water supply & sewerage infrastructure for yaroomba beach
TRANSCRIPT
Yaroomba Beach Water Supply & Sewerage Infrastructure Assessment
3 May 2017
REVISION 6
www.smec.com
Image: : Hassell
Water Supply & Sewerage Infrastructure for Yaroomba Beach | i
TABLE OF CONTENTS
1 INTRODUCTION ......................................................................................................................2
2 DESIGN CRITERIA ....................................................................................................................3 2.1 Water Supply ............................................................................................................................. 3
2.1.1 Demand and Peaking Factors ............................................................................................... 3 2.1.2 Storage ................................................................................................................................. 3 2.1.3 Fire Fighting .......................................................................................................................... 3 2.1.4 Residual Pressures ................................................................................................................ 4 2.1.5 Hazen-Williams Coefficient & Velocity ................................................................................. 4
2.2 Sewerage.................................................................................................................................... 4 2.2.1 Gravity Sewer ....................................................................................................................... 4 2.2.2 Pumping Stations .................................................................................................................. 4 2.2.3 Rising Mains .......................................................................................................................... 4
3 ESTIMATED POPULATION AND FLOW ......................................................................................5 3.1 Equivalent Population ................................................................................................................ 5 3.2 Staging Plan ................................................................................................................................ 7 3.3 Projected Water Demands and Sewage Loads .......................................................................... 8 3.4 Outdoor Water Use.................................................................................................................... 9 3.5 Comparison to Previous Development Proposal ....................................................................... 9
4 INTEGRATED WATER CYCLE MANAGEMENT .......................................................................... 10 4.1 Demand Management .............................................................................................................10 4.2 Alternative Water Sources .......................................................................................................10
5 WATER SUPPLY INFRASTRUCTURE ........................................................................................ 12 5.1 Bulk Water Source Capacity .....................................................................................................12 5.2 Bulk Water Network Capacity ..................................................................................................12 5.3 Storage Requirements .............................................................................................................12 5.4 Trunk Network .........................................................................................................................14 5.5 Connection & Metering ...........................................................................................................14 5.6 Reticulation Network ...............................................................................................................14
6 SEWERAGE INFRASTRUCTURE ............................................................................................... 15 6.1 Sewage Treatment Strategy.....................................................................................................15 6.2 Trunk Network .........................................................................................................................15 6.3 Reticulation Network ...............................................................................................................16 6.4 Recycled Water ........................................................................................................................16
7 CONCLUSIONS ...................................................................................................................... 18
Appendix A Masterplan Layout ................................................................................................ 20
Appendix B Previously Proposed Augmentations (2013) ........................................................... 21
DOCUMENT / REPORT CONTROL FORM ....................................................................................... 22
Water Supply & Sewerage Infrastructure for Yaroomba Beach | 2
1 INTRODUCTION
SMEC Australia has been engaged by SH Coolum Pty Ltd to undertake civil engineering services for the proposed re-visioning of the Coolum Beachside Precinct, now called Yaroomba Beach, which is located on the eastern side of the David Low Way in Yaroomba.
The historical plans for the site developed in 2005 included a gated housing and apartment residential subdivision. The current plan for the site is a revised concept to create a coastal village to promote public access and a change in the use and density to accommodate a 5-star international resort, public amenities and a range of residential products.
This report has been developed to document the outcomes of a Water Supply and Sewerage Assessment undertaken as part of the broader project for the proposed new development. The objectives of this assessment are to identify opportunities for integrated water cycle management and to assess likely water and sewerage trunk infrastructure requirements.
Water Supply & Sewerage Infrastructure for Yaroomba Beach | 3
2 DESIGN CRITERIA
The Design Criteria and Desired Standards of Service (DSS) adopted for this study are the South East Queensland Water Supply and Sewerage Design and Construction Code (SEQ Code) – Design Criteria, July 2013. Key criteria are detailed in the sections below for the Unitywater service area.
2.1 Water Supply
2.1.1 Demand and Peaking Factors
Average Day Consumption (AD) = 230 L/EP/day
Non-revenue Water (NRW) = 30 L/EP/d
Residential:
Mean Day Maximum Month/Average Day (MDMM/AD) = 1.5
Peak Day/ Average Day (PD/AD) = 2
Peak Hour/ Peak Day (PH/PD) = 2
Peak Hour/ Average Day (PH/AD) = 4
High Density Residential:
Mean Day Maximum Month/Average Day (MDMM/AD) = 1.5
Peak Day/ Average Day (PD/AD) = 2
Peak Hour/ Peak Day (PH/PD) = 1.75
Peak Hour/ Average Day (PH/AD) = 3.5
2.1.2 Storage
Ground Level Reservoir = 3 x (PD – MDMM) + Emergency Storage
(Emergency Storage - Greater of 4hrs at MDMM or 0.5 ML)
Elevated Reservoir = 6 x (PH – 1/12 MDMM)+150kL fire storage
(PH is in kL/h, MDMM is in kL/d and reservoir storage is in kL)
In supply zones where 8xPH is less than or equal to MDMM the following equation is used: (2 x PH) + 150 kL fire storage.
2.1.3 Fire Fighting
Fire Flow Detached Res (<= 3 storeys): 15 L/s for 2hrs with background Demand
Multi story Res (> 3 storeys): 30 L/s for 4hrs with background Demand
Commercial/Industrial: 30 L/s for 4hrs with background Demand
Single fire event only
Where the background demand for Residential Areas (Detached/ Multi storey) is the Highest of 2/3 PH or AD, and for Commercial / Industrial is PH demand (between 10am and 4pm).
Water Supply & Sewerage Infrastructure for Yaroomba Beach | 4
2.1.4 Residual Pressures
Maximum pressure = 55 m
Minimum pressure = 22 m
Minimum pressure firefighting = 12 m
2.1.5 Hazen-Williams Coefficient & Velocity
Hazen Williams Friction Factors for internal diameter as follows:
<=150 C=100
>150 -300mm, C=110
Additional Design Criteria for Head Loss rate limits (PH) as follows:
DN<=150, 5m/km
DN>=200, 3m/km
Maximum allowable velocity: 2.5m/s
2.2 Sewerage
2.2.1 Gravity Sewer
Per Capita Flow:
Average Dry Weather Flow (ADWF) = 200 L/EP/d
For RIGS1
Peaking Factor:
Peak Wet Weather Flow (PWWF) = 5 x ADWF
Friction Coefficient – Manning’s ‘n’ =0.0128
2.2.2 Pumping Stations
Minimum Operational Volume of Wet Well (m3) = (0.9 x Pump Rate)/N
Where pump rate is in L/s
N=12 for motors<100kw
N=8 for 100-200kw
N=5 of motors >200kw
Single Pump Capacity = C1 x ADWF
Where C1 = 15 x (EP) – 0.1587
Total Pump Station Capacity = 5 x ADWF
2.2.3 Rising Mains
Preferred Velocity: 1.0 – 1.5 m/s
1 RIGS: Reduced Infiltration Gravity Sewers
Water Supply & Sewerage Infrastructure for Yaroomba Beach | 5
3 ESTIMATED POPULATION AND FLOW
3.1 Equivalent Population
Various methods have been used to calculate the demand, with the demand assumptions summarised in Table 1. Rates used in other SEQ tourism areas2 have been considered in this assessment as they provide a further breakdown for hotel rooms and multi-unit dwellings not currently covered by the Unitywater guidelines. The equivalent population associated with the full proposed development has been calculated in Table 2 to allow assessment of the impact of the development on the surrounding water supply and sewerage networks.
Table 1 – Demand Assumptions, for three calculation methods
Type of Dwelling Assumed Development
Type Unit EPW/Unit EPS/Unit
Method 1: Unitywater Schedule of Works3
Single Dwelling Detached Residential Dwelling ET 2.7 2.7
Hotel Rooms Serviced Apartments Apartments
Attached Residential Dwelling ET 1.8 2.7
Retail (Internal/External) Commercial (Retail/Hotel)
Centres 100 m2 GFA 1.32 1.54
Community Space (Internal/External)
Community 100 m2 GFA 3.13 3.13
Method 2: Unitywater proposed Schedule of Works changing Hotels4, still subject to review
As per Method 1, except hotel
Hotel Rooms Hotel 100 m2 GFA 2.4 2.4*
Method 3: Alternative SEQ Tourism Rates2 ET/Unit EP/Unit**
Single Dwelling Detached Dwelling dwelling 1 2.7
Hotel Rooms Motel / Hotel bedroom 0.6 1.62
Serviced Apartments Apartments
Multi Unit Dwelling 1 bedroom Multi Unit Dwelling 2 bedroom
dwelling 0.47 0.63
1.27 1.70
Retail (Internal/External) Retail 100 m2 GFA 0.6 1.62
Commercial (Retail/Hotel) Commercial (other) 100 m2 GFA 0.6 1.62
Community Space (Internal/External)
Conference / meeting venue 100 m2 GFA 1.6 4.32
*Assumed to be the same as EPW ** EP/ET = 2.7 for Unitywater as per SEQ Code Design Criteria, Appendix A
2 SEQ Code Design Criteria – Table A2 Typical Water and Wastewater Supply Demand Generation Rates for Development Types (Gold Coast Area), Version 1.0 – 1 July 2013 3 Unitywater Schedule of Works, Version 1.0, 25 June 2014 – Section 1.3 4 As supplied by Unitywater 20/02/2017
Water Supply & Sewerage Infrastructure for Yaroomba Beach | 6
Table 2 – Estimated Equivalent Full Development Population, for three calculation methods
Type of Dwelling Qty Unit
Method 1: Unitywater
Method 2: Unitywater
Proposed, with Hotel adjusted
Method 3: Alternative
SEQ Tourism Rates
EPW EPS EPW EPS EP
(EPW & EPS)
Hotel
Rooms 220
(16,202) Bedroom
(GFA) 396 594 389 389 356
Dual Key Serviced Apartments* (42 x 1 bed, 28 x 2 bed)
70 dwelling
392 589 293 388 335
Serviced Apartments (35 x 1 bed, 43 x 2 bed)
78 dwelling
Sub Total Hotel 368 - 788 1,183 682 777 691
Residential
Apartment (2 bed) 757 dwelling 1,363 2,044 1,363 2,044 1,288
Single Dwelling 102 dwelling 275 275 275 275 275
Sub Total Residential 859 - 1,638 2,319 1,638 2,319 1,563
Retail / Commercial 3,549 GFA 47 55 47 55 58
Community 356 GFA 11 11 11 11 15
TOTAL 2,484 3,568 2,378 3,162 2,327
* Note for the dual key apartments the following has been assumed for the calculation of loads: 1-bedroom apartment = 2 x hotel rooms 2-bedroom apartment = 1 x hotel room + 1 x 1 bedroom apartment
There is a significant variance between the EP loads calculated using the Alternative SEQ Tourism and Unitywater demand rates. Method 2: Unitywater Proposed, will be adopted in this report as it provides a conservative estimate, while still recognising the difference between a hotel and a detached dwelling. The reduced load using Method 3: Alternative SEQ Tourism Rates, should also be considered for this development given the adoption of water saving initiatives discussed in Section 4.
It should also be noted that some of the GFA included in the Retail / Commercial use is located within the hotel, and therefore the load may already be covered by the hotel load calculation. However, at this stage, for a conservative approach, it has been included separately.
Water Supply & Sewerage Infrastructure for Yaroomba Beach | 7
3.2 Staging Plan
The proposed development is to be implemented in five precinct stages, as shown in Appendix A. The configuration of the precincts is outlined in Table 3. This staging plan has been factored into the assessment of water and sewerage infrastructure requirements.
Table 3 – Staging Plan (Using Method 2: Unitywater Proposed calculation method)
Precinct Type of Dwelling Qty EPW EPS
1
Hotel Rooms 220
(16,202 m2 GFA) 389 389
Serviced Apartments 148 293 388
Single Dwellings 16 43 43
Retail / Commercial / Community 3,905 m2 GFA 58 66
SUB-TOTAL 783 886
2
Apartments (2 bed) 139 250 375
Single Dwelling 10 27 27
SUB-TOTAL 277 402
3
Apartments (2 bed) 152 274 410
Single Dwelling 32 86 86
SUB-TOTAL 360 497
4
Apartments (2 bed) 178 320 481
Single Dwelling 24 65 65
SUB-TOTAL 385 545
5
Apartments (2 bed) 288 518 778
Single Dwelling 20 54 54
SUB-TOTAL 572 832
TOTAL 2,378 3,162
Water Supply & Sewerage Infrastructure for Yaroomba Beach | 8
Based on the staging plan in Table 3, a cumulative growth curve is illustrated in Figure 1.
Figure 1 Projected Growth Curve
3.3 Projected Water Demands and Sewage Loads
The projected water supply demand and sewage loads for the proposed development site have been assessed based on the estimate equivalent population and the design criteria as outlined in Section 2. These are outlined in Table 4 and Table 5 respectively.
Table 4 – Projected Potable Water Demand (Using Method 2: Unitywater Proposed)
Precinct EPW AD* MDMM PD PH
L/s kL/day kL/day kL/day L/s
Hotel 682 2.1 177 256 334 7.5
Residential 1,638 4.9 426 614 803 18.0
Retail / Commercial / Community
58 0.2 15 22 28 0.6
Total 2,378 7.2 618 892 1,165 26
*including NRW
0
500
1,000
1,500
2,000
2,500
3,000
3,500
1 2 3 4 5
Esti
mat
ed
Po
pu
lati
on
(EP
)
Stage
Total EP Water Total EP Sewer
Water - Hotel & Serviced Apartments Sewer - Hotel & Serviced Apartments
Water - Retail / Community Sewer - Retail / Community
Water - Residential Sewer - Residential
Water Supply & Sewerage Infrastructure for Yaroomba Beach | 9
Table 5 – Projected Sewage Loads (Using Method 2: Unitywater Proposed)
Precinct EPS ADWF PWWF
kL/d L/s kL/d L/s
Hotel 777 155 1.8 777 9
Residential 2,319 464 5.4 2,319 27
Retail / Commercial / Community
66 13 0.2 66 0.8
Total 3,162 632 7.3 3,162 37
3.4 Outdoor Water Use
The proposed development consists of large areas of open space that would require irrigation. These areas include a central Lake area, generous landscaped corridors and buffer strips along David Low Way.
The landscape architects have previously estimated peak irrigation demand would be in the order of 0.14 ML/d (based on irrigating 50% of the softscape). At this stage irrigation demand has been based on this estimated.
It is proposed that an alternative non-potable water source such as spear bores or rainwater harvesting be used for outdoor irrigation, supplemented by potable water only when necessary. Refer to Section 4.2.
3.5 Comparison to Historical Development Proposal
In 2005, a development proposal was assessed for the Yaroomba Beach site, as part of the Hyatt Coolum project. The proposal covered a larger area, with the area covered in this assessment known as the Beachside Precinct. Since this previous assessment, both the estimated population for the site and the applied DSS have changed, impacting on the water and sewerage infrastructure required to accommodate growth at the site.
Key changes and their impacts are outlined below:
The estimated population of the proposed development has increased since 2005
Unit water demands have reduced significantly since 2005
The estimated water demand for the site has increased since 2005
For the wider Coolum Area, the total projected water demand has reduced by around 40%, resulting in significant spare capacity in the existing water network
Unit sewage loads have reduced since 2005
The estimated sewage load for the site has increased since 2005.
Water Supply & Sewerage Infrastructure for Yaroomba Beach | 10
4 INTEGRATED WATER CYCLE MANAGEMENT
4.1 Demand Management
The historical plans for the site were developed in 2005, since then unit water demands have significantly reduced, due to changed community behaviours around water conservation, the widespread introduction of water efficient appliances and improved system management. Therefore, opportunities to achieve significant water savings through targeted demand management strategies have also reduced.
Current average water usage across the Unitywater service area is reported to be lower than the design unit demand of 230L/EP/day.
It is possible that the development of Yaroomba Beach can maintain lower than average water consumption through strategies such as:
Native vegetation and drought tolerant landscapes
Source substitution (refer Section 4.2).
4.2 Alternative Water Sources
There are a range of non-potable water sources that could be considered as part of an integrated water strategy for Yaroomba Beach.
Alternative Water Sources include:
Rainwater harvesting
Stormwater harvesting
Ground water extraction
Recycled water from a centralised facility
Localised sewer mining.
The key non potable water uses include:
Toilet Flushing (via Dual Reticulation) – not feasible or endorsed by Unitywater
Irrigation of gardens and landscaped areas – recommended
Topping up the Lake (not included in EP calculations) – recommended.
Table 6 – Preliminary Assessment of Alternative Water Sources
Option Advantages Constraints Recommendation
Rainwater Harvesting (roof)
Reduces runoff and erosion
Potential improvement in local waterway health
Widely accepted by community
Minimal design requirements
Controlled catchment and first flush devices achieve a relatively high water quality
Increased electricity consumption to operate rainwater pumps
Limited yield per dwelling due to spatial constraints i.e. limited roof space and large water tanks etc.
Should be considered
Water Supply & Sewerage Infrastructure for Yaroomba Beach | 11
Option Advantages Constraints Recommendation
Stormwater harvesting
Utilises future impervious surfaces
Large storage capacity reduces localised flooding
Improves water quality
Can be aesthetically pleasing e.g. wetlands, buffer zones etc.
Opportunity to incorporate WSUD principals such as swales and litter traps
Large investment required upfront for design and construction
Larger ongoing maintenance requirements / costs for WSUD treatment devices to be borne by body corporate or Council
Risk of over extraction of stormwater flows impacting on natural environment
Impact on development layout
Should be incorporated
where possible
Groundwater Harvesting
Reduced storage and distribution requirement as can be extracted as needed and where needed
Limited treatment required
Over extraction could impact on lake levels and cause salt water intrusion
Increased energy consumption through use of pumps
Should be incorporated for
Open Space Irrigation
Recycled water
Reliable supply achieves large reduction in potable water usage
Reduction in wastewater discharge volume and loading
Effective short-term water supply for irrigation while Coolum STP operational
Potentially sunk costs if infrastructure becomes redundant once the STP is decommissioned
Large investment required upfront for design and construction of distribution network
Large maintenance/labour costs
Further treatment is likely to be required to bring the water quality up to Class A+ required for public irrigation and topping up of the lake.
Not considered feasible due to loss of supply in
the future.
Sewer mining
Source for non-potable water for irrigation of open spaces after decommissioning of Coolum STP i.e. long-term solution
Potentially large reduction in potable water usage
Reduces wastewater loads on trunk network, reduces sewer overflows
Reduction in wastewater discharge volume and loading
Large investment required upfront for design and construction
Larger ongoing maintenance requirements / costs to be borne by body corporate or Council
Most expensive solution
Should be considered only if a need for a large
and reliable source of non-
potable water is identified
While demand management through source substitution could be implemented at Yaroomba Beach to reduce potable water demand, significant work would be required to develop a sound business case to negotiate an associated reduction in potable water supply infrastructure requirements.
For the purpose of this initial investigation, zero reduction in potable water demand has been adopted as a conservative basis for the water supply infrastructure assessment outlined in Section 5.
Water Supply & Sewerage Infrastructure for Yaroomba Beach | 12
5 WATER SUPPLY INFRASTRUCTURE
The following sections outline the water supply infrastructure required to accommodate for the proposed development of Yaroomba Beach.
For the purpose of this initial investigation, zero reduction in potable water demand has been adopted as a conservative basis for the assessment of water supply infrastructure requirements.
5.1 Bulk Water Source Capacity
Water supply for the Coolum area is sourced from Image Flat WTP, which is located approximately 30km to the south west of Coolum. A new off take and cross connection to the Northern Pipeline Interconnector (NPI) is currently being implemented downstream of Image Flat WTP, to supplement supply to the Coolum area from the SEQ Water Grid.
On this basis, source water capacity is considered adequate to support future growth in the area, including the proposed development.
5.2 Bulk Water Network Capacity
Planning undertaken by Unitywater in 2010 identified that the existing bulk water network which extends between Image Flat WTP / NPI and Coolum and onto the Peregian Springs growth area, is currently operating at capacity. Parts of this system have a history of frequent failure.
Based on past planning, any future growth in Coolum or Peregian Springs would trigger a major augmentation of this system known as the North Shore Mains, at an estimated capital cost of $40M - $50M. Unitywater developed a staged implementation plan extending between 2011 and 2021. The practicality of this solution is problematic due to alignment issues and is subject to detailed planning.
The adoption of new design standards in June 2013 as part of the SEQ Design and Construction has resulted in a 40% reduction in adopted water demands. It is likely that this significant change will effectively defer the need for future augmentation of the North Shore Mains until 2026. Renewal or reconfiguration of this system may still be required to address recent failures.
The impact of reduced demands on planned augmentations was being assessed by Unitywater in 2013. Based on discussions with Unitywater in 2013, the assessment and augmentation of the North Shore Mains is considered to be a regional issue outside the scope of a development application for Yaroomba Beach. Further assessment by Unitywater and liaison between regional stakeholders is required to determine the need for augmentation and the preferred approach.
5.3 Storage Requirements
The proposed development site falls within the Coolum Intermediate Level Zone (ILZ), supplied from the 13.3ML Lang Street Reservoir (TWL 70m AHD) which is located directly north of the site. Supply currently passes through the Lang Street Reservoir before being delivered to both the Coolum Low Level and Peregian Springs zones.
The Ground Level storage requirements for Yaroomba Beach are 1.3 ML based on the current DSS. Based on current DSS the capacity of the Lang Street Reservoir is adequate across all planning horizons, as shown in Table 7, and has sufficient spare capacity at 2031 (4.8 ML) to accommodate the proposed development at Yaroomba Beach.
Water Supply & Sewerage Infrastructure for Yaroomba Beach | 13
Table 7 – Reservoir Storage Analysis (2017 DSS and Population Forecast, Unitywater) – Excluding current Yaroomba Beach Proposal
Year Population
Demand L/s Demand ML/d
Current Capacity
Required Capacity
Spare Capacity
Storage Capacity
EP AD MDMM MD PH AD MDMM MD ML ML ML ML
2014 14,841 45 64 84 163 3.9 5.6 7.3 13.3 6.0 7.3 Adequate
2016 15,331 46 67 87 169 4.0 5.7 7.5 13.3 6.2 7.1 Adequate
2021 16,584 50 72 94 182 4.3 6.2 8.1 13.3 6.8 6.5 Adequate
2026 18,429 55 80 105 203 4.8 6.9 9.0 13.3 7.5 5.8 Adequate
2031 20,373 61 88 116 224 5.3 7.6 10.0 13.3 8.3 5.0 Adequate
2036 20,924 63 91 119 230 5.4 7.8 10.3 13.3 8.5 4.8 Adequate
Water Supply & Sewerage Infrastructure for Yaroomba Beach | 14
Previous planning allows for a 6ML augmentation of the Lang Street reservoir in 2026 to cater for growth in the area outside of the Coolum Intermediate Level zone (therefore not relevant to Yaroomba Beach) as construction of additional storage at both Coolum High Level Reservoir and the Coolum Low Level Reservoirs sites is not feasible.
5.4 Trunk Network
In 2010, Unitywater constructed a dedicated DN375 outlet main from Lang Street Reservoir down Wattle Street, over a length of 670 m. This main increased the capacity of supply to the area and improved general system operation, and was required to accommodate future growth at Yaroomba Beach.
The capacity of the remaining external trunk network is adequate to cater for the proposed development. An existing DN300 trunk water main runs along David Low Way, directly past the proposed development site. Under worst case conditions (Fire flow plus peak demand) the velocity in this main does not exceed the maximum allowable velocity of 2.5 m/s and sufficient pressure can be maintained across the development.
5.5 Connection & Metering
The proposed connection to the Unitywater network is at the proposed main entry to the development on David Low Way. It is a Unitywater requirement to install a master meter at the boundary of community title developments, with sub-meters within the development. Unitywater may give approval for independent water services, with no master meter, if there is no common property usage. For this development, common property usage is expected and therefore a master meter, with sub-meters will be required.
5.6 Reticulation Network
Preliminary internal layouts for water supply infrastructure have been developed based upon the proposed internal road layout. The internal layouts are within private property and are therefore subject to Plumbing Approval through Council, rather than Unitywater approval. The exact configuration and sizing of the network will be developed at a later stage of the project, however it is expected that it will consist of the following:
A potable water supply loop main
A boosted fire main to service street hydrants, and hose reels and sprinklers in the apartment buildings and hotel.
Water Supply & Sewerage Infrastructure for Yaroomba Beach | 15
6 SEWERAGE INFRASTRUCTURE
6.1 Sewage Treatment Strategy
Sewage for the Coolum area is currently directed to Coolum Sewage Treatment Plant (STP), located approximately 3km west of the proposed development area. A small recycled water scheme is also in place to distribute treated effluent from the Coolum STP to irrigate the Palmer Coolum Resort & Golf Course and nearby public golf course on an as needed basis. The remainder of treated effluent from this plant is transported south and discharged to the Maroochy River downstream of the confluence with Coolum Creek.
The Coolum STP is generally considered to be in fair to good condition. A demonstration wetland was constructed at the STP, with the trial due to finish in 2019.
In 2013 Unitywater was developing a long term treatment strategy which provided a blueprint for investing in wastewater infrastructure for the Sunshine Coast over the next 50 years (CH2MHill Treatment Services Strategy - Strategy Report, November 2012). This strategy involved the decommissioning of Coolum STP in 2019 and diverting the sewage south to the Kawana STP. Unitywater has since revisited this strategy and it is likely that Coolum STP will be diverted to the Maroochydore STP instead, however the timing of this is not yet known.
The timing of this diversion will be subject to future detailed planning and business case development by Unitywater. However, based on the adopted strategy, projected growth at Yaroomba Beach (3,162 EP) would ultimately need to be catered for at the Maroochydore or Kawana STPs.
The scope and associated cost of infrastructure required to implement the diversion of sewage from Coolum STP to the Maroochydore or Kawana STPs will be significant and subject to extensive further investigation by Unitywater. This strategic diversion is considered outside the scope of a development application for Yaroomba Beach.
6.2 Trunk Network
The overall treatment strategy is likely to have a minimal impact on the local sewerage network. Sewage will continue to be transferred to the Coolum STP site, where it will be re-pumped to the Maroochydore or Kawana STP.
Previous planning for the area was based on the assumption that growth within Yaroomba Beach area would be directed south to the existing pump station CLM087 which injects into a common rising main with CLM085, extending directly west to the Coolum STP. With any additional growth on the western side of David Low Way directed north to CLM091, which injects into a large common rising main system which extends down from CLM081 and receives injected flow from CLM097, CLM091 and CLM096 prior to discharging to Coolum STP.
It is proposed that this plan is maintained, and all loading from Yaroomba Beach directed towards pump station CLM087. This system would have sufficient capacity to cater for flow from over half of the development, up to Precinct 4. For Precinct 4 and 5, pump station CLM087 would need to be augmented to increase the flow by 17 L/s. These calculations are based on Method 2: Unitywater Proposed (Table 2), however if a less conservative load was adopted, as per Method 3: Alternative SEQ Tourism Rates (Table 2), the flow rate would be reduced by 10 L/s to 27 L/s, bringing the projected load at 2031 for CLM087 to 60 L/s, reducing the augmentation of the pump station to only 7 L/s and delaying it until Precinct 5.
Water Supply & Sewerage Infrastructure for Yaroomba Beach | 16
Table 8 – Pump Station Assessment
Pump Station
Existing dual pump
capacity (L/s)
Projected Load at 2036
(L/s)
Spare Capacity at
2036 (L/s)
Load from Yaroomba
Beach (L/s)
New Projected
Load at 2036 (L/s)
Capacity
CLM087 53 33 20 37 70 Augmentation
Needed
Increase 17
In an earlier assessment undertaken in 2013, for a different layout, it was estimated that the increase in flow at CLM087 would be 21 L/s. This required a pump station augmentation. While the single rising main downstream of CLM087 would have sufficient capacity across all planning horizons, the length of combined rising main downstream of CLM085 (Points B to C) would have required augmentation (approximately 1,500 m of DN300) when the pump station was upgraded. Appendix B shows a marked-up excerpt of the Coolum Sewerage Scheme Network Master Plan - Existing Sewer Network (South) from 2013 showing the layout of the existing and proposed system upgrade (Green line).
Given the increase in flow is now 17 L/s, it is likely that similar upgrades will be required to the pump station and rising main. Further discussions with Unitywater will be required during the approval phase to determine the need for and the timing of any upgrades required.
6.3 Reticulation Network
The early stages of the original Beachside Precinct are currently serviced by a private sewerage network, including a pump station which was designed to cater for the historical 2005 development proposal. This pump station has sufficient depth to receive gravity flow from across the Yaroomba Beach site. Negotiation with the asset owners is required to determine the possibility of utilising available capacity in the existing private sewerage network.
While details of the existing private assets have not been provided, it is understood that this pump station and rising main have sufficient capacity to cater for 27 L/s PWWF, which is sufficient for up to and including Precinct 3 (23 L/s PWWF) plus the previous residential precinct. Augmentation or a new pump station and rising main would be required ahead of Precinct 4 on the basis of the proposed staging plan.
Preliminary internal layouts for sewerage reticulation infrastructure have been developed based upon the site contours and finished surface levels, with consideration to the final internal road layout. The internal layouts are within private property and are therefore subject to Plumbing Approval through Council, rather than Unitywater approval. The exact configuration and sizing of the network will be developed at a later stage of the project.
6.4 Recycled Water
A small recycled water scheme is also in place to distribute treated effluent from the Coolum STP to irrigate the Palmer Coolum Resort Golf Course and nearby public golf course on an as needs basis.
The overall sewerage treatment strategy for the Sunshine Coast involves decommissioning the Coolum STP, which will end the supply of recycled water to the Coolum area. All wastewater will be redirected to the Maroochydore or Kawana STP, and Unitywater does not have plans to implement a new recycled water scheme to distribute treated effluent for open space irrigation at this stage. The timing for this has not yet been finalised.
Given that a long term supply of recycled water supply is unavailable, a localised sewer mining facility could be considered to maintain recycled water supply to the Coolum area, however it is unlikely
Water Supply & Sewerage Infrastructure for Yaroomba Beach | 17
that this system would be feasible for Yaroomba Beach in isolation and should be considered on a regional scale. The preferred location for a facility would be at the existing Coolum STP site to utilise available treatment, storage and recycled water distribution infrastructure where possible.
Water Supply & Sewerage Infrastructure for Yaroomba Beach | 18
7 CONCLUSIONS
The following conclusions can be drawn from this study:
Population and Demand
The estimated population of the proposed development is approximately 2,378 Equivalent Persons for Water (EPW) and 3,162 EP for Sewer (EPS).
The estimated population is made up of three areas:
o Short-term (Hotel & Serviced Apartments): 682 EPW & 777 EPS
o Residential: 1,638 EPW & 2,319 EPS
o Retail / Commercial & Community: 58 EPW & 66 EPS
Unit water demands have reduced significantly (40%) since 2005 across South East Queensland.
The proposed water demand for Yaroomba Beach is 0.62 ML/day (average day).
The projected sewage load for Yaroomba Beach is 0.63 ML/day (average dry weather flow).
The demand for non-potable water for irrigation is estimated to be 0.14 ML/day (peak day).
Demand Management
Given water demands have significantly reduced since 2005, there is limited opportunity to achieve additional water savings through targeted demand management strategies.
The following demand management initiatives are recommended at Yaroomba Beach:
- Native vegetation and drought tolerant landscapes
- A combination of stormwater and ground water harvesting (spear bores) to source water for open space irrigation.
The supply of recycled water to the Coolum area will stop following the planned decommissioning of Coolum STP. A localised sewer mining facility could be implemented to maintain a reliable non-potable supply to irrigate local golf courses and open spaces; however, it is unlikely that this system would be feasible for Yaroomba Beach in isolation and should be considered on a regional scale.
Water Supply Assessment
Water supply for the Coolum area is sourced from Image Flat WTP, supplemented by the SEQ Water Grid via a cross connection to the NPI. Source water capacity is adequate to support projected future growth in the area.
Water supply to the Coolum area is currently constrained by the capacity of the North Shore Trunk Mains. Unitywater are investigating the staged augmentation of this system and advised in 2013 that this bulk supply issues are outside the scope of a development assessment.
The proposed development site falls within the Coolum Intermediate Level Zone (ILZ). There is adequate storage capacity to accommodate growth across all planning horizons and the external trunk network has sufficient capacity to cater for growth.
Water Supply & Sewerage Infrastructure for Yaroomba Beach | 19
The internal water reticulation network will be within private property and therefore subject to Plumbing Approval through Council, rather than Unitywater approval. It will consist of both a potable water supply loop main and a separate fire main. The exact configuration and sizing of the network will be developed at a later stage of the project.
Sewerage Assessment
Sewage for the Coolum area is currently directed to Coolum Sewage Treatment Plant (STP). Based on a long term servicing strategy, this STP shall be decommissioned and flow diverted south to the Maroochydore or Kawana STPs. The timing of this diversion is not yet confirmed and will be subject to future detailed planning. Sewage from Coolum will continue to be transferred to the Coolum STP site, where it will be re-pumped to the Maroochydore or Kawana STP.
The preferred strategy for Yaroomba Beach is to direct flow to the existing pump station CLM087 which injects into a common rising main with CLM085, extending directly west to the Coolum STP. It is expected that this has capacity for up to the first three precincts, however further discussions with Unitywater will be required during the approval phase to determine the need for and the timing of any upgrades required.
There is a private sewerage network which provides an existing connection to the Yaroomba Beach site and should have sufficient capacity to cater for the first three precincts, plus the existing residential precinct. Coordination with the Body Corporate / asset owner is required to facilitate the connection. Augmentation or a new internal pump station and rising main would be required prior to Precinct 4.
Preliminary internal layouts for sewerage reticulation infrastructure have been developed based upon the site contours and finished surface levels, with consideration to the final internal road layout. The internal layouts are within private property and are therefore subject to Plumbing Approval through Council, rather than Unitywater approval. The exact configuration and sizing of the network will be developed at a later stage of the project.
Water Supply & Sewerage Infrastructure for Yaroomba Beach | 20
APPENDIX A MASTERPLAN LAYOUT
5-7 STOREY RESORT COMPLEX2, 7 STOREY SERVICED APARTMENTS
4 STOREY APARTMENTS
4 STOREYAPARTMENTS
EXISTING RESIDENTIAL
4 STOREY APARTMENTS
3 STOREY DWELLINGS
4 STOREYAPARTMENTS
VILLAGE CENTRE
FRONTAL DUNE
PARABOLIC DUNE
LAKE
LAKE
PARK
BEACH
DAVID LOW WAY
4 STOREY APARTMENTS
1 STOREYTRANSFERSTATION
ENTRY
PRECINCT 5LAKESIDE NORTH
3 STOREY DWELLINGS
PRECINCT 4LAKESIDE SOUTH
PRECINCT 2YAROOMBA BEACHCENTRAL
PRECINCT 3YAROOMBA BEACH SOUTH
4 STOREYAPARTMENTS
2STO
REY
DWEL
LING
S
3 STOREY DWELLINGS3 STOREY DWELLINGS
PRECINCT 1YAROOMBA BEACH NORTH
3 STOREY DWELLINGS
LOT 14 SP238214
LOT 902 SP269561
1 STOREY RETAIL & SURFLIFE SAVING AMENITIES
LOT 19 SP238214
EXISTING BEACHACCESS PATH
EXISTING BEACHACCESS PATH
COOLUMBEACHSIDECTS 38537
BELLE MARECTS 431571-2 STOREY
RETAIL,EDUCATIONCENTRE,COMMERCIAL
KEYEXISTING TREESTO BE RETAINED
PRECINCT BOUNDARY
DEVELOPMENT ZONE
0 20 40 80m
1:1000
Scale Project Name Drawing
HASSELLOriginal Sheet Size A1- 841 x 594mm
Revision Date
1 : 1000 @ A1 A_0002YAROOMBA BEACHMASTERPLAN MASTERPLAN - PROPOSED
A DEVELOPMENT APPROVALAPPLICATION
10-03-17
Water Supply & Sewerage Infrastructure for Yaroomba Beach | 21
APPENDIX B PREVIOUSLY PROPOSED AUGMENTATIONS (2013)
Water Supply & Sewerage Infrastructure for Yaroomba Beach | 22
DOCUMENT / REPORT CONTROL FORM
Project Name: Yaroomba Beach Water Supply & Sewerage Infrastructure Assessment
Project Number: 30031110
Revision Number: 6
Revision History
Revision # Date Prepared by Reviewed by Approved for Issue by
1 30-07-2013 Alice Twomey Sarah Board Chris Green
2 9-08-2013 Sarah Board Chris Green Chris Green
3 23-08-2013 Sarah Board Chris Green Chris Green
4 11-09-2013 Sarah Board Chris Green Chris Green
5 24-04-2017 Karina Thiele Carl Wilkinson Carl Wilkinson
6 03-05-2017 Karina Thiele Carl Wilkinson Carl Wilkinson
Issue Register
Distribution List Date Issued Number of Copies
Unity Water 1
SH Coolum Pty Ltd 1
Office Library [South Brisbane] 1
SMEC Project File 1
SMEC Company Details
Carl Wilkinson
Level 1, Building C, 6 Innovation Pkwy, Birtinya QLD 4575
Tel: +61 7 3029 6700 Fax: +61 7 5437 6525
Email: [email protected] Website: www.smec.com
The information within this document is and shall remain the property of:
SH Coolum Pty Ltd