silver seven corporate centre phase 2
TRANSCRIPT
SERVICING BRIEF
Silver Seven Corporate Centre Phase 2
15 & 19 Frank Nighbor Place and 737 & 777 Silver Seven Road
Kanata, Ontario
Report No. 13047-SB
City of Ottawa Site Plan Control Application File Number: D07-12-14-0147
September 5, 2014 Revised February 19, 2015
D. B. G R A Y E N G I N E E R I N G I N C.
Stormwater Management - Grading & Drainage - Storm & Sanitary Sewers - Watermains
700 Long Point Circle 613-425-8044 Ottawa, Ontario K1T 4E9 [email protected]
1
SERVICING BRIEF
Silver Seven Corporate Centre Phase 2
15 & 19 Frank Nighbor Place and 737 & 777 Silver Seven Road Kanata, Ontario
The following Servicing Brief is a description of the services of Phase 2 of a proposed mixed-use commercial development located on a total of 4.9 hectares of land having frontage on Frank Nighbor Place and Silver Seven Road in Kanata. The description of the services for Phase 1 (2.2 hectares) is addressed in the Servicing Brief Report No. 12022-SWM (Revised February 25, 2013) prepared by D. B. Gray Engineering Inc. (City of Ottawa Site Plan Control Application File Number: D07-12-14-0147.) The proposed storm sewer and sanitary sewer systems Phase 2 (2.7 hectares) are independent of Phase 1 and will have separate connections to the municipal sewer system. Refer to the latest revision of drawings C-1 to C-4, prepared by D. B. Gray Engineering Inc. Water Supply for Fire Fighting: The site is located in the City of Ottawa water distribution network 3W Pressure Zone. There are two existing fire hydrants in the Frank Nighbor Place right-of-way and three existing fire hydrants in the Silver Seven Road right-of-way near the proposed development, 30m to 46m from the proposed buildings. Two on-site fire hydrant are proposed. They will be located 25m to 44m from the fire department connection for each building. (There is also an existing on-site fire hydrant located 44m from the main entrance of the Phase One building.) The fire flow requirements for each building (including the Phase One building) varies from 100 to 150 l/s, as calculated as per the Fire Underwriter Survey "Water Supply For Fire Protection". Each building will have a sprinkler system, as such, as per NFPA13, it is estimated that an additional flowrate of 500 USgpm (31.5 l/s) is required (includes the inside hose allowance). Therefore a maximum flowrate required for firefighting, including the maximum daily domestic demand of 8.4 l/s, is 189.9 l/s (150 + 31.5 + 8.4). A model was created using EPANET software to analyze the hydraulics of the proposed 250mm watermain and water distribution system using the following boundary conditions provided by the city were used:
At 19 Frank Nighbor Place: Max day + Fire Flow: 172 l/s at 150.9 m HGL At 737 Silver Seven Road: Max day + Fire Flow: 172 l/s at 153.0 m HGL New boundary conditions have been requested based on 189.9 l/s, when received the hydraulics will be recalculated. Under 172 l/s boundary conditions and a 106.6 to 123.2 l/s fire flow conditions the following are the summary of the results: Hydrant FH 1: 66.7 l/s at 539 kPa (83.1 psi) plus Athletic Club (Sprinklers) + Max Day: 35.4 l/s at 539 kPa (83.2 psi) Hydrant FH 2: 66.7 l/s at 400 kPa (62.7 psi)
plus Building C-1 (Sprinklers) + Max Day: 32.5 l/s at 539 kPa (60.4 psi)
Hydrant FH 3: 83.3 l/s at 529 kPa (81.2 psi) plus Building IL-1 (Sprinklers + Max Day): 33.4 l/s at 523 kPa (80.2 psi)
2
With the new boundary conditions it is expected that in all cases the water pressure will be above 138 kPa (20 psi) the proposed water distribution system will provide an adequate supply of water for fire fighting. Water Service: An existing private 250mm watermain connects to an existing 300mm municipal watermain at the end of Frank Nighbor Place terminates near the boundary between Phase 1 and 2. In Phase 2 the 250mm watermain will be extended and connect to an existing 300mm municipal watermain in Silver Seven Road. To service the sprinkler systems a 150mm water service is proposed for each building. Phase 1 & 2: Based on the City of Ottawa Design Guidelines the daily average consumption rate for a commercial development is 28,000 litres per day per hectare and 35,000 litres per day for industrial (used for Industrial Building IL-1). The daily average flow for the entire 4.9 hectare development is 5.6 l/s. Based on this flowrate and the City of Ottawa Design Guidelines for peaking factors of 1.5 and 1.8, a maximum daily demand of 8.4 l/s and a maximum hourly demand 10.1 l/s can be expected. The following boundary conditions provided by the city were used: At 19 Frank Nighbor Place: Maximum HGL: 163.2 m HGL Minimum HGL: 155.7 m HGL
At 737 Silver Seven Road: Maximum HGL: 163.7 m HGL Minimum HGL: 155.8 m HGL
Based on the above boundary conditions the water pressure in the area is calculated to vary from 577 kPa to 660 kPa (83.8 to 95.8 psi). Since the water pressure is above 80 psi it is recommended that at the completion of construction a pressure test be performed to determine if pressure reducing valves are required to be installed. Sanitary Service: Based on the on the Sanitary Drainage Plan, drawing No. 91005-SAN prepared by Novatech Engineering a design flow rate of 45,000 l/ha/day was used. Based on the City of Ottawa Sewer Design Guidelines for the commercial property part of the property (1.5 peaking factor); and the light industrial part of the property (Appendix 4-B – 1.03 ha – 6.6 peaking factor); and a 0.28 l/s infiltration flow) the post development flow for Phase Two is calculated to be 5.74 l/s. This flow will be adequately handled by the proposed sanitary sewer service (200mm @ 1.74% - 44.6 l/s capacity). The proposed sanitary service will connect to an existing 375mm municipal sanitary sewer in Silver Seven Road. The 5.74 l/s in sanitary flows contributing to the existing 375mm municipal sanitary sewer is expected to have an acceptable impact given its capacity of 115.7 l/s. (The sanitary sewer system for Phase One is independent of Phase Two and has a separate connection to the municipal storm sewer system.)
3
Stormwater: The Phase Two storm sewer system has been designed to meet the following stormwater quantity control criteria: The release rate for post-development storm events is equal to or less than a 50 litres per second flowrate (as per Novatech Drawing No. 91005-STM2). (The stormwater quantity control measure for Phase 1 was also 50 l/s.) The proposed storm sewer system and stormwater management for Phase 2 will be independent of Phase 1 and will have a separate connection to the municipal storm sewer system. In Phase Two stormwater will be stored within the development on the roof of the proposed buildings; on the surface in the car park area; in depressed landscaped areas (stormwater detention areas); and underground (in catch basins, manholes and sewer pipes). The Phase Two unrestricted flowrate resulting from one in five year storm event will produce a peak flow of 444.0 l/s. However an inlet control devices (ICDs) located at the outlet pipe of four on-site manholes will restrict the flow to a maximum flow of 37.2 l/s during the one in five year storm event. The restricted flow will be adequately handled by the proposed 450mm storm sewer (at 0.20% - 133.3 l/s). Stormwater will be conveyed off the site via the 450mm storm sewer connecting to a proposed manhole in a 750mm municipal storm sewer in Frank Nighbor Place. The restricted flow off the site is expected to a negligible impact on the existing 750mm municipal storm sewer given its capacity (at 0.20% - 519.4 l.s). Conclusions: 1. It is expected that there will be an adequate water supply for fire fighting. 2. The existing water pressure is adequate for the proposed development. 3. It is recommended that at the completion of construction a pressure test be
performed to determine if pressure reducing valves are required to be installed. 4. The proposed watermain and water distribution system is adequately sized to serve
the development. 5. The expected sanitary sewage flow will be adequately handled by the proposed
sanitary sewer service connection. 6. The increase in sanitary flows contributing to the existing 375mm municipal sanitary
sewer is expected to have an acceptable impact. 7. The proposed storm sewers are oversized to meet the quantity control criteria and
can adequately handled the flow produced by a 1:5 year storm.
4
Ottawa, Ontario
Fire Flow Requirements
COMMERCIAL BUILDING C-1 (Phase Two) - 1 Storey
Fire Protection Water Supply
F = 220 C A0.5
F = the required fire flow in litres per minute
C = coefficient related to the type of construction
= 1.5 for wood frame construction (combustible construction)
= 1.0 for ordinary construction (masonary wall, combustible floor and interior)
= 0.8 for non-combustible construction (unprotected structural components)
= 0.6 for non-combustible construction (protected structural components, floor and roof)
= 0.8
A = floor area
Floor Area: 1912 sq.m.
F = 7,696 L/min
= 8,000 L/min (rounded off to the nearest 1,000 L/min)
0% No Change: Combustible Contents
= 8,000 L/min
-40% Reduction: Sprinkler Protection - Not Supervised
= 4,800 L/min
Added to above Contents Fire Hazard for Separation Exposed Buildings
0% Side 1 > 45m
0% Side 2 >45m
15% Side 3 10.1 to 20m
0% Side 4 > 45m
15% Total Increase for Exposure (maximum 75%)
= 5,520 L/min
F = 6,000 L/min (rounded off to the nearest 1,000 L/min)
= 100.0 l/s
19-Feb-15
15 & 19 Frank Neighbor Place and 737 & 777 Silver Seven Road
Silver Seven Corporate Center
5
MEDICAL BUILDING (Phase Two) - 4 Storeys
Fire Protection Water Supply
F = 220 C A0.5
F = the required fire flow in litres per minute
C = coefficient related to the type of construction
= 1.5 for wood frame construction (combustible construction)
= 1.0 for ordinary construction (masonary wall, combustible floor and interior)
= 0.8 for non-combustible construction (unprotected structural components)
= 0.6 for non-combustible construction (protected structural components, floor and roof)
= 0.8
A = Total Area
Ground Floor Area: 1394 sq.m.
Second Floor Area: 1394 sq.m.
1394 sq.m.
1394 sq.m.
Total Area: 5576 sq.m.
F = 13,142 L/min
= 13,000 L/min (rounded off to the nearest 1,000 L/min)
-25% Reduction: Non-Combustible Contents
= 9,750 L/min
-50% Reduction: Sprinkler Protection - Fully Supervised
= 4,875 L/min
Added to above Contents Fire Hazard for Separation Exposed Buildings
15% Side 1 10.1 to 20m
0% Side 2 > 45m
0% Side 3 > 45m
15% Side 4 10.1 to 20m
30% Total Increase for Exposure (maximum 75%)
= 6,338 L/min
F = 6,000 L/min (rounded off to the nearest 1,000 L/min)
= 100.0 l/s
Third Floor Area:
Fourth Floor Area:
6
COMMERCIAL BUILDING C-2 (Phase Two) 1 Storey
Fire Protection Water Supply
F = 220 C A0.5
F = the required fire flow in litres per minute
C = coefficient related to the type of construction
= 1.5 for wood frame construction (combustible construction)
= 1.0 for ordinary construction (masonary wall, combustible floor and interior)
= 0.8 for non-combustible construction (unprotected structural components)
= 0.6 for non-combustible construction (protected structural components, floor and roof)
= 0.8
A = floor area
Floor Area: 1861 sq.m.
F = 7,593 L/min
= 8,000 L/min (rounded off to the nearest 1,000 L/min)
0% No Change: Combustible Contents
= 8,000 L/min
-40% Reduction: Sprinkler Protection - Not Supervised
= 4,800 L/min
Added to above Contents Fire Hazard for Separation Exposed Buildings
0% Side 1 >45
15% Side 2 10.1 to 20m
0% Side 3 >45m
0% Side 4 > 45m
15% Total Increase for Exposure (maximum 75%)
= 5,520 L/min
F = 6,000 L/min (rounded off to the nearest 1,000 L/min)
= 100.0 l/s
7
INDUSTRIAL BUILDING IL-1 (Phase Two) - 2 Storeys
Fire Protection Water Supply
F = 220 C A0.5
F = the required fire flow in litres per minute
C = coefficient related to the type of construction
= 1.5 for wood frame construction (combustible construction)
= 1.0 for ordinary construction (masonary wall, combustible floor and interior)
= 0.8 for non-combustible construction (unprotected structural components)
= 0.6 for non-combustible construction (protected structural components, floor and roof)
= 0.8
A = floor area
Ground Floor Area: 2963.5 sq.m.
Second Floor Area: 2963.5 sq.m.
Total Area: 5927.0 sq.m.
F = 13,550 L/min
= 14,000 L/min (rounded off to the nearest 1,000 L/min)
0% No Change: Combustible
= 14,000 L/min
-40% Reduction: Sprinkler Protection - Not Supervised
= 8,400 L/min
Added to above Contents Fire Hazard for Separation Exposed Buildings
0% Side 1 >45m
0% Side 2 > 45m
0% Side 3 >45m
5% Side 4 30.1 to 45m
5% Total Increase for Exposure (maximum 75%)
= 8,820 L/min
F = 9,000 L/min (rounded off to the nearest 1,000 L/min)
= 150.0 l/s THE GOVERNING FIRE FLOW
8
ATHLETIC CLUB (Phase One)
Fire Protection Water Supply
F = 220 C A0.5
F = the required fire flow in litres per minute
C = coefficient related to the type of construction
= 1.5 for wood frame construction (combustible construction)
= 1.0 for ordinary construction (masonary wall, combustible floor and interior)
= 0.8 for non-combustible construction (unprotected structural components)
= 0.6 for non-combustible construction (protected structural components, floor and roof)
= 0.8
A = floor area
Ground Floor Area: 3269 sq.m.
Second Floor Area: 3269 sq.m.
Total Area: 6538 sq.m.
F = 14,231 L/min
= 14,000 L/min (rounded off to the nearest 1,000 L/min)
-25% Not Combustible
= 10,500 L/min
-40% Reduction: Sprinkler Protection - Not Supervised
= 6,300 L/min
Added to above Contents Fire Hazard for Separation Exposed Buildings
0% Side 1 >45m
0% Side 2 > 45m
0% Side 3 >45m
0% Side 4 > 45m
0% Total Increase for Exposure (maximum 75%)
= 6,300 L/min
F = 6,000 L/min (rounded off to the nearest 1,000 L/min)
= 100.0 l/s
150.0 l/s Required fire flow requirement for BUILDING IL-1 as per FUS
31.5 l/s 500 USgpm Minimum Required Flowrate for Sprinklers
8.4 l/s ���������������� ����������
189.9 l/s Required Minimum Water Supply Flow Rate
(MAX DAY + FIRE FLOW)
(wet pipe sprinklers and standpipe fire
hose cabinets including inside/outside
hose allowance as per NFPA 13 to be
confirmed by mechanical engineer)
9
DAILY AVERAGE 335.8 l / min 5.60 l / sec 88.7 Usgpm
MAXIMUM DAILY DEMAND 503.6 l / min 8.39 l / sec 133.1 Usgpm
MAXIMUM HOURLY DEMAND 604.4 l / min 10.07 l / sec 159.7 Usgpm
ATHLETIC CLUB
DAILY AVERAGE 28,000 litres / ha / day
2.67 hectares
74,712 litres / day
8 hours / day
155.7 l / min 2.59 l / sec 41.1 Usgpm
MAXIMUM DAILY DEMAND 1.5 Peaking Factor
Silver Seven Corporate Centre Phase 1&215&19 Frank Neigbor Place and 737&777 Silver Seven Road
Ottawa, Ontario
Water Demand
PHASE 1 & 2 - Summary
02-Sep-14
PHASE 1
233.5 l / min 3.89 l / sec 61.7 USgpm
MAXIMUM HOURLY DEMAND 1.8 Peaking Factor
280.2 l / min 4.67 l / sec 74.0 USgpm
COMMERCIAL BUILDING C-1
DAILY AVERAGE
COMMERCIAL: 28,000 l /gross ha / day (as per Ottawa Design Guidelines)
0.67 ha (land area)
18760 l / day
8 hour day
39 l / min 0.7 l / sec 10 Usgpm
MAXIMUM DAILY DEMAND 1.5 (Peaking Factor as per Ottawa Design Guidelines)
59 l / min 1.0 l / sec 15 Usgpm
MAXIMUM HOURLY DEMAND 1.8 (Peaking Factor as per Ottawa Design Guidelines)
70 l / min 1.2 l / sec 19 Usgpm
PHASE 2
10
MEDICAL BUILDING
DAILY AVERAGE
COMMERCIAL: 28,000 l /gross ha / day (as per Ottawa Design Guidelines)
0.49 ha (land area)
13720 l / day
8 hour day
29 l / min 0.5 l / sec 8 Usgpm
MAXIMUM DAILY DEMAND 1.5 (Peaking Factor as per Ottawa Design Guidelines)
43 l / min 0.7 l / sec 11 Usgpm
MAXIMUM HOURLY DEMAND 1.8 (Peaking Factor as per Ottawa Design Guidelines)
51 l / min 0.9 l / sec 14 Usgpm
COMMECERICAL BUILDING C-2
DAILY AVERAGE
COMMERCIAL: 28,000 l /gross ha / day (as per Ottawa Design Guidelines)
0.64 ha (land area)
17920 l / day
8 hour day
37 l / min 0.6 l / sec 10 Usgpm
MAXIMUM DAILY DEMAND 1.5 (Peaking Factor as per Ottawa Design Guidelines)
56 l / min 0.9 l / sec 15 Usgpm
MAXIMUM HOURLY DEMAND 1.8 (Peaking Factor as per Ottawa Design Guidelines)MAXIMUM HOURLY DEMAND 1.8 (Peaking Factor as per Ottawa Design Guidelines)
67 l / min 1.1 l / sec 18 Usgpm
INDUSTRIAL BUILDING L-1
DAILY AVERAGE
LIGHT INDUSTRIAL: 35,000 l /gross ha / day (as per Ottawa Design Guidelines)
1.03 ha (land area)
36050 l / day
8 hour day
75 l / min 1.3 l / sec 20 Usgpm
MAXIMUM DAILY DEMAND 1.5 (Peaking Factor as per Ottawa Design Guidelines)
113 l / min 1.9 l / sec 30 Usgpm
MAXIMUM HOURLY DEMAND 1.8 (Peaking Factor as per Ottawa Design Guidelines)
135 l / min 2.3 l / sec 36 Usgpm
98.45 m ASL
Finish Floor Elevation: 97.55 m ASL
Static Pressure at Water Meter
MINIMUM HGL: 155.7 m ASL 81 psi 561 kPa
96.75 m ASL
Elevation of Water Meter
(Athletic Club - lowest buildings):
Elevation of Water Meter
(Buiding C-2 - highest buildings):
96.75 m ASL
Finish Floor Elevation: 95.85 m ASL
Static Pressure at Water Meter
MAXIMUM HGL: 163.7 m ASL 95 psi 656 kPa
(Athletic Club - lowest buildings):
11
�����
�������� ����������������� � ������������������� ������� ����������� ������������� ! " �#��"�#��$�%��������������������������� ��%
����������&�������� ����������'
(�)���*��+�,-%�.����. ��� ������� /�0�
( � .�.���+�,,% .
(�) .�.���+�1!%/.������� .�������������#�� �� ��,% .2���.�) .�.3������� ���� .���������13� �� �� �.�������4-3� %53�������������3����.������.3��� ������������ ���� �������. �� 3�������������� ���6� ���%
�����/& ! " �#��"�#��$�'*������&�������� ����������'
(�)���*��+�,!%-.����. ��� ������� /�0�&�� ! " �#��"�#��$�'
( � .�.���+�,,%4.
(�) .�.���+�1!% .������� .�������������#�� �� �� %7.2���.�) .�.3������� ���� .���������7%!3� �� �� �.�������4-3� %53�������������3����.������.3��� ������������ ���� �������. �� 3�������������� ���6� ���%
�������������������������� � �������������� �������.3����.����� .���� ��%
����������� �������������������������������������������������������������� ��������������������������������� ���������������������������������������� �������������������������������� ��������� ��������������� ������������������������������� ���������������������������������������������������������������������� ��� ������������������������������������������������������� ��������������������� �������������������������������������� ��������������� ������������������������������ ������������ ������������� ���������������������������
$�������
��. ��8� ��������%9��%
���:���(������
��#���3.���$�# ���"�������"��# ���; 8���
��-���� ��5#����8����7�������
1�!;,4-;/7/7)�1�14
��. ��%�� ������<������%��
������=>��5"�$5?@.� ���A������<������%��.B����=�������,�/-�/7A//�(��8� ���������. ����� ���$�A" �#��"�#���� #�C������ ����������
������!�� ��
/70�-0/-�/���3A00��;.�1%.� �%�����%��.0���0������D%3������+������;���C%����+��,�:1��� -7�
12
� ��. ��
�����=��� �����������������)�����%
E�������� �#���������������� ..�� ���3��������������%
����
�%F%�$5?9��E�99$E��E�G%
��������������������� ������� ���������� ����� ���������������� !��������
�-,/H������ #����A1�!;/7�;4-77
=������=���� ���)A1�!;/7�;�4�,
H��7��������<������%��.
�����I8� ���������. ��IJ��. ��%8� ������<������%��K���=>��5"�$5?J������<������%��.K����(������=�������,�/-�//A-�A7!�(��� ���$9A" �#��"�#���� #�C������ ����������
�����
G�����3���������.����3��� ����� . ������3�����D
���������
��. ��8� ��������%9��%���:���(������
��#���3.���$�# ���"�������"��# ���; 8�����-���� ��5#����8����7�������1�!;,4-;/7/7)�1�14��. ��%�� ������<������%��
������=>��5"�$5?@.� ���A������<������%��.B����=�������/�/-�/�A,15(��8� ���������. ����� ���" �#��"�#���� #�C������ ����������
� ��. ��
E�.���� ��������3������..��� ����#���3.�����" �#��"�#��$���������� �������%
������3��# ����������������� � ������� �����%E��#������������������� ����.����A
������&������������ � �������������������� ����������'A5#������� ����.���A/%-7�0�(�) .�.�� ����.���A!%-1�0�(�) .�.�������� ����.���A!%14�0�� ��������.���A� /�0�
�����/&������6� ����������������� � �����" �#��"�#��$����������� ����������'5#������� ����.���A7% 1�0�(�) .�.�� ����.���A %�,�0�(�) .�.�������� ����.���A4%,4�0�
����/�!�� ��
/70�-0/-�/���3A00��;.�1%.� �%�����%��.0���0������D%3������+������;���C%����+��,�:1��� -7�
13
� ��������.���A� /�0�
$�����������
�%F%�$5?9��E�99$E��E�G%��������������������� ������� ���������� ����� ���������������� !��������
�-,/H������ #����A1�!;/7�;4-77=������=���� ���)A1�!;/7�;�4�,H��7��������<������%��.
�� ��;.� ��� � �������.���G ���=������;.� ������.%5��� ��� ��� ����������3� ����� ��;
.� ������ ���.�� �� ������ ���������������� ���������� 3 ���&�' ��������� L��%E������������ ���������� 3 ����3�������� �.����������3������.�����������#������������;.� ������������ ���..�� ��� ����������3� ..�� �����%��������%��3�M���� ����� ���M�M �)3M� M3���� ����N.� �� ����� ��� ����O ��� �P=�����%������ ��� ��� ����� � ��� �� ����3������ ���� ����� �� �� ��� ����� ���.���� 6� �P� ����#���3����� 3������� ����� 6��
������� ���� �� 3�M#���� ����� ��%" #��� �#�L ��Q� ��.������3���������#�� ���L .P�� �# ���3���M�M3����&�� ��.M�� 3�M� �M'��3������� ���3� � ��33� .�������M�� ��#��� ���� � ���� ������..�� ��� ��� �� 6�� ������ �����3 ��%R� #��� ��.��� � �� #�������������� ��%
�� ��;.� ��� � �������.���G ���=������;.� ������.%5��� ��� ��� ����������3� ����� ��;.� ������ ���.�� �� ������ ���������������� ���������� 3 ���&�' ��������� L��%E���������
��� ���������� 3 ����3�������� �.����������3������.�����������#������������;.� ������������ ���..�� ��� ����������3� ..�� �����%��������%
��3�M��������� ���M�M�)3M� M3��������N.�������� �������O ����P=�����%������ ��� ��� ���
�� � ��� ������3������ ��������� ������������ ���.����6� �P�����#���3�����3������������6��������� ���� ��3�M#���� ����� ��%" #����#�L��Q���.������3���������#�� ���L.P���# ���3���M�M3����&����.M��3�M� �M'��3������� ���3� ���33� .�������M�� ��#��� ���� � ����������..�� ��� ��� �� 6�������������3 ��%R�#�����.��� ���#�������������� ��%
����!�!�� ��
/70�-0/-�/���3A00��;.�1%.� �%�����%��.0���0������D%3������+������;���C%����+��,�:1��� -7�
14
GF
GF
610mm
305
mm
406mm
152mm
203mm
254mm
51mm
203mm
305
mm
254mm
305mm
152m
m
152m
m
203m
m
203mm
152mm152mm
152mm
203
mm
152m
m
152mm
152mm
203
mm
610mm
305
mm
406mm
152mm
20
50
0
10
14
7
77
0
50
20
1
19
16
55
61
0
15
28
5
63
0
70
0
73
7
33
3
33
3
10
0
58
0
77
7
57
8
16
25
35
0
60
0
40
0
30
8
90
62
0
30
1 33
3 10
0
16
25
25
5
6
3
88
70
0
33
3
8
34
90
79
38
86
36
11 69
30
1
84
40 4
232
34
5
44
92
21
15
29
46
30
8
65
61
41
35
30
30
45
57
53
47 51
59
32
44
34
48
39
24
8
21
6
24
6
22
6
50
23
0
23
2 24
0
23
4
23
6
23
8
24
4
22
8
52
57
8
20
22
18
10
282
4
26
16
21
2
94
96
78
80
40
14
60
54
66
38
50
36
70
72
76
64
12
48
52
56
58
62 6
8
46
82
42
10
1
21
0
10
325
0
21
4
98
10
7
70
0
20
8
30
8
28
54
35
0
10
9
30
8
10
0
22
7
56
22
3
22
9
10
0
21
9
23
3
23
5
21
7
20
4
58
26
HIG
HW
AY
417
PA
LLA
DIU
M D
R
TERRY FOX DR
SILVER SEVEN RD
HW
Y4
17
IC
140
RA
MP
51
ROWE DR
HW
Y4
17
IC
140
RA
MP
36
FR
AN
K N
IGH
BO
R P
L
HW
Y417 IC
140 RAM
P25
KATIM
AV
IK R
D
HW
Y417 IC
140 R
AM
P35
HIG
HW
AY
417
$B
ou
nd
ary
Co
nd
itio
n f
or
19
Fra
nk N
igh
bo
r a
nd
73
7 S
ilve
r S
eve
n
Leg
en
d
Pip
e O
wn
ers
hip
Pri
va
te
Pu
blic
15
13-Feb-15
19 Frank Nighbor Place HGL
m psi kPa
Grade Elevation 95.85 m *Maximum HGL 163.2 95.8 660
*Minimum HGL 154.8 83.8 578
Fire Flow 123.3 l/s *Max Day + Fire Flow 154.7 83.7 577
737 Silver Seven Road HGL
m psi kPa
Grade Elevation 97.12 m *Maximum HGL 163.2 94.0 648
*Minimum HGL 154.8 82.0 566
Fire Flow 123.3 l/s *Max Day + Fire Flow 155.3 82.7 570
* Information supplied by City of Ottawa
Fire Flow - Fire Hydrant 1 / Sprinklers Athletic Club
Demand Elevation Head
l/s m m m psi kPa
1 Reservoir 1 -65.0 95.85 154.70 58.85 83.7 577
2 Athletic Club 35.4 95.57 154.06 58.49 83.2 573
3 FH 1 66.7 95.48 153.93 58.45 83.1 573
4 0.0 96.24 154.20 57.96 82.4 568
5 FH 2 0.0 96.29 154.20 57.91 82.3 568
6 Commerical Building C-1 1.0 96.5 154.20 57.70 82.0 566
7 0.0 96.27 154.44 58.17 82.7 570
8 Industrial Building IL-1 1.9 96.50 154.44 57.94 82.4 568
9 FH 3 0.0 96.42 154.75 58.33 82.9 572
10 0.0 96.59 154.86 58.27 82.9 571
11 Medical Building 0.7 96.07 154.85 58.78 83.6 576
12 0.0 97.3 155.07 57.77 82.1 566
13 Commercial Building C-2 0.9 97.55 155.07 57.52 81.8 564
14 Reservoir 2 -41.6 97.12 155.30 58.18 82.7 570
Diameter Length Flow Velocity Headloss
mm m l/s m/s m/km
Pipe 1 to Athletic Club 250 47.07 2.15 65.0 1.32 13.66
Pipe 2 to FH 1 250 50.36 0.60 29.6 0.60 2.46
Pipe 3 250 70.34 1.00 37.1 0.76 3.80
Pipe 4 to FH 2 150 30.81 2.40 1.0 0.01 0.07
Pipe 5 to C-1 150 33.25 0.60 1.0 0.06 0.06
Pipe 6 250 57.49 1.20 38.1 0.78 4.20
Pipe 7 to IL-1 150 5.30 2.00 1.9 0.11 0.42
Pipe 8 to FH 3 250 64.86 1.60 40.0 0.81 4.73
Pipe 9 250 10.06 2.00 40.0 0.81 10.62
Pipe 10 to Medical Building 150 29.72 3.20 0.7 0.04 0.04
Pipe 11 250 45.14 1.00 40.7 0.83 4.80
Pipe 12 to C-2 150 7.70 2.00 0.9 0.05 0.08
Pipe 13 to Reservoir 2 250 31.58 2.60 41.6 0.85 7.20
Pressure
Link IDLoss
Coeff.
EPANET HYDRAULIC MODELLING RESULTS
Node IDPressure
HGL / PRESSURE CALCULATIONS
Silver Seven Corporate Centre Phase 1&215&19 Frank Neigbor Place and 737&777 Silver Seven Road
Ottawa, Ontario
Pressure
16
Fire Flow - Fire Hydrant 2 / Sprinklers Commerical Building C-1
Demand Elevation Head
l/s m m m psi kPa
1 Reservoir 1 -53.0 95.85 154.70 58.85 83.7 577
2 Athletic Club 3.9 95.57 154.26 58.69 83.5 575
3 FH 1 0.0 95.48 153.95 58.47 83.1 573
4 0.0 96.24 153.49 57.25 81.4 561
5 FH 2 66.7 96.29 140.36 44.07 62.7 432
6 Commerical Building C-1 32.5 96.5 138.99 42.49 60.4 417
7 0.0 96.27 153.90 57.63 81.9 565
8 Industrial Building IL-1 1.9 96.50 153.90 57.40 81.6 563
9 FH 3 0.0 96.42 154.40 57.98 82.4 568
10 0.0 96.59 154.58 57.99 82.5 569
` 11 Medical Building 0.7 96.07 154.58 58.51 83.2 574
12 0.0 97.3 154.93 57.63 81.9 565
13 Commercial Building C-2 0.9 97.55 154.93 57.38 81.6 563
14 Reservoir 2 -53.6 97.12 153.70 56.58 80.5 555
Diameter Length Flow Velocity Headloss
mm m l/s m/s m/km
Pipe 1 to Athletic Club 250 47.1 2.15 53.0 1.08 9.28
Pipe 2 to FH 1 250 50.4 0.60 49.1 1.00 6.31
Pipe 3 250 70.3 1.00 49.1 1.00 6.42
Pipe 4 to FH 2 150 30.8 2.40 99.2 5.61 426.22
Pipe 5 to C-1 150 33.3 0.60 32.5 1.84 41.24
Pipe 6 250 57.5 1.20 50.1 1.02 7.02
Pipe 7 to IL-1 150 5.3 2.00 1.9 0.11 0.42
Pipe 8 to FH 3 250 64.9 1.60 52.0 1.06 7.75
Pipe 9 250 10.1 2.00 52.0 1.06 17.70
Pipe 10 to Medical Building 150 29.72 3.20 0.7 0.04 0.04
Pipe 11 250 45.14 1.00 52.7 1.07 7.8
Pipe 12 to C-2 150 7.7 2.00 0.9 0.05 0.08
Pipe 13 to Reservoir 2 250 31.58 2.60 53.6 1.09 11.71
Fire Flow - Fire Hydrant 3 / Sprinklers Industrial Building IL-1
Demand Elevation Head
l/s m m m psi kPa
1 Reservoir 1 -46.1 95.85 154.70 58.85 83.7 577
2 Athletic Club 3.9 95.57 154.36 58.79 83.6 576
3 FH 1 0.0 95.48 154.12 58.64 83.4 575
4 0.0 96.24 153.78 57.54 81.8 564
5 FH 2 0.0 96.29 153.78 57.49 81.7 564
6 Commerical Building C-1 1.0 96.5 153.78 57.28 81.5 562
7 0.0 96.27 153.50 57.23 81.4 561
8 Industrial Building IL-1 33.4 96.50 152.93 56.43 80.2 553
9 FH 3 83.3 96.42 153.49 57.07 81.2 560
10 0.0 96.59 153.86 57.27 81.4 561
11 Medical Building 0.7 96.07 153.85 57.78 82.2 566
12 0.0 97.3 154.56 57.26 81.4 561
13 Commercial Building C-2 0.9 97.55 154.56 57.01 81.1 559
14 Reservoir 2 -77.1 97.12 155.30 58.18 82.7 570
Diameter Length Flow Velocity Headloss
mm m l/s m/s m/km
Pipe 1 to Athletic Club 250 47.07 2.15 46.1 0.94 7.13
Pipe 2 to FH 1 250 50.36 0.60 42.2 0.86 4.76
Pipe 3 250 70.34 1.00 42.2 0.86 4.85
Pipe 4 to FH 2 150 30.81 2.40 1.0 0.06 0.07
Pipe 5 to C-1 150 33.25 0.60 1.0 0.06 0.06
Pipe 6 250 57.49 1.20 41.2 0.84 4.88
Pipe 7 to IL-1 150 5.30 2.00 33.4 1.89 108.78
Pipe 8 to FH 3 250 64.86 1.60 7.9 0.16 0.22
Pipe 9 250 10.06 2.00 75.5 1.54 36.56
Pipe 10 to Medical Building 150 29.72 3.20 0.7 0.04 0.04
Pipe 11 250 45.14 1.00 76.2 1.55 15.57
Pipe 12 to C-2 150 7.70 2.00 0.9 0.05 0.08
Pipe 13 to Reservoir 2 250 31.58 2.60 77.1 1.57 23.47
Node IDPressure
Link IDLoss
Coeff.
Pressure
Link IDLoss
Coeff.
Node ID
17
18
Netw
ork
Table
- N
odes
Ele
vati
on
Base D
em
and
Dem
and
Head
Pre
ssure
Node I
Dm
LP
SL
PS
mm
Junc 2
95.5
735.3
935.3
9154.0
658.4
9
Junc 3
95.4
866.7
66.7
0153.9
358.4
5
Junc 4
96.2
40
0.0
0154.2
057.9
6
Junc 5
96.2
90
0.0
0154.2
057.9
1
Junc 6
96.5
1.0
1.0
0154.2
057.7
0
Junc 7
96.2
70
0.0
0154.4
458.1
7
Junc 8
96.5
01.9
1.9
0154.4
457.9
4
Junc 9
96.4
20
0.0
0154.7
558.3
3
Junc 1
096.5
90
0.0
0154.8
658.2
7
Junc 1
196.0
70.7
0.7
0154.8
558.7
8
Junc 1
297.3
00.0
0155.0
757.7
7
Junc 1
397.5
50.9
0.9
0155.0
757.5
2
Resvr
1154.7
#N
/A-6
5.0
0154.7
00.0
0
Resvr
14
155.3
#N
/A-4
1.5
9155.3
00.0
0
EP
AN
ET
2P
age 1
19
Net
work
Tab
le -
Lin
ks
Len
gth
Dia
met
erR
oughnes
sF
low
Vel
oci
tyU
nit
Hea
dlo
ss
Lin
k I
Dm
mm
LP
Sm
/sm
/km
Pip
e 1
47.0
7250
110
65.0
01.3
213.6
6
Pip
e 2
50.3
6250
110
29.6
10.6
02.4
6
Pip
e 3
70.3
4250
110
-37.0
90.7
63.8
0
Pip
e 4
30.8
1150
100
1.0
00.0
60.0
7
Pip
e 5
33.2
5150
100
1.0
00.0
60.0
6
Pip
e 6
57.4
9250
110
-38.0
90.7
84.2
0
Pip
e 7
5.3
150
100
1.9
00.1
10.4
2
Pip
e 8
64.8
6250
110
-39.9
90.8
14.7
3
Pip
e 9
10.0
6250
110
-39.9
90.8
110.6
2
Pip
e 10
29.7
2150
100
0.7
00.0
40.0
4
Pip
e 11
45.1
4250
110
-40.6
90.8
34.8
0
Pip
e 12
7.7
150
100
0.9
00.0
50.0
8
Pip
e 13
31.5
8250
110
-41.5
90.8
57.2
0
EP
AN
ET
2P
age 1
20
21
Netw
ork
Table
- N
odes
Ele
vati
on
Base D
em
and
Dem
and
Head
Pre
ssure
Node I
Dm
LP
SL
PS
mm
Junc 2
95.5
73.8
93.8
9154.2
658.6
9
Junc 3
95.4
80
0.0
0153.9
558.4
7
Junc 4
96.2
40
0.0
0153.4
957.2
5
Junc 5
96.2
966.7
66.7
0140.3
644.0
7
Junc 6
96.5
32.5
32.5
0138.9
942.4
9
Junc 7
96.2
70
0.0
0153.9
057.6
3
Junc 8
96.5
01.9
1.9
0153.9
057.4
0
Junc 9
96.4
20
0.0
0154.4
057.9
8
Junc 1
096.5
90
0.0
0154.5
857.9
9
Junc 1
196.0
70.7
0.7
0154.5
858.5
1
Junc 1
297.3
00.0
0154.9
357.6
3
Junc 1
397.5
50.9
0.9
0154.9
357.3
8
Resvr
1154.7
#N
/A-5
2.9
9154.7
00.0
0
Resvr
14
155.3
#N
/A-5
3.6
0155.3
00.0
0
EP
AN
ET
2P
age 1
22
Net
work
Tab
le -
Lin
ks
Len
gth
Dia
met
erR
oughnes
sF
low
Vel
oci
tyU
nit
Hea
dlo
ss
Lin
k I
Dm
mm
LP
Sm
/sm
/km
Pip
e 1
47.0
7250
110
52.9
91.0
89.2
8
Pip
e 2
50.3
6250
110
49.1
01.0
06.3
1
Pip
e 3
70.3
4250
110
49.1
01.0
06.4
2
Pip
e 4
30.8
1150
100
99.2
05.6
1426.2
2
Pip
e 5
33.2
5150
100
32.5
01.8
441.2
4
Pip
e 6
57.4
9250
110
-50.1
01.0
27.0
2
Pip
e 7
5.3
150
100
1.9
00.1
10.4
2
Pip
e 8
64.8
6250
110
-52.0
01.0
67.7
5
Pip
e 9
10.0
6250
110
-52.0
01.0
617.7
0
Pip
e 10
29.7
2150
100
0.7
00.0
40.0
4
Pip
e 11
45.1
4250
110
-52.7
01.0
77.8
0
Pip
e 12
7.7
150
100
0.9
00.0
50.0
8
Pip
e 13
31.5
8250
110
-53.6
01.0
911.7
1
EP
AN
ET
2P
age 1
23
24
Netw
ork
Table
- N
odes
Ele
vati
on
Base D
em
and
Dem
and
Head
Pre
ssure
Node I
Dm
LP
SL
PS
mm
Junc 2
95.5
73.8
93.8
9154.3
658.7
9
Junc 3
95.4
80
0.0
0154.1
258.6
4
Junc 4
96.2
40
0.0
0153.7
857.5
4
Junc 5
96.2
90
0.0
0153.7
857.4
9
Junc 6
96.5
11.0
0153.7
857.2
8
Junc 7
96.2
70
0.0
0153.5
057.2
3
Junc 8
96.5
033.4
33.4
0152.9
356.4
3
Junc 9
96.4
283.3
83.3
0153.4
957.0
7
Junc 1
096.5
90
0.0
0153.8
657.2
7
Junc 1
196.0
70.7
0.7
0153.8
557.7
8
Junc 1
297.3
00.0
0154.5
657.2
6
Junc 1
397.5
50.9
0.9
0154.5
657.0
1
Resvr
1154.7
#N
/A-4
6.1
3154.7
00.0
0
Resvr
14
155.3
#N
/A-7
7.0
6155.3
00.0
0
EP
AN
ET
2P
age 1
25
Net
work
Tab
le -
Lin
ks
Len
gth
Dia
met
erR
oughnes
sF
low
Vel
oci
tyU
nit
Hea
dlo
ss
Lin
k I
Dm
mm
LP
Sm
/sm
/km
Pip
e 1
47.0
7250
110
46.1
30.9
47.1
3
Pip
e 2
50.3
6250
110
42.2
40.8
64.7
6
Pip
e 3
70.3
4250
110
42.2
40.8
64.8
5
Pip
e 4
30.8
1150
100
1.0
00.0
60.0
7
Pip
e 5
33.2
5150
100
1.0
00.0
60.0
6
Pip
e 6
57.4
9250
110
41.2
40.8
44.8
8
Pip
e 7
5.3
150
100
33.4
01.8
9108.7
8
Pip
e 8
64.8
6250
110
7.8
40.1
60.2
2
Pip
e 9
10.0
6250
110
-75.4
61.5
436.5
6
Pip
e 10
29.7
2150
100
0.7
00.0
40.0
4
Pip
e 11
45.1
4250
110
-76.1
61.5
515.5
7
Pip
e 12
7.7
150
100
0.9
00.0
50.0
8
Pip
e 13
31.5
8250
110
-77.0
61.5
723.4
7
EP
AN
ET
2P
age 1
26
D.
B.
G
R A
Y E
N G
I N
E E
R I
N G
I
N C
.S
AN
ITA
RY
SE
WE
R D
ES
IGN
FO
RM
Avera
ge D
aily
Flo
ws:
Peakin
g F
acto
r:P
RO
JE
CT
: S
ILV
ER
SE
VE
N P
ha
se
2,
Ott
aw
aR
esi
dential:
350
l /
capita /
day
Resi
dential (H
arm
on E
quation):
P.F
. =
1
+14
70
0 L
ong P
oin
t 61
3-4
25-8
044
Com
merc
ial:
50000
l /
ha /
day
4
+
P
0.5
Desi
gned B
y:
DB
G
Ott
awa,
Onta
rio
K
1T
4E
9dbgra
y@
roger
s.co
mIn
stituational:
50000
l /
ha /
day
Lig
ht
Indust
rial:
35000
l /
ha /
day
Infiltra
tion A
llow
ance:
0.2
8l /
s /
ha
19-F
eb-1
5
Heavy I
ndust
rial:
55000
l /
ha /
day
Page:
1 o
f 1
n =
0.0
13
ST
RE
ET
FR
OM
TO
ppu =
3.4
ppu =
2.7
ppu =
2.3
ppu =
1.8
ppu =
1.4
ppu =
2.1
ppu =
3.1
Type o
fD
ia.
Actu
al
Dia
. N
om
.S
lope
Length
Capacity
Velo
city
Ratio
ha
ha
l/ha/d
ay
ha
l/s
l/s
l/s
Pip
e(m
m)
(mm
)(%
)(m
)(l
/s)
(m/s
)Q
/Qfu
ll
Co
mm
erc
ial B
uild
ing
C-1
MH
-SA
.30
.67
45
00
01
.50
.67
00
.52
0.1
90
.71
PV
C S
DR
35
20
3.2
20
01
.00
02
8.3
34
.21
.06
0.0
2
Ind
ustr
ial B
uild
ing
IL
-1M
H-S
A.3
1.0
34
50
00
6.6
1.0
30
3.5
40
.29
3.8
3P
VC
SD
R 3
52
03
.22
00
1.0
00
30
.43
4.2
1.0
60
.11
Me
dic
al B
uild
ing
M
H-S
A.3
0.4
94
50
00
1.5
0.4
90
0.3
80
.14
0.5
2P
VC
SD
R 3
52
03
.22
00
2.0
00
7.5
48
.41
.49
0.0
1
Co
mm
erc
ial B
uild
ing
C-2
MH
-SA
.30
.64
45
00
01
.50
.64
00
.50
0.1
80
.68
PV
C S
DR
35
20
3.2
20
02
.00
04
.54
8.4
1.4
90
.01
MH
-SA
.3M
H-S
A.2
45
00
01
.52
.83
4.9
50
.79
5.7
4P
VC
SD
R 3
52
03
.22
00
1.7
00
89
.74
4.6
1.3
80
.13
MH
-SA
.2M
H-S
A.1
1.5
2.8
34
.95
0.7
95
.74
PV
C S
DR
35
20
3.2
20
06
.00
01
2.4
83
.82
.58
0.0
7
38
1.0
37
50
.40
01
15
.71
.01
MU
NIC
IPA
L S
AN
ITA
RY
SE
WE
R IN
SIL
VE
R S
EV
EN
RO
AD
P =
Popula
tion /
1000
LO
CA
TIO
NC
OM
ME
NT
S
No.
of
Units
No.
of
Units
SE
WE
R D
AT
AC
um
ula
tive
Section
Sem
i /
Tow
nhouse
Duple
x /
Tri
ple
x
Apart
ments
(avera
ge)
Sin
gle
Fam
ily
Apart
ments
(2 B
ed.)
Apart
ments
(3 B
ed.)
Apart
ments
(1 B
ed.)
Resid
ential
Are
aP
eakin
g
Facto
r
Flo
w
Cum
ula
tive
Are
aS
ew
age
Flo
w
Infil-
tration
Flo
w
Tota
l
Flo
w
Section
No.
of
Units
No.
of
Units
No.
of
Units
No.
of
Units
No.
of
Units
Non-R
esi
dential
Are
a
Resi
dential
Pop.
Peakin
g
Facto
r
Sto
rmw
ate
r M
anagem
ent
- G
radin
g &
Dra
ina
ge
- Sto
rm &
Sanit
ary
Sew
ers
- W
ate
rmain
s
27
D. B
. G
R A
Y E
N G
I N
E E
R I
N G
I
N C
.S
torm
wa
ter
Ma
na
gem
ent
- G
rad
ing
& D
rain
ag
e -
Sto
rm &
Sa
nit
ary
Sew
ers
- W
ate
rma
ins
ST
OR
M S
EW
ER
CO
MP
UT
AT
ION
FO
RM
PR
OJE
CT
: S
ilve
r S
eve
n P
ha
se
2
70
0 L
on
g P
oin
t C
ircl
e6
13
-42
5-8
04
4R
AT
ION
AL M
ET
HO
D Q
= 2
.78 A
I R
F
IVE
YE
AR
EV
EN
TD
esig
ned B
y:D
BG
Ott
awa,
On
tari
o
K1
T 4
E9
db
gra
y@
roger
s.co
mn =
0.0
13
Date
:19-F
eb-1
5
Page:
1 o
f 2
Tim
e o
fR
ain
fall
Conc.
Inte
nsity
Typ
e o
fD
ia. A
ctu
al
Dia
. N
om
.S
lope
Length
Capacity
Velo
city
Tim
e o
f R
atio
ST
RE
ET
FR
OM
TO
R =
0.9
R =
0.7
0R
=0.2
R =
0.9
(min
)I (m
m/h
r)P
ipe
(mm
)(m
m)
(%)
(m)
(l/s
)(m
/s)
Flo
w (
min
)Q
/Qfu
ll
CB
/MH
-32
CB
/MH
-31
0.1
25
0.1
25
10.0
104
13.0
CO
NC
RE
TE
457.2
450
0.2
00
35.2
133.0
0.8
10.7
0.1
0
CB
/MH
-31
CB
/MH
-41
0.4
24
0.5
48
10.7
101
55.1
CO
NC
RE
TE
457.2
450
0.2
00
24.6
133.0
0.8
10.5
0.4
1
CB
/MH
-41
MH
-30
0.0
35
0.5
83
11.2
98
57.2
CO
NC
RE
TE
457.2
450
0.2
00
6.2
133.0
0.8
10.1
0.4
3
MH
-30
MH
-29
0.0
00
0.5
83
11.4
98
56.9
CO
NC
RE
TE
457.2
450
0.2
00
19.1
133.0
0.8
10.4
0.4
3
MH
-29
MH
-28
0.0
00
0.5
83
11.8
96
55.8
CO
NC
RE
TE
457.2
450
0.2
00
98.0
133.0
0.8
12.0
0.4
2
CB
-45
MH
-28
0.0
19
0.0
19
10.0
104
1.9
PV
C S
DR
35
304.8
300
0.3
40
1.1
58.8
0.8
10.0
0.0
3
Ind-B
ldg IL-1
CB
/MH
-22
0.7
41
0.7
41
10.0
104
77.2
PV
C S
DR
35
203.2
200
1.0
00
10.5
34.2
1.0
60.2
2.2
6
Cm
rcl-B
ldg C
-2C
B-3
60.4
65
0.4
65
10.0
104
48.5
PV
C S
DR
35
203.2
200
1.0
00
10.7
34.2
1.0
60.2
1.4
2
CB
-40
CB
/MH
-39
0.0
22
0.0
22
10.0
104
2.2
PV
C S
DR
35
254.0
250
0.4
32
27.5
40.8
0.8
00.6
0.0
5
CB
/MH
-39
CB
/MH
-38
0.0
19
0.0
40
10.6
101
4.1
PV
C S
DR
35
254.0
250
0.4
32
27.5
40.8
0.8
00.6
0.1
0
CB
/MH
-38
MH
-37
0.0
20
0.0
60
11.1
99
5.9
PV
C S
DR
35
254.0
250
0.4
32
17.8
40.8
0.8
00.4
0.1
5
MH
-37
MH
-33
0.0
00
0.0
60
11.5
97
5.8
PV
C S
DR
35
254.0
250
0.4
32
33.8
40.8
0.8
00.7
0.1
4
CB
-36
CB
/MH
-35
0.1
30
0.5
95
10.2
103
61.5
PV
C S
DR
35
254.0
250
0.4
32
25.7
40.8
0.8
00.5
1.5
1
CB
/MH
-35
CB
/MH
-34
0.1
29
0.7
25
10.7
101
72.9
PV
C S
DR
35
254.0
250
0.4
32
26.0
40.8
0.8
00.5
1.7
9
CB
/MH
-34
MH
-33
0.0
95
0.8
19
11.2
98
80.4
PV
C S
DR
35
254.0
250
0.4
32
16.8
40.8
0.8
00.3
1.9
7
MH
-33
MH
-28
0.0
00
0.8
79
12.2
94
82.5
CO
NC
RE
TE
457.2
450
0.2
00
14.1
133.0
0.8
10.3
0.6
2
Mdcl-B
ldg
CB
-44
0.3
55
0.3
55
10.0
104
36.9
PV
C S
DR
35
203.2
200
1.0
00
8.8
34.2
1.0
60.1
1.0
8
Cm
rcl-B
ldg C
-1M
H-9
0.4
78
0.4
78
10.0
104
49.8
PV
C S
DR
35
203.2
200
1.0
00
1.4
34.2
1.0
60.0
1.4
6
CB
-44
CB
/MH
-43
0.0
85
0.4
40
10.1
103
45.5
PV
C S
DR
35
304.8
300
0.3
40
26.7
58.8
0.8
10.6
0.7
7
CB
/MH
-43
CB
/MH
-42
0.0
15
0.4
54
10.7
101
45.7
CO
NC
RE
TE
609.6
600
0.1
40
31.3
239.7
0.8
20.6
0.1
9
CB
/MH
-42
CB
/MH
-30.0
16
0.4
70
11.3
98
45.9
CO
NC
RE
TE
457.2
450
0.2
00
23.1
133.0
0.8
10.5
0.3
5
MH
-28
CB
/MH
-30.0
00
1.4
81
13.8
88
130.0
CO
NC
RE
TE
457.2
450
0.2
00
53.2
133.0
0.8
11.1
0.9
8
0.1
911
0.0
634
0.0
199
0.0
263
0.0
387
0.1
417
0.0
291
0.0
520
0.0
335
0.0
517
LO
CA
TIO
N
0.0
481
0.0
076
CO
MM
EN
TS
In
div
idual
2.7
8 A
R
Accum
.
2.7
8 A
R
Peak F
low
Q (
l/s)
SE
WE
R D
AT
AA
RE
A (h
a)
0.1
631
0.0
282
0.0
357
0.0
378
0.1
860
0.2
960
0.0
621
0.0
097
0.0
052
28
D. B
. G
R A
Y E
N G
I N
E E
R I
N G
I
N C
.S
torm
wa
ter
Ma
na
gem
ent
- G
rad
ing
& D
rain
ag
e -
Sto
rm &
Sa
nit
ary
Sew
ers
- W
ate
rma
ins
ST
OR
M S
EW
ER
CO
MP
UT
AT
ION
FO
RM
PR
OJE
CT
: S
ilve
r S
eve
n P
ha
se
2
70
0 L
on
g P
oin
t C
ircl
e6
13
-42
5-8
04
4R
AT
ION
AL M
ET
HO
D Q
= 2
.78 A
I R
F
IVE
YE
AR
EV
EN
TD
esig
ned B
y:D
BG
Ott
awa,
On
tari
o
K1
T 4
E9
db
gra
y@
roger
s.co
mn =
0.0
13
Date
:19-F
eb-1
5
Page:
2 o
f 2
Tim
e o
fR
ain
fall
Conc.
Inte
nsity
Typ
e o
fD
ia. A
ctu
al
Dia
. N
om
.S
lope
Length
Capacity
Velo
city
Tim
e o
f R
atio
ST
RE
ET
FR
OM
TO
R =
0.9
R =
0.7
0R
=0.2
R =
0.9
(min
)I (m
m/h
r)P
ipe
(mm
)(m
m)
(%)
(m)
(l/s
)(m
/s)
Flo
w (
min
)Q
/Qfu
ll
CB
/MH
-25
CB
/MH
-24
0.1
37
0.1
37
10.0
104
14.2
CO
NC
RE
TE
1066.8
1050
0.1
00
15.0
900.9
1.0
10.2
0.0
2
CB
/MH
-24
CB
/MH
-23
0.0
57
0.1
94
10.2
103
19.9
CO
NC
RE
TE
838.2
825
0.1
00
18.7
473.6
0.8
60.4
0.0
4
CB
/MH
-23
CB
/MH
-20
0.0
46
0.2
40
10.6
101
24.3
CO
NC
RE
TE
838.2
825
0.1
00
19.7
473.6
0.8
60.4
0.0
5
CB
/MH
-22
CB
/MH
-21
0.1
45
0.8
85
10.2
103
91.5
CO
NC
RE
TE
1066.8
1050
0.1
00
19.7
900.9
1.0
10.3
0.1
0
CB
/MH
-21
CB
/MH
-20
0.0
65
0.9
50
10.5
102
96.6
CO
NC
RE
TE
838.2
825
0.1
00
19.9
473.6
0.8
60.4
0.2
0
CB
/MH
-20
CB
/MH
-19
0.1
44
1.3
34
11.0
99
132.4
CO
NC
RE
TE
838.2
825
0.1
00
22.9
473.6
0.8
60.4
0.2
8
CB
/MH
-19
CB
/MH
-18
0.1
80
1.5
14
11.4
97
147.1
CO
NC
RE
TE
838.2
825
0.1
00
20.5
473.6
0.8
60.4
0.3
1
CB
/MH
-18
CB
/MH
-17
0.1
06
1.6
20
11.8
95
154.6
CO
NC
RE
TE
838.2
825
0.1
00
17.7
473.6
0.8
60.3
0.3
3
CB
/MH
-27
CB
/MH
-26
0.1
98
0.1
98
10
104
20.6
CO
NC
RE
TE
609.6
600
0.1
40
17.8
239.7
0.8
20.4
0.0
9
CB
/MH
-26
CB
/MH
-17
0.1
68
0.3
66
10.4
102
37.4
CO
NC
RE
TE
838.2
825
0.1
00
24.9
473.6
0.8
60.5
0.0
8
CB
/MH
-17
CB
/MH
-14
0.1
17
2.1
03
12.2
94
197.5
CO
NC
RE
TE
838.2
825
0.1
00
24.7
473.6
0.8
60.5
0.4
2
CB
/MH
-16
CB
/MH
-15
0.1
18
0.1
18
10
104
12.3
CO
NC
RE
TE
1066.8
1050
0.1
00
17.9
900.9
1.0
10.3
0.0
1
CB
/MH
-15
CB
/MH
-14
0.1
13
0.2
31
10.3
103
23.7
CO
NC
RE
TE
838.2
825
0.1
00
18.0
473.6
0.8
60.3
0.0
5
CB
/MH
-14
MH
-90.1
16
2.4
50
12.7
92
225.3
CO
NC
RE
TE
838.2
825
0.1
00
24.2
473.6
0.8
60.5
0.4
8
CB
/MH
-13
CB
/MH
-12
0.1
45
0.1
45
10
104
15.1
CO
NC
RE
TE
1066.8
1050
0.1
00
24.4
900.9
1.0
10.4
0.0
2
CB
/MH
-12
CB
/MH
-11
0.1
25
0.2
70
10.4
102
27.5
CO
NC
RE
TE
1066.8
1050
0.1
00
24.5
900.9
1.0
10.4
0.0
3
CB
/MH
-11
CB
/MH
-10
0.1
21
0.3
90
10.8
100
39.1
CO
NC
RE
TE
838.2
825
0.1
00
45.0
473.6
0.8
60.9
0.0
8
CB
/MH
-10
MH
-90.0
88
0.4
79
11.7
96
46.0
CO
NC
RE
TE
838.2
825
0.1
00
10.7
473.6
0.8
60.2
0.1
0
MH
-9M
H-8
0.0
00
3.4
07
13.1
90
307.1
CO
NC
RE
TE
838.2
825
0.1
00
36.8
473.6
0.8
60.7
0.6
5
MH
-8C
B/M
H-7
0.0
00
3.4
07
13.8
87
298.1
CO
NC
RE
TE
838.2
825
0.1
00
19.4
473.6
0.8
60.4
0.6
3
CB
/MH
-7C
B/M
H-6
0.0
20
3.4
27
14.2
86
295.3
CO
NC
RE
TE
838.2
825
0.1
00
28.7
473.6
0.8
60.6
0.6
2
CB
/MH
-6C
B/M
H-5
0.0
15
3.4
42
14.8
84
290.1
CO
NC
RE
TE
838.2
825
0.1
00
28.6
473.6
0.8
60.6
0.6
1
CB
/MH
-5M
H-4
0.0
14
3.4
56
15.3
82
285.1
CO
NC
RE
TE
838.2
825
0.1
00
17.3
473.6
0.8
60.3
0.6
0
MH
-4C
B/M
H-3
0.0
00
3.4
56
15.7
81
281.5
CO
NC
RE
TE
457.2
450
0.2
02.7
133.0
0.8
10.1
2.1
2
CB
/MH
-3M
H-2
0.0
55
5.4
62
15.7
81
444.0
CO
NC
RE
TE
457.2
450
0.2
03.2
133.0
0.8
10.1
3.3
4
MH
-2M
H-1
0.0
00
5.4
62
15.8
81
442.9
CO
NC
RE
TE
457.2
450
0.2
015.5
133.0
0.8
10.3
3.3
3
37.2
CO
NC
RE
TE
457.2
450
0.2
015.5
133.0
0.8
10.3
0.2
8R
ES
TR
ICT
ED
FLO
W
762.0
750
0.2
0519.4
1.1
4
SE
WE
R D
AT
A
CO
MM
EN
TS
LO
CA
TIO
NA
RE
A (h
a)
Indiv
idual
2.7
8 A
R
Accum
.
2.7
8 A
R
Peak F
low
Q (
l/s)
0.0
500
0.0
207
0.0
244
0.0
565
0.0
111
0.0
160
0.0
214
0.0
062
0.0
058
0.0
070
0.0
059
0.0
441
0.0
058
0.0
458
0.0
067
0.0
452
0.0
087
0.0
651
0.0
091
0.0
771
0.0
079
0.0
408
0.0
092
0.0
698
0.0
056
0.0
564
0.0
360
0.0
275
0.0
030
0.0
064
0.0
041
0.0
580
0.0
491
0.0
468
0.0
344
0.0
184
0.0
178
0.0
041
MU
NIC
IPA
L S
EW
ER
IN
FR
AN
K N
IGH
BO
R P
LA
CE
0.0
246
0.0
456
29
City of Ottawa Servicing Study Checklist
General Content
Executive Summary (for large reports only): not applicable
Date and revision number of the report: see page 1 of Servicing Brief
Location map and plan showing municipal address, boundary, and layout of proposed
development: see drawings C-1 to C-4
Plan showing the site and location of all existing services: see drawings C-1 to C-4
Development statistics, land use, density, adherence to zoning and official plan, and reference to
applicable subwatershed and watershed plans that provide context to which individual
developments must adhere: not applicable
Summary of Pre-consultation Meetings with City and other approval agencies: not available
Reference and confirm conformance to higher level studies and reports ( Master Servicing
Studies, Environmental Assessments, Community Design Plans), or in the case where it is not in
conformance, the proponent must provide justification and develop a defendable design criteria:
not applicable
Statement of objectives and servicing criteria: see page 2 of Servicing Brief
Identification of existing and proposed infrastructure available in the immediate area: see
drawings C-1 and C-2
Identification of Environmentally Significant Areas, watercourses and Municipal Drains
potentially impacted by the proposed development ( Reference can be made to the Natural
Heritage Studies, if available). see page 2 of Stormwater Management Report (Carp River)
Concept level master grading plan to confirm existing and proposed grades in the development
and drainage, soil removal and fill constraints, and potential impacts to neighbouring properties.
This is also required to confirm that the proposed grading will not impede existing major system
flow paths: not applicable
Identification of potential impacts of proposed piped services on private services (such as wells
and septic fields on adjacent lands) and mitigation required to address potential impacts: not
applicable
Proposed phasing of the development, if applicable: not applicable
Reference to geotechnical studies and recommendations concerning servicing: see note 1.5 on
drawing C-2
All preliminary and formal site plan submissions should have the following information:
• Metric scale: included
• North arrow: included
� (including construction North): not included
• Key Plan: included
• Name and contact information of applicant and property owner: not available
• Property limits: included
� including bearings and dimensions: not included
• Existing and proposed structures and parking areas: included
• Easements, road widening and rights-of-way: included
• Adjacent street names: included
Development Servicing Report: Water
Confirm consistency with Master Servicing Study, if available: not applicable
Availability of public infrastructure to service proposed development: see page 2 of Servicing Brief
Identification of system constraints: see page 2 of Servicing Brief
Confirmation of adequate domestic supply and pressure: see page 2 of Servicing Brief
30
Confirmation of adequate fire flow protection and confirmation that fire flow is calculated as per
the Fire Underwriter‘s Survey. Output should show available fire flow locations throughout the
development: see page 2 & 4 to 11 of Servicing Brief
Provide a check of high pressures. If pressure is found to be high, an assessment is required to
confirm the application of pressure reducing valves: see page 2 of Servicing Brief
Definition of phasing constraints. Hydraulic modeling is required to confirm servicing for all
defined phases of the project including the ultimate design: not applicable
Address reliability requirements such as appropriate location of shut-off valves: not applicable
Check on the necessity of a pressure zone boundary modification:. not applicable
Reference to water supply analysis to show that major infrastructure is capable of delivering
sufficient water for the proposed land use. This includes data that shows that the expected
demands under average day, peak hour and fire flow conditions provide water within the
required pressure range: not applicable
Description of the proposed water distribution network, including locations of proposed
connections to the existing systems, provisions for necessary looping, and appurtenances
(valves, pressure reducing valves, valve chambers, and fire hydrants) including special metering
provisions: not applicable
Description of off-site required feedermains, booster pumping stations, and other water
infrastructure that will be ultimately required to service proposed development, including
financing, interim facilities, and timing of implementation: not applicable
Confirmation that water demands are calculated based on the City of Ottawa Design Guidelines:
see page 3 of Servicing Brief
Provision of a model schematic showing the boundary conditions locations, streets , parcels,
and building locations for reference: not applicable
Development Servicing Report: Wastewater
Summary of proposed design criteria: see page 3 of Servicing Brief
(Note: Wet-weather flow criteria should not deviate from the City of Ottawa Sewer Design
Guidelines. Monitored flow data from relatively new infrastructure cannot be used to justify
capacity requirements for proposed infrastructure): not applicable
Confirm consistency with Master Servicing Study and /or justification for deviations: not
applicable
Consideration of local conditions that may contribute to extraneous flows that are higher than
the recommended flows in the guidelines. This includes groundwater and soil conditions, and
age and conditions of sewers: not applicable
Descriptions of existing sanitary sewer available for discharge of wastewater from proposed
development: see page 3 of Servicing Brief
Verify available capacity in downstream sanitary sewer and / or identification of upgrades
necessary to service the proposed development. (Reference can be made to previously
completed Master Servicing Study if applicable): not applicable
Calculations related to dry-weather and wet-weather flow rates from the development in standard
MOE sanitary sewer design table (Appendix C) format. see page 12 of Servicing Brief
Description of proposed sewer network including sewers, pumping stations, and forcemains: see
page 3 of Servicing Brief
Discussion of previously identified environmental constraints and impact on servicing
(environmental constraints are related to limitations imposed on the development in order to
preserve the physical condition of watercourses, vegetation, soil cover, as well as protecting
against water quantity and quality): not applicable
Pumping stations: impacts of proposed development on existing pumping stations or
requirements for new pumping station to service development: not applicable
31
Forcemain capacity in terms of operational redundancy, surge pressure and maximum flow
velocity: not applicable
Identification and implementation of the emergency overflow from sanitary pumping stations in
relation to the hydraulic grade line to protect against basement flooding: not applicable
Special considerations such as contamination, corrosive environment etc: not applicable
Development Servicing Report: Stormwater Checklist
Description of drainage outlets and downstream constraints including legality of outlets (i.e.
municipal drain, right-of-way, watercourse, or private property): see page 3 of Servicing Brief
Analysis of available capacity in existing public infrastructure. not applicable
A drawing showing the subject lands, its surroundings, the receiving watercourse, existing
drainage patterns, and proposed drainage pattern: see drawing C-1
Water quality control objective (e/g/ controlling post-development peak flows to pre-development level for storm events ranging from the 2 or 5 year event (dependent on the receiving sewer design) to 100 year return period); if other objectives are being applied, a rationale must be included with reference to hydrologic analyses of the potentially affected subwatersheds, taking
into account long-term cumulative effects: see Stormwater Management Report Water Quality control objective (basic, normal or enhanced level of protection based on the
sensitivities of the receiving watercourse) and storage requirements: see Stormwater Management Report Descriptions of the references and supporting information. Set-back from private sewage disposal systems. not applicable
Watercourse and hazard lands setbacks: see drawing C-1
Record of pre-consultation with the Ontario Ministry of Environment and the Conservation
Authority that has jurisdiction on the affected watershed: not avaiable
Confirm consistency with sub-waterched and Master Servicing Study, if applicable study exists:
not applicable
Storage requirements (complete with calculations) and conveyance capacity for minor events (1:5 year return period) and major events (1:100 year return period). see drawing C-1 & C-2 and Stormwater Management Report Identification of watercourses within the proposed development and how watercourses will be protected, or , if necessary, altered by the proposed development with applicable approvals. see drawing C-1 & C-2 and Stormwater Management Report Calculate pre and post development peak flow rates including a description of existing site conditions and proposed impervious areas and drainage catchments in comparison to existing conditions: see Stormwater Management Report Any proposed diversion of drainage catchment areas from one outlet to another. : not applicable
Proposed minor and major systems including locations and sizes of stormwater trunk sewers,
and stormwater management facilities. : not applicable
If quantity control is not proposed, demonstration that downstream system has adequate capacity for the post-development flows up to and including the 100-year return period storm event: not applicable Identification of potential impacts to receiving watercourses: see Stormwater Management Report Identification of municipal drains and related approval requirements. : not applicable
Descriptions of how the conveyance and storage capacity will be achieved for the development:
see page 4 of Servicing Brief
100 year flood levels and major flow routing to protect proposed development from flooding for
establishing minimum building elevations (MBE) and overall grading:
Inclusion of hydraulic analysis including hydraulic grade line elevations. : not applicable
32
Description of approach to erosion and sediment control during construction for the protection
of receiving watercourses of drainage corridors: see notes 2.1 to 2.5 on drawing SG-2
Identification of floodplains – proponent to obtain relevant floodplain information from the
appropriate Conservation Authority. The proponent may be required to delineate floodplains
elevations to the satisfaction of the Conservation Authority if such information is not available or
if information does not match current: not applicable
Identification of fill constraints related to floodplain and geotechnical investigation. : not
applicable
Approval and Permit Requirements: Checklist
The Servicing Study shall provide a list of applicable permits and regulatory approvals
necessary for the proposed development as well as the relevant issues affecting each approval.
The approval and permitting shall include but not be limited to the following:
Conservation Authority as the designated approval agency for modification of floodplain,
potential impact on fish habitat, proposed works in or adjacent to a watercourse, cut/fill permits
and Approval under Lakes and Rivers Improvement Act. The Conservation Authority is not
approval authority for the Lakes and Rivers Improvement Act. Where there are Conservation
Authority regulations in place, approval under the Lakes and Rivers Improvement Act is not
required, except in cases of dams as defined in the Act: the Rideau Conservation Authority has
been contacted but no comments have been received
Application for Certificate of Approval (CofA) under the Ontario Water Resources Act:
Changes to Municipal Drains. : not applicable
Other permits (National Capital commission, Parks Canada, public Works and Government
Services Canada, Ministry of transportation etc.) : not applicable
Conclusion Checklist
Clearly stated conclusions and recommendations: see page 4 of Servicing Brief
Comments received from review agencies including the City of Ottawa and information on how
the comments were addressed. Final sign-off from the responsible reviewing agency.
All draft and final reports shall be signed and stamped by a professional Engineer registered in
Ontario: included
33