sec projects 2010 - 2018

1
Year Projects Power (MW) Inservice Date Rabigh Steam Power Plant Extension and connection with the main grid (2nd Stage) 630 2013 Tenth Power Plant Extension (Steam Section) 990 2013 Al-Sheqaiq Steam Power Plant and connection with thw main grid (1st Stage) 1,200 2014 Tabouk Power Plant Extension 120 2012 Al-Wajh Power Plant Extension 30 2012 Tabarjal Power Plant Extension 25 2012 Deba Power Plant (1st Stage) 500 2014 Power Station Interconnection Connection of the Eleventh Power Plant in Riyadh 2012 Jezan - Najran Interconnection 380 kV 2013 The Fifth Interrconnection Line Between Eastern and Central Regions 380 kV 2012 Extra High & High Voltage Several Projects of Substations and Transmission lines of Volage levals 110-380 kV 2013 Sevaral Distribution Projects 2011 Jeddah South Steam Power Plant and connection with thw main grid (1st Stage) 630 2015 Al-Sheqaiq Steam Power Plant and connection with thw main grid (2nd Stage) 400 2015 Al-Qurayat Power Plant Extension 25 2013 Al-Wajh Power Plant Extension 30 2013 Al-Jubail/Rass-El-Zoor Power Plant (1st Stage) 630 2015 Power Station Interconnection Connection of Marafiqu Plant at Yanbou 2013 Quaysoma Rejion interconnection 380 kV 2014 Bisha - Wadi Addwaser Interconnection 380 kV 2014 Extra High & High Voltage Several Projects of Substations and Transmission lines of Volage levals 110-380 kV 2014 Sevaral Distribution Projects 2012 Al-Sheqaiq Steam Power Plant and connection with thw main grid (3rd Stage) 400 2016 Jeddah South Steam Power Plant and connection with thw main grid (2nd Stage) 630 2016 Rafha Power Plant Extension 30 2014 Al-Jubail/Rass-El-Zoor Power Plant (2nd Stage) 1,260 2015 Deba Power Plant (2nd Stage) 500 2016 Power Station Interconnection Connection of Qurayaa Plant (IPP) 2014 Central - Western Regions Interrconnection (HVDC) 2017 Madina - Hail Interconnection 380 kV 2015 North Western Region Network 2016 Extra High & High Voltage Several Projects of Substations and Transmission lines of Volage levals 110-380 kV 2015 Sevaral Distribution Projects 2013 Al-Akeer South Power Plant and connection with the main Network (1st Stage) 1,260 2018 Activity Saudi Electricity Company Projects (Forecast) upto 2018 Transmission Distribution Transmission Distribution Strategic Interconnection Generation 2011 Generation 2012 Strategic Interconnection Generation 2010 Transmission Distribution Strategic Interconnection Jeddah South Steam Power Plant and connection with thw main grid (3rd Stage) 630 2018 Tabarjal Power Plant Extension 25 2015 Sharoura Power Plant Extension 15 2015 Al-Jubail/Rass-El-Zoor Power Plant (3rd Stage) 630 2017 Power Station Interconnection Connection of Jubail PP and Ras-El-Zoor IPP (1st Stage) 2016 Tabouk - Tabarjal Interconnection 380 kV 2016 Reinforce Interconnection between the Southen and Weastern Regions 2015 Extra High & High Voltage Several Projects of Substations and Transmission lines of Volage levals 110-380 kV 2016 Sevaral Distribution Projects 2014 Jeddah South Steam Power Plant and connection with thw main grid (4th Stage) 630 2019 Al-Akeer South Power Plant and connection with the main Network (2nd Stage) 1,260 2019 Al-Sheqaiq Power Plant (4th Stage) 400 2018 Power Station Interconnection Connection of Jubail PP and Ras-El-Zoor IPP (2nd Stage) 2016 Strategic Interconnection Omlog - Alwajh/Alola Interconnection 380 kV 2017 Extra High & High Voltage Several Projects of Substations and Transmission lines of Volage levals 110-380 kV 2017 Sevaral Distribution Projects 2015 Al-Qurayat Power Plant Extension 25 2016 Al-Akeer South Power Plant and connection with the main Network (3rd Stage) 1260 2017 Al-Sheqaiq Power Plant (5th Stage) 400 2019 Power Station Interconnection Connection of Sheqaiq IPP (1st Stage) 2016 Western - Southern Regions Second Interconnection Line 2018 Jouf - Tabarjal Interconnection 380 kV 2018 Extra High & High Voltage Several Projects of Substations and Transmission lines of Volage levals 110-380 kV 2018 Sevaral Distribution Projects 2016 Jeddah South Power Plant and connection with the main Network (5th Stage) 1260 2021 Sharoura Power Plant Extension 30 2018 Al-Jubail/Rass-El-Zoor Power Plant (4th Stage) 1890 2020 Power Station Interconnection Strategic Interconnection Reinforce Interconnection between Madina and Hail 2018 Extra High & High Voltage Several Projects of Substations and Transmission lines of Volage levals 110-380 kV 2019 Sevaral Distribution Projects 2017 Al-Akeer South Power Plant and connection with the main Network (4th Stage) 1260 2022 Al-Sheqaiq Power Plant (6th Stage) 800 2021 Power Station Interconnection Strategic Interconnection Connection of Tabarjal and Qurayat 380 kV 2020 Extra High & High Voltage Several Projects of Substations and Transmission lines of Volage levals 110-380 kV 2020 Transmission Distribution Generation 2015 Strategic Interconnection Generation 2017 Transmission Distribution Generation 2016 Transmission 2014 Generation Transmission Distribution Transmission Distribution Strategic Interconnection 2013 Generation Sevaral Distribution Projects 2018 Jeddah South Power Plant and connection with the main Network (6th Stage) 1260 2023 Power Station Interconnection Strategic Interconnection Extra High & High Voltage Several Projects of Substations and Transmission lines of Volage levals 110-380 kV 2021 Sevaral Distribution Projects 2019 2018 Generation Transmission Distribution Distribution

Upload: skohli2000

Post on 27-Oct-2015

110 views

Category:

Documents


1 download

DESCRIPTION

Saudi Electricity Company Projects

TRANSCRIPT

Page 1: SEC Projects 2010 - 2018

Year ProjectsPower (MW)

InserviceDate

Rabigh Steam Power Plant Extension and connection with the main grid (2nd Stage) 630 2013Tenth Power Plant Extension (Steam Section) 990 2013Al-Sheqaiq Steam Power Plant and connection with thw main grid (1st Stage) 1,200 2014Tabouk Power Plant Extension 120 2012Al-Wajh Power Plant Extension 30 2012Tabarjal Power Plant Extension 25 2012Deba Power Plant (1st Stage) 500 2014

Power Station Interconnection

Connection of the Eleventh Power Plant in Riyadh 2012

Jezan - Najran Interconnection 380 kV 2013

The Fifth Interrconnection Line Between Eastern and Central Regions 380 kV 2012 Extra High

& High VoltageSeveral Projects of Substations and Transmission lines of Volage levals 110-380 kV 2013

Sevaral Distribution Projects 2011Jeddah South Steam Power Plant and connection with thw main grid (1st Stage) 630 2015Al-Sheqaiq Steam Power Plant and connection with thw main grid (2nd Stage) 400 2015Al-Qurayat Power Plant Extension 25 2013Al-Wajh Power Plant Extension 30 2013Al-Jubail/Rass-El-Zoor Power Plant (1st Stage) 630 2015

Power Station Interconnection

Connection of Marafiqu Plant at Yanbou 2013

Quaysoma Rejion interconnection 380 kV 2014

Bisha - Wadi Addwaser Interconnection 380 kV 2014 Extra High

& High VoltageSeveral Projects of Substations and Transmission lines of Volage levals 110-380 kV 2014

Sevaral Distribution Projects 2012Al-Sheqaiq Steam Power Plant and connection with thw main grid (3rd Stage) 400 2016Jeddah South Steam Power Plant and connection with thw main grid (2nd Stage) 630 2016Rafha Power Plant Extension 30 2014Al-Jubail/Rass-El-Zoor Power Plant (2nd Stage) 1,260 2015Deba Power Plant (2nd Stage) 500 2016

Power Station Interconnection

Connection of Qurayaa Plant (IPP) 2014

Central - Western Regions Interrconnection (HVDC) 2017

Madina - Hail Interconnection 380 kV 2015North Western Region Network 2016

Extra High & High Voltage

Several Projects of Substations and Transmission lines of Volage levals 110-380 kV 2015

Sevaral Distribution Projects 2013Al-Akeer South Power Plant and connection with the main Network (1st Stage) 1,260 2018

Activity

Saudi Electricity Company Projects (Forecast) upto 2018

Tran

smissio

n

Distribution

Tran

smissio

n

Distribution

StrategicInterconnection

Generation

2011

Generation

2012

StrategicInterconnection

Generation

2010

Tran

smissio

n

Distribution

StrategicInterconnection

( g )Jeddah South Steam Power Plant and connection with thw main grid (3rd Stage) 630 2018Tabarjal Power Plant Extension 25 2015Sharoura Power Plant Extension 15 2015Al-Jubail/Rass-El-Zoor Power Plant (3rd Stage) 630 2017

Power Station Interconnection

Connection of Jubail PP and Ras-El-Zoor IPP (1st Stage) 2016

Tabouk - Tabarjal Interconnection 380 kV 2016

Reinforce Interconnection between the Southen and Weastern Regions 2015 Extra High

& High VoltageSeveral Projects of Substations and Transmission lines of Volage levals 110-380 kV 2016

Sevaral Distribution Projects 2014Jeddah South Steam Power Plant and connection with thw main grid (4th Stage) 630 2019Al-Akeer South Power Plant and connection with the main Network (2nd Stage) 1,260 2019Al-Sheqaiq Power Plant (4th Stage) 400 2018

Power Station Interconnection

Connection of Jubail PP and Ras-El-Zoor IPP (2nd Stage) 2016

StrategicInterconnection

Omlog - Alwajh/Alola Interconnection 380 kV 2017

Extra High & High Voltage

Several Projects of Substations and Transmission lines of Volage levals 110-380 kV 2017

Sevaral Distribution Projects 2015Al-Qurayat Power Plant Extension 25 2016Al-Akeer South Power Plant and connection with the main Network (3rd Stage) 1260 2017Al-Sheqaiq Power Plant (5th Stage) 400 2019

Power Station Interconnection

Connection of Sheqaiq IPP (1st Stage) 2016

Western - Southern Regions Second Interconnection Line 2018Jouf - Tabarjal Interconnection 380 kV 2018

Extra High & High Voltage

Several Projects of Substations and Transmission lines of Volage levals 110-380 kV 2018

Sevaral Distribution Projects 2016Jeddah South Power Plant and connection with the main Network (5th Stage) 1260 2021Sharoura Power Plant Extension 30 2018Al-Jubail/Rass-El-Zoor Power Plant (4th Stage) 1890 2020

Power Station Interconnection

StrategicInterconnection

Reinforce Interconnection between Madina and Hail 2018

Extra High & High Voltage

Several Projects of Substations and Transmission lines of Volage levals 110-380 kV 2019

Sevaral Distribution Projects 2017Al-Akeer South Power Plant and connection with the main Network (4th Stage) 1260 2022Al-Sheqaiq Power Plant (6th Stage) 800 2021

Power Station Interconnection

StrategicInterconnection

Connection of Tabarjal and Qurayat 380 kV 2020

Extra High & High Voltage

Several Projects of Substations and Transmission lines of Volage levals 110-380 kV 2020

Tran

smissio

n

Distribution

Generation

2015 Strategic

Interconnection

Generation

2017

Tran

smissio

n

Distribution

Generation

2016

Tran

smissio

n

2014

GenerationT

ransm

ission

Distribution

Tran

smissio

n

Distribution

StrategicInterconnection

2013

Generation

g g

Sevaral Distribution Projects 2018Jeddah South Power Plant and connection with the main Network (6th Stage) 1260 2023

Power Station Interconnection

StrategicInterconnection

Extra High & High Voltage

Several Projects of Substations and Transmission lines of Volage levals 110-380 kV 2021

Sevaral Distribution Projects 2019

2018

Generation

Tran

smissio

n

Distribution

Distribution