Sewerage Infrastructure Development in Sarawak
Lau Hieng UngSewerage Services Department Sarawak
1
![Page 2: Sewerage Infrastructure Development in Sarawak](https://reader035.vdocuments.net/reader035/viewer/2022062223/5a4d1b2a7f8b9ab059998e51/html5/thumbnails/2.jpg)
CONTENTA. Existing Sewerage Infrastructure
B. Legal Framework
C. Organizational Set Up
D. Current Development
E. Future Direction
2
![Page 3: Sewerage Infrastructure Development in Sarawak](https://reader035.vdocuments.net/reader035/viewer/2022062223/5a4d1b2a7f8b9ab059998e51/html5/thumbnails/3.jpg)
3
Area in sq km Population (2014 estimate)
Malaysia 329,847 30.6 millionSarawak 124,450 2.67 million
37.7% 8.7%
![Page 4: Sewerage Infrastructure Development in Sarawak](https://reader035.vdocuments.net/reader035/viewer/2022062223/5a4d1b2a7f8b9ab059998e51/html5/thumbnails/4.jpg)
Depends almost entirely on individual septic tanks
Commercial complexes, major institutions and high-rise buildings are provided with Imhoff tanks or small package plants
Grey water, oil and grease are not collected or treated
A. Existing Sewerage Infrastructure
4
![Page 5: Sewerage Infrastructure Development in Sarawak](https://reader035.vdocuments.net/reader035/viewer/2022062223/5a4d1b2a7f8b9ab059998e51/html5/thumbnails/5.jpg)
Existing Sewerage Infrastructures in Sarawak
A. Sewerage Inventory as at 31 Dec 2013
Population Equivalent Connected to Centralised System as at 31 May 2015
Type of Treatment Population Equivalent (PE)Septic Tank 2,007,820
Communal Septic Tank 10,900Package Plant 126,926
Centralised System 128,893Total 2,274,539
Area Population Equivalent (PE)Kuching Package 1 68,253Bintulu Town 87,550
Source: Inventory of JPPS
![Page 6: Sewerage Infrastructure Development in Sarawak](https://reader035.vdocuments.net/reader035/viewer/2022062223/5a4d1b2a7f8b9ab059998e51/html5/thumbnails/6.jpg)
Rancangan Malaysia Ke-11 (RMK-11)
Include Public Sewage Treatment Plant, Private Sewage Treatment Plant and Communal Septic Tank
![Page 7: Sewerage Infrastructure Development in Sarawak](https://reader035.vdocuments.net/reader035/viewer/2022062223/5a4d1b2a7f8b9ab059998e51/html5/thumbnails/7.jpg)
Sewerage Systems and Services Ordinance, 2005
Applies to areas under Municipal Councils and City Administration ( 50% of State Population)
Powers, functions and duties conferred by this Ordinance are vested in the Urban Sewerage Systems Authority
Director of Sewerage Services Department is appointed to assume the role of the Authority
B. LEGAL FRAMEWORK
7
![Page 8: Sewerage Infrastructure Development in Sarawak](https://reader035.vdocuments.net/reader035/viewer/2022062223/5a4d1b2a7f8b9ab059998e51/html5/thumbnails/8.jpg)
To plan, design and establish public sewerage systems(Minister Responsible for Urban Development)
To appoint a management agency to manage, operate and maintain any public sewerage system or to provide sewerage services(Minister Responsible for Environment)
To supervise, monitor and provide direction for the performance and activities of any management agency
Powers and Functions of The Authority
8
![Page 9: Sewerage Infrastructure Development in Sarawak](https://reader035.vdocuments.net/reader035/viewer/2022062223/5a4d1b2a7f8b9ab059998e51/html5/thumbnails/9.jpg)
To issue guidelines for design standards and specification of septic tank, private and public sewerage systems
To regulate the process of treatment and disposal of sewage and sewage sludge and its by-products
To fix fees and charges for sewerage services provided by the management agency and the payment or recovery of such fees or charges (State Cabinet)
Powers and Functions of The Authority
9
![Page 10: Sewerage Infrastructure Development in Sarawak](https://reader035.vdocuments.net/reader035/viewer/2022062223/5a4d1b2a7f8b9ab059998e51/html5/thumbnails/10.jpg)
MMKN approved the creation of Sewerage Services Department on 12.04.2007
Sewerage Systems and Services Ordinance, 2005 was put in force on 01.10.2007
C. ORGANISATION Department Set up
10
![Page 11: Sewerage Infrastructure Development in Sarawak](https://reader035.vdocuments.net/reader035/viewer/2022062223/5a4d1b2a7f8b9ab059998e51/html5/thumbnails/11.jpg)
11
D. Current Development• Systematic planning and development of Sewerage Infrastructures in Sarawak commenced under Ninth Malaysia Plan(from 2006)• Main Emphases are on : (a) Provision of a Centralized Sewerage System for Kuching City (b) Provision of a Centralized Sewerage System for Miri City (c) Provision of Septic Sludge Treatment Plants
for major towns (d) Formulation of Centralized Sewerage System
Master Plans for major towns
![Page 12: Sewerage Infrastructure Development in Sarawak](https://reader035.vdocuments.net/reader035/viewer/2022062223/5a4d1b2a7f8b9ab059998e51/html5/thumbnails/12.jpg)
Kuching City Centralised Sewerage System Masterplan (2003)
![Page 13: Sewerage Infrastructure Development in Sarawak](https://reader035.vdocuments.net/reader035/viewer/2022062223/5a4d1b2a7f8b9ab059998e51/html5/thumbnails/13.jpg)
13Centralized Sewerage System in Kuching City (Package 1)
-Proposed 67,000 PE with Trunk Sewer for 270,000 PE
![Page 14: Sewerage Infrastructure Development in Sarawak](https://reader035.vdocuments.net/reader035/viewer/2022062223/5a4d1b2a7f8b9ab059998e51/html5/thumbnails/14.jpg)
14
Key Features of Kuching Centralised Sewerage System Package 1 Which Will Set the Direction for Future Centralised Sewerage Infrastructure Development In Sarawak
• True gravity flow – one pump station
• Micro-Tunneling extensively used
• Modular Construction of Treatment Plant
• Inclusion of Property Connections in the Contract
![Page 15: Sewerage Infrastructure Development in Sarawak](https://reader035.vdocuments.net/reader035/viewer/2022062223/5a4d1b2a7f8b9ab059998e51/html5/thumbnails/15.jpg)
Shaft Construction in Progress15
![Page 16: Sewerage Infrastructure Development in Sarawak](https://reader035.vdocuments.net/reader035/viewer/2022062223/5a4d1b2a7f8b9ab059998e51/html5/thumbnails/16.jpg)
16
Tunneling with 1.5 m diameter Tunnel Boring Machine (TBM) in progress at Manhole T12 (Trunk Sewer)
![Page 17: Sewerage Infrastructure Development in Sarawak](https://reader035.vdocuments.net/reader035/viewer/2022062223/5a4d1b2a7f8b9ab059998e51/html5/thumbnails/17.jpg)
17
1.5 m diameter Connecting MH-T6 to MH-T7A Under Sarawak River
![Page 18: Sewerage Infrastructure Development in Sarawak](https://reader035.vdocuments.net/reader035/viewer/2022062223/5a4d1b2a7f8b9ab059998e51/html5/thumbnails/18.jpg)
Miri Centralised Wastewater Management System Phase 1Main Components:
a)Centralised Sewage Treatment Plant (100,000PE module)
b)Sewer Network Trunk Sewer (0.6m to
1.8m dia.)–15km Local Sewer (0.225m to
0.45m dia.)–51km c) Property Connection -
3,000 properties
Status : Survey and Design Stage (target
to call tender by February 2016)
![Page 19: Sewerage Infrastructure Development in Sarawak](https://reader035.vdocuments.net/reader035/viewer/2022062223/5a4d1b2a7f8b9ab059998e51/html5/thumbnails/19.jpg)
Septic Sludge Treatment Plants
To enable Scheduled Desludging of septic tanks and package plants to improve their treatment efficiency.
Existing three plant : Matang, Sibu and Miri.Priority Towns: Sarikei/Bintangor, Sri
Aman/Betong, Kapit and Limbang.Mechanism: SSD builds and operates the plant.
Local councils desludge and send sludge to the plant for treatment. Local councils collect through council rates and pay for the operation of the plant.
19
![Page 20: Sewerage Infrastructure Development in Sarawak](https://reader035.vdocuments.net/reader035/viewer/2022062223/5a4d1b2a7f8b9ab059998e51/html5/thumbnails/20.jpg)
20
Master Plan Studies
Cities and municipalities currently with Central Sewerage Master Plans are :Kuching (2003), Sibu (2009) and Miri (2009). Bintulu Sewerage Master Plan is completed by Bintulu Development Authority (1980’s).
Priority towns for Master Plan Studies are:Samarahan, Mukah and Sarikei/Bintangor.
![Page 21: Sewerage Infrastructure Development in Sarawak](https://reader035.vdocuments.net/reader035/viewer/2022062223/5a4d1b2a7f8b9ab059998e51/html5/thumbnails/21.jpg)
E. Future Direction
Project Financing
21
Capital Expenditure by Government
Operating Expenditure by Users
![Page 22: Sewerage Infrastructure Development in Sarawak](https://reader035.vdocuments.net/reader035/viewer/2022062223/5a4d1b2a7f8b9ab059998e51/html5/thumbnails/22.jpg)
Institutional ArrangementDepartment shall plan, implement and
operate new public centralised sewerage systems.
Local authorities will still operate existing treatment systems until these are rationalised.
22
![Page 23: Sewerage Infrastructure Development in Sarawak](https://reader035.vdocuments.net/reader035/viewer/2022062223/5a4d1b2a7f8b9ab059998e51/html5/thumbnails/23.jpg)
Public Acceptance/Rejection Individual Septic Tanks are generally acceptable to
the public and it costs them nothing. We need awareness programs and public relation
exercise to change this mindset.
We have to move the mindset of the general public from “sanitation and public health” to “water resource and environmental protection”.
23
![Page 24: Sewerage Infrastructure Development in Sarawak](https://reader035.vdocuments.net/reader035/viewer/2022062223/5a4d1b2a7f8b9ab059998e51/html5/thumbnails/24.jpg)
Our Success will depend on:
Efficient Management and Public Relation:Construction Stage (traffic management and
property damages)
Connection Stage (enter private properties)
Operation and Maintenance Stage (billing)
24
![Page 25: Sewerage Infrastructure Development in Sarawak](https://reader035.vdocuments.net/reader035/viewer/2022062223/5a4d1b2a7f8b9ab059998e51/html5/thumbnails/25.jpg)
25
Thank Youwww.ssd.sarawak.gov.my