes.
-
8/12/2019 Scope Mgmt
5/18
Product Break down Structure
A deliverable-oriented WBS defines project work interms of the components (physical or functional) that
make up the deliverable.
In this case, the first word in a given WBS element is a
noun, such as, Module A, Subsystem A, Automobile
Engine, Antenna, etc.
This WBS type is called Product Breakdown Structure
(PBS).
5
Types of Work Breakdown Structures
-
8/12/2019 Scope Mgmt
6/18
6
PBS
-
8/12/2019 Scope Mgmt
7/18
Task Oriented WBS
A task-oriented WBS defines the deliverable of project
work in terms of the actions that must be done to
produce the deliverable. The first word in a given WBS
element usually is a verb, such as, design, develop,optimize, transfer, test, etc.
7
Types of Work Breakdown Structures
-
8/12/2019 Scope Mgmt
8/18
Task oriented WBS
-
8/12/2019 Scope Mgmt
9/18
Time-phased WBS
Time-phased WBS is one that is used on very long
projects. It breaks the project into major phases instead
of tasks.
In this type, a rolling wave approach is adopted and
only the near-term phase is planned in detail.
9
Types of Work Breakdown Structures
-
8/12/2019 Scope Mgmt
10/18
WBS Design Principles
The 100% Rule
The 100% Rulestates that the WBS includes 100% of the work defined by the project
scope and captures all deliverablesinternal, external, interimin terms of the work to
be completed, including project management. The 100% rule is one of the most important
principles guiding the development, decomposition and evaluation of the WBS.
The rule applies at all levels within the hierarchy: the sum of the work at the child level
must equal 100% of the work represented by the parent and the WBS should not
include any work that falls outside the actual scope of the project, that is, it cannot
include more than 100% of the work It is important to remember that the 100% rule
also applies to the activity level.
The work represented by the activities in each work package must add up to 100% of the
work necessary to complete the work package.1
10
http://www.pmhut.com/wbs-typeshttp://www.pmhut.com/wbs-types -
8/12/2019 Scope Mgmt
11/18
WBS Design PrinciplesMutually-exclusive Elements
In addition to the 100% Rule, it is important that there is no
overlap in scope definition between two elements of a WBS.
This ambiguity could result in duplicated work or
miscommunications about responsibility
Such overlap is likely to cause overlap in scope definition and
confusion in project cost accounting
If the WBS between two elements of a element names are
ambiguous, a WBS dictionary can clarify the distinctions
between WBS elements11
-
8/12/2019 Scope Mgmt
12/18
WBS Design PrinciplesPlanned Outcomes
Action-oriented details in the WBS, will most likely include either too many
actions or too few actions. Too many actions will exceed 100% of the parent's
scope and too few will fall short of 100% of the parent's scope.
The best way to adhere to the 100% Rule is to define WBS elements in terms
of outcomes or results.
Work breakdown structures that subdivide work by project phases (e.g.
Preliminary Design Phase, Critical Design Phase) must ensure that phases areclearly separated by a deliverable (e.g. an approved Preliminary Design
Review document, or an approved Critical Design Review document).
12
-
8/12/2019 Scope Mgmt
13/18
WBS Design Principles
Second Level is the most Important
It determines how actual costs and schedule data are grouped for
future project cost and schedule estimating.
It is therefore used to capture actuals" from a project for future
estimating purposes.
13
-
8/12/2019 Scope Mgmt
14/18
WBS Design PrinciplesHow Far Down?
The WBS is decomposed down to the work package level. A work package isthe lowest level in the WBS, and is the point at which the cost and schedule
for the work can be reliably estimated.
If WBS terminal elements are defined too broadly, it may not be possible to
track project performance effectively. If a WBS terminal elements are toogranular, it may become inefficient to keep track of so many terminal
granularity
An effective limit of WBS granularity may be reached when it is no longer
possible to define planned outcomes, and the only details remaining areactions.
Unless these actions can be defined to adhere to the 100% Rule, the WBS
should not be further subdivided
14
-
8/12/2019 Scope Mgmt
15/18
Rule of ThumbThe 40-Hour Rule of Decomposition
When a project has been decomposed down to an element that has about 40 hours ofallocated direct labor, there is no need to decompose further.
The 40 Hour Rule is based on a 40-hour work week.
Because of this, most WBS diagrams are not symmetrical. Some legs may go down toLevel-4 while others may go down to Level-5
The 4% Rule of Decomposition
A WBS is adequately decomposed when the lowest element is about 4% of the total
project.
For a 26-week schedule, the lowest element should be about one week.
For a $2.6M project, the lowest level should be about $104K.
15
-
8/12/2019 Scope Mgmt
16/1816
Scope Control
Scope controlinvolves controlling changes to the
project scope.
Goalsof scope control are to:
Influence the factors that cause scope changes.
Ensure changes are processed according to procedures
developed as part of integrated change control.
Manage changes when they occur.
Varianceis the difference between planned and actual
performance.
-
8/12/2019 Scope Mgmt
17/18
Scope Creep
Scope creep is defined as adding features and functionality (projectscope) without addressing the effects on time, costs, and resources,or without customer approval.
Poor implementation of change control. Incomplete gathering of requirements before project execution
begins.
Insufficient involvement of critical stakeholders (includingcustomer)
Lack of support from executive sponsor and enforcement powerin project manager
-
8/12/2019 Scope Mgmt
18/18
118