Page 1: Shepherd Elementary School SIT Presentation (February 17, 2016)

Elevating the Quality of Life in the District

Page 2: Shepherd Elementary School SIT Presentation (February 17, 2016)

Agenda SITE VIEW SECTIONS CONSTRUCTION STRATEGY

TIMELINE – JUNE 2013 TO JULY 2015 TIMELINE – AUGUST 2015 TO APRIL 2016 TIMELINE – EASTER BREAK 2016 TIMELINE – APRIL 2016 TO JULY 2016

ACCESS & FLOW Foundation to Grade Building Permit Building Permit

NEXT STEPS 18, Feb. to 3, Mar. Activities two week look ahead. Construction Images of Courtyard & 1956 Building. Construction Milestone. Frequently Asked Questions.

Q & A

Elevating the Quality of Life in the District

Page 3: Shepherd Elementary School SIT Presentation (February 17, 2016)

Elevating the Quality of Life in the DistrictElevating the Quality of Life in the District

RULES OF THE ROAD RESPECT EACH OTHER

CELLPHONES OFF OR ON VIBRATE

Q&A WILL BE TAKEN AT THE END OF THE PRESENTATION

Page 4: Shepherd Elementary School SIT Presentation (February 17, 2016)

Elevating the Quality of Life in the DistrictElevating the Quality of Life in the District

SITE VIEW

Page 5: Shepherd Elementary School SIT Presentation (February 17, 2016)

Elevating the Quality of Life in the DistrictElevating the Quality of Life in the District

COURTYARD

AFTER RENOVATION AFTER RENOVATIONBEFORE RENOVATION

BEFORE RENOVATION

Page 6: Shepherd Elementary School SIT Presentation (February 17, 2016)

Elevating the Quality of Life in the District

MEDIA CENTERAFTER RENOVATIONBEFORE RENOVATION

Page 7: Shepherd Elementary School SIT Presentation (February 17, 2016)

Elevating the Quality of Life in the District

BEFORE RENOVATION AFTER RENOVATIONSOUTH ELEVATION

Page 8: Shepherd Elementary School SIT Presentation (February 17, 2016)

Elevating the Quality of Life in the District

AFTER RENOVATIONBEFORE RENOVATION

REAR ELEVATION

Page 9: Shepherd Elementary School SIT Presentation (February 17, 2016)

Elevating the Quality of Life in the District

BEFORE RENOVATION AFTER RENOVATION

MAIN ENTRANCE

Page 10: Shepherd Elementary School SIT Presentation (February 17, 2016)

Elevating the Quality of Life in the District

SECTIONS

Page 11: Shepherd Elementary School SIT Presentation (February 17, 2016)

Elevating the Quality of Life in the District

COURTYARD

Page 12: Shepherd Elementary School SIT Presentation (February 17, 2016)

Elevating the Quality of Life in the District

FIVE STOPS ELEVATOR

Page 13: Shepherd Elementary School SIT Presentation (February 17, 2016)

Elevating the Quality of Life in the District

CONSTRUCTION STRATEGY

TIMELINE – JUNE 2013 TO JULY 2015

Page 14: Shepherd Elementary School SIT Presentation (February 17, 2016)

Elevating the Quality of Life in the District

GROUND FLOOR PLAN

SECOND FLOOR PLAN

FIRST FLOOR PLAN

Page 15: Shepherd Elementary School SIT Presentation (February 17, 2016)

Elevating the Quality of Life in the District

CONSTRUCTION STRATEGY

TIMELINE – AUGUST 2015 TO APRIL 2016

Page 16: Shepherd Elementary School SIT Presentation (February 17, 2016)

Elevating the Quality of Life in the DistrictElevating the Quality of Life in the District

SITE VIEW

Page 17: Shepherd Elementary School SIT Presentation (February 17, 2016)

Elevating the Quality of Life in the District

GROUND FLOOR PLAN

SECOND FLOOR PLAN

FIRST FLOOR PLAN

TIMELINE AUGUST 2015 – APRIL 2016

UNDER CONSTRUCTIONEGRESS DURING

CONSTRUCTION

LOGISTICS AND PHASING PLAN ARE CONTINENT UPON OBTAINING PERMITS AND DOEE APPROVALS PER TURNER’S SCHEDULE

Page 18: Shepherd Elementary School SIT Presentation (February 17, 2016)

Elevating the Quality of Life in the District

CONSTRUCTION STRATEGY

TIMELINE – EASTER BREAK 2016

Page 19: Shepherd Elementary School SIT Presentation (February 17, 2016)

Elevating the Quality of Life in the District

TIMELINE EASTER BREAK 2016

UNDER CONSTRUCTION

LOGISTICS AND PHASING PLAN ARE CONTINENT UPON OBTAINING PERMITS AND DOEE APPROVALS PER TURNER’S SCHEDULE

Page 20: Shepherd Elementary School SIT Presentation (February 17, 2016)

Relocation of IT Closet 1970 Building

Page 21: Shepherd Elementary School SIT Presentation (February 17, 2016)

Relocation of IT Closet 1970 BuildingSTORAGE ROOMS

SHEPHERD ELEMENTARY SCHOOLPHASE 2013-2016

ProposedProgram Area per Area per Room

• WORKROOM - 1 (First Floor Building 1931) 300 470 57%• WORKROOM - 2 (First Floor Building 1970 300 152 -49% TOTAL FOR WORKROOMS 600 622 4%

• STORAGE - 1 - BOOK STORAGE (Ground Floor) 400 433 8%• STORAGE - 2 (First Floor Building 1970) 400 79 -80%• SUPPLY STORAGE/RECEIVING (Ground Floor) 350 412 18% TOTAL FOR STORAGES 1,150 924 -20%

Page 22: Shepherd Elementary School SIT Presentation (February 17, 2016)

Relocation of IT Closet 1970 Building

Page 23: Shepherd Elementary School SIT Presentation (February 17, 2016)

Elevating the Quality of Life in the District

CONSTRUCTION STRATEGY

TIMELINE – APRIL 2016 TO JULY 2016

Page 24: Shepherd Elementary School SIT Presentation (February 17, 2016)

Elevating the Quality of Life in the District

SITE VIEW

Page 25: Shepherd Elementary School SIT Presentation (February 17, 2016)

Elevating the Quality of Life in the District

GROUND FLOOR PLAN

SECOND FLOOR PLAN

FIRST FLOOR PLAN

TIMELINE APRIL 2016 – JULY 2016

UNDER CONSTRUCTIONEGRESS DURING

CONSTRUCTION

LOGISTICS AND PHASING PLAN ARE CONTINENT UPON OBTAINING PERMITS AND DOEE APPROVALS PER TURNER’S SCHEDULE

Page 26: Shepherd Elementary School SIT Presentation (February 17, 2016)

Elevating the Quality of Life in the District

SITE VIEW

TWO CREPE MYRTLE TREES WILL BE RELOCATED

1

2

Page 27: Shepherd Elementary School SIT Presentation (February 17, 2016)

Excavation & Demo in Courtyard

Page 28: Shepherd Elementary School SIT Presentation (February 17, 2016)

Excavation & Demo in Courtyard

Page 29: Shepherd Elementary School SIT Presentation (February 17, 2016)

Excavation & Demo in Courtyard

Page 30: Shepherd Elementary School SIT Presentation (February 17, 2016)

Installation of Foundation System & Elevator Pit in Courtyard

Page 31: Shepherd Elementary School SIT Presentation (February 17, 2016)

Installation of Foundation System & Elevator Pit in Courtyard

Page 32: Shepherd Elementary School SIT Presentation (February 17, 2016)

Courtyard Retaining Wall Installation

Page 33: Shepherd Elementary School SIT Presentation (February 17, 2016)

Courtyard Retaining Wall Installation

Page 34: Shepherd Elementary School SIT Presentation (February 17, 2016)

Courtyard Concrete Slab Installation

Page 35: Shepherd Elementary School SIT Presentation (February 17, 2016)

Erection of Structural Steel in Cafeteria & Roof of 1956 Building

Page 36: Shepherd Elementary School SIT Presentation (February 17, 2016)

Erection of Structural Steel in Cafeteria & Sprinkler of 1956 Building

Page 37: Shepherd Elementary School SIT Presentation (February 17, 2016)

Erection of Structural Steel in the 1956 Building

Page 38: Shepherd Elementary School SIT Presentation (February 17, 2016)

Courtyard Concrete Slab Retaining Wall & Elevator Shaft Installation

Page 39: Shepherd Elementary School SIT Presentation (February 17, 2016)

1956 Building Addition Structural Steel Installation

Page 40: Shepherd Elementary School SIT Presentation (February 17, 2016)

1956 Building Addition Structural Steel, Framing Installation

Page 41: Shepherd Elementary School SIT Presentation (February 17, 2016)

1956 Building Addition Structural Steel, Framing Installation

Page 42: Shepherd Elementary School SIT Presentation (February 17, 2016)

1956 Building Addition Structural Steel, Framing Installation

Page 43: Shepherd Elementary School SIT Presentation (February 17, 2016)

1956 Building Addition Structural Steel, Framing Installation

Page 44: Shepherd Elementary School SIT Presentation (February 17, 2016)

1956 Building Addition Structural Steel Installation

Page 45: Shepherd Elementary School SIT Presentation (February 17, 2016)

Entrance Structural Steel Installation

Page 46: Shepherd Elementary School SIT Presentation (February 17, 2016)

Courtyard Structural Steel & Sprinkler Installation

Page 47: Shepherd Elementary School SIT Presentation (February 17, 2016)

1956 Building Addition Metal Deck Installation

Page 48: Shepherd Elementary School SIT Presentation (February 17, 2016)

1956 Building Addition Concrete Slab Installation

Page 49: Shepherd Elementary School SIT Presentation (February 17, 2016)

1956 Building Addition MEP Installation

Page 50: Shepherd Elementary School SIT Presentation (February 17, 2016)

1956 Building Addition Structural Steel Framing and MEP Installation

Page 51: Shepherd Elementary School SIT Presentation (February 17, 2016)

Courtyard Steel and Opening Installation

Page 52: Shepherd Elementary School SIT Presentation (February 17, 2016)

Courtyard Steel and Opening Installation

Page 53: Shepherd Elementary School SIT Presentation (February 17, 2016)

Courtyard Steel and Opening Installation

Page 54: Shepherd Elementary School SIT Presentation (February 17, 2016)

Playground Entrance Steel and Opening Installation

Page 55: Shepherd Elementary School SIT Presentation (February 17, 2016)

Elevating the Quality of Life in the District

SITE VIEW

TWO CREPE MYRTLE TREES WILL BE RELOCATED

1

2

Page 56: Shepherd Elementary School SIT Presentation (February 17, 2016)

Infiltration System Impact Crepe Myrtle Trees in Images

Page 57: Shepherd Elementary School SIT Presentation (February 17, 2016)

Infiltration System Impact Crepe Myrtle Trees Relocated

Page 58: Shepherd Elementary School SIT Presentation (February 17, 2016)

Silver Maple Tree Impact Relocated Crepe Myrtle Tree

Page 59: Shepherd Elementary School SIT Presentation (February 17, 2016)

Elevating the Quality of Life in the DistrictElevating the Quality of Life in the District

CONSTRUCTION MILESTONE COMMENCEMENT OF CONCRETE WORK; OCTOBER

COMMENCEMENT OF ELEVATOR SHAFT; NOVEMBER

COMMENCEMENT OF COURTYARD STRUCTURAL STEEL; DECEMBER

JANUARY

COMMENCEMENT OF MECHANICAL, ELECTRCAL & PLUMBING WORK

INFILTRATION TRENCH INSTALLATION

SPRINKLER MAIN SERVICE LINE INSTALLATION PARKING AREA

CONCRETE SLAB ON DECK INSTALLATION

1956 ADDITION EXTERIOR FRAMING

Page 60: Shepherd Elementary School SIT Presentation (February 17, 2016)

Shepherd ES Logoin Courtyard & Mural

Page 61: Shepherd Elementary School SIT Presentation (February 17, 2016)

Frequently Asked Questions1. Will the asphalt area on theplayground be repaired or replaced?Answer:- The asphalt will be repaired

2. The Mural on the concrete wall will not be impacted by the construction Activities.

3. All Egress routes are accessible during Construction Per Building Codes.

4. Air monitoring scheduled to be performed once per month.

5. Memorial Gardens will be restored.

Page 62: Shepherd Elementary School SIT Presentation (February 17, 2016)

Elevating the Quality of Life in the DistrictElevating the Quality of Life in the District

NEXT STEPS TWO WEEK LOOK AHEAD EXCAVATION ON INFILTRATION TRENCH AT SOUTH SITE

EXCAVATION OF SPRINKLER MAIN LINE PARKING AREA

ERECTION OF STRUCTURAL STEEL IN COURTYARD AND 1956 BUILDING

INSTALLATION OF 1956 ADDITION EXTERIOR FRAMING

INTERIOR PARTITION INSTALLATION

MEP INSTALLATION

Page 63: Shepherd Elementary School SIT Presentation (February 17, 2016)

Kenneth DiggsDGS Associate Director

DGS Government Affairs & [email protected]

(202) 580-9361