session no. g i won a construction contract, …c.ymcdn.com/sites/ won a construction contract, now...
TRANSCRIPT
US Army Corps of Engineers
BUILDING STRONG®
Session no. G
I WON A CONSTRUCTION CONTRACT,
NOW WHAT DO I DO? (Sequel)
Dennis Chung P. E.
Resident Engineer Schofield Barracks
Area Office Ph: 655-1508
U.S. Army Corps of Engineers
20 May 2010
BUILDING STRONG®2
Learn about the Corps’ and Honolulu District’s
construction contract expected deliverables
after contract award and challenges in
meeting requirements in a timely manner.
Ideas to minimize delays and maintain a
steady product delivery to meet contract
completion date.
Preface
BUILDING STRONG®3
Agenda Acronyms and Terms
Post-Award
► Key Personnel
► Contract Documents
► Repetitive Issues
Discussion and Questions
BUILDING STRONG®4
One of OUR missions is to execute
and deliver quality facilities for our
customers within time and budget
Timely construction contract startup
enables continued progress toward
this mission.
Mission
BUILDING STRONG®5
Acronyms and Terms
Military
Army
Corps of Engineers
►Staff (KO, ACO, COR, AE, RE, PE, QAR)
►Systems (QCS, RMS, ECATTS, CCASS)
►Documents (EM385; DD Forms 1354, 1391;
Eng Form 4025, 4288, 93; RFP)
►Plans (APP, EPP, NAS, AHA)
BUILDING STRONG®
Contract Relationships
KO – Contracting Officer
ACO – Administrative Contracting Officer
►AE – Area Engineer
►RE – Resident Engineer
COR Contracting Officer’s Representative
►PE – Project Engineer
►QAR – Quality Assurance Representative
BUILDING STRONG®
Who Are These Guys?
Contracting Officer (KO)► Signs contract; decides if changes can be made; makes
changes; has final decision.
Administrative Contracting Officer (ACO)► Authority from KO to make limited changes.
► Area Engineer (AE) & Resident Engineer (RE)
Contracting Officer’s Representative (COR)► Authority from KO signed by COR & KTR
► Administers construction contract
► Pay requests; Request for Information (RFI); Submittals;
BUILDING STRONG®
Who Are These Guys? (cont)
Project Engineer (PE)► On-site administration & direction of one or more construction
contracts. PE will typically have COR authority.
Quality Assurance Representative (QAR)
► On-site administration and primary POC for KTR & Customer.
► Receives and coordinates QC Plan, AHA, Submittals, RFI and
initiates Pay Requests.
► Cannot change any term or condition of specification or drawings
without KO’s written authorization.
► May stop work due to safety violations.
BUILDING STRONG®
EVALUATION OF PERFORMANCE ELEMENTS
9
FOR OFFICIAL USE ONLY (WHEN COMPLETED)
DD FORM 2626, JUN 94
PART III - EVALUATION OF PERFORMANCE ELEMENTSCONTRACT NUMBER NA
N/A = NOT APPLICABLE O = OUTSTANDING A = ABOVE AVERAGE S = SATISFACTORY M = MARGINAL U = UNSATISFACTORY
N/A O A S M U N/A O A S M U15.QUALITY CONTROL
a. QUALITY OF WORKMANSHIP X
b. ADEQUACY OF THE CQC PLAN X
c. IMPLEMENTATION OF THE CQCPLAN
X
d. QUALITY OF QCDOCUMENTATION
X
e. STORAGE OF MATERIALS X
f . ADEQUACY OF MATERIALS X
g. ADEQUACY OF SUBMITTALS X
h. ADEQUACY OF QC TESTING X
i. ADEQUACY OF AS-BUILTS X
j. USE OF SPECIFIED MATERIALS X
k. IDENTIFICATION / CORRECTIONOF DEFICIENT WORK IN A TIMELYMANNER
X
17.TIMELY PERFORMANCE
a. ADEQUACY OF INITIAL PROGRESSSCHEDULE
X
b. ADHERENCE TO APPROVEDSCHEDULE
X
c. RESOLUTION OF DELAYS X
d. SUBMISSION OF REQUIREDDOCUMENTATION
X
e. COMPLETION OF PUNCHLISTITEMS
X
f . SUBMISSION OF UPDATED ANDREVISED PROGRESS SCHEDULES
X
g. WARRANTY RESPONSE X
16.EFFECTIVENESS OF MANAGEMENT
a. COOPERATION AND RESPONSIVENESS X
b. MANAGEMENT OF RESOURCES /PERSONNEL X
c. COORDINATION AND CONTROL OFSUBCONTRACTORS X
d. ADEQUACY OF SITE CLEAN-UP X
e. EFFECTIVENESS OF JOB-SITESUPERVISION X
f . COMPLIANCE WITH LAWS ANDREGULATIONS X
g. PROFESSIONAL CONDUCT X
h. REVIEW/RESOLUTION OFSUBCONTRACTOR'S ISSUES X
i. IMPLEMENTATION OFSUBCONTRACTING PLAN X
18.COMPLIANCE WITH LABORSTANDARDS
a. CORRECTION OF NOTED DEFICIENCIES X
b. PAYROLLS PROPERLY COMPLETEDAND SUBMITTED X
c. COMPLIANCE WITH LABOR LAWSAND REGULATIONS WITH SPECIFICATTENTION OF THE DAVIS-BACONACT AND EEO REQUIREMENTS X
19.COMPLIANCE WITH SAFETYSTANDARDS
a. ADEQUACY OF SAFETY PLAN X
b. IMPLEMENTATION OF SAFETY PLAN X
c. CORRECTION OF NOTED DEFICIENCIES X
20.REMARKS (Explanation of unsatisfactory evaluation is required. Other comments are optional. Provide facts concerning specif icevents or actions to justify the evaluation. These data must be in suff icient detail to assist contracting off icers in determining thecontractor's responsibility. Continue on separate sheet(s), if needed.)
EVALUATOR REMARKS:
BUILDING STRONG®
EVALUATION OF PERFORMANCE ELEMENTS
(cont)
N/A O A S M U
15. QUALITY CONTROL
16. EFFECTIVENESS OF MANAGEMENT
17. TIMELY PERFORMANCE
18. COMPLIANCE W/ LABOR STANDARDS
19. COMPLIANCE W/ SAFETY STANDARDS
BUILDING STRONG®11
Pre-Award Stage
►Site Orientation – submit written questions
►Solicitation – FedBizOps; “late is late”
►Proposals and Bids –• Design-Build (DB) Solicitations.
Best Value selection process.
• Design-Bid-Build (DBB) Solicitations.
Best Value selection process.
Low-Price, Technically Acceptable (LPTA).
Pre-Award
BUILDING STRONG®12
Post Award► Contract Bonds (Contract award+14)
► Notice To Proceed (NTP)
► Ground Breaking Ceremony (Optional)
► Pre-Design/Pre-Construction Conf (NTP+10)
► Quality Control System (QCS) Startup (NTP+10)
► Mutual Understanding Meetings (Pre-con+30)
► Plans• Key Personnel/Organization Plan (NTP+10)
• Accident Prevention Plan (NTP+10)
• Environmental Protection Plan (NTP+10)
• Excavation & Burn Permits (NTP+20)
• Preliminary Schedule, NAS Format (NTP+20)
• Initial Submittals (NTP+20)
• Quality Control Plan (NTP+30)
Post Award
BUILDING STRONG®13
Contract Bonds (Award + 14 days)
Type of bonds per contract.
Protects both parties.
Mid-contract partial bonding.
BUILDING STRONG®14
Notice To Proceed (NTP)
Receipt of the NTP via letter signed by the
Contracting Officer.
Acknowledgement by the Contractor
initiates the contract performance period.
The NTP is issued after bond certification.
BUILDING STRONG®15
Ground Breaking Ceremony
Unsolicited nor discouraged, this ceremony may
be held at the expressed desire of the
Contractor. Contractor shall conduct the first
and second phase of the Corps 3-phase quality
control procedures, Preparatory and Initial, prior
to the ceremony. Ceremony shall conform to
DoD’s Joint Ethics Regulation, DoD 5500.7R.
BUILDING STRONG®16
Pre-Design/Pre-Construction
Conference
Scheduled as soon as possible after receipt of the NTP,
the conference generally has 2 parts, one with just the
Contractor’s Key Personnel and the other with general
invitees to include CUSTOMER (DPW), PPM, Using
Agency, Resident Office, Fire Department, NEC (DOIM),
PMO, Safety and any other contract related agencies.
Invitations are sent out via e-mail and minutes are taken
by the Contractor.
BUILDING STRONG®17
Quality Control System (QCS)
Construction software system linked to the
Corps QA management software, RMS.
Used to submit documents electronically.
Permission access by the Corps.
Web based software.
Linked to Primavera 6 scheduling
software.
BUILDING STRONG®18
Mutual Understanding Meetings
Provides detailed discussion of contract
specific topics.
Invitees incl Subject Matter Experts (SME).
Common meetings include Safety and
Quality Control.
BUILDING STRONG®19
“The Team”
Key Personnel/Organization Plan
“Tree” identifying Contractor’s staffing and the supervisory functions/chain of command.
Includes resumes with information that meet minimum contract requirements.
Provides personnel representing Contractor’s company and signature authority for all future documents.
“Living” document, updated as changes occur.
BUILDING STRONG®20
“The Team – On-site (cont)”
Key Personnel/Organization Plan
PROJECT MANAGER – Experience based position.
QUALITY CONTROL MANAGER (QCM) –
Certification and experience based position.
SITE SAFETY & HEALTH OFFICER (SSHO) –
Certification and experience based position.
SUPERINTENDENT – Experience based position.
BUILDING STRONG®21
Initial Plans
Governed by the specifications and unique to every contract or task order, initial plans are key to starting construction, and are submitted as a regular contract submittal.
► Examples: Organization Plan, Accident Prevention Plan (APP), Environmental Protection Plan (EPP), Preliminary Schedule (in NAS format), initial material submittals, long-lead material submittals and the Quality Control Plan (utilizing 3-phase).
BUILDING STRONG®22
Accident Prevention Plan
AKA the “Safety Plan” and requires written Government acceptance.► Requires accompanying Activity Hazard Analysis
(AHA’s).
IAW EM 385-1-1 (15 Sep 08 & yellow in color)
Reviewed and approved by the Contractor’s approved Safety Officer and accepted by the Corp’s COR.
BUILDING STRONG®23
Accident Prevention Plan (cont)
Asbestos Abatement Plan
Confined Space Plan
Critical Lift Plan
Demolition Plan
Emergency Response Plan
Formwork/Shoring Plan
Hazardous Communication Plan
Respiratory Protection Plan
A-E Design Safety Plan
BUILDING STRONG®24
Environmental Protection Plan
Project specific and requires written Government
acceptance.
Reviewed and approved by KTR’s Safety Officer
and the Corps’ COR.
Includes NPDES Form C and Best Management
Practices (BMP’s) previously submitted to the
State of Hawaii Clean Water Branch.
BUILDING STRONG®25
Excavation Permit
Contractor submitted and routed through
different agencies.
Required for any subsurface disturbance
(usually starting with temporary
construction fencing).
May require Cultural Monitor
Current form available upon request.
BUILDING STRONG®26
Preliminary/Initial Schedule
Detailed analysis of first 60 days with rough outline of
entire project.
In data exchange format, most commonly Primavera
software.
Includes narrative.
Requires KTR’s Project Manager & COR approval.
Subsequent monthly updates as attachment to Progress
Payments.
BUILDING STRONG®27
Initial Submittals
Covers any documents submitted to the Government
other than certified letters.
Uses form ENG Form 4025 as cover.
Requires Contractor’s Quality Control Manager (QCM)
approval.
Startup and long lead materials, followed by sequential
material requirements.
Utility outage requests (120 days for electrical, 45 days
for water, Aqua Engr permit for wastewater).
BUILDING STRONG®28
Quality Control Plan
Requires approval of the KTR’s Quality Control Manager
& Corps’ COR.
QC = Contractor vs QA = Government
Includes detailed QC utilizing the Corps 3-Phase plan,
Preliminary-Initial-Follow-up quality control procedures.
Detailed Coverage at Mutual Understanding Meeting.
Separate QC Plan required for design under DB
contracts, by Designer of Record (DOR).
BUILDING STRONG®29
Contract Progress
Successful projects have successful starts.
All documents are “living” & require constant review &
updates when applicable.
3-Phase QC & QA program continues through contract
closeout.
“Equilateral Triangle” approach, Quality Control-Safety-
Environmental, is our business.
Current environment dictates an on-time completion with
an integrated (punch-list, comm/data, furniture) close-
out.
BUILDING STRONG®30
EVALUATION OF PERFORMANCE ELEMENTSFOR OFFICIAL USE ONLY (WHEN COMPLETED)
DD FORM 2626, JUN 94
PART III - EVALUATION OF PERFORMANCE ELEMENTSCONTRACT NUMBER NA
N/A = NOT APPLICABLE O = OUTSTANDING A = ABOVE AVERAGE S = SATISFACTORY M = MARGINAL U = UNSATISFACTORY
N/A O A S M U N/A O A S M U15.QUALITY CONTROL
a. QUALITY OF WORKMANSHIP X
b. ADEQUACY OF THE CQC PLAN X
c. IMPLEMENTATION OF THE CQCPLAN
X
d. QUALITY OF QCDOCUMENTATION
X
e. STORAGE OF MATERIALS X
f . ADEQUACY OF MATERIALS X
g. ADEQUACY OF SUBMITTALS X
h. ADEQUACY OF QC TESTING X
i. ADEQUACY OF AS-BUILTS X
j. USE OF SPECIFIED MATERIALS X
k. IDENTIFICATION / CORRECTIONOF DEFICIENT WORK IN A TIMELYMANNER
X
17.TIMELY PERFORMANCE
a. ADEQUACY OF INITIAL PROGRESSSCHEDULE
X
b. ADHERENCE TO APPROVEDSCHEDULE
X
c. RESOLUTION OF DELAYS X
d. SUBMISSION OF REQUIREDDOCUMENTATION
X
e. COMPLETION OF PUNCHLISTITEMS
X
f . SUBMISSION OF UPDATED ANDREVISED PROGRESS SCHEDULES
X
g. WARRANTY RESPONSE X
16.EFFECTIVENESS OF MANAGEMENT
a. COOPERATION AND RESPONSIVENESS X
b. MANAGEMENT OF RESOURCES /PERSONNEL X
c. COORDINATION AND CONTROL OFSUBCONTRACTORS X
d. ADEQUACY OF SITE CLEAN-UP X
e. EFFECTIVENESS OF JOB-SITESUPERVISION X
f . COMPLIANCE WITH LAWS ANDREGULATIONS X
g. PROFESSIONAL CONDUCT X
h. REVIEW/RESOLUTION OFSUBCONTRACTOR'S ISSUES X
i. IMPLEMENTATION OFSUBCONTRACTING PLAN X
18.COMPLIANCE WITH LABORSTANDARDS
a. CORRECTION OF NOTED DEFICIENCIES X
b. PAYROLLS PROPERLY COMPLETEDAND SUBMITTED X
c. COMPLIANCE WITH LABOR LAWSAND REGULATIONS WITH SPECIFICATTENTION OF THE DAVIS-BACONACT AND EEO REQUIREMENTS X
19.COMPLIANCE WITH SAFETYSTANDARDS
a. ADEQUACY OF SAFETY PLAN X
b. IMPLEMENTATION OF SAFETY PLAN X
c. CORRECTION OF NOTED DEFICIENCIES X
20.REMARKS (Explanation of unsatisfactory evaluation is required. Other comments are optional. Provide facts concerning specif icevents or actions to justify the evaluation. These data must be in suff icient detail to assist contracting off icers in determining thecontractor's responsibility. Continue on separate sheet(s), if needed.)
EVALUATOR REMARKS:
BUILDING STRONG®
EVALUATION OF PERFORMANCE ELEMENTS
(cont)
N/A O A S M U
15. QUALITY CONTROL
16. EFFECTIVENESS OF MANAGEMENT
17. TIMELY PERFORMANCE
18. COMPLIANCE W/ LABOR STANDARDS
19. COMPLIANCE W/ SAFETY STANDARDS
BUILDING STRONG®
ARRA Overview
Requirement - Section 1215 of the 2009
Recovery Act requires Prime Contractors,
Sub Contractors & Federal Agencies to
submit data for federally awarded
contracts funded under the Recovery Act
BUILDING STRONG®
ARRA Overview (cont)
Who/What/When
Prime Contractors/
Sub Contractors
Registers each ARRA
project awarded
Submits quarterly project
progress reports
Federal Agencies
(USACE)
Tracks each ARRA
project it administers
Performs Quality
Assurance (QA) on the
reports submitted by the
contractors
BUILDING STRONG®
ARRA (cont) What is reported
Award Recipient Information
Award Information
Project Information
BUILDING STRONG®
ARRA (cont) Where to report & Why
Where
►www.FederalReporting.gov
►Reports published on www.Recovery.gov
Why?
►Fosters accountability & transparency
►Tracking tool for Office of Management &
Budget