Saudi Electricity Company ProjectsTRANSCRIPT
Year ProjectsPower (MW)
InserviceDate
Rabigh Steam Power Plant Extension and connection with the main grid (2nd Stage) 630 2013Tenth Power Plant Extension (Steam Section) 990 2013Al-Sheqaiq Steam Power Plant and connection with thw main grid (1st Stage) 1,200 2014Tabouk Power Plant Extension 120 2012Al-Wajh Power Plant Extension 30 2012Tabarjal Power Plant Extension 25 2012Deba Power Plant (1st Stage) 500 2014
Power Station Interconnection
Connection of the Eleventh Power Plant in Riyadh 2012
Jezan - Najran Interconnection 380 kV 2013
The Fifth Interrconnection Line Between Eastern and Central Regions 380 kV 2012 Extra High
& High VoltageSeveral Projects of Substations and Transmission lines of Volage levals 110-380 kV 2013
Sevaral Distribution Projects 2011Jeddah South Steam Power Plant and connection with thw main grid (1st Stage) 630 2015Al-Sheqaiq Steam Power Plant and connection with thw main grid (2nd Stage) 400 2015Al-Qurayat Power Plant Extension 25 2013Al-Wajh Power Plant Extension 30 2013Al-Jubail/Rass-El-Zoor Power Plant (1st Stage) 630 2015
Power Station Interconnection
Connection of Marafiqu Plant at Yanbou 2013
Quaysoma Rejion interconnection 380 kV 2014
Bisha - Wadi Addwaser Interconnection 380 kV 2014 Extra High
& High VoltageSeveral Projects of Substations and Transmission lines of Volage levals 110-380 kV 2014
Sevaral Distribution Projects 2012Al-Sheqaiq Steam Power Plant and connection with thw main grid (3rd Stage) 400 2016Jeddah South Steam Power Plant and connection with thw main grid (2nd Stage) 630 2016Rafha Power Plant Extension 30 2014Al-Jubail/Rass-El-Zoor Power Plant (2nd Stage) 1,260 2015Deba Power Plant (2nd Stage) 500 2016
Power Station Interconnection
Connection of Qurayaa Plant (IPP) 2014
Central - Western Regions Interrconnection (HVDC) 2017
Madina - Hail Interconnection 380 kV 2015North Western Region Network 2016
Extra High & High Voltage
Several Projects of Substations and Transmission lines of Volage levals 110-380 kV 2015
Sevaral Distribution Projects 2013Al-Akeer South Power Plant and connection with the main Network (1st Stage) 1,260 2018
Activity
Saudi Electricity Company Projects (Forecast) upto 2018
Tran
smissio
n
Distribution
Tran
smissio
n
Distribution
StrategicInterconnection
Generation
2011
Generation
2012
StrategicInterconnection
Generation
2010
Tran
smissio
n
Distribution
StrategicInterconnection
( g )Jeddah South Steam Power Plant and connection with thw main grid (3rd Stage) 630 2018Tabarjal Power Plant Extension 25 2015Sharoura Power Plant Extension 15 2015Al-Jubail/Rass-El-Zoor Power Plant (3rd Stage) 630 2017
Power Station Interconnection
Connection of Jubail PP and Ras-El-Zoor IPP (1st Stage) 2016
Tabouk - Tabarjal Interconnection 380 kV 2016
Reinforce Interconnection between the Southen and Weastern Regions 2015 Extra High
& High VoltageSeveral Projects of Substations and Transmission lines of Volage levals 110-380 kV 2016
Sevaral Distribution Projects 2014Jeddah South Steam Power Plant and connection with thw main grid (4th Stage) 630 2019Al-Akeer South Power Plant and connection with the main Network (2nd Stage) 1,260 2019Al-Sheqaiq Power Plant (4th Stage) 400 2018
Power Station Interconnection
Connection of Jubail PP and Ras-El-Zoor IPP (2nd Stage) 2016
StrategicInterconnection
Omlog - Alwajh/Alola Interconnection 380 kV 2017
Extra High & High Voltage
Several Projects of Substations and Transmission lines of Volage levals 110-380 kV 2017
Sevaral Distribution Projects 2015Al-Qurayat Power Plant Extension 25 2016Al-Akeer South Power Plant and connection with the main Network (3rd Stage) 1260 2017Al-Sheqaiq Power Plant (5th Stage) 400 2019
Power Station Interconnection
Connection of Sheqaiq IPP (1st Stage) 2016
Western - Southern Regions Second Interconnection Line 2018Jouf - Tabarjal Interconnection 380 kV 2018
Extra High & High Voltage
Several Projects of Substations and Transmission lines of Volage levals 110-380 kV 2018
Sevaral Distribution Projects 2016Jeddah South Power Plant and connection with the main Network (5th Stage) 1260 2021Sharoura Power Plant Extension 30 2018Al-Jubail/Rass-El-Zoor Power Plant (4th Stage) 1890 2020
Power Station Interconnection
StrategicInterconnection
Reinforce Interconnection between Madina and Hail 2018
Extra High & High Voltage
Several Projects of Substations and Transmission lines of Volage levals 110-380 kV 2019
Sevaral Distribution Projects 2017Al-Akeer South Power Plant and connection with the main Network (4th Stage) 1260 2022Al-Sheqaiq Power Plant (6th Stage) 800 2021
Power Station Interconnection
StrategicInterconnection
Connection of Tabarjal and Qurayat 380 kV 2020
Extra High & High Voltage
Several Projects of Substations and Transmission lines of Volage levals 110-380 kV 2020
Tran
smissio
n
Distribution
Generation
2015 Strategic
Interconnection
Generation
2017
Tran
smissio
n
Distribution
Generation
2016
Tran
smissio
n
2014
GenerationT
ransm
ission
Distribution
Tran
smissio
n
Distribution
StrategicInterconnection
2013
Generation
g g
Sevaral Distribution Projects 2018Jeddah South Power Plant and connection with the main Network (6th Stage) 1260 2023
Power Station Interconnection
StrategicInterconnection
Extra High & High Voltage
Several Projects of Substations and Transmission lines of Volage levals 110-380 kV 2021
Sevaral Distribution Projects 2019
2018
Generation
Tran
smissio
n
Distribution
Distribution